Microsoft Word - Session 14 - Moss Maritime - Iversen,
Oivin.docØivin Iversen &
Roy-Inge Sørensen
Moss Maritime
© Gastech 2005 Iversen & Sørensen 2
Abstract: The single barrier Moss Spherical Tank Design has through
a service period of more than 30 years built up an unparalleled
record regarding safety, reliability and availability.
Nevertheless, as new design tools become available the concept is
continuously being re-examined in search of enhanced safety as well
as improved technical and economical performance. In this paper we
will outline the results of development work carried out during the
last few years. We believe this work has resulted in design
improvements, which makes the Moss design even better able to meet
the future challenges and demands for safe and economical LNG
transport in a world-wide market.
The following key areas will be highlighted:
• Larger Carriers: Large sized LNG projects where larger volumes of
LNG are to be delivered to the same receiving
terminal allows the use of larger LNG carriers. Are there technical
limitations to the size of the carrier? Moss LNG carrier designs
will be presented.
• Alternative propulsion systems: The focus on transportation cost
has made other propulsion systems than the steam plant
interesting.
• Cargo handling: Introduction of the slow-speed diesel engine as
propulsion plant has also pressed forward alternative handling of
the boil off gas. The Moss® Reliquefaction System will be
presented.
• Ship vibrations: Slow-speed diesel engines expose the carrier to
other vibration frequencies. A vibration analysis has therefore
been performed for Moss type LNG carriers.
• Improved operational procedures: New cool-down estimates based on
stress and cargo-handling calculations will be presented.
© Gastech 2005 Iversen & Sørensen 3
1 INTRODUCTION
The original Moss® LNG carrier design incorporated some unique
features: • Single barrier containment • Leak before failure
principle • Full access for external and internal inspection The
result was a containment design which for more than 3 decades in
world-wide operation has shown unparalleled dependability and
availability. The first Moss ship, the Normal Lady was commissioned
in 1973 and is still in service, fulfilling a charter which will
end in 2021. The Lady will then be 48 years old. The steady
improvement in computer software for analysis and simulation since
the 1970’s together with lessons learned from general ship
operation is the basis for design scrutiny and search for
improvements. During the last few years, Moss Maritime has invested
in development work in order to enhance our concept and meet future
requirments from owners and operators. Some results of this work
are described in the paper. Some of these developments and their
advantages are described in this paper.
2 THE BASIS OF THE MOSS TYPE LNG CARRIERS
Advances in design must build on established configurations and
operating experience. Developments should be concentrated in areas
where enhancements seem possible in order to ensure technical and
economical progress. A review of the background and performance of
the Moss type carrier is therefore appropriate before describing
the results of the development work. The international regulatory
situation regarding liquefied gas ships during the period 1960 to
1970 was fragmented and in a state of formation and emergence, to
say the least. Each of the several ship classification societies
had its own rules, with each differing from the others in numerous
important respects. Until 1965 there were no uniform international
rules to be observed for the transport of liquefied gases. In 1965
The US Coast Guard issued a regulation entitled “Navigation and
Vessel Inspection Circular No. 13-65: Foreign Vessels Carrying Bulk
Liquid Cargoes Which Involve Potential Unusual Operating Risks;
Requirements for Plan Review and Inspection”. The logic behind this
regulation which was immediately understood and accepted worldwide,
was that if a hazardous cargo ship had problems in a U.S. port, the
danger was to that U.S. port specifically, regardless of the
vessel’s flag of registry. From then on universal / international
rules for LNG ships were in effect via the Coast Guard’s
regulations and these rules were strictly enforced. Thus, the
international hazardous cargo ships ‘playing field’ was levelled,
and all ship builders and ship owners, irrespective of flag or
class, had to meet the same rules if they intended ever to trade to
the U.S. The Moss design was originated in the late 1960’s and
early 1970’s when overseas LNG transport was in its infancy. Even
though the owners of the first Moss carriers were indeed pioneers
and should be credited for vision and courage, the designers felt
that the design incorporated adequate safety margins. The reason
being that accurate strength analysis methods were available and
extensive testing was carried out. Time has indeed proven the
integrity of the Moss design as a review of available operating
records easily verifies. As of July 2004 the statistics shows the
following: MOSS GT TGZ Other No. of ships in operation 79 56 25 6
Accumulated ship years 1033 716 373 239 Accumulated tank years 4946
3630 1929 ---- Average days unscheduled offhire pr. shipyear 0.4
4.1 1.8 1.4
Table 2-1 Fleet statistics as of July 2004
All ships and tanks of Moss type ever built are still in service.
There is not detected leak from any of the 365 Moss spherical
tanks. Unscheduled offhire for Moss type of ships are significant
lower than for any other LNG ship design.
© Gastech 2005 Iversen & Sørensen 4
0 50
D ay
s of
fh ire
19 72
19 74
19 76
19 78
19 80
19 82
19 84
19 86
19 88
19 90
19 92
19 94
19 96
19 98
20 00
20 02
Figure 2-1 Annual unscheduled offhire
The statistics show that the existing Moss design is reliable and
endurable and all research and development performed have had the
same focus; safety, reliability and availability.
3 LNG CARRIER SIZING
Traditionally the restrictions to the carrier size are due to other
factors than the technological limitations of the ships. It has
been the terminals and the access to these terminals that have
dictated the ship sizes. The Bay of Tokyo has a maximum
displacement restriction of 105 000 tonnes. However, new projects
are being developed, where Energy Majors have interests in all
parts of the LNG chain. Larger carriers giving reduced
transportation costs, which will most probably be dedicated to one
trade through out their lifetime, are of outmost interest. Both the
liquefaction plant and the receiving terminal can be designed for
larger vessels to take advantage of the economy of scale factor.
