Date post: | 07-May-2015 |
Category: |
Engineering |
Upload: | sonia-patel |
View: | 1,119 times |
Download: | 5 times |
KKKB 4844BIOPROCESS PLANT DESIGN PROJECT II
Lim Kah HuayA132816Low Bee Chan A132764Sonia Dilip Patel A/P Dilip Kumar A133115Fatin Atikah Binti Kassim A132739Jamilah Binti Ahmad A133159Muhammad Khairil Azim bin Abdullah A133275
PRODUCTION OF BIOETHANOL FROM GLYCEROL USING Enterobacter aerogenes TISTR1468
Group KB4
2
CONTENT
1. Introduction2. Summary of Production3. List of improvement work4. Heat integration5. PFD after heat integration6. Piping and Instrumentation7. P&ID after HAZOP8. Detailed Unit & Mechanical Design9. Waste Management10. Process Hazard Analysis11. Plant Layout12. Conclusion
SUMMARY OF PRODUCTIONSpecifications Description
Product Bioethanol
Microorganism used Enterobacter aerogenes TSITR 1468
Processes involved • Micro-aerobic fermentation• Stripping• Binary Distillation• Extraction• Flash Vaporization
Production basis (per hour) 3676.47 kg
Bioethanol sale price (RM / kg) 3.04
Return on investment, ROI 0.25
Payback period, PBP 3.46 years
Net present value, NPV RM 10.37 million
Discounted cash flow rate of return, DCFRR 0.19
Site location Pengerang, Johor3
List of Improvement Work
4
CHAPTERS PROBLEM CORRECTION DONE
Chapter 3 - PFD • Size of bioreactors in series doesn’t shows its effectiveness in improving productivity of fermentation process
• Mass flow rate of medium from distillation column to condensers and reboilers are too big
• Stream tables lacks of data
• Bioreactors arrangement in parallel
• Re-calculation of mass balance
• Edited stream table data
Chapter 5 - Heat integration
Mistakes in inlet and outlet temperature
Corrected pinch analysis with heat recovery integrated in PFD
To be continued…
5
CHAPTERS PROBLEM CORRECTION DONE
Chapter 6 – Piping and Instrumentation
• Control loops with electrical signal were not drawn correctly and some loops were not complete
• Relief valve for after HAZOP study was not done
• Mistakes in P&ID drawing
• Complete drawing of controllers for the entire plant
• Sizing calculated and type of valve determined
• Improved drawing with second layer of safety incorporated
Chapter 7 – Detailed Process Design
Design calculation had some mistake since inlet and outlet of stream changed
All the design calculation had been calculated and redesign for all unit
Chapter 8 - Mechanical Design
The calculation for the design and mechanical drawing are not complete
All the calculation design and drawing AUTOCAD is done
…continueList of Improvement Work
To be continued…
6
CHAPTERS PROBLEM CORRECTION DONE
Chapter 10 – Production Hazard Analysis
HAZOP was incomplete and did not consider P&ID
HAZOP done after complete P&ID drawing
Chapter 11 – Site Location and Plant Layout
Plant layout need to reconstruct, details were not drawn out clearly and wrong arrangement of unit operations in plant layout
Completed plant layout drawing
List of Improvement Work…continue
7
Temperature interval start with 0KW
start with 5.915445 kW
107.5 0
105.5 0.004115 -0.004115 0.004115 5.91133
92.9 0.33933 -0.343445 0.33933 5.572
92.5 2.262 -2.605445 2.262 3.31
77.5 2.01 -4.615445 2.01 1.3
67.5 1.3 -5.915445 1.3 0
52.5 -0.4455 -5.469945 -0.4455 0.4455
29.5 0.0824 -5.552345 0.0824 0.3631E-103
HEAT INTEGRATION
PROCESS FLOW DIAGRAM after Heat integration
8
Relief System
