+ All Categories
Home > Documents > Gas Transmission Costs Report

Gas Transmission Costs Report

Date post: 02-Jun-2018
Category:
Upload: armel-brissy
View: 218 times
Download: 0 times
Share this document with a friend

of 30

Transcript
  • 8/11/2019 Gas Transmission Costs Report

    1/30

    Core Energy Group 2012 April 2012 i

    Gas Transmission Costs

    April 2012

  • 8/11/2019 Gas Transmission Costs Report

    2/30

    Gas Transmission Costs Disclaimer

    Core Energy Group 2012 April 2012 i

    Terms of Use

    This document has been prepared by Core Energy Group Pty Limited, A.C.N. 110 347 085, holder of AFSL 307740 (Core )

    for the sole purpose of providing the AEMO with an analysis of the gas transmission costs for eastern Australia as at 1

    January 2012.

    This document has been prepared on the basis of a specific scope and does not purport to contain all the information that a

    particular party may require. The information contained in this document is general in nature and may not be appropriate for

    all persons and it is not possible for Core to have regard to the investment objectives, financial situation and particular needs

    of each party who reads or uses this document. It must not be distributed to retail investors. The information is not an

    invitation to invest or deal in any securities and you should seek independent professional advice before making any

    investment decisions.

    Core believes that the information contained in this document has been obtained from sources that are accurate at the time

    of issue, but makes no representation or warranty as to the accuracy, reliability, completeness or suitability of the information

    contained within this document. To the extent permitted by law, Core, its employees, agents and consultants accept noliability (including liability to any person by reason of negligence or negligent misstatement) for any statements, opinions,

    information or matter (expressed or implied) arising out of the information contained within this document.

    Core Energy Group All material in this document is subject to copyright under the Copyright Act 1968 (Commonwealth)

    and international law and permission to use the information must be obtained in advance and in writing from Core.

  • 8/11/2019 Gas Transmission Costs Report

    3/30

    Gas Transmission Costs Table of Contents

    Core Energy Group 2012 April 2012 ii

    Table of Contents

    Terms of Use ............................................................................................................................................................................ i

    List of Tables and Figures .............................................................. ................................................................ ........................ iii

    List of Tables .................................................................................................................................................................................................. iii

    List of Figures ................................................................................................................................................................................................. iii

    1.

    Introduction .................................................................. .................................................................... ......................... 1

    2. Background....................................................................................... ..................................................................... .... 1

    3.

    Scope ......................................................................................................................................................................... 1

    4.

    Methodology ......................................................................................................................... .................................... 2

    5.

    Relationship Between Pipeline Costs and Tariffs ............................................................... .................................... 3

    5.2.

    Illustrative Calculation of Tariff ........................................................................................................................................................ 5

    5.3.

    Relative Composition of Pipeline Tariffs ......................................................................................................................................... 5

    6.

    Major Existing Pipelines ....................................................................... ................................................................ .... 7

    6.1. Location Overview .......................................................................................................................................................................... 7

    6.2. Existing Pipeline Profiles ................................................................................................................................................................. 8

    6.3. Cost Projections .............................................................................................................................................................................. 9

    7.

    Major Proposed Domestic Pipelines ........................................................................ .............................................. 13

    7.1.

    Location Overview ........................................................................................................................................................................ 13

    7.2.

    Proposed Domestic Pipeline Profiles ............................................................................................................................................ 14

    7.3. Cost Projections ............................................................................................................................................................................ 15

    8.

    Major Proposed LNG Pipelines ........................................................... ................................................................... 17

    8.1. Proposed LNG Pipeline Profiles .................................................................................................................................................... 17

    8.2. Cost Projections ............................................................................................................................................................................ 18

    9.

    New Pipelines ..................................................................... ................................................................. .................... 20

    10.

    Validation of Capital and Non-Capital Expenditure ............................................................................................. 21

    10.1. Capital Expenditure ....................................................................................................................................................................... 21

    10.2.

    Non-Capital Expenditure................................................................................................................................................................ 24

    10.3. Tariffs ............................................................................................................................................................................................ 25

  • 8/11/2019 Gas Transmission Costs Report

    4/30

    Gas Transmission Costs List of Tables and Figures

    Core Energy Group 2012 April 2012 iii

    List of Tables and Figures

    List of Tables

    Table 6.1: Existing Transmission Pipelines ............................................................................................................ ............... 8

    Table 6.2: Existing Pipelines Near Term Planned Expansions ................................................................ .......................... 9

    Table 6.3: Existing Pipelines Forward Non-Capital Costs ............................................................... ................................... 10

    Table 6.4: Existing Pipeline Tariffs ................................................................ ....................................................................... 12

    Table 7.1: Planned and Proposed Transmission Pipelines .................................................................... ............................. 14

    Table 7.2: Proposed Domestic Transmission Pipelines Estimated Capital Cost ........................................................... 15

    Table 7.3: Proposed Domestic Transmission Pipelines Estimated Non-Capital Costs ................................................. 16

    Table 8.1: Proposed LNG Gas Transmission Pipelines................................................................................ ....................... 17

    Table 8.2: Proposed LNG Gas Transmission Pipelines - Estimated Capital Cost ............................................. ............... 18

    Table 8.3: Proposed Domestic Transmission Pipelines Non-Capital Costs ...................................................................... 19

    List of Figures

    Figure 5.1: Typical Pipeline Construction Sequence ............................................................................................................ 4

    Figure 5.2: Revenue Composition of Transmission Pipelines ............................................... .............................................. 6

    Figure 6.1: Existing Gas Transmission Pipelines ................................................................................................... ............... 7

    Figure 7.1: Committed and Proposed Domestic Gas Transmission Pipelines ................................................................. 13

    Figure 10.1: Capital Cost per Kilometre Proposed LNG Gas Transmission Pipelines ......... ......................................... 21

    Figure 10.2: Capital Cost per Kilometre Proposed Domestic Gas Transmission .......................................................... 22

    Figure 10.3: Non Capital Costs per km ............................................................... ................................................................. 24

    Figure 10.4: Effective Gas Transmission Pipeline Tariff ..................................................................................................... 25

  • 8/11/2019 Gas Transmission Costs Report

    5/30

    Gas Transmission Costs 1. Introduction

    Core Energy Group 2012 April 2012 1

    1. IntroductionThe objective of this report is to present certain projections of gas transmission cost for defined pipelines in east and south

    eastern Australia as at 1 January 2012.

    2. BackgroundIn March 2012 Core Energy was engaged by AEMO to support the development of six defined elements of the 2012 Gas

    Statement of Opportunities (GSOO), including this element; the scope of which is set out below.