So, what are the technical limitations to the size of a Moss type
LNG carrier? Theoretically, the largest possible Moss type LNG
carrier will be the defined by the largest possible diameter of the
sphere multiplied by number of tanks. Today, the largest existing
sphere is almost 42 meters in diameter. Carriers with spheres of up
to 46 meters have been approved by class. So, is this the maximum
diameter? We do not believe so. It will be difficult to answer this
question without performing comprehensive analyses of a specific
design. It should be mentioned that for offshore applications
spheres of up to 56 meter in diameter has been evaluated.
3.1 RANGE OF MOSS TYPE LNG CARRIERS
The last years developments have resulted in a range of Moss type
LNG carriers which can meet future demands. All carriers are
designed for 40 years world-wide/20 years North Atlantic operation
and all filling levels.
3.1.1 Moss 147k m3 LNG carrier
A standard 147k m3 Moss type carrier has 4 tanks each with a
diameter of approximately 41.5 meters and a volume of 37 500
m3.
Figure 3-1 147k m3 Moss type LNG carrier
© Gastech 2005 Iversen & Sørensen 5
The main parameter of the 147k m3 design are: • Length, o.a. 289.00
m • Length, p.p. 274.00 m • Breadth, moulded 49.00 m • Depth,
moulded 27.00 m • Draught, design 11.40 m
3.1.2 Moss 200k m3 LNG carrier
Using the sphere diameter as for a 147k m3 LNG carrier with a
vertical cylindrical section above equator additional cargo volume
can be obtained. A design consisting of 5 tanks with a diameter of
41.6 meters, 4 of them with a cylindrical insert has been developed
giving a total carrying capacity of 200 000 m3.
Figure 3-2 200k m3 Moss type LNG carrier
The main parameter of the 200k m3 design are: • Length, o.a. 315.00
m • Length, p.p. 300.00 m • Breadth, moulded 50.00 m • Depth,
moulded 29.00 m • Draught, design 12.00 m
3.1.3 Moss 235k m3 LNG carrier
Extensive analyses have also been performed for larger diameter
spheres. A tank with a diameter of 46 meters has been examined and
approved by Class. Such tank will have a cargo volume of more than
50 000 m3. A concept consisting of 4 such tanks together with one
“standard” 40.44 meters tank has been developed and approved. This
design has a carrying capacity of 235 000 m3.
Figure 3-3 235k m3 Moss type LNG Carrier
The main parameters of the 235k m3 design are: • Length, o.a.
344.90 m • Length, p.p. 328.50 m • Breadth, moulded 55.00 m •
Depth, moulded 32.50 m • Draught, design 12.00 m
© Gastech 2005 Iversen & Sørensen 6
3.1.4 Moss 250k m3 LNG carrier
A further development of the 235k m3 design has also been performed
arriving at the carrying capacity of 250 000 m3. The diameter of
the 4 aft tanks is increased to 47 meters.
The main parameters of the 250k m3 design are: • Length, o.a.
349.40 m • Length, p.p. 333.00 m • Breadth, moulded 57.00 m •
Depth, moulded 32.50 m • Draught, design 13.00 m
3.1.5 Hull performance
When developing new carriers, Moss puts a lot of effort into the
hull design. Shaping of the hull is important for the overall
performance of the carrier. For the range of carriers described
above new twin skeg twin propeller hullforms where developed. No
carrier of today has a twin skeg hull and it was then even more
important for Moss to present hullforms with performance
characterises which could match that of existing carriers.
Therefore, Moss has done extensive test of both the new 147k m3 and
the new 235k m3 hullforms in a model basin. The results of the
tests are presented in figure 3-5.
Theoretically, a hull with twin skeg will have a higher resistance
that a similar hull with single skeg due to a larger wetted
surface. However, a better propulsion efficiency can be obtained
with a twin skeg arrangement. When comparing the new twin skeg 147k
LNG carrier hullform ( white curve) with existing single skeg 137k
LNG carriers (yellow curve) it can be seen that a 10% reduction in
required power is achieved even with a 7% higher cargo
intake.
1 9 .0 1 9 .5 2 0 .0 2 0 .5 2 1 .0 2 1 .5 2 2 .0
S p e e d (k n o ts )
1 4 7 k T w in s c re w d e s ig ns 4 th g e n . 1 4 7 k s in g le
3 rd g e n . 1 3 7 k s ing le s c re w d e s ig n s M o s s 2 3 5 k
T w in
B ra
ke P
ow er
P b
[k W
Figure 3-4 250k m3 Moss LNG carrier
© Gastech 2005 Iversen & Sørensen 7
4 ALTERNATIVE PROPULSION SYSTEMS
4.1 PROPULSION STATUS
Propulsion systems of today’s merchant ships are dominated by
diesel engines. A configuration of a single slow-speed diesel is
the overall preferred choice for high sea shipping of any cargo,
and especially for larger vessels. The configuration of multiple
medium-speed diesels is the preferred choice for passenger vessels,
special trades and short sea shippingi). The steam turbine solution
is the choice only for LNG carriers and naval vessels. Gas turbine
solutions are found mainly in naval vessels and fast ferries. Also
Cruise ships of the latest generation use gas turbines to some
extent. For LNG carriers the propulsion status is that all existing
carriers are equipped with steam propulsion except two small
30-year-old LNG carriers, the Havfru and Century and the new Gaz de
France Energy. Havfru and Century are equipped with diesel engines
while Gaz de France Energy is equipped with a diesel electric
propulsion system. For the LNG carriers in order, the status is as
follows: • 2 carriers with Diesel electric propulsion at Chantier
de l’Atlanique, • carriers with Diesel electric propulsion at
Hyundai Heavy Industries • 8 carriers with slow speed diesel
propulsion at Hyundai Heavy Industries, Samsung and Daewoo.