Spring-loaded relief valve Gas leaks when pressure
reaches 92-95%
Bursting disc (rupture disc) ‘engineered weak spot’ Low cost, leak tight, instantaneous
response , reliable operation
9
DESIGN OF RELIEF VALVELocation Type Function A (mm2)
F-101 Spring-loaded To prevent the rupture of vessel due to overpressure during process and
sterilization
20 921.57
F-102 Spring-loaded To prevent rupture of vessel due to overpressure during process and
sterilization
18 673.24
F-103 Spring-loaded To prevent rupture of vessel due to overpressure during process and
sterilization
21 879.60
C-101 Spring-loaded To avoid damage to C-101 due to overpressure
17 614.22
C-102 Spring-loaded To avoid damage to C-101 due to overpressure
16 392.17
C-103 Spring-loaded To avoid damage to C-101 due to overpressure
15 670.20
C-104 Spring-loaded To avoid damage to C-101 due to overpressure
17 986.11
10
11P&ID after HAZOP
DETAIL UNIT & MECHANICAL DESIGN
i. Seed Fermenter, F-101
ii. Stripping Column, C-01
iii. Binary Distillation Column, C-102
iv. Extractive Column, C-103
v. Flash Drum, C-104
vi. Cooling Tower
vii. Heat Exchanger, E-103
12
Dimension layout of impeller design
Axial hydrofoil with 3 blades Pitched-blade impellerSource: Lightnin 2013
Source: Hayward Gordon Ltd. 2013
Source: Geankoplis 2013
DETAILED DESIGNLim Kah Huay(A132816)
13Fermenter layoutSource: iGEM 2010
Detailed Design FermentersDesign Parameters F-101 F-102 & F-103
Tank diameter, Dt 1.91 m 3.50 m
Tank height, Ht 5.72 m 10.49 m
Working volume, V 16.35 m3 100.86 m3
Design of Cooling Jacket
Height of jacket 2 m 3.5 m
Spacing between jacket and vessel wall
50 mm 50 mm
Overall heat transfer coefficient, U
500.63 W/m.°C 201 W/m.°C
Pressure drop, ∆P 0.42 kPa 0.16 kPa
Design of Impeller
Type of impeller Axial flow 3 blades hydrofoil
Axial flow pitched-blade 45°impeller
Impeller diameter, Da 0.98 m 1.05 m
Depth of impeller in vessel, H
1.96 m 3.50 mTo be continued… 14
15
Design Parameters F-101 F-102 & F-103
Height of impeller above vessel floor, C 0.65 m 1.17 mImpeller width, W 0.20 m 0.13 mLength of impeller width, L 0.25 m 0.26 mDiameter of impeller base, Dd 0.65 m 0.70 mBaffle width, J 0.16 m 0.29 m
Power number, Np 0.3 1.6
Flow number, Nq 0.55 0.85
Impeller speed 0.10 rps 0.01 rps
Power, P 0.3057 W 0.0008 W
Sparger ring diameter, Ds 1.08 m 1.15 m
Sparger location above vessel floor, S 0.49 m 0.53 m
Mixing time, tT 6.67 s 2041.06 s
Circulation rate, Q 0.05 m3/s 0.29 m3/s
…Continue
Detailed Design Fermenters
16
MECHANICAL DESIGNSEED FERMENTER, F-101
Process Description Microaerobic continuous fermentation with an aeration rate of 0.5
vvm, medium consistently mixed by agitator. Glycerol and ammonium phosphate serve as raw material of carbon
and nitrogen source respectively Fermentation output consists of bioethanol and carbon dioxide
Material of Construction Carbon Steel SA 537
17
Design Specifications Details
Operating Pressure 1 atm (15 psia)
Operating Temperature 37°C (310 K)
Corrosion Allowance 2 mm
Vessel Layout Vertical
H/D ratio 3:1
Volume 16.35
Torispherical Head (Top and Bottom Design)
Crown radius, R (m) 1.81
Knuckle radius, a (m) 0.19
Distance from the center of the torus to the center of the torus tube, c (m)
0.76
Height from the base of the dome to the top, h (m) 0.38
Cylindrical Shell (Shell Design)
Height, (m) 4.96
Effective Length, L (m) 5.21
18
Vessel Parts Dimensions (mm)