    3. ScopeThe scope agreed between Core Energy and AEMO for this element of the engagement, as incorporated in the final

    executed agreement, is presented below:

  • 8/11/2019 Gas Transmission Costs Report

    6/30

    Gas Transmission Costs 4. Methodology

    Core Energy Group 2012 April 2012 2

    4. MethodologyCore Energy has developed a seven part process to ensure the delivery of accurate/ high quality information to AEMO.

    Review existing CoreEnergy gas transmission

    databases and references

    Construct spreadsheetframework to address totalneeds of AEMO, includingall technical assumptions

    for each proposed pipelineand relevant existing

    pipelines

    Submit spreadsheetframework and exampledata to AEMO to confirm

    consistent with needs

    Conduct thoroughresearch to populate all

    cost information bypipeline, working with AWT

    Develop and run cash flowmodels to derive

    breakeven capital andoperating costs at10% and

    0% WACC.

    Submit progress reports toAEMO to ensure

    satisfaction and submitfinal draft spreadsheet for

    review

    Prepare draft report,submit for review, finalise

    report incorporating AEMOcomments, together with

    final spreadsheet andreferences

  • 8/11/2019 Gas Transmission Costs Report

    7/30

    Gas Transmission Costs 5. Relationship Between Pipeline Costs and Tariffs

    Core Energy Group 2012 April 2012 3

    5. Relationship Between Pipeline Costs and Tariffs

    The cost of transmitting gas from one point to another is captured by the tariffs charged by pipeline operators to customers.

    Generally, pipeline tariffs are reflective of an objective of the pipeline owners to recover the costs of constructing, operating

    and maintaining the pipeline, as well as make a return on their investment.

    For existing regulated or covered pipelines, tariffs are usually determined on a periodic basis by the Australian Energy

    Regulator (AER) through approved access arrangements. The basis of the determination of tariffs is the building block

    approach, which applies the net present value (NPV) methodology as permitted by Section 8.4 of the Gas Code, to

    estimate the total annual revenue / tariffs that service providers will require over the regulatory period to provide its investors

    with a reasonable rate of return commensurate with the business risks involved and to allow the service providers to meet

    efficiently incurred costs relevant to providing the regulated services.

    The building block approach involves projecting the following types of costs or building blocks for each year of a regulatory

    period:

    Indexation of the regulatory asset base (RAB );

    Return on capital;

    Depreciation;

    Estimated cost of corporate income tax;

    Revenue increments or decrements resulting from the operation of an incentive mechanism; and

    Forecast operating expenditure, including unaccounted for gas.

    RAB

    The RAB serves two purposes:

    To establish the asset base upon which a rate of return must be earned in any period; and

    To form the basis for calculating the regulatory depreciation charge over any period.

    The RAB equals initial asset base plus capital expenditure less regulatory depreciation, plus asset revaluation less

    disposals. The initial asset base is based on the capital cost of the infrastructure for a facility, or the commercial fair value,

    derived using principles set out in the Gas Code.

    The costs incurred in the construction of a transmission pipeline are ordinarily the major contributor to the asset base. The

    following figure illustrates the various stages of a typical pipeline construction sequence and hence draws attention the

    various cost elements that should be considered in determining the capital cost base for determining the tariff of potential

    future pipelines.

  • 8/11/2019 Gas Transmission Costs Report

    8/30

    Gas Transmission Costs 5. Relationship Between Pipeline Costs and Tariffs

    Core Energy Group 2012 April 2012 4

    Figure 5.1: Typical Pipeline Construction Sequence

    Source: APA Investor Presentation, Site Visit 2010

    In addition to the pipeline construction costs, a number of other capital expenditure items include pigging, pipeline

    excavation and inspection and compressor overhauls, are included as capital expenditure items.

    Return on Capital

    To calculate the rate of return used, it is common practice to use the weighted average cost of capital (WACC) approach

    based on the capital asset pricing model (CAPM), to arrive at a post-tax rate.

    Regulatory Depreciation

    Regulatory depreciation or return of capital to reflect the gradual recovery of capital costs associated with the project.

    Regulatory depreciation is calculated on a straight line basis.

    Income Tax

    Service Providers are subject to Australian income tax at the statutory corporate tax rate. When setting the annual revenue

    requirement, the Service Providers effective tax rate is considered, which takes into account the impact of accelerated

    depreciation, etc to ensure the correct post-tax rate of return required by investors is achieved.

  • 8/11/2019 Gas Transmission Costs Report

    9/30

    Gas Transmission Costs 5. Relationship Between Pipeline Costs and Tariffs

    Core Energy Group 2012 April 2012 5

    Incentive Mechanisms

    Incentive mechanisms are employed to entice the service provider to pursue efficiencies in the delivery of its service to

    customers. These incentive mechanisms and are commonly based on outperforming operating expenditure forecasts and

    may result in the service provider receiving an increment to revenue in the following Access Arrangement period.

    Operating Expenditure

    Forecast costs are treated as a pass through item in establishing regulated revenues, and include operating and

    maintenance costs, wages and salaries.

    One significant uncontrollable cost is unaccounted for gas (UAG), representing purchases of gas in replacement of gas lost

    in network, commonly as a result of leaking distribution pipes and inaccuracies in gas meters.

    5.2. Illustrative Calculation of Tariff

    Customer usage demand forecasts are used to calculate the reference tariffs and also influence forecast capital and

    operating expenditure.

    Source: APA Group;Access Arrangement Information for Roma to Brisbane Pipeline; 28 February 2007

    5.3. Relative Composition of Pipeline Tariffs

    From the above overview of the building block approach, it can be understood that the calculated tariffs are reflective of a

    number of different cost components as well as a return on investment. It is therefore interesting to see the breakdown of a

    calculated tariff to understand the relative contribution of each of those components to the final calculated tariff.

    The following figure illustrates the breakdown of the tariffs for the Declared Transmission System (DTS) and Roma to

    Brisbane Pipeline (RBP), amongst components return on capital, depreciation, operating and maintenance and taxation.

    The figure shows that the relative composition of tariffs is materially consistent between the two relevant pipelines

    Year 1 Year 2 Year 3 Year 4 Year 5

    Return on Capital 16.17 16.08 15.86 15.62 15.38

    Non-Capital Costs 8.31 8.28 8.24 8.19 8.14

    Taxation 0.69 0.74 0.79 0.82 0.91

    Depreciation 5.85 6.12 6.19 6.32 6.62

    Less: Capital Contributions - - - - -

    Less: Ancillary Services Revenue - - - - -

    Total Revenu e (AUDm) 31.01 31.22 31.08 30.94 31.06

    Projected Demand (PJ / a) 51.1 56.5 57.3 57.5 57.7

    Calcul ated Tariff (AUD / GJ) 0.55

  • 8/11/2019 Gas Transmission Costs Report

    10/30

    Gas Transmission Costs 5. Relationship Between Pipeline Costs and Tariffs

    Core Energy Group 2012 April 2012 6

    Figure 5.2: Revenue Composition of Transmission Pipelines

    Source: ACCC, Revised access arrangement by GasNet Australia Ltd for the principal transmission system, final decision, April 2008; and ACCC, Revisedaccess arrangement by APT Pipelines Ltd for the Roma to Brisbane Pipeline, final decision, December 2006.