4.2 ALTERNATIVE PROPULSION SYSTEMS FOR LNG CARRIERS
Alternatives to the traditional steam turbine plant has been
discussed and evaluated for use onboard LNG carriers for decades.
The main reason is the significant difference in thermal efficiency
as shown in figure 4-1 below and as relative fuel consumption in
table 4-1.
PROPULSION TYPE FUEL
CONSUMPTION RELATIVE
CONSUMPTION [g/kWh] [%]
CONV. STEAM PLANT 290 100 COMBINED CYCLE GT 200 69 DIESEL ELECTRIC
200 69 MEDIUM SPEED DIESEL 180 62 SLOW SPEED DIESEL 170 59
Table 4-1 Relative fuel consumption
Source: Man B&W
© Gastech 2005 Iversen & Sørensen 8
All relevant propulsion system alternatives give higher fuel
efficiency than the steam plant. The most interesting alternatives
are: • Slow speed diesels with reliquefaction system • Dual-fuel
diesel electric propulsion • Gas turbines The required power for
propulsion can be generated by single, twin or multiple, fuel or
gas driven, prime movers. The engines can either be directly
coupled to the propeller(s), geared or coupled to an electrical
generator. Single or twin propellers can be chosen. The choice will
depend on economical and operational aspects. Historically, the
assessment of these factors for the option of propulsion technology
have for ordinary larger cargo vessels of the following categories;
container vessels, bulk carriers and tankers, ended at the
selection of a single, heavy fuel-burning, slow speed diesel engine
in more than 90% of contemporary vessels. The LNG carrier is in
fact a large bulk carrier for liquid cargo, operating at somewhat
higher speed. The Moss type LNG carriers described in section 3
have all been design for using slow speed diesels for propulsion.
The arrangements consist of two diesels directly coupled to
separate propeller shafts. However, other types of propulsion
systems can also be installed.
4.3 SLOW SPEED DIESEL PROPULSION
In a diesel engine driven LNG carrier, the energy requirement is
less due to the higher efficiency. So, the supplementary energy by
boil-off or fuel oil can be reduced significantly as shown in
figure 4-2. For a LNG carrier with slow speed diesel propulsion the
natural boil off can be handled by a reliquefaction system as
described in section 6. Moss Maritime has for our new LNG carrier
designs proposed to install two slow speed diesel engines and twin
propeller. Each engine directly coupled to a separate propeller
shaft. Thus, the gear is redundant. The reliability of the slow
speed diesel is also as good as steam propulsion. Statistics from
one particular ship owner, operating both steam propelled LNG
carriers and other single diesel driven merchant ships shows that
the annual unscheduled stoppage at sea is insignificantly
different. The statistics is presented in table 4-2. Applying this
for a twin diesel arrangement will give an availability of the
propulsion plant of close to 100%.
Figure 4-2 Propulsion alternative - energy need for
propulsion
Source: Man B&W
5 VIBRATION ANALYSIS
Installation of slow speed diesel engines as prime mover for
propulsion in LNG carriers means introduction of additional
excitation sources acting on a wide range of frequencies. In order
to disclose unforeseen problems, a detailed investigation of
vibration response of cargo tank structure as well as the global
hull structure has been conducted. The base case to be studied has
been a large carrier with cargo capacity of 235k m3. The design
comprises four spherical cargo tanks with diameter 46 meters and
one smaller tank forward with diameter 41.6 meters. The vessel is
provided with twin skeg afterbody with two, seven cylinder, slow
speed diesel engines installed. Two four bladed, fixed propellers
are directly connected to the propeller shafts. The main parameters
of the vessel is as follows: Hull Length, o.a 344.90 m Length, p.p.
328.50 m Breadth, moulded 55.00 m Depth, moulded 32.50 m Draught,
design 12.00 m Ship speed 20 knots Main Engines Number of sets 2
Type Slow Speed Diesel Engine MAN B&W 7S70MC-C MCR 2 x 19.5 MW
Propellers Number of 2 Number of blades 4 Diameter 7800 mm
Revolutions, max 80 Both full load condition as well as ballast
condition with empty cargo tanks have been assumed. The seven
cylinder engines are considered to represent an optimum
installation for the actual vessel. However, transfer functions
covering all actual categories of excitation forces and moments
have been performed. This makes it possible to estimate vibration
response for alternative number of cylinders as well as different
engine designs. The finite element model of the hull girder with
deck houses and tank covers consist of 24 super elements. The model
is shown on fig. 5-1. The containment system comprising tank shell,
tank skirt and pipe tower consists of abt. 2700 basis elements
sufficient for defining the stiffness of the subject structure.
This element model is illustrated in fig. 5-2.
Table 4-2 Availability of propulsion plant
Steam 99.9% Single Diesel 99.8% Twin diesel: one of two engines
running 100 % Twin diesel: both engines running 99.7% Source: LNG
ship owner/operator
© Gastech 2005 Iversen & Sørensen 10
For a slow speed, 2-stroke diesel engine, the forces and moments
may be divided in the following categories: • Free moments and
forces due to rotating and oscillating parts • Guide force moments
due to reaction forces in the engines crosshead and bearings. The
engine forces were applied as couples to the engine structure as
shown on fig. 5-3. The pressure field from the propellers was
applied as shown on fig. 5-4.