Torispherical Top 5.72
Cylindrical Shell 8.89
Torispherical Bottom 5.72
Overall 11
Minimum Wall Thickness
Design of Cooling JacketDesign Parameters Details
Type Type 1 (confined entirely to the cylindrical shell)
Closure Type (b-2)
Material of Construction Carbon Steel SA537
Jacket Space 50 mm
Required minimum thickness of closure member as determined ()
0.91 mm
Nominal thickness of closure member ()
2.91 mm
Corner radius of torus closures 5.84 mm
19
Stresses Details
Longitudinal stress, (N/ 4.83
Circumferential stress, (N/ 9.66
Direct stress, (N/) 0.6324
Bending stress, (N/)
Primary stresses
upwind (N/) 6.53
downwind (N/) 4.40
Maximum allowable stress intensity, Δσ (N/)
5.26
Design stress, S (N/) 157
Critical buckling stress, (N/) 1361.54
Combined Loading
Design of Vessel Support
20
Design Parameters Details
Type of support Bracket support
Type of bracket Double gusset Type 1
Type of beam Wide-flange
Number of legs 4
Vertical load per support leg,
47 kN
Area of base plate required,
7.55
Standard wide flange beam leg type base plate
W6
21
Flanged Joint Design
Design Parameters Details
Type of flanged joint Welding neck flange
Flange faces Gasket between bolt circle
Outside diameter of flange (mm)
Stream 2&4 – 107.95Stream 3&5 – 152.4Stream 1&6 – 228.6
DISTILLATION COLUMN (C-101)SONIA DILIP PATEL (A133115)
C-101
D-101
H-101
BIOETHANOLBIOMASSWATER
55% Bioethanol45%Water
WASTEWATER TREATMENT/ STILLAGE
S14
S16
S18 S17
S20
S19
S21
Parameter Dimension
Column design Tray
Diameter, DT (m) 1.913
Height, H (m) 9.772
Tray spacing(m) 0.457
Number of actual stages 17
Design of plate Sieve plate
Plate spacing (m) 0.457
Downcomer area 0.2725m2
Active area 1.726m2
Holes area, 0.173m2
Number of holes 880522
MECHANICAL DESIGN OF C-101SONIA DILIP PATEL (A133115)
• Material usedSS-308
• Properties
Source : MIT Department of Civil and Environment 1999
Element Content (%)
Iron, Fe 66
Chromium, Cr 20
Nickel, Ni 11
Manganese, Mn 2.0
Silicon, Si 1.0
Carbon, C 0.080
Phosphorus, P 0.045
Sulfur, S 0.030
Properties Metric
Density 8 g/cm3
Tensile strength 585 MPa
Yield strength 240 MPa
Poisson’s ratio 0.27-0.30
23
• Design parameter for C-101Parameter Value (SI unit) Value (English unit)
Temperature, T 100 OC 212 OF
Operating pressure (gage), P0 101.325 kPa 15 psig
Height of vessel , H 9.3262 m 367.1732’’, 30.5978’
Inside diameter of vessel, Di 1.91 m 75.1969’’,6.6224’
Height of cylinder shell, Hcylinder 7.772 m 305.9843”, 25.4987’
Height of torispherical heads, Htoris 0.3688 m 14.5197”, 1.2100’
Torispherical head
, CA = 3.46 mm
24
• Combine loading
Primary Stress Value (N/mm2)
Longitudinal stress, 3.6226
Circumferential stress, 7.2453
Direct stress , -0.7885
Bending stress, 1.84 x
∑ σmax<σ c
0.7885 N mm−2<154.64 N mm− 2
( Δσ )max<Sdesign
4.4112 N mm− 2<138 N mm− 2
Criterion met. Design is satisfied.
25
Vessel Support Straight Cylindrical skirt.
σ s (tensile )=σbs− σ ws
σ s (compressive )=σ bs+σ ws
M s=26 647.7635 Nm
σ bs=0.0009252 N /mm2
σ ws (test )=2.9155 N /mm2
σ ws (operating )=1.9386 N /mm2
= -
=
σ s (tensile )≤ f s J sinθ
−1.9377 ≤132.32
σ s (compressive )<0.125 EY ( t s
Ds)sin θs
1.9395 ≤ 130.8901
Criterion satisfied, 2 mm CA added. Final skirt thickness = 12 mm
26
• Base ring and Anchor Belt Design
= 1934 mm Nb = 4 bolts M s=5974.56 Nm = = 10.79 mm
Bolt size = nominal diameter (BS 4190: 1967) Bolt used = M24 with root area = 353 mm2.
