G. Passaleva Roma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva
Transcript
Page 1: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Status of MWPC production site in Florence

G. Passaleva

Page 2: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

InfrastructureWiring machine in the clean room Consolle of the wiring machine

View of the open area and the “gray room” Yunshan in the “gray room” picking up panels for measurements

Page 3: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Panel gluing1. Panels are checked for planarity…2. …cleaned under the hut with

isopropilic alcohol…3. …glued on the gluing machine with

automatic glue dispensing…4. …measured again after gluing…5. …and stored in the shelf

1

2

3

43

5

Page 4: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

wiring machine

Laser soldering bridge Glue dispensing bridge and wire torque motor

Page 5: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Assembly tables

Panels wired glued soldered and cleaned are…

1. …measured with WTM…2. …and with WDM,3. tested for HV with the

nAmperometer.4. On the same table we glue side bars

1

2

3

4

Final chamber assembly table (thanks to ROME 2 for the realization of the tools)

3

Page 6: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Quality controls: WTM, WDM ,HV test

WDM cameras

WTM hammer laser spot and photodiode HV connections and nAmperometer

Page 7: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Building chamber 1

a) Wiring machine enters the clean room

c) Placing the spacers…

b) Gluing the top bars…

d) The chamber is ready to be closed

We built ch1 to go through the full production chain.

The WM placed in the clean room on the 28th of June

The chamber was closed on July 10 and brought to LNF the 13th.

Ch1 was built with the very first panels assembled. Panel L1 in particular was one the first glued with the automatic gluing machine

Gap A was severely leaking (most probably due to bad gluing of the HVbar see above) and needed to be sealed.

Several wires needed to be replaced ( repair procedure tested)

Page 8: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Building chamber 1

Fernando checks with the spacers the clamping strength

The chamber is closed

Page 9: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Results on chamber 1Test made @ LNFMany thanks to M. Anelli !

HV: 2.6 kV.Expected current: 100 nA

Gap A was leaking from one corner (probably hvbar not well glued)

Gap B looks reasonable

Gap C is not uniform and the gain is too low

Gap D looks more uniform but in fact there is current limitation set by Mario !!!!

Page 10: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Building chamber 2

Two panels (701,1255) already wired,soldered and tested

Two panels (706,1027) glued and measured

Plan to close ch2 by the end of this week

Page 11: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Building chamber 2: HV bars gluing

2.44 2.47 2.50 2.52 2.52 2.47 2.54

2.53 2.48 2.50 2.50 2.55 2.49 2.47

2.47 2.43 2.46 2.45 2.43 2.46 2.44

2.46 2.47 2.46 2.42 2.42 2.43 2.47

Hv bar height after gluing. Measurements taken near the spacer holes with a comparator.Yellow: panel #706 (first batch)Green: panel #1027 (last batch)

Page 12: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Building chamber 2: WTM

Panel 1255 Panel 1255

Mean=63 gSigma = 2.5 g

Panel 701

Detailed analysis from raw data

Panel 701Display of WTM program

Page 13: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Building chamber 2: WDM

Panel 701 camera 1 Panel 701 camera 2

Page 14: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Building chamber 2: WDM

!!!Panel 701, camera 2

8 9 10 11

Page 15: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Building chamber 2: WDM

Panel 1255 camera 1 Panel 1255 camera 2

Page 16: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Building chamber 2: HV test

Measurements taken with the LNF nAmperometer.

Panel 1255

Panel 701

Page 17: G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.

G. Passaleva Roma - July 28, 2004

Road towards the PRR

• At the moment the main missing item is (still !!!!) the laser soldering (even though it is finally converging)

• Ch 2 will be closed this week

• We will try to close another 3 chambers by the end of august (test all or some at LNF ?)

• Clearly, we want to understand well all the problems that are arising while building our first chambers