    46%

    28%

    26%

    Revenue composi tion for the DeclaredTransmission System

    2008 - 12

    Return on Capital

    Depreciation

    Operating andmaintenance

    Tax

    48%

    21%

    29%

    2%

    Revenue composi tion fo r the Roma toBrisbane Pipeline

    2007 - 11

    Return on Capital

    Depreciation

    Operating andmaintenance

    Tax

  • 8/11/2019 Gas Transmission Costs Report

    11/30

    Gas Transmission Costs 6. Major Existing Pipelines

    Core Energy Group 2012 April 2012 7

    6. Major Existing Pipelines

    6.1. Location Overview

    The following map provides an overview of all existing gas transmission pipelines in eastern and south eastern

    Australia.

    Figure 6.1: Existing Gas Transmission Pipelines

    Source: Core Energy Group.

  • 8/11/2019 Gas Transmission Costs Report

    12/30

    Gas Transmission Costs 6. Major Existing Pipelines

    Core Energy Group 2012 April 2012 8

    6.2. Existing Pipeline Profiles

    Key features of these pipelines are summarised in the following table:

    Table 6.1: Existing Transmission Pipelines

    Source: Core Energy Group.

    A brief description of each processing pipeline is presented in Attachment 3 to the Item 1 report, Review of Facilities:

    Existing and New.

    1AEMO; Gas Statement of Opportunities; 2011

    2APA Group website.

    3Jemena website.

    4APA Group website.

    5Epic Energy website.

    6APA Group website.

    7http://www.ghd.com/PDF/NthQldGasPipelin%20ProjectSheet.pdf

    8APA Group website.

    9Jemena website.

    10APA Group website.

    11APA Group website.12

    SEA Gas Pipeline website.13

    AER; State of the Energy Market; 200914

    Tasmania Gas Pipeline website.

    Pipeline

    ExistingCapacity

    (TJ / d)

    Length

    (km)

    Diameter

    (mm)1

    Start Node End NodeRegulation

    Status

    Carpentaria Gas Pipeline2 108 840 150, 300 Ballera Mt Isa Light

    Eastern Gas Pipeline3 268 797 450 Longford Sydney Not Covered

    Longford to Melbourne Gas Pipeline4 1,030 174 500, 750 Longford Melbourne Covered

    Moomba to Adelaide Pipeline System(MAPS)

    5

    253 1,185 150, 200,550

    Moomba Adelaide Not Covered

    Moomba to Sydney Pipeline System(MSP)

    6

    439 1,300 150, 200,250, 300,450, 850

    Moomba Sydney Covered

    North Queensland Gas Pipeline7 108 392 254 Moranbah Townsville Not Covered

    NSW - Victoria Interconnect8 71 to NSW,

    92 to VIC88 450 Wagga

    WaggaAlbury Not Covered

    Queensland Gas Pipeline (QGP)9 142 627 200, 300 Wallumbilla Gladstone Not Covered

    Roma to Brisbane Pipeline (RBP)10

    219 438 250, 300,400

    Wallumbilla Brisbane Covered

    South East Australia (SEA) GasPipeline

    11

    314 680 350, 450 PortCampbell

    Adelaide Not Covered

    South West Pipeline12

    353 150 500 Iona Portland Covered

    South West Queensland Pipeline13

    385 937 400 Wallumbilla Moomba Not Covered

    Tasmania Gas Pipeline14

    129 734 150, 200,

    350

    Longford Hobart Not Covered

  • 8/11/2019 Gas Transmission Costs Report

    13/30

    Gas Transmission Costs 6. Major Existing Pipelines

    Core Energy Group 2012 April 2012 9

    6.3. Cost Projections

    6.3.1. Capital Costs

    At the date of this report, the following table provides an estimate of forward capital costs for existing transmission pipelines:

    Table 6.2: Existin g Pipelin es Near Term Planned Expansions

    Source: Bureau of Resources and Energy Economics; Core Energy Group.

    15APA Group website.

    16Bureau of Resources and Energy Economics, Mining Industry Major Projects October 2011, November 2011.17

    Jemena website.18

    Ibid.19

    Hastings Diversified Utilities Fund; SWQP Santos Backhaul Contract Announcement.

    PipelineExisting Capacity

    (TJ / d)Planned Expansion

    EstimatedExpansion Timing

    Capital Cost

    (AUDm)

    Carpentaria Gas Pipeline 108

    Eastern Gas Pipeline 268

    Longford to Melbourne Gas Pipeline 1030

    Moomba to Adelaide Pipeline System 253

    Moomba to Sydney Pipeline System15

    439 5 year program toincrease wintercapacity by 20%.

    Prior to winter 2013. 10016

    North Queensland Gas Pipeline 108

    NSW - Victoria Interconnect 71 to NSW, 92 toVIC

    Queensland Gas Pipeline 142

    Roma - Brisbane Pipeline17

    219 10% capacityexpansion additionalcompressor at Dalbyand duplication of6km

    To be completed 2H2012.

    5018

    South East Australia Gas Pipeline 314

    South West Pipeline 353

    South West Queensland Pipeline 385 Backhaul 52 TJ / d19

    30

    Tasmania Gas Pipeline 129

  • 8/11/2019 Gas Transmission Costs Report

    14/30

    Gas Transmission Costs 6. Major Existing Pipelines

    Core Energy Group 2012 April 2012 10

    6.3.2. Non-Capital Costs

    At the date of this report, the following table provides an estimate of forward real non-capital costs for existing transmission

    pipelines:

    Table 6.3: Existing Pipelines Forward Non-Capital Costs

    Source: APA Group; Core Energy Group.

    * Insufficient publicly available information from which to derive estimates of non-capital costs, e.g. tariffs, etc.^ Non-capital costs as a percentage of revenue were determined, from available information, to average approximately 26%. On this basis, with knowninformation regarding pipeline tariffs, lengths and capacity, non-capital costs were estimated.^^ Non-capital costs were determined as a percentage of revenue (estimated to be approximately 26%) and calculated through an extrapolation of publiclyavailable pipeline tariff data, pipeline length and capacity. These costs are exclusive of marketing and system administration costs.

    A closer analysis of the above table identifies that between existing transmission pipelines, even when compared on an AUD

    per kilometre basis in order to remove the impact of length on cost, there exists material variances between the non-capital

    costs. The following is an analysis of the primary factors giving rise to those variances:

    Moomba to Sydney Pipeline ( MSP )

    Compared to a number of other similar pipelines, for example MAPS and the Roma-Brisbane Pipeline, the MSP has

    relatively lower operating and maintenance costs due to its lower level of compression and fuel usage for compression.

