Gantt chart Building Ground Floor

Date post: 30-Oct-2014
Category:
Upload: riazahemad-b-jagadal
View: 66 times
Download: 0 times
Share this document with a friend
Description:
construction management gantt chart task wise program of work
1
ID Task Name Duration Start Finish 1 project management Police Station Guledagudda 202 days? Mon 24-12-12 Thu 15-08-13 2 site clearance leveling and pooja 1 day Mon 24-12-12 Mon 24-12-12 3 line out 1 day Tue 25-12-12 Tue 25-12-12 4 excavation in column pits 6 days Wed 26-12-12 Tue 01-01-13 5 shed construction 1 day Wed 26-12-12 Wed 26-12-12 6 Borewell 2 days Thu 27-12-12 Fri 28-12-12 7 temp electric meter 1 day Thu 27-12-12 Thu 27-12-12 8 Bed concrete M7.5 2 days Wed 02-01-13 Thu 03-01-13 9 cement,Agregate,sand procurement 3 days Wed 26-12-12 Fri 28-12-12 10 steel procurement and bending 4 days Wed 26-12-12 Sat 29-12-12 11 steel col erection and shuttering 7 days Fri 04-01-13 Fri 11-01-13 12 footing concrete M20 2 days Sat 12-01-13 Mon 14-01-13 13 Excavation strip for SSM walls 6 days Tue 15-01-13 Mon 21-01-13 14 Bed For SSM walls 4 days Tue 22-01-13 Fri 25-01-13 15 steel procurement and bending Plinth Beams 10 days Mon 24-12-12 Thu 03-01-13 16 SSM walls in foundation 6 days Tue 22-01-13 Mon 28-01-13 17 SSM in Basement 18 days Tue 29-01-13 Mon 18-02-13 18 cement,Agregate,sand, bricks procurement 4 days Mon 24-12-12 Thu 27-12-12 19 Back Filling foundation and plinth 8 days Fri 01-02-13 Sat 09-02-13 20 Erection of Plinth beam Bars and Shuttering 4 days Tue 19-02-13 Fri 22-02-13 21 concrete M 20 Plinth Beams 3 days Sat 23-02-13 Tue 26-02-13 22 removing shuttering Plinth beam 1 day Wed 27-02-13 Wed 27-02-13 23 procure and erect r 1 day? Thu 28-02-13 Thu 28-02-13 24 BBM in Super structure 24 days Fri 01-03-13 Thu 28-03-13 25 steel procurement and bending lintals, chajja,Beams 8 days Sat 02-03-13 Mon 11-03-13 26 Lintal, chajjal and Beams bar erection and shuttering 10 days Mon 18-03-13 Thu 28-03-13 27 Concrete M20 to lintals, chajja and beams,etc 2 days Fri 29-03-13 Sat 30-03-13 28 removing shuttering Lintal 1 day Mon 01-04-13 Mon 01-04-13 29 BBM in Super structure abv lintal 6 days Mon 01-04-13 Sat 06-04-13 30 bending for slab 10 days Mon 01-04-13 Thu 11-04-13 31 steel, cement,Agregate,sand procurement 5 days Mon 01-04-13 Fri 05-04-13 32 floor bed concrete in rooms. Verandha 3 days Mon 01-04-13 Wed 03-04-13 33 centring shutterig & bending slab, beam & stair 8 days Thu 04-04-13 Fri 12-04-13 34 concrete slab beam 1 day Sat 13-04-13 Sat 13-04-13 35 removing shuttering Roof slab beam 14 days Mon 15-04-13 Tue 30-04-13 36 pointing to SSM 10 days Tue 19-02-13 Fri 01-03-13 37 Padadi Casting 2 days Wed 01-05-13 Thu 02-05-13 38 RCC shelves 4 days Wed 01-05-13 Sat 04-05-13 39 GF plaster mesh b/n wall rcc col,beam joints 3 days Wed 01-05-13 Fri 03-05-13 40 grill work for Lockups 5 days Sat 04-05-13 Thu 09-05-13 41 GF plumbing work concealed 3 days Wed 01-05-13 Fri 03-05-13 42 GF electric wall conduits concealed 3 days Wed 01-05-13 Fri 03-05-13 43 drainage work all bath and wc 5 days Wed 01-05-13 Mon 06-05-13 44 parapet BBM walls 4 days Mon 15-04-13 Thu 18-04-13 45 GF plaster 18mm outside 18 days Mon 15-04-13 Sat 04-05-13 46 GF plaster 12 mm lime render to walls inside 18 days Sat 04-05-13 Fri 24-05-13 47 GF glazed bath ,wc, kit tiles 8 days Sat 04-05-13 Mon 13-05-13 48 GF flooring inside rooms 18 days Sat 04-05-13 Fri 24-05-13 49 GF door frame procumnt and fixing 5 days Sat 25-05-13 Thu 30-05-13 50 GF Door shutters 8 days Sat 25-05-13 Mon 03-06-13 51 GF electric wiring inside 4 days Sat 25-05-13 Wed 29-05-13 52 GF plumbing inside 2 days Tue 14-05-13 Wed 15-05-13 53 Kitchen katta and sink fixing 12 days Sat 25-05-13 Fri 07-06-13 54 extrnal drainage work all bath and wc 5 days Thu 16-05-13 Tue 21-05-13 55 Electric Meters LT Line and Street Lamps and TC 45 days Wed 22-05-13 Fri 12-07-13 56 Approach Roads 7 days Sat 13-07-13 Sat 20-07-13 57 Window grill work 7 days Sat 25-05-13 Sat 01-06-13 58 collapseble shutter 3 days Mon 03-06-13 Wed 05-06-13 59 Solar fixing 6 days Thu 06-06-13 Wed 12-06-13 60 Painting inside 45 days Tue 04-06-13 Thu 25-07-13 61 painting outside 15 days Fri 26-07-13 Mon 12-08-13 62 Windows 10 days Fri 26-07-13 Tue 06-08-13 63 painting doors/ shutter grill 15 days Fri 26-07-13 Mon 12-08-13 64 site finishing and handing over 10 days Mon 05-08-13 Thu 15-08-13 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 2 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline Page 1 Project: Project GF Police Station Guld Date: Fri 16-11-12
Transcript
Page 1: Gantt chart Building Ground Floor