• Flanged Joint
Welding Neck Flange
27
28
DISTILLATION COLUMN (C-102)LOW BEE CHAN (A132764)
Parameter Dimension
Column design Tray
Diameter, DT (m) 1.524
Height, H (m) 26.50
Tray spacing(m) 0.46
Number of actual stages 53
Design of plate Sieve
Plate spacing (m) 0.457
Downcomer area (m2) 0.146
Active area (m2) 0.925
Holes area (m2) 0.0925
Number of holes 4720
29
Mechanical Design Of Stripping Column C-102LOW BEE CHAN A132764
Process Description:Purify ethanol-water mixture to form azeotrope with 95.63% ethanol and 4.37% water (by weight)
Material Selection:Austenitic Stainless Steel 304L
Design Specification:• External pressure vessel• Cylindrical shell• Torispherical heads
31
Minimum wall thickness (mm)
Top and bottom heads 5.08
Cylindrical shell 15.24
Overall(standard) 18
Primary Stresses (N/mm2)
Longitudinal Stress, σL 2.1447
Circumferential Stress, σh 4.2894
Direct Stress, σw 6.65
Bending Stress, σb ± 46.66
)
Elasticity Stability (N/mm2)
; No Buckling
CYLINDRICAL COLUMN DESIGN
31
VESSEL SUPPORT DESIGNResultant Stresses (N/mm2)
<
STRAIGHT SKIRT SUPPORT
Skirt thickness (mm) 20
Skirt height (mm) 2000
Base Ring and Anchor Bolt Design
Number of bolts 12
Actual width 220mm
Minimum thickness 50mm
M56 bolts (BS 4190: 1967)
32
FLANGE DESIGN
ParameterS26feed
S27top
S29refluxed
S31bottom
S32reboiled
Flow rate (kg/s) 0.4233 4.314 3.356 1.054 4.314
Density (kg/m3) 846.389 1.507 770.216 796.255 1.429
Optimum diameter 34.103 614.71 97.20 54.47 625.19
Nominal pipe size 50.8 660.4 101.6 101.6 660.4
Flange class 150 150 150 150 150
Outside flange diameter, O
152.4 831.85 228.6 228.6 831.85
Thickness of flange, Tf 17.526 63.5 22.352 22.352 63.5
Diameter of hub, X 77.724 708.152 134.874 134.874 708.152
Chamfer beginning diameter, A
60.452 609.6 114.3 114.3 609.6
Length through Hub, Y 61.976 127 74.676 74.676 127
Bore 52.578 355.6 102.362 102.362 355.6
Number of bolts 8 8 8 8 8
• Welding Neck Flange
33
DESIGN SUMMARY
Parameter Value
Operating temperature 100
Operating pressure (atm) 1
Material of construction Austenitic stainless steel Type 304L
Vessel internal diameter (m) 1.524
Vessel height (m) 2.65
Type of head and bottom Torispherical
Type of vessel Cylindrical
Vessel wall thickness (mm) 18
Stress analysis (N/mm2) (Δσ)max S < , (7.7128 < 137.89) [Safe]
Elastic stability (N/mm2) < σ , (1.0921< 70.09) [Safe]
Type of vessel support Straight conical skirt
Type of flanged joint Welding neck flange
Flange faces Gasket between bolt circle
Flange diameter (mm) 50.8, 101.6, 660.4
34
Specifications H-101 H-103Pitch pattern Square pitch Square pitchBrass, kw (W/m°C) 110 110Floating head Split-ring Split-ring Shell pass 1 1Tube pass 4 4Number of tubes, Nt 998 1596Outer diameter, do(m) 0.0381 0.0381Inner diameter, di(m) 0.0168 0.0168Length of tubes, l (m) 5 7Tube pitch, Pt (m) 0.0125 0.0125Heat transfer area, A (m2) 596.96 1336.46Shell inside diameter, Ds (m) 1.915 2.335Baffle spacing, lB(m) 0.036 0.036Baffle cut, (%) 45 45Tube side coefficient, hi(W/m2∆°C) 12473.48 11138.26Shell side coefficient, hs(W/m2∆°C) 3310.721 1053.628Overall coefficient, Uo(W/m2°C) 991.88 603.28Tube side pressure drop, ∆Pt(kPa) 78.83 44.67Shell side pressure drop, ∆Ps (kPa) 1.47 14.36
CONDENSER DESIGN
35
KETTLE REBOILER DESIGN
Specifications H-102 H-104
Pitch pattern Square pitch Square pitch
Carbon steel, kw (W/m.°C) 55 55
Number of U tubes 404 374
Outer diameter, do(m) 0.022 0.0381
Inner diameter, di(m) 0.01688 0.0168
Length of tubes, l (m) 5 4
Heat transfer area, A (m2) 158.78 94.09
Baffle spacing, lB (m) 0.036 0.036
Baffle cut (%) 45 45
Tube side coefficient, hi(W/m2∆°C) 736000 734000
Shell side coefficient, hnb (W/m2∆°C) 28137.52 28565.69
Overall coefficient, Uo (W/m2°C) 1444 1239.23
Tube side pressure drop, ∆Pt (kPa) 174.89 168.6