    Longford to Melbourne Pipeline and South West Pipeline (Declared Transmission System)

    The non-capital cost assumptions for the Longford to Melbourne Pipeline and South West Pipeline are derived from costs

    incurred and extrapolated over the entire length of the Declared Transmission System (DTS). The inputs into these

    estimations were sourced from the access arrangement of the owner, APA Group.

    In Cores view, based on discussion on the comparison of the DTS to other transmission pipeline systems taken from

    various access arrangement decisions, a primary driver of the higher non-capital costs of the operator, as relating to the

    DTS, is the added complexity of the integrated Victorian system due to factors such as grid arrangement and volatility of gas

    flow through the system.

    20ACCC;Access Arrangement Information for Roma Brisbane Pipeline; March 2007.

    21Ibid.

    22Ibid.

    PipelineCapacity

    (TJ / d)

    Length

    (km)Non-Capital Costs

    (AUD / km)

    Carpentaria Gas Pipeline 108 840 14,057^

    Eastern Gas Pipeline 268 797 30,500^

    Longford to Melbourne Gas Pipeline 1030 174 45,270^^

    Moomba to Adelaide Pipeline System 253 1,185 17,50020

    Moomba to Sydney Pipeline System 439 1,300 10,00021

    North Queensland Gas Pipeline 108 392 *

    NSW-Victoria Interconnect 71 to NSW, 92 to VIC 88 *

    Queensland Gas Pipeline 142 627 11,060^

    Roma - Brisbane Pipeline 219 438 12,40022

    South East Australia Gas Pipeline 314 680 17,000^

    South West Pipeline 353 150 20,655^

    South West Queensland Pipeline 385 937 14,000^

    Tasmania Gas Pipeline 129 734 12,300^

  • 8/11/2019 Gas Transmission Costs Report

    15/30

    Gas Transmission Costs 6. Major Existing Pipelines

    Core Energy Group 2012 April 2012 11

    Another specific factor relating to the Longford to Melbourne Pipeline is its capacity, being tasked with supplying much of

    Victorias indigenous gas; the pipeline has a capacity of approximately 1,030 TJ per day. With increased pipeline diameter to

    handle higher volumes of gas throughput, the Longford to Melbourne Pipeline requires higher levels of operating and

    maintenance expenditure per kilometre than pipelines of a lesser size and capacity.

    Eastern Gas Pipeline (EGP )It should be noted that non-capital costs of pipelines were estimated as a percentage of revenues (approximately 26%)

    based on the indicative revenue composition of a number of existing pipelines for which that information was made publicly

    available including MAPS, MSP and the RBP.

    The EGP can be distinguished from those pipelines firstly by its age the EGP was constructed in 2000, whilst those

    aforementioned pipelines were constructed during the late 1960s and early 1970s. Accordingly, the revenue calculation of

    those pipelines is likely to comprise a greater non-capital cost component due to the substantially depreciated nature of

    capital costs. A newer pipeline such as the EGP on the other hand is likely to be characterised by non-capital costs

    comprising a less significant proportion of the revenue calculation relative to depreciation and return on capital.

    In further support of this, in its application for coverage of the EGP in 2000, the National Competition Council made

    submissions to the effect that the EGP would be characterised by high construction costs and low operating costs.23

    In light of the above, the estimated non-capital costs per kilometre for EGP may not necessarily be indicative and should

    therefore be construed with care.

    Roma-Brisbane Pipeline ( RBP)

    It should be noted that this non-capital costs per kilometre figure published by APA Group represents total pipeline length,

    rather than route distance. The RBP is unique in the eastern Australian gas market in that it is characterised by extensive

    looping almost along its entirety. Although there are some non-capital costs that are dependent on overall pipeline length as

    opposed to route length, for example intelligent pigging costs, there are a range of costs that can be shared by pipeline

    loops, for example easement patrols. Accordingly the RBP compares favourably to a pipeline such as the MAPS, which has

    similar compression requirements, on a non-capital cost per kilometre basis.

    23National Competition Council;Application for Coverage of the Eastern Gas Pipeline; June 2000.

  • 8/11/2019 Gas Transmission Costs Report

    16/30

    Gas Transmission Costs 6. Major Existing Pipelines

    Core Energy Group 2012 April 2012 12

    6.3.3. Access Tariffs

    At the date of this report, the following table provides an estimate of tariff charges for existing transmission pipelines that are

    covered or for which tariff information has been otherwise made publicly available:

    Table 6.4: Existing Pipeline Tariffs

    Source: Core Energy Group.

    * Current publicly available tariff components data unavailable.

    24NERA; The Gas Supply Chain in Eastern Australia ; June 2007.

    25APA Group website.

    26Jemena website.

    27NERA; The Gas Supply Chain in Eastern Australia ; June 2007.

    28Epic Energy; MAPS Key Commercial Terms; 2011.

    29Ibid.

    30APA Group website.

    31Ibid.

    32Jemena website.

    33Ibid.

    34Ibid.35

    AUD0.63 per GJ in 2006 per Epic Energy; Application by Epic Energy to Revoke Coverage of the Moomba-Adelaide Pipeline; 3 May2005. Inflated by CPI ~2.5% p.a.36

    AER; State of the Energy Market; 2009.

    PipelineCapacity

    (TJ / d)

    Length

    (km)

    CapacityCharge

    (AUD / GJ)

    CommodityCharge

    (AUD / GJ)

    Tariff AEMC Jan

    2007

    (AUD / GJ)24

    IndicativeTariff

    (AUD / GJ)

    Carpentaria Gas Pipeline 108 840 * 1.4425

    1.44 1.44

    Eastern Gas Pipeline 268 797 * Firm: 1.1642

    Non-Firm:1.5135

    26

    1.04 1.16

    Longford to Melbourne Gas Pipeline 1030 174 * * 0.23 0.2427

    Moomba to Adelaide Pipeline System 253 1,185 0.513928

    0.136129

    0.55 0.65

    Moomba to Sydney Pipeline System 439 1,300 0.832530

    0.0469331

    0.68 0.88

    Queensland Gas Pipeline 142 627 * Firm: 0.8993Non-Firm:1.6128

    32

    0.90

    Roma - Brisbane Pipeline 219 438 0.474233

    0.031734

    0.05 0.51

    South East Australia Gas Pipeline 314 680 * * 0.72 0.7335

    South West Pipeline 353 150 * * 0.24 0.27

    South West Queensland Pipeline 385 937 * * 0.85 0.96

    Tasmania Gas Pipeline 129 734 * * 1.85 2.0036

  • 8/11/2019 Gas Transmission Costs Report

    17/30

    Gas Transmission Costs 6. Major Proposed Domestic Pipelines

    Core Energy Group 2012 April 2012 13

    7. Major Proposed Domestic Pipelines

    7.1. Location Overview

    The following map provides an overview of all committed and proposed domestic gas transmission pipelines in

    eastern and south eastern Australia.