ID Task Name Duration Start Finish

1 project management Police Station Guledagudda 202 days? Mon 24-12-12 Thu 15-08-13

2 site clearance leveling and pooja 1 day Mon 24-12-12 Mon 24-12-12

3 line out 1 day Tue 25-12-12 Tue 25-12-12

4 excavation in column pits 6 days Wed 26-12-12 Tue 01-01-13

5 shed construction 1 day Wed 26-12-12 Wed 26-12-12

6 Borewell 2 days Thu 27-12-12 Fri 28-12-12

7 temp electric meter 1 day Thu 27-12-12 Thu 27-12-12

8 Bed concrete M7.5 2 days Wed 02-01-13 Thu 03-01-13

9 cement,Agregate,sand procurement 3 days Wed 26-12-12 Fri 28-12-12

10 steel procurement and bending 4 days Wed 26-12-12 Sat 29-12-12

11 steel col erection and shuttering 7 days Fri 04-01-13 Fri 11-01-13

12 footing concrete M20 2 days Sat 12-01-13 Mon 14-01-13

13 Excavation strip for SSM walls 6 days Tue 15-01-13 Mon 21-01-13

14 Bed For SSM walls 4 days Tue 22-01-13 Fri 25-01-13

15 steel procurement and bending Plinth Beams 10 days Mon 24-12-12 Thu 03-01-13

16 SSM walls in foundation 6 days Tue 22-01-13 Mon 28-01-13

17 SSM in Basement 18 days Tue 29-01-13 Mon 18-02-13

18 cement,Agregate,sand, bricks procurement 4 days Mon 24-12-12 Thu 27-12-12

19 Back Filling foundation and plinth 8 days Fri 01-02-13 Sat 09-02-13

20 Erection of Plinth beam Bars and Shuttering 4 days Tue 19-02-13 Fri 22-02-13

21 concrete M 20 Plinth Beams 3 days Sat 23-02-13 Tue 26-02-13

22 removing shuttering Plinth beam 1 day Wed 27-02-13 Wed 27-02-13

23 procure and erect r 1 day? Thu 28-02-13 Thu 28-02-13

24 BBM in Super structure 24 days Fri 01-03-13 Thu 28-03-13

25 steel procurement and bending lintals, chajja,Beams 8 days Sat 02-03-13 Mon 11-03-13