Shell side pressure drop, ∆Ps (kPa) 14.59 14.36
36
EXTRACTIVE DISTILLATION COLUMN (C-103)JAMILAH AHMAD (A133159)
Material Carbon steel 516
Actual no of stages 27
Diameter of the column (m) 4.68
Height of the column (m) 21.19
CONDENSER H-105
Cooling water flow rate 11409.8
Area required 3.531 m2
Outside diameter 19.05 mm
Inside diameter 14.83 mm
Length 5 m
Number of tube 12
Diameter of the bundle, Db 0.11 m
Shell-side coefficient 1030.137 W/m2oC
Tube-side coefficient 8982.51 W/m2oC
Overall heat transfer cofficient, Uo 649.99 W/m2oC
Total heat load (kW) 771
Area required 6.3
Shell side coefficient
Overall heat transfer coefficient (W/m2oC)
496
Pressure drop (kPa) 12.1
KETTLE REBOILER H-106
37
MECHANICAL DESIGN EXTRACTIVE COLUMN
JAMILAH AHMAD (A133159)
INTRODUCTION
• Wall thickness required for the vessel
• Pressure exerted by the outside force weather the vessel can withstand or not.
• Type of top & bottom and shell used for the vessel
• Type of vessel support to withstand the vessel.
38
EXTRACTIVE COLUMN
Parts Value/Description
Main Part:•Vessel height•Diameter•Shell height•Top & bottom height•Thickness•Type of shell•Type of head & bottom•Material
• 21.49 m• 4.68 m• 19.15 m• 1.17 m• 30 mm• Cylindrical• Torispherical• Carbon steel 516
Support•Type•Material•Height•Thickness
• Straight skirt• Carbon Steel• 1.219 m• 30 mm
Flanges• Type of flange • Welding neck
39
Detailed Design of Flash Drum C-104KHAIRIL AZIM (A133275)
Inlet (S41)
Vapour Outlet (S42)
Liquid Outlet (S43)
h=1.219m
Dv=0.366
Flash drum C-104 is used to separate the vapour and liquid. For design calculations it is normally assumed that the vapour and liquid are in equilibrium and the vessel is adiabatic
Condition Value
Temperature 100 oC
Pressure 1 atm
Density of Water 958.4 kg/m3
Vapour Density 1.422 kg/m3
From the calculation,•The diameter must be large enough•The high of vessel outlet above the gas inlet should be sufficient for liquid drops.•Liquid level will depend on hold up time necessary for smooth operations and control
hv=0.283 m3
The conclusion from the calculation,Minimum vessel diameter,Dv = 0.366 mLiquid depth required,hv = 0.238 m3Height of the tank,H = 1.219 m
Mechanical Design of Flash Drum C-104KHAIRIL AZIM (A133275)
Parts Value/Description
Main Part:•Height•Diameter•Thickness•MAWPvessel
1.219 m0.366 m3.5 mm1.714 kPa
Support•Type•Material•Height•Thickness
Conical skirtPlain Carbon Steel0.25 m3.5 mm
Flanges•Feed•Liquid•Vapour
Welding neckWelding neckWelding neck
Design Summary of C-104
41
Properties Value
Cooling water flow rate (kg/h) 105458
Water inlet temperature (°C)
37
Water outlet temperature (°C)
28
Ambient wet bulb temperature (°C)
23.9
Tower characteristic, KaL/V
1.5
Minimum tower area (m2)
17
Height of cooling tower (m)
10.4Source : HarrisonCooling Tower 2002
DETAIL DESIGN OF COOLING TOWERFATIN ATIKAH (A132739)
42
DETAIL DESIGN OF HEAT EXCHANGERNumber of tube 43
Length tube 4 m
Shell-Side Pressure Drop 78.94 kPa
Tube-Side Pressure Drop 1.84 kPa
Shell-side coefficient 63.94 W/m2oC
Tube-side coefficient 661 W/m2oC
Overall heat transfer cofficient, Uo
549.47 W/m2oC
Shell and Tube Exchanger
FATIN ATIKAH (A132739)
43
MECHANICAL DESIGN FOR HEAT EXCHANGER (E-103) Parts Value/Description
Main Part:•Vessel length•Height vessel•Inner diameter•Outer diameter
4.0 m0.267 m0.016 m0.02 m
Support•Type•Material•Height•Thickness
Saddle support Carbon Steel 0.8 m0.15 m
Flanges Welding neck
Shell and Tube Exchanger
Saddle support Welding neck flanges
FATIN ATIKAH (A132739)
44
Faculty of Engineering and Built Environment
Department of Chemical and Biochemical Engineering
Project Title:
Production of Bioethanol from Enterobacter aerogenes
TISTR1468 using Glycerol
Activated Sludge Wastewater Treatment Plant (WWTP)
Drawn by:
LOW BEE CHAN
Group Member:
Date:
Drawing no.