    Figure 7.1: Committed and Proposed Domestic Gas Transmis sion Pipeli nes

    Source: Core Energy Group.

  • 8/11/2019 Gas Transmission Costs Report

    18/30

    Gas Transmission Costs 6. Major Proposed Domestic Pipelines

    Core Energy Group 2012 April 2012 14

    7.2. Proposed Domestic Pipeline Profiles

    Key features of these pipelines are summarised in the following table:

    Table 7.1: Planned and Proposed Transmissio n Pipelines

    Source: Various and Core Energy Group.

    * No specifications publicly available.

    A brief description of each processing pipeline is presented in Attachment 3 to the Item 1 report.

    37Bureau of Resources and Energy Economics, Mining Industry Major Projects October 2011, November 2011.

    38Eastern Star Gas, Coolah to Newcastle Pipeline Preliminary Environmental Assessment.

    39ERM; Environmental Assessment Young to Wellington Gas Pipeline; May 2010.

    40Energy World Corporation;Annual Report 2011.

    41Ibid.

    42Galilee Energy;AGM Presentation; November 2010.

    43AGL; Gloucester Gas Project Environmental Assessment; November 2009.

    44AGL website.

    45Origin Energy; Ironbark Project Initial Advice Statement; October 2011.

    46NSW Dept of Planning; Liddell Pipeline North South Route Major Project Assessment; June 2009.

    47NSW Dept of Planning; Liddell Pipeline East West Route Major Project Assessment ; July 2009.48

    Metgasco; The Lions Way Pipeline Brochure.49

    Hunter Gas Pipeline; Queensland Hunter Gas Pipeline Environmental Assessment; September 2008.50

    Eastern Star Gas; Narrabri CSG Project Preliminary Environmental Assessment; September 2010.

    PipelineCapacity

    (TJ / d)

    Length

    (km)Start Node End Node Status

    37

    Coolah to NewcastlePipeline

    38

    >400 280 Gunnedah Newcastle Advanced

    ERM Wellington Pipeline39

    * 219 Young Wellington Advanced

    EWC Pipeline (Surat /Bowen)

    40

    * 350 * Abbot Point / HayPoint

    Publiclyannounced

    EWC Pipeline (Gilmore /Eromanga)

    41

    * 550 * Abbot Point / HayPoint

    Publiclyannounced

    Galilee to BarcaldinePipeline

    42

    * 80 * Barcaldine Publiclyannounced

    Gloucester CSG Pipeline43

    40 - 60 95 100 Stratford Hexham Advanced

    Hunter Gas ProjectPipeline

    44

    96 Hunter Valley Newcastle Publiclyannounced

    Ironbark Project Pipeline45

    50 - 140 440 Tara Darling DownsPipeline

    Publiclyannounced

    Lidell Gas Pipeline46

    47

    * 76 Various Mines inHunter Valley

    Liddell PowerStation

    Publiclyannounced

    Lions Way Pipeline48

    74 145 Casino Ipswich Advanced

    Queensland Hunter GasPipeline

    49

    230 - 450 825 Wallumbilla Newcastle Advanced

    Wallumbilla to GunnedahGas Pipeline

    50

    * 850 Gunnedah Wallumbilla orQGP

    Publiclyannounced

  • 8/11/2019 Gas Transmission Costs Report

    19/30

    Gas Transmission Costs 6. Major Proposed Domestic Pipelines

    Core Energy Group 2012 April 2012 15

    7.3. Cost Projections

    7.3.1. Capital Costs

    At the date of this report, the following table provides an estimate of forward capital costs for proposed domestic

    transmission pipelines:

    Table 7.2: Proposed Domestic Transmission Pipelines Estimated Capital Cost

    Source: Various and Core Energy Group

    * No specifications publicly available.

    **Capital cost estimated by Core Energy Group due to lack of publicly available cost estimates. Please refer to subsection 10.1 for basis of calculation.

    51Bureau of Resources and Energy Economics, Mining Industry Major Projects October 2011, November 2011.

    52Ibid.

    53Ibid.

    54Ibid.

    55NSW Dept of Planning; Liddell Pipeline North South Route Major Project Assessment; June 2009.56

    NSW Dept of Planning; Liddell Pipeline East West Route Major Project Assessment ; July 2009.57

    Bureau of Resources and Energy Economics, Mining Industry Major Projects October 2011, November 2011.58

    Ibid.

    PipelineLength

    (km)

    Diameter

    (inches)

    Operating Pressure

    (MPa)

    Estimated CapitalCost

    (AUDm)

    Coolah to Newcastle Pipeline 280 * * 252**

    ERM Wellington Pipeline 219 20.3 15.3 20051

    EWC Pipeline (Surat / Bowen) 350 N/A * 58352

    EWC Pipeline (Gilmore / Eromanga) 550 N/A * 91653

    Galilee to Barcaldine Pipeline 80 * * 72**

    Gloucester CSG Pipeline 95 100 18 15.3 50 - 80

    54

    Hunter Gas Project Pipeline 96 * * 87**

    Ironbark Project Pipeline 440 * * 396**

    Lidell Gas Pipeline 76 20 1.05 2555

    56

    Lions Way Pipeline 145 * * 12057

    Queensland Hunter Gas Pipeline(QHGP)

    825 20 15.3 90058

    Wallumbilla to Gunnedah Gas Pipeline 850 * * 765**

  • 8/11/2019 Gas Transmission Costs Report

    20/30

    Gas Transmission Costs 6. Major Proposed Domestic Pipelines

    Core Energy Group 2012 April 2012 16

    7.3.2. Non-Capital Costs

    At the date of this report, there had been limited disclosure with regards to estimates of forward real non-capital costs for

    proposed domestic transmission pipelines, however on the basis of guidance previously provided by the ACCC

    (approximately 2% of replacement cost for uncompressed pipelines); non-capital costs for proposed domestic transmission

    pipelines have been estimated and summarized below:

    Table 7.3: Proposed Domestic Transmission Pipelines Estimated Non-Capital Costs

    Source: Various and Core Energy Group

    ^ Operating costs estimated on the basis of approximate range from 2.0% of replacement cost for uncompressed pipelines as previously prescribed by the

    ACCC as appropriate

    59

    .

    The above figures are intended to be illustrative only and are largely dependent on the capital cost assumptions for each of

    the proposed pipelines. Accordingly, with the exception of the Lidell Gas Pipeline, which is a low pressure pipeline and

    therefore expected to have materially lower operating expenditure requirements, variances in non-capital cost estimates for

    each of the above pipelines is a result of differences in construction cost estimates, which may be a product of timing and

    prevailing market conditions, the maturity of respective project plans and due diligence, and various other factors.