Figure 5-1 Finite element model
Figure 5-2 Model of sphere, skirt and tank
© Gastech 2005 Iversen & Sørensen 11
The different excitation sources, which have been analyzed, are the
following: • 2ndv = 2nd order free moment, vertical • 4thv = 4th
order free moment, vertical • 7thH = 7th order H-moment • 4thX =
4th order X-moment • 4thPr = 4th order propeller excitation In
addition the response was calculated for the 1st order free moments
in vertical and horizontal direction. The vibration levels were
however found to be below 0.1 mm/s, and are not presented. The
inphase and antiphase modes of the two diesel engines have been
investigated. For the present study, phasing of the engines and/or
propellers has not been found necessary for obtaining acceptable
response. However devices are available for keeping the phase
constant between the two propulsion units if found favorable for
other projects. Further, influence by adopting active as well as
inactive top stays have also been evaluated. The response has been
investigated for the following location and type of structure: •
Natural frequency of the hull girder and girder system inside •
Lower tank skirt connection to the foundation deck • Cargo tank
shell structure • Pipe tower tank structure • Tank cover structure
• Top of deckhouse
Figure 5-4 Propeller forces acting on the hull
Figure 5-3 Forces applied to engine structure
© Gastech 2005 Iversen & Sørensen 12
The vibration levels for the various excitation sources have been
compared with the response caused by a normal “good” propeller
design. It is recognized that the response representing the diesel
engines are of the same magnitude or less then the response created
by propellers. It is also acknowledged through long service
experience that Moss LNG carriers equipped with proven and well
adapted propeller designs do not suffer any harm from vibrations.
The overall maximum vibration levels as calculated are presented in
figure 5-5 and 5-6 for loaded and ballasted condition respectively.
The highest vibration levels are caused by local resonance of the
structure and may easy been avoided by minor counter measures if
found necessary.
0
2
4
6
8
10
12
14
16
18
20
22
0
1
2
3
4
5
6
7
8
© Gastech 2005 Iversen & Sørensen 13
6 MOSS RELIQUEFACTION SYSTEM
Reliquefaction systems have been proposed and considered at regular
intervals ever since the building of LNG carriers started in
earnest around 1970. The systems proposed in the past were rejected
due to high cost, complexity and large space requirement. However,
during the last 30 years, the efficiency of diesel-based propulsion
plants has increased dramatically compared with the steam turbine
plants used on LNG carriers. It is now more than 10 years since
Moss Maritime decided to develop a reliquefaction system of their
own that they could offer to their licensing yards. The Moss RS
concept was first presented in 1995. Since then, further
development work has been carried out and the system has been
refined and simplified. Present status Recently, the Qatargas
placed an order for eight large LNG carriers at Daewoo (4
carriers), Hyundai (2 carriers) and Samsung (2 carriers). The order
is part of the Qatargas II project. This is the first order ever of
a LNG carrier equipped with a reliquefaction system and slow speed
diesel engines. It is fair to say that this order inaugurates a new
era for the LNG carrier design. All eight carriers will be equipped
with the Moss Reliquefaction System (Moss RS). Although the
reliquefaction system has already been described in several media,
we feel that the new order mentioned above justifies a brief
presentation of the system here. Reliquefaction concept The Moss
Reliquefaction System is based on a closed nitrogen expansion cycle
extracting heat from the boil- off gas (BOG). Several novel
features such as partial liquefaction, separation of
non-condensables and N2- compressor/expander unit mounted on a
common gear have resulted in a compact system with reasonable power
consumption. The diagram in Figure 6-1 shows the equipment located
in the cargo machinery deckhouse. The reliquefaction plant is
configured with 2x100% Moss RS one cryogenic heat exchanger (cold
box). The 2x100% high duty (HD) compressors are connected to a
combined HD heater and vaporizer. A BOG heater, required in case of
discharge directly from the low duty compressor to the thermal
oxidizer, is not shown in the diagram. The high duty (HD)
compressors and combined HD heater/vaporizer will be used for the
same operations as in conventional LNG carriers. The combined HD
heater and vaporizer are described in more detail in a separate
section.
Figure 6-1 Diagram of the cargo system inside the machinery
deckhouse
© Gastech 2005 Iversen & Sørensen 14
Figure 6-2 shows a model of a cargo machinery deckhouse with
equipment as outlined in Figure 6.1. The nitrogen
compressors/expanders and cold box are located on the first floor
while the BOG compressors, high duty compressors and the combined
high duty heater and vaporizer are located on the second floor. The
nitrogen reservoir is located on the roof of the deckhouse. The
equipment is fitted in a deckhouse with the same “footprint” as a
standard 135.000 m3 Moss LNG carrier.
Figure 6-2 Arrangement of the reliquefaction plant inside the
machinery deckhouse Boil-off gas cycle BOG is removed from the
cargo tanks by means of conventional LD compressors. The LD
compressor discharge pressure is 4.5 bar and the BOG is cooled and
condensed to LNG at this elevated pressure in a 3- stream plate-fin
cryogenic heat exchanger (cold box). Non-condensibles, mainly
nitrogen, are removed from the separator vessel maintained at 4.5
bar and transferred to a thermal oxidizer or other acceptable means
of disposal. From the separator, the LNG is forced or pumped back
to the cargo tanks. Nitrogen cycle The cryogenic temperature inside
the cold box is produced by means of a nitrogen
compression-expansion cycle. Nitrogen at 14 bar with ambient
temperature is compressed in a 3-stage centrifugal compressor. Exit
pressure from the third stage is 57 bar. Three seawater coolers
handle inter-cooling and after-cooling. From here, the gas is
pre-cooled by passing through the warm part of the cold box. It is
then cooled by use of the expander reducing the pressure to 14.5
bar to cryogenic temperature -163ºC. The cooled nitrogen is then
led to the cold part of the cold box where it cools and condenses
the BOG. After having processed the BOG, the nitrogen returns to
the warm part for pre-cooling before it is returned to the nitrogen
compressor. This completes the cycle.