GRPKB4/C2H6O/PFD/01
Prepared by:
Group KB4
Checked by:
27 MARCH 2014
PROF. DR. SAHAID KALILDR NORLIZA ABDUL RAHMAN
LIM KAH HUAY (A 132816)
LOW BEE CHAN(A 132764)
SONIA DILIP PATEL A/P DILIP KUMAR (A 133115)
FATIN ATIKAH BINTI KASSIM (A132739)
JAMILAH BINTI AHMAD (A133159)
MUHAMMAD KHAIRIL AZIM BIN ABDULLAH (A133275)
Symbol:
1 Stream number
Major Streamline
T-101 Flocculation Tank T-103 Aeration Tank T-104 Secondary ClarifierT-102 Primary Clarifier A-101 Air Blower T-105 Sludge Storage Tank
Check Pond
Wastewater from production
plant
Air
Flocculants and Coagulant
T-101
T-102T-103
A-101
T-104
T-105
1
2 3
4
5
7
8
9
10
6
WASTEWATER MANAGEMENT
ACTIVATED SLUDGE WASTEWATER TREATMENT PLANT PROCESS FLOW DIAGRAM
Stream 1
Flowrate(m3/day) 892.99
S,BOD (mg/L) 362422.7
X, SS (mg/L) 16792.5Stream 8
Flowrate (m3/day) 0.47
S,BOD (mg/L) -
X, SS (mg/L) 5850.5
Stream 7
Flowrate (m3/day) 4.25
S,BOD (mg/L) -
X, SS (mg/L) 5850.5
Stream 6
Flowrate(m3/day) 4.72
S,BOD (mg/L) -
X, SS (mg/L) 5850.5
Stream 5
Flowrate (m3/day) 884.29
S,BOD (mg/L) 362422.7
X, SS (mg/L) 5940.5
Stream 4
Flowrate(m3/day) 9.45
S,BOD (mg/L) -
X, SS (mg/L) 11775.7
Stream 3
Flowrate(m3/day) 883.54
S,BOD (mg/L) 362422.7
X, SS (mg/L) 5016.8
Stream 2
Flowrate (m3/day) 892.99
S,BOD (mg/L) 362422.7
X, SS (mg/L) 16792.5
Stream 10
Flowrate (m3/day) 879.57
S,BOD (mg/L) 45
X, SS (mg/L) 90
Stream 9
Flowrate(m3/day) 9.92
S,BOD (mg/L) -
X, SS (mg/L) 12290.9
Flocculation tank
Sludge storage tank
Aeration tank
Secondary clarifier
Primary clarifier
46.51 m3
60 min
93.02 m3
SL: 40m3/m2.day
188. 06 m3
Length: 8.17 mWidth: 3.8 mHeight: 3m
93.02 m3
Length: 9.3 mWidth: 5 mHeight: 2 m
45
46
PLANT LAYOUT
Process Hazard Analysis
Components Hazardous Properties
Glycerol • Flammable• Explosion• Toxic
Ammonium phosphate • Toxic
Oxygen • Flammable• Toxic
Ethanol • Fire• Explosion• Toxic
Carbon dioxide • Explosion• Toxic
Nitrogen • Toxic
Hazard IdentificationLegal Acts Requirement1. Environmental Quality Act
(EQA) 19742. Occupational Safety and Health
Act (OSHA) 19943. Factory and Machinery Act
(FMA) 1967
Methods for PHA:1. HAZOP analysis2. FMEA
Set of organized and systematic assessments of the potential hazards associated with an industrial process. A PHA provides information intended to assist managers and employees in making decisions for improving safety and reducing the consequences of unwanted or unplanned releases of hazardous chemicals.