    59ACCC;Access Arrangement Information for Roma Brisbane Pipeline; March 2007

    PipelineLength

    (km)

    Estimated CapitalCost

    (AUDm)

    Estimated Non-Capital Cost

    (AUDm p.a.)^

    Estimated Non-Capital Cost

    (AUD / km)

    Coolah to Newcastle Pipeline 280 252 5.0 18,000

    ERM Wellington Pipeline 219 200 4.0 18,265

    EWC Pipeline (Surat / Bowen) 350 583 11.7 33,300

    EWC Pipeline (Gilmore / Eromanga) 550 916 18.3 33,300

    Galilee to Barcaldine Pipeline 80 72 1.4 18,000

    Gloucester CSG Pipeline 95 100 50 - 80 1.3 13,000

    Hunter Gas Project Pipeline 96 87 1.7 18,125

    Ironbark Project Pipeline 440 396 7.9 18,000

    Lidell Gas Pipeline 76 25 0.5 6,600

    Lions Way Pipeline 145 120 2.4 16,500

    Queensland Hunter Gas Pipeline(QHGP)

    825 900 18.0 21,800

    Wallumbilla to Gunnedah Gas Pipeline 850 765 15.3 18,000

  • 8/11/2019 Gas Transmission Costs Report

    21/30

    Gas Transmission Costs 7. Major Proposed LNG Pipelines

    Core Energy Group 2012 April 2012 17

    8. Major Proposed LNG Pipelines

    8.1. Proposed LNG Pipeline Profi les

    Key features of these pipelines are summarised in the following table:

    Table 8.1: Proposed LNG Gas Transmissio n Pipelines

    Source: Various and Core Energy Group

    * No specifications publicly available.

    A brief description of each processing pipeline is presented in Attachment 3 to the Item 1 report.

    60Australia Pacific LNG; Project Environmental Impact Statement; March 2010.

    61Arrow Energy, Surat to Gladstone Pipeline Project Environmental Impact Statement Executive Summary, July 2009.

    62Arrow Energy;Arrow Bowen Pipeline Project Environmental Impact Statement;March 2012.

    63AEMO; Gas Statement of Opportunities; 2011.

    64Bureau of Resources and Energy Economics, Mining Industry Major Projects October 2011, November 2011.

    65Blue Energy; Review of Operations AGM Presentation; 11 November 2009.66

    Santos; GLNG Project - Envirnmental Impact Statement; March 2009.67

    QGC; Queensland Curtis LNG Environmental Impact Statement; July 2009.68

    http://www.industry.qld.gov.au/lng/projects-queensland.html

    PipelineCapacity

    (TJ / d)

    Length

    (km)Start Node End Node Status

    APLNG Pipeline60

    1,250 362 Miles Gladstone Committed

    Arrow Surat Pipeline61

    490 1,000 470 Surat Basin Gladstone Advanced

    Arrow Bowen Pipeline62

    490 1,000 600 Bowen Basin Gladstone Advanced

    Blackwater to Gladstone Pipeline63

    274 257 Blackwater Gladstone Publiclyannounced

    Central Queensland Gas Pipeline64

    55 137 440 Moranbah Gladstone Advanced

    Galilee to Export Markets65

    * * * Gladstone Publiclyannounced

    GLNG Pipeline66

    630 - 2100 435 Surat / BowenBasins

    Gladstone Committed

    QCLNG Pipeline67

    1,410 334 Miles Gladstone Committed

    Southern Cross LNG Pipeline68

    * 400 * * Publiclyannounced

  • 8/11/2019 Gas Transmission Costs Report

    22/30

    Gas Transmission Costs 7. Major Proposed LNG Pipelines

    Core Energy Group 2012 April 2012 18

    8.2. Cost Projections

    8.2.1. Capital Costs

    At the date of this report, the following table provides an estimate of forward capital costs for proposed LNG transmission

    pipelines:

    Table 8.2: Proposed LNG Gas Transmis sion Pip elines - Estimated Capital Cost

    Source: Core Energy Group, 2012

    * No specifications published, however to estimate capital cost, Core have assumed internal diameter of approximately 20 inches and operating pressure of15.3MPa.

    **Capital cost estimated by Core Energy Group due to lack of publicly available cost estimates. Please refer to subsection 10.1 for basis of calculation.

    69Australia Pacific LNG; Project Environmental Impact Statement; March 2010.

    70Estimate sourced from a former project engineer involved in the contract award of the APLNG pipeline contract.

    71Arrow Energy, Surat to Gladstone Pipeline Project Environmental Impact Statement Executive Summary, July 2009.

    72Bureau of Resources and Energy Economics, Mining Industry Major Projects October 2011, November 2011.

    73Arrow Energy;Arrow Bowen Pipeline Project Environmental Impact Statement;March 2012.

    74Ibid.

    75AEMO; 2011 Gas Statement of Opportunities

    76Bureau of Resources and Energy Economics, Mining Industry Major Projects October 2011, November 2011.

    77Ibid.

    78Ibid.

    79Santos; GLNG Project - Environmental Impact Statement; March 200980

    Penn Energy; Saipem Wins Gladstone LNG Pipeline Work in Australia; 17 January 201181

    QGC; Queensland Curtis LNG Environmental Impact Statement; July 200982

    Estimate sourced from a former project engineer involved in the contract award of the QCLNG pipeline contract.

    PipelineLength

    (km)

    Diameter

    (inches)

    OperatingPressure

    (MPa)

    ConstructionLabour

    (ppl)

    Estimated CapitalCost

    (AUDm)

    APLNG Pipeline69

    362 42.0 15.3 800 1,25070

    Arrow Surat Pipeline71

    470 26.4 * 450 60072

    Arrow Bowen Pipeline73

    600 42.0 * 693 1,20774

    Blackwater to GladstonePipeline

    75

    257 24.4 * * 321**

    Central Queensland Gas

    Pipeline76

    440 * * 25077

    47578

    Galilee to Export Markets * * * * *

    GLNG Pipeline79

    435 36.4 15.3 * 1,00080

    QCLNG Pipeline81

    334 42.0 10.2 450 1,10082

    Southern Cross LNGPipeline

    400 * * * 500**

  • 8/11/2019 Gas Transmission Costs Report

    23/30

    Gas Transmission Costs 7. Major Proposed LNG Pipelines

    Core Energy Group 2012 April 2012 19

    8.2.2. Non-Capital Costs

    At the date of this report, there had been limited disclosure with regards to estimates of forward real non-capital costs for

    proposed LNG transmission pipelines, however on the basis of guidance previously provided by the ACCC; non-capital costs

    for the proposed pipelines have been estimated.