© Gastech 2005 Iversen & Sørensen 15
Technical merits: • The system only uses proven components with
extensive references from air-separation, peak-shaving
plants world-wide. • The onshore LNG production plant at
Snurrevarden, Norway, started production at the beginning of
2003.
This plant operates with a nitrogen/expander unit identical to the
one that will be installed on LNG carriers.
• The total quantity of Btu’s loaded can now be delivered to the
customer. • The LNG nitrogen content is reduced during the voyage,
thus facilitating tank pressure control and
reducing power consumption for the reliquefaction plant. • The
system is prefabricated in skid modules for installation and
hook-up on board. • No increase in cargo machinery space is
necessary. • The system has automatic capacity control. • The
system can be stopped when the cargo pumps are in operation. This
will reduce the need for extra
generator capacity. • Several alternatives of the system can be
offered, all of which fulfil the rule requirement for redundancy. •
No extra personnel are required for operation and maintenance.
Economical merits: • Increased cargo quantity delivered. • Reduced
heel required on ballast voyage • Large savings in total fuel
consumption • Improved propulsion redundancy • More qualified crew
available for handling of the propulsion plant • More flexibility
in contract negotiations
Redundancy Several alternatives of the reliquefaction system can be
offered, all in compliance with the IGC requirements for
redundancy. The alternatives are: • 2x100% Moss RS with one cold
box • 3x50% RS plant with two cold boxes Another alternative to
reliquefaction is using a thermal oxidizer to burn the boil-off
gas. Combining reliquefaction and gas burning gives other
alternatives like: • 1x100% Moss RS and one 100% thermal oxidizer •
2x50% Moss RS plant with one 100% thermal oxidizer • 2x100% Moss RS
with one or two cold boxes, in combination with a thermal oxidizer
The eight LNG carriers mentioned above for the Qatargas II project
are all specified with 2x100% Moss RS with one cold box and one
100% thermal oxidizer. The equipment specified gives a redundancy
above the rule requirement. Operation and control The
reliquefaction unit is equipped for automatic capacity control with
a theoretic turn down to zero capacity in idling mode. The LD
compressor capacity is adjusted automatically in accordance with
the BOR, i.e. pressure control, or it can be operated at a fixed
capacity. Increasing or decreasing the pressure in the nitrogen
cycle controls the plant. Sensors and transmitters provide the
required input signals to a programmable logic controller (part of
the main vessel control system). Conditioned output signals are led
to control valves and inlet guide vane actuators. Start/stop is
manual, but with automatic turndown. Start-up time from warm
condition is 6 hours after pre-cooling with BOG circulation.
Start-up from cold condition will vary from one to six hours.
Dynamic simulation At the beginning of 2004, a comprehensive new
dynamic model was developed in co-operation with Kongsberg Maritime
and Hamworthy Gas Systems for further verification and simulation
of the reliquefaction plan behavior. The main purpose is to confirm
the stability and convergence of the proposed control system and to
check system response to transients such as load changes, warm
start-up, cold start and emergency shut down. The model will also
function as a training platform for operations of the system.
Figure 6-3 shows the operator interface of the model.
© Gastech 2005 Iversen & Sørensen 16
Size range The guaranteed boil off rate (BOR) is traditionally
calculated based on pure methane and maximum filling limit of the
tank. This is also taken as design capacity for the reliquefaction
plant. Before the design capacity is fixed, an evaluation of the
heat ingress from the piping between tanks and reliquefaction plant
and BOR when sailing in rough seas, should be conducted. The
presented reliquefaction system is easy to adapt to new capacities
and will therefore fit LNG carriers of any size. As per today, the
capacity of the Snurrevarden project in Norway is 2500 kg/h and
will for the Qatargas II project be about 5600 kg/h.
7 IMPROVED OPERATIONAL PROCEDURES
7.1 COOL DOWN OF CARGO TANK
Background All LNG carriers with Moss containment systems must
follow a procedure for tank cool down and subsequent loading. The
present restrictions, forming the procedure for tank cool down
(from warm condition), are as follows: • Progressive cool down of
tank by means of LNG spraying before loading starts • When the
average sensor temperature has reached -110°C, loading is permitted
• The time to reach 50% tank filling shall not be less than 6 hours
• Loading can then proceed at a constant rate which corresponds to
full tank after 12 hours It has been recognised that if the
requirement of –110°C at the sensors can be increased, operational
flexibility will improve. The advantages of such a modification
are: • Reduced requirement for the heel • Reduced spraying during
the ballast leg and in the best case no spraying, subject to the
length of ballast
leg as well as ambient temperatures • Reduced cool down time when
commissioning the carrier • Earlier loading start
Figure 6-3 Interface panel of the dynamic model
© Gastech 2005 Iversen & Sørensen 17
A study has therefore been conducted to investigate if it would be
feasible to start loading cargo tanks earlier than accepted in
previous procedures. Basics of the study The operational
restrictions are related mainly to stress levels appearing in the
equatorial groove through transient thermal loads in addition to
gravity loads during the cool down and loading phase. The thermal
analysis has been based on the assumption that the loading of LNG
can start when the average temperature for the sensors in the
equator area is –80 °C, which is 30°C higher than currently
accepted. There are four sensors located on the outside of the tank
skirt. They are equally distributed over the circumference and
located 200 mm below the equatorial plane. The analysis was also
based on the following operational cool down procedure: Spraying
0-6 hours 40 m3/hour Spraying 6-12 hours 20 m3/hours Loading 6-12
hours up to 50% filling Loading 12-18 hours up to 100% filling The
study was performed on the basis of a four-tank LNG carrier with a
cargo capacity of 137 000 m3 and a tank diameter of 40.44 m. The
tank material is aluminium and the supporting skirt is constructed
partly of aluminium, partly of stainless steel and high tensile
mild steel. The cryogenic insulation material is mostly
polystyrene. The transient temperature and stress distributions in
the tank structure, including the equatorial profile, have been
calculated by means of ANSYS Professional Software package. The
ANSYS program is a 3-dimensional element program suitable for
solving non-linear multi-physic problems like complex transient
thermal and mechanical behaviour of all types of structures. The
tank geometry is axis symmetrical about the vertical tank centre.