26 Lintal, chajjal and Beams bar erection and shuttering 10 days Mon 18-03-13 Thu 28-03-13

27 Concrete M20 to lintals, chajja and beams,etc 2 days Fri 29-03-13 Sat 30-03-13

28 removing shuttering Lintal 1 day Mon 01-04-13 Mon 01-04-13

29 BBM in Super structure abv lintal 6 days Mon 01-04-13 Sat 06-04-13

30 bending for slab 10 days Mon 01-04-13 Thu 11-04-13

31 steel, cement,Agregate,sand procurement 5 days Mon 01-04-13 Fri 05-04-13

32 floor bed concrete in rooms. Verandha 3 days Mon 01-04-13 Wed 03-04-13

33 centring shutterig & bending slab, beam & stair 8 days Thu 04-04-13 Fri 12-04-13

34 concrete slab beam 1 day Sat 13-04-13 Sat 13-04-13

35 removing shuttering Roof slab beam 14 days Mon 15-04-13 Tue 30-04-13

36 pointing to SSM 10 days Tue 19-02-13 Fri 01-03-13

37 Padadi Casting 2 days Wed 01-05-13 Thu 02-05-13

38 RCC shelves 4 days Wed 01-05-13 Sat 04-05-13

39 GF plaster mesh b/n wall rcc col,beam joints 3 days Wed 01-05-13 Fri 03-05-13

40 grill work for Lockups 5 days Sat 04-05-13 Thu 09-05-13

41 GF plumbing work concealed 3 days Wed 01-05-13 Fri 03-05-13

42 GF electric wall conduits concealed 3 days Wed 01-05-13 Fri 03-05-13

43 drainage work all bath and wc 5 days Wed 01-05-13 Mon 06-05-13

44 parapet BBM walls 4 days Mon 15-04-13 Thu 18-04-13

45 GF plaster 18mm outside 18 days Mon 15-04-13 Sat 04-05-13

46 GF plaster 12 mm lime render to walls inside 18 days Sat 04-05-13 Fri 24-05-13

47 GF glazed bath ,wc, kit tiles 8 days Sat 04-05-13 Mon 13-05-13

48 GF flooring inside rooms 18 days Sat 04-05-13 Fri 24-05-13

49 GF door frame procumnt and fixing 5 days Sat 25-05-13 Thu 30-05-13

50 GF Door shutters 8 days Sat 25-05-13 Mon 03-06-13

51 GF electric wiring inside 4 days Sat 25-05-13 Wed 29-05-13

52 GF plumbing inside 2 days Tue 14-05-13 Wed 15-05-13

53 Kitchen katta and sink fixing 12 days Sat 25-05-13 Fri 07-06-13

54 extrnal drainage work all bath and wc 5 days Thu 16-05-13 Tue 21-05-13

55 Electric Meters LT Line and Street Lamps and TC 45 days Wed 22-05-13 Fri 12-07-13

56 Approach Roads 7 days Sat 13-07-13 Sat 20-07-13

57 Window grill work 7 days Sat 25-05-13 Sat 01-06-13

58 collapseble shutter 3 days Mon 03-06-13 Wed 05-06-13

59 Solar fixing 6 days Thu 06-06-13 Wed 12-06-13

60 Painting inside 45 days Tue 04-06-13 Thu 25-07-13

61 painting outside 15 days Fri 26-07-13 Mon 12-08-13

62 Windows 10 days Fri 26-07-13 Tue 06-08-13

63 painting doors/ shutter grill 15 days Fri 26-07-13 Mon 12-08-13

64 site finishing and handing over 10 days Mon 05-08-13 Thu 15-08-13

09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 182 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13

Task

Progress

Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Rolled Up Progress

Split

External Tasks

Project Summary

Group By Summary

Deadline

Page 1

Project: Project GF Police Station GuldDate: Fri 16-11-12