    Table 8.3: Proposed Domestic Transmission Pipelines Non-Capital Costs

    Source: Various and Core Energy Group

    ^ Non-capital costs estimated on the basis of approximately 2.0% of replacement cost as previously prescribed by the ACCC as appropriate83

    .

    The above figures are intended to be illustrative only and are largely dependent on the capital cost assumptions for each of

    the proposed pipelines. Variances in non-capital cost estimates for each of the above pipelines is a result of differences in

    construction cost estimates, which may be a product of timing and prevailing market conditions, the maturity of respective

    project plans and due diligence, and various other factors.

    83ACCC;Access Arrangement Information for Roma Brisbane Pipeline; March 2007

    PipelineLength

    (km)

    Estimated CapitalCost

    (AUDm)

    Estimated Non-Capital Cost

    (AUDm p.a.)^

    Estimated Non-Capital Cost

    (AUD / km)

    APLNG Pipeline 362 1,250 25.0 69,000

    Arrow Surat Pipeline 470 600 12.0 25,500

    Arrow Bowen Pipeline 600 1,207 24.1 40,200

    Blackwater to Gladstone Pipeline 257 321 6.4 25,000

    Central Queensland Gas Pipeline 440 475 9.5 21,600

    GLNG Pipeline 435 1,000 20.0 46,000

    QCLNG Pipeline 334 1,100 22.0 65,900

    Southern Cross LNG Pipeline 400 500 10.0 25,000

  • 8/11/2019 Gas Transmission Costs Report

    24/30

    Gas Transmission Costs 8. New Pipelines

    Core Energy Group 2012 April 2012 20

    9. New Pipelines

    For hypothetical new transmission pipelines of varying lengths, AWT provided Core Energy Group with a number of specific

    operating assumptions and pipeline specifications. In addition, Core Energy sourced input information from a number of

    other sources. This information was used to construct detailed economic models to analyse the cost of constructing and

    operating new transmission pipelines, as well as the cost of gas transmission through these pipelines, having relevant

    consideration of returns on capital, depreciation and taxation.

    The following table details the specifications of the modelled pipelines:

    Source: AWT; Core Energy Group

    A full list of references for AEMO information purposes only is included in the spreadsheet titled Item 3 Input Sheet.

    Generally, given identical specifications with the exception of length, an increase in length should result in the gaining of

    some economies of scale. However, in the present case, given the substantial length differential between the two

    hypothetical pipelines, the maintenance of pressure is of significance.

    In the modelling process, the longer pipeline was assumed to also have a larger diameter and thicker walls than the shorter

    pipeline. Generally, pipelines of larger diameter will experience lower degree of pressure loss due to friction than those of

    lesser diameter.

    Had the diameter and wall thickness specifications of the pipelines been consistent, the longer pipeline would demonstrate

    much more significant pressure loss from inlet to outlet, possibly requiring the addition of compressor stations, which are an

    additional cost component.

    The result of the above considerations is an increase in the relative capital and non-capital cost estimates for the longer

    pipeline compared to its shorter hypothetical counterpart.

    PipelineLength

    (km)

    Diameter

    (inches)

    Capacity

    (TJ / d)

    OperatingPressure

    (MPa)

    Non-CapitalCost

    (AUD / km)

    Capital Cost

    (AUDm)

    Capital Cost

    (AUDm / km)

    A 1,000 12 39.2 15.0 21,893 1,033 1.03

    B 500 10 34.1 15.0 18,600 400 0.80

  • 8/11/2019 Gas Transmission Costs Report

    25/30

    Gas Transmission Costs 8. New Pipelines

    Core Energy Group 2012 April 2012 21

    10. Validation of Capital and Non-Capital Expenditure

    10.1. Capital Expenditure

    As a part of AEMOs 2011 National Transmission Network Development Plan (NTNDP), a cost analysis of building gas and

    electricity transmission infrastructure was undertaken, resulting in the provision of indicative cost estimates for gas

    connections over three distances:

    At 100 km, gas connection costs AUD60 120 million;

    At 250 km, gas connection costs AUD150 305 million; and

    At 500 km, gas connection costs AUD305 610 million.84

    The following figures illustrate those capital costs per kilometre of pipeline that have been calculated by Core and those

    previously published by AEMO, compared to a number of proposed pipelines for which estimated capital expenditure

    information has been made publicly available. Figure 10.1 covers LNG gas transmission pipelines and Figure 10.2 covers

    proposed domestic gas transmission pipelines:

    Figure 10.1: Capital Cost p er Kilo metre Proposed LNG Gas Transmis sion Pipelines

    Source: Various; Core Energy Group.

    84AEMO, National Transmission Network Development Plan, December 2011

    0.00

    0.50

    1.00

    1.50

    2.00

    2.50

    3.00

    3.50

    4.00

    APLNGPipeline

    (Contract

    Award)

    QCLNG

    Pipeline

    (Contract

    Award)

    GLNGPipeline

    (Contract

    Award)

    ArrowBowen

    Pipeline

    CentralQLD

    GasPipeline

    EWCPipeline

    (Gilmore/

    Eromanga)

    EWCPipeline

    (Surat/Bowen)

    ArrowSurat

    Pipeline

    Capital Cost (AUDm / km)

    Uncontracted

    Projects Ave:

    AUD1.25m

    /

    km

    Contracted

    Projects Ave:

    AUD3.02m

    /

    km

  • 8/11/2019 Gas Transmission Costs Report

    26/30

    Gas Transmission Costs 8. New Pipelines

    Core Energy Group 2012 April 2012 22

    Figure 10.2: Capital Cost per Kilometre Proposed Domestic Gas Transmission

    Source: Various; Core Energy Group.

    In Figure 10.1, some of the LNG pipelines, namely those relating to the APLNG, GLNG and QCLNG projects had awarded

    engineering and construction contracts to service suppliers at the time of this report. Accordingly, due to greater certainty

    around cost estimates (taken from contract values), these were distinguished from other proposed LNG-related pipelines,

    whose cost estimates were taken at an earlier stage of planning and therefore likely to be less accurate by virtue of depth of

    planning and due diligence undertaken. Some key points to be taken from an analysis of this data include:

    Average capital cost per kilometre for contracted LNG pipelines is AUD3.02m;

    Average capital cost per kilometre for uncontracted LNG pipelines is AUD1.25m; and

    With early planning stage estimates for a number of the proposed LNG-related pipelines, there is room for significant

    upside risk with regards to the construction cost of pipelines as they progress along the planning lifecycle towards final

    investment decisions (FID). Comparing similar projects such as the Arrow Bowen pipeline against the APLNG and

    QGLNG pipelines, there is room for substantial inflation of final costs.

    In Figure 10.2 illustrates the publicly released cost estimates of a number of proposed domestic gas transmission pipelines,

    and alongside these, indicative cost estimates from the NTNDP and Core / AWTs estimated costs for new transmission

    pipeline installations.