All other properties like material properties, constraints as well
as the major part of the actual loads are symmetrical around the
same axis. Therefore, it has derived advantages from applying a
fully axis- symmetrical 2-dimensional model. Such analyses will be
as accurate as those created from an equivalent 3- dimensional
model. Material properties as function of temperature are used. The
instant values during the transient temperature progress are
accounted for. The structural modelling is defined and a
calculating mesh is generated in sufficient detail to allow the
program to model the physics of the system. Figure 7-1 shows a
slice model picture of one-half of the tank, including the skirt
and the mesh density used in the groove area of the equator
profile.
Figure 7-1 Geometry of the tank / skirt model in ANSYS
Ta n
k si
sensor location
© Gastech 2005 Iversen & Sørensen 18
Stress basics During cool down, the skirt side of the equatorial
profile groove experiences tensile stresses, whereas during service
with full load, compressive stresses arise. The full-load service
condition includes static as well as dynamic loads on probability
level Q=10-8 (service life 20 years). Consequently, the groove area
is considered to be the most important field to be investigated in
order to verify the extreme stress range. The criterion for
permissible stresses during cool down is a “stress range”
criterion. It means that the total stress variation experienced at
any point in the equator groove, during the lifetime, has to be
within a specified range: σ = /σe /service + /σe /cool down ≤ cF
where: σ is variation in equivalent stress according to von Mises
yield criterion. However, since this stress is always
a positive scalar, it has to be assigned a positive or negative
sign corresponding to the dominant component of the bi-axial
surface stress in the groove.
F is design equivalent stress as defined in the DNV rules and in
the IGC Code. c is a value which is a subject for discussion.
However, in the present study c=2.8 is used. The stresses are
calculated in terms of von Mises equivalent stress criteria versus
time after start of cool-down and up to 28 hours where the tank is
fully loaded and the temperature in the construction is considered
to be close to “steady state” condition. In order to define the
correct sign of the von Mises values, the meridional stresses,
considered to be the dominant stress component, are also
calculated. The value of this component will disclose whether
tensile or compressive stresses is dominant. The maximum service
stresses appearing during the whole service life of the vessel are
also calculated for the same locations as in the cooling down
analysis. The same ANSYS element model is used. The stresses
recorded after 27 hours are representative. At this time, the
temperature in the structure will be close to balance with only
minor adjustments. Further, the loads at the same moment of time
include appropriate accelerations as well as internal overpressure.
The model was not able to absorb interaction forces from the hull.
For this reason, an allowance of 15% was added to the calculated
stress values to verify the correct stress range. This allowance is
based on experience from previous studies. Temperature gradients
The temperature gradients are illustrated in Figures 7-2 to 7-4 for
several locations. The cool down process starts at +25°C and has
implemented the restrictions for cool down as outlined above. The
loading however, starts when the temperature in the equator profile
has reached –80°C, about 5.5 hours after start. The sudden change
in cool down rate occurring after 11 hours is due to the liquid
reaching the level of the equator profile.
Figure 7-2 Transient temperature profile at location of the
sensors
© Gastech 2005 Iversen & Sørensen 19
Figure 7-3 Transient temperature at tank side of groove
Figure 7-4 Transient temperature at skirt side of groove
Illustrations defining typical temperature distribution in the
skirt and shell are shown Figures 7-5 and 7-6.
Figure 7-5 Temperature distribution at part of tank shell/skirt
100% loaded
© Gastech 2005 Iversen & Sørensen 20
Figure 7-6 Temperature distribution at skirt 100% loaded Stress
results Figure 7-7 illustrates the maximum von Mises stresses
appearing in the whole groove area during the complete process,
regardless of the specific location. The stresses are recorded in
MPa units. Part of the curve, representing the time after 24 hours,
records the maximum service condition where the temperature
gradient is considered to be more or less levelled out, and where
the maximum dynamic accelerations are included.
Figure 7-7 Maximum appearing von Mise stress in groove area
© Gastech 2005 Iversen & Sørensen 21
Figures 7-8 and 7-9 illustrate stress plots of von Mises stresses
at various progress phases. The stresses are recorded in Pa
units.
Fig. 7-8 von Mise stresses after 10 hours
Fig. 7-9 von Mise stresses after 20 hours
Ta n
k si
© Gastech 2005 Iversen & Sørensen 22
Conclusion The conclusion is that the stress range margin is
significant, indicating that the present minimum temperature
requirement of –110°C in the equator profile can be increased. The
study paves the way for further work in order to predict
temperature limits and quantify the impact on operations and costs
for a full round trip. Application of the results on existing LNG
carriers The results from this study will in principle be
applicable for existing Moss LNG carriers. However, a separate
study is required for each carrier in order to make sure that the
carrier can increase the loading temperature as outlined in the
present study. In addition, adequate documentation must be prepared
for verification and approval by the classification society.