47
FMEA method- Systematic process to identify potential failures to fulfill the intended function, to identify possible failure and locate the failure impacts- Example of the method is shown in Seed Fermenter F-101
Component Failure mode Failure effects Symptom Safeguard ActionLevel control valve
Valve fails openValve fails closed
Fluid will exceed the level of storage tank causing overflow and rupture the tank
Liquid overflow None Schedule inspection and maintenance required
Pure glycerol valve
Valve fails open No glycerol in the tank. Product produce does not meet the specification.
The reaction is not complete
None Daily check
Temperature control valve
Valve fails open High temperature in the tank. It will effect product reaction
No cooling water is supply to the tank
Low level alarm Daily check
Process Hazard Analysis
48
Component Failure mode Failure effects Symptom Safeguard Action
Heat exchanger Tube failure High pressure and
could cause a cause
a major fire
Odors at the
cooling tower
None Daily check and
schedule
maintenance
Centrifugal pump Pump stop Loss of power
which cause
mechanical failure
Risk of upstream
process pump
damage due to
overpressure
None Preventive
maintenance
Temperature
control valve
Heater failure Electric device
failure. Loss of
electric power
May cause over
temperature which
will rupture the
wall
None Schedule
inspection and
maintenance
Condenser(Cooler) Power failure Unable to cool the
outlet stream
Very high
temperature is
flowing out
None Back-up power
supply generator
Level control valve Valve fails open
Valve fails closed
Fluid will exceed
the level of storage
tank causing
overflow and
rupture the tank
Liquid overflow None Schedule
inspection and
maintenance
required
- FMEA analysis for Distillation Column C-101
49
PROCESS HAZARD ANALYSIS
HAZOP Analysis
• HAZOP Analysis is to identify how a process deviation can be prevented or mitigate to minimize the potential hazard. Example of the analysis is in the distillation column.
Project name : Process Plant Design
Process : Bio ethanol production
Part : Distillation Column
Study node Process parameterDeviations
(guide words)Possible causes Possible consequence Action required
Stream 28 Flow NO Pipe broken or plugging
Loss of feed into column/not achieve into desired output.
Level decrease in distillation column.Off specification product.
1. Schedule inspection and maintene.an
LOW 1. Pipe partial plugged or leakage.
1. Level decrease in distillation column.
2. Off specification product.3. Back flow of material.
Install check valve.
HIGH 1. High pressure from source
1. Flooding in distillation column. 1. Install bypass line with manual valve.
Distillation column Level HIGH 1. Output pipe blockage.
Overpressure of reflux drum.Condensed liquid flow back to
distillation.
1. Install high level alarm2. Scheduling inspection
LOW Pipe partial clogged & leakage. Level decrease in the vessel The valve closed.Back flow of material.
1. Scheduling inspection2. Install valve.
Temperature HIGH 1. Low incoming flow from H-101 cause overheating.
Off specification product.
Install temperature sensor.
LOW 1. H-101 malfunction.2. High incoming flow through H-
101.
Low level inside reboiler.Off specification product.
1. Scheduling inspection2. Install temperature sensor.
50
CONCLUSION
51
A high yield and potential for ethanol as fuel from Enterobacter aerogenes. Pengerang has been the best location judging from the coming development as Asia’s largest storage terminal.
Production rate of 3276 kg/hr and high demand in 2018 (projection) will leave a very stable economic growth for ethanol.
65% saving of energy through pinch and heat exchanger installation will further bloom the net profit.
Mechanical calculations and drawings for main utilities provide a clearer insight of the sizing and supports.
Safety has been of top consideration through FMEA and HAZOP performed. Layers of control aspect will further enhance the safety and continuous operation of ethanol plant.
Waste management has been of top priority and calculations from waste treatment plant designed is able to lower down pollutants to allowable limits.