    With the exception of the proposed Lidell Gas Pipeline, which is a low pressure pipeline and therefore having substantially

    different specifications to the other pipelines, the average construction cost estimate for these proposed pipelines was

    approximately AUD 900,000 per kilometer.

    These estimates are consistent with the NTNDP indicative estimates; however this may be primarily due to the basis of

    estimation to arrive at those NTNDP values. The NTNDP indicative cost estimates were noted to have been based on

    publicly available information regarding a number of gas transmission pipeline projects commissioned over the past five

    years, including, but not limited to:

    Bonaparte Gas Pipeline;

    Corio Loop (DTS);

    QSN Link (SWQP); and

    0.00

    0.20

    0.40

    0.60

    0.80

    1.00

    1.20

    Queensland

    HunterGas

    Pipeline

    ERM

    Wellington

    Pipeline

    LionsWay

    Pipeline

    Gloucester

    CSGPipeline

    LidellGas

    Pipeline

    NTNDP100

    km

    NTNDP250

    km

    NTNDP500

    km

    NTNDP500

    km

    Compressed

    1,0

    00kmNew

    Pipeline

    500kmNew

    Pipeline

    Capital Cost (AUDm / km)

    Proposed

    Domestic

    Projects Ave:

    AUD0.90m

    /

    km

  • 8/11/2019 Gas Transmission Costs Report

    27/30

    Gas Transmission Costs 8. New Pipelines

    Core Energy Group 2012 April 2012 23

    Young to Wagga Looping Pipeline (MSP).

    The construction of the above-listed projects commenced during the period between 2006 and 2008. At the time of this

    report, since that time, with the exception of the 2008 year during which commodity prices surged before collapsing in the

    aftermath of the global financial crisis, steel prices have increased on average approximately 25 percent (at an approximate

    CAGR of 5 percent)85

    and domestic labour costs in the gas sector have increased approximately 20 percent (at an

    approximate CAGR of 4 percent)86.

    A similar approach was taken by AWT in arriving at assumptions for the construction and operation of new pipelines. That is,

    drawing on recent examples of completed transmission pipeline capital expenditure programs.

    Accordingly, as was the case with proposed LNG-related pipelines, there is a resulting risk that actual construction costs for

    proposed domestic gas transmission pipelines may greatly exceed current estimates.

    85US Bureau of Labor Statistics; Producer Price Index Data; 1967 2012.

    86Australian Bureau of Statistics; Labour Price Index Data.

  • 8/11/2019 Gas Transmission Costs Report

    28/30

    Gas Transmission Costs 8. New Pipelines

    Core Energy Group 2012 April 2012 24

    10.2. Non-Capital Expenditure

    The following figure illustrates the calculated non-capital costs per kilometre of pipeline:

    Figure 10.3: Non Capital Costs per km

    Source: Core Energy, APA Group

    Figure 10.3 above illustrates that the non-capital cost outputs from Core / AWTs modelling of hypothetical new are

    comparable with cost measures for existing transmission pipelines. The indicative non-capital costs are also consistent with

    previous statements by the Australian Competition & Consumer Commission (ACCC) that pipeline non-capital cost should

    be in a range of 2 percent of replacement cost for uncompressed pipelines and 5 percent of replacement cost for

    compressed pipelines87

    .

    Please refer to section 6.3.2 above for detailed commentary regarding the variances observed amongst non-capital costs of

    existing transmission pipelines.

    87ACCC;Access Arrangement Information for Roma Brisbane Pipeline; March 2007

    0

    5,000

    10,000

    15,000

    20,000

    25,000

    30,000

    35,000

    DTS MoombaAdelaide

    DampierBunbury

    MoombaSydney

    GoldfieldsGas

    RomaBrisbane

    AmadeusDarwin

    1000kmNew

    500kmNew

    Non Capital Costs(AUD / km)

    Average:

    AUD17,400

    / km

  • 8/11/2019 Gas Transmission Costs Report

    29/30

    Gas Transmission Costs 8. New Pipelines

    Core Energy Group 2012 April 2012 25

    10.3. Tariffs

    The following figure illustrates the calculated gas transmission tariff per gigajoule per kilometre. In calculating the tariffs for

    the hypothetical new pipelines, the building block method was applied, making allowances for non-capital costs, regulatory

    depreciation, taxation and a return on capital. The specific assumptions are included in the aforementioned spreadsheet

    titled: Item 3 Input Sheet.

    Figure 10.4: Effective Gas Transmis sion Pip eline Tariff

    Source: Core Energy Group; APA Group; ACCC.

    An analysis of the results illustrated in the above figure shows that the calculated transmission costs for new pipelines

    appear to be reasonable compared to the costs of existing transmission pipelines. Reasons for variance include:

    The Tasmania Gas Pipeline is an outlier with a low level of utilization relative to available capacity, requiring increased

    revenues on a gigajoule per kilometre basis;

    The Longford to Melbourne Pipeline and South West Pipeline form part of the DTS and therefore are expected to incur

    greater operating costs by virtue of the added complexity of that system resulting from grid arrangement and volatility of

    flow;

    The SEAGas and Eastern Gas Pipelines are newer pipelines, constructed in the past 10-15 years, and are therefore

    likely to be more comparable to the hypothetical new pipelines in terms of cost structure and also depreciation

    adjustments; and

    The MSP and MAPS have lower tariff charges indicative of older age and therefore lesser depreciation and return on

    capital contributions to the tariff calculations.

    Other specific contributing factors to the calculated hypothetical pipeline tariffs being higher than existing pipelines include:

    Some contingencies assumed in input assumptions for construction and non-capital expenditure; and

    The modeled pipelines have a relatively low throughput capacity given their length. Pipeline length is a significant driver

    of capital and non-capital costs, and therefore in this case there is a potential skewing of the output transmission coststowards the high side.

    0.0000 0.0010 0.0020 0.0030

    Eastern Gas Pipeline

    Moomba to Adelaide

    Moomba to Sydney

    South East Australia

    Tasmania Gas Pipeline

    South West Pipeline

    Roma to Brisbane Pipeline

    Longford to Melbourne

    1000km Hypothetical

    500km Hypothetical

    (A$ per GJ.km)

    WACC Component Depreciation Component O&M Component

    Taxation Component Tariff - Extrapolated at 2012

  • 8/11/2019 Gas Transmission Costs Report

    30/30

    Gas Transmission Costs 8. New Pipelines

    The majority of the comparative pipelines are substantially aged, resulting in a largely depreciated asset base upon

    which the depreciation and return on capital components of the tariff are calculated. The hypothetical pipelines on the

    other hand would be newly constructed at higher material and labour costs than the comparative pipelines at their time of

    construction. This has resulted in an increased contribution from depreciation and return on capital components on the

    required revenue and resulting access tariff.


Recommended