7.2 COMBINED HIGH DUTY HEAT EXCHANGER
Conventional LNG carriers are equipped with separate heat
exchangers for high duty (HD) LNG vaporising and gas heating. A
simplified flow diagram for the heat exchanger system is shown in
figure 7-10. The high duty heater is operated as part of the
decommissioning and provides the gas heating for the following
operations: 1. Boil down of LNG residual 2. Warm up of the cargo
tanks The LNG vaporizer is operated as part of the commissioning
and general cargo handling. The vaporizer provides the heating
requirements for the following cargo operations. 1. Gassing up the
cargo tanks following inert gas purging 2. Replacement gas while
discharging cargo at full rate in the absence of vapor return from
shore 3. Pressurizing the cargo tanks for emergency discharge, if
appropriate. The above listing shows that the heat exchangers are
dedicated to different operation procedures. Onboard an LNG
carrier, the nature of these procedures excludes simultaneous
operation of the heat exchangers. This allows the installation of
one combined heat exchanger that handles both vaporizing and
superheating of LNG.
Figure 7-10
© Gastech 2005 Iversen & Sørensen 23
A simplified flow diagram for the combined heat exchanger is shown
in Figure 7-11. Moss Maritime has developed and patented such a
combined heat exchanger of shell and tube type, with separate
u-bundles for vaporizing and superheating. The head of the heat
exchanger is fitted with a combined outlet chamber and two separate
chambers for LNG and vapor at the inlet side. The gas temperature
at the exit of the heat exchanger is kept constant at all time by
means of bypass flow control. Steam is used as a heating medium and
is applied on the shell side. The steam supply valve is left fully
open and is not controlled during operation. The combined heat
exchanger can be adapted for any LNG carrier size or design data
specification. A sketch of the heat exchanger is shown in Figure
7-12.
Application of the combined heat exchanger results in a simpler
overall installation. One of the challenges in the present Moss
carrier design has been the cargo machinery room piping
arrangement. This is because the large diameter piping must be
arranged to connect several equipment units, such as compressors
and heat exchangers, in a very concentrated area. During ship
operation, there are many operational modes. This results in
different patterns of thermal loading. Thermal gradients up to
180°C must be accommodated without excessive pipe stress and loads
on equipment nozzles. In addition, the piping must be arranged so
that severe vibrations are avoided at all times. Consequently, many
of the existing carriers have cargo machinery rooms with an
abundance of bellows compensators, spring supports and vibration
dampers. This limits access to valves and instrumentation and
installation and maintenance work is difficult and costly. As a
result of the combined heat exchanger installation, there are fewer
components, and the challenges outlined above are reduced. The
total piping length will be reduced as well as the number of
bellows compensators and spring supports. Vibration dampers can be
omitted. Insulation requirements will also be reduced, and for the
steam side, the number of valves and steam tramps will be halved.
The cargo machinery
Figure 7-12 Combined High Duty Heat Exchanger
Figure 7-11
© Gastech 2005 Iversen & Sørensen 24
room will appear more “organized” with improved access to valves
and instrumentation. The installation and maintenance costs will be
lowered due to the combined heat exchanger. A budgetary cost
comparison between the combined high duty heat exchanger
arrangement and the conventional heat exchanger arrangement
included costs for relevant hardware and installation. The
comparison is based on a 145k m3 LNG carrier. The net savings in
connection with applying the combined heat exchanger solution are
USD 155 000 per vessel.
7.3 SIMPLIFIED BOG SYSTEM
The boil-off gas (BOG) system on conventional LNG carriers consists
of BOG compressor, forcing vaporizer, gas heater and mist
separator. If the steam boilers are operating in the 100% gas mode,
the forcing vaporizer is used to supplement the natural boil off.
Since the BOG compressor is located downstream of the forcing
vaporizer, it must be sized to handle a gas quantity equal to the
full boiler load. This means about 7800 kg/h for a 135,000 m3 LNG
Carrier. However, with zero forcing, which is the most frequently
used operating mode, the compressor will handle only about 3200
kg/h. In other words, the BOG compressor runs more or less
permanently with a turn down of more than 60%. This is not an ideal
arrangement and has led to control problems and operation with
permanently open anti-surge valve. Figure 7-13 shows a simplified
flow diagram for the conventional BOG system.
As for the high duty heater case, Moss Maritime has patented a
combined forcing vaporizer and gas heater. In this unit, LNG for
additional BOG production (forcing) is vaporized and mixed with the
BOG from the cargo tanks to produce a common superheated vapor. The
unit will condition LNG or BOG alone or in any combination up to
the design capacity.
Figure 7-13
© Gastech 2005 Iversen & Sørensen 25
The combined heat exchanger is of shell and tube type, with
separate u-bundles for vaporizing and BOG heating. The head of the
heat exchanger is fitted with a combined outlet chamber and two
separate chambers for LNG and vapor at the inlet side. The gas
temperature at the exit of the heat exchanger is kept constant at
all times by means of bypass flow control. Steam is used as a
heating medium and is applied on the shell side. The steam supply
valve is left fully open and is not controlled during operation.
The combined heat exchanger can be adapted for any LNG carrier size
or design data specification. Figure 7-14 shows a sketch of the
heat exchanger.
Figure 7-15 shows a new arrangement of the BOG system.
Figure 7-14 Combined Low Duty Heat Exchanger
Figure 7-15
© Gastech 2005 Iversen & Sørensen 26
The arrangement is based on use of the patented combined vaporizer
and heater in combination with the BOG compressor located upstream
of the heat exchanger. The BOG compressor handles the boil off
only, unlike the conventional system where the BOG compressor
handles both BOG and forcing vapor. This arrangement means that the
BOG compressor can be sized for the maximum boil-off rate instead
of for combined duty. For a 135 000 m3 LNG carrier, this may for
example be 4 000 kg/h. The normal BOG quantity of 3 200 kg/h will
then be well within the operating envelope with a discharge
pressure of up to 1.9 bara. The advantages with this arrangement
are considerable and for some cases identical to those described
above for the combined high duty heat exchanger. • Smaller BOG
compressor and electric motor • Split range control by speed and
inlet guide vanes are not required • Discharge pressure will be
high enough for easy downstream throttling control • The mist
separator used today can be omitted • Simpler piping arrangements
with fewer supports, insulation and bellows compensators • Reduced
investment cost and improved operational reliability
A budgetary cost comparison between the combined BOG/forcing heat
exchanger arrangement and the conventional heat exchanger
arrangement including cost for relevant hardware and installation
has been conducted. The comparison is based on a 145k m3 LNG
carrier. The net savings by applying the combined heat exchanger
solution are USD 450 000 per vessel.
8 TRANSPORTATION COST ASSESSMENT
A simplified cost assessment of some of the new developments has
been done. The comparison has been made with the basis of the same
cargo tank volume regardless of the propulsion system. There has
been argued that some of the alternative propulsion systems
required reduced engine room length and thus allows for larger
carrying capacity within the same main parameters. However, Moss
together with others believes that this is a very theoretical
approach as a hull can be easily modified to a marginally cost to
obtain the same carrying capacity. Fuel cost: The unit cost of
fuel, whether it is gas or oil, is not constant. The heavy fuel oil
cost fluctuates and is as of 5th January 2005 in the range of
140-230 USD/ton. The cost of Marine Diesel oil is in the range of
330- 470 USD/ton. The cost of fuel differs from port to port. In
this cost assessment the heavy fuel cost is set to 150 USD/ton. The
value to be set for BOG used in the propulsion plant is even more
debated. At the loading port LNG value is defined by the FOB price.
However, the LNG value at the receiving terminal is set by the CIF
cost. Which value shall be used for the BOG? It is our belief that
all LNG loaded on a carrier and not used for propulsion can be sold
to CIF cost, and that is what should be used to define the BOG
value. The results from the cost comparison are given in figure
8-1.
Mo s s 137k S team
BOG+HFO Mo s s 147 Steam
100% BOG
BOG+HFO Mo s s 147 Twin Dies e l
Mo s s 235K Twin Dies e l
-40.0 %
-35.0 %
-30.0 %
-25.0 %
-20.0 %
-15.0 %
-10.0 %
-5.0 %
0.0 %
% c
© Gastech 2005 Iversen & Sørensen 27
Comparing a 147k m LNG carrier with steam propulsion with an
equally sized carrier with twin screw twin slow speed diesel
propulsion and a reliquefaction plant installed, a significant
saving can be achieved. The savings are in the range of 7%. For an
annual transportation of 1 million tons of LNG, cost reduction is
in the range of 3 million USD. If a higher service speed of 21
knots can be accommodated in your trade, an additional 3% cost
saving is possible. At the last LNG14 conference in 2004 Mr. Ohira
of Mitsubishi Heavy Industries presented a graph saying that for
LNG/HFO price ratios of 0.5 and above a gas fired propulsion plant
is less economical than a for a slow speed diesel plant with
reliquefaction. Mr. Ohira's graph is presented below.
9 CONCLUSIONS
Research and development are mainly done to improve safety and
availability or to reduce the costs. In the LNG industry safety
comes first. Any new development must not compromise safety or
reliability. In this paper, it is described some of the research
and development work done for the Moss type LNG carrier in the
recent years. Development of larger diameter of the spherical tanks
has shown that the Moss type LNG carrier can be designed for
capacities of 200k-250k m3. Even larger carriers can be designed,
as the maximum diameter of the sphere has not been reached. By
carefully developing the hull lines, significant reduction in
required propulsion power can be obtained, as the model tests of
the Moss 147k m3 LNG carrier with twin skeg - twin propeller has
shown. Alternative propulsion systems such as diesel electrical
plants or slow speed diesels combined with a reliquefaction system
can significantly reduce the transportation cost of a LNG carrier.
Such systems have already been ordered and we will most probably
see more carriers being ordered with other propulsion systems than
the traditional steam plant. Introduction of slow speed diesel
engines for propulsion means introduction of additional excitation
sources acting on a wide range of frequencies. In order to disclose
unforeseen problems, a detailed investigation of vibration response
of cargo tank structure as well as the global hull structure has
been conducted. The analysis shows that the response representing
the diesel engines are of the same magnitude or less than the
response created by the propellers. It is also acknowledged through
long service experience that Moss type LNG carriers equipped with
proven and well adapted propeller designs do not suffer any harm
from vibrations. Recently an order for eight large LNG carriers was
placed at three yards in South Korea as a part of the Qatargas II
project. This is the first order ever of a LNG carrier equipped
with reliquefaction system. In view of that, a brief presentation
of the Moss Reliquefaction system is given. It has been recognised
that increased operational flexibility will be achieved if the
restriction concerning the temperature in the equator profile can
be relaxed. The study performed has shown positive results.
The
Figure 8-2 Fuel cost graph from Mitsubishi H. I.
© Gastech 2005 Iversen & Sørensen 28
present minimum temperature requirement of –110°C in the equator
profile can be increased, improving the operational flexibility of
the containment system further. Presentation of new arrangements
for BOG handling and high duty heater and vaporiser are given. By
applying combined type heat exchanger, improvements are achieved in
way of layout, operation and cost. Overall transportation cost
assessments indicates that a LNG carrier equipped with slow speed
diesel engines and reliquefaction system has a potential for
significantly reducing the transportation costs over a wide range
of LNG/HFO price ratios.
i MAN B&W