Commissioning & Sustainability: Ensuring your ROI
Cobalt Engineering
At Cobalt, we give life to buildings.
Adopting a holistic perspective, we
offer fully integrated mechanical
and electrical services with a
sustainable focus to deliver high
performance building solution for
every project.
IKEA, Calgary, AB
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Adding Value
• Advanced Energy,
Building Comfort Modeling
• Passive Design
• Microclimate Analysis/Modeling
• Daylighting Analysis
• Façade Design
• Sustainable Master Planning
• External Airflow Analysis
• LEED Consulting
• Commissioning
Metropolis at Metrotown Mall, Burnaby, BC
Boston Pizza, Various locations across Canada
IGA, Various locations across Canada
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Today’s Global Issues
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Why Commission Buildings?
A 2002 study of 60 buildings in USA found:
• 50% had control problems
• 40% of HVAC equipment did not function properly
• 15% had missing equipment
• 25% of energy management systems, economizers and variable speed
drives did not function correctly
• 60% of insurance claims are related to HVAC issues
• The number one source of complaints is HVAC
• The average cost of energy due to above $3 ft2
LBNL. (2002). Lawrence Berkeley National Laboratory Survey of 60 Buildings in USA. http://buildings.lbl.gov/hpcbs/Year_01/Element_5)/
01_E5.html
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Why Commission Buildings?
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Why Commission Buildings?
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Why Commission Buildings?
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
No Commissioning?
Image courtesy of Zurich U.S.
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
The American Society of Heating,
Refrigeration and Air-Conditioning
Engineers (ASHRAE) Guideline 0-2005:
The Commissioning Process, defines
commissioning as a “Quality oriented
process for achieving, verifying and
documenting that the performance of
facilities, systems and assemblies meets
defined objectives and criteria”.
Commissioning is multi discipline and can
be considered a bridge between the design
and delivery of a project. The more
complex and interconnect the systems or
building the greater the need for
commissioning.
Commissioning Definition
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
The commissioning process is based on larger global quality process
movement.
The key tenants of a quality process are:
The end goal must be defined
Work to be done right the first time
Each individual worker is responsible for quality
Verification of work, not inspection
Focus on long term whole life of product i.e. building
Improve quality and lower costs - lean construction
Commissioning and Quality
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
What is Commissioning?
• A planned, collaborative and
systematic process
• Takes place and adds value
throughout the entire project
• Confirms that systems and the
building function as an
integrated whole
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
What is Commissioning?
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Commissioning Sustainable Buildings
• Commissioning, maybe counter intuitively, is very important for highly sustainable “green” buildings or “Net Zero” buildings
• Buildings are systems in their own right
• Commissioning commences at the component level and extends to the building level
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Risks to Project Completion
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Commissioning Adds Value
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Commissioning KPI’s“You cannot manage what you do not measure”
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Commissioning ProcessPre Design Phase = Quality Management
Pre Design
Owner hires design team
Owner hires commissioning authority
Develop expectations & budgets
Determine scope & budget
Develop owners intent
Deliverables
✓ Team appointed
✓ Draft scope & budget
✓ Draft owners intent document
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Commissioning ProcessDesign Phase = Quality Management
Design
Design for commissioning review
Develop basis of design document
Commissioning Charrette
Develop commissioning plan
Review LEED check list
Develop commissioning contract
document clauses
Develop test sheet suite
Develop draft functional test
protocols(FTP’S)
Deliverables
✓ Owners intent document
✓ Basis of design document - design team
✓ Issues log and Risk register
✓ Robust design
✓ Integrated commissioning logic network
✓ Commissioning plan
Commissioning Plan includes:
✓ Scope
✓ Responsibility matrix
✓ Documentation matrix
✓ Systems logic networks
✓ Book of systems interfaces
✓ Pre-functional test documentation
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Commissioning ProcessConstruction Phase = Quality Control
Construction Phase
Contractors commissioning workshop
Review submittals & O&M’s
Assistance in problem resolution
Installation inspections
Sample witness of static systems testing
Observe equipment & systems start up
Finalize functional test protocols(FTP’S)
Refine basis of design document
Refine commissioning plan
Finalize commissioning program
Deliverables
✓ Ownership of the commissioning plan
✓ Low levels of installation defects
✓ Agreed commissioning plan
✓ Right first time commissioning
✓ Quality control
✓ Deficiency reports
✓ On time systems commissioning
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Contractors’ First Reaction to Commissioning!
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Commissioning Process Acceptance Phase = Quality Control
Acceptance
Sample witness vendor commissioning
Sample witness systems commissioning
Sample witness TAB
Witness 100% all life safety systems
Use FTP’s to verify systems performance
Global integration testing
Black building test
Assist in problem resolution
Collate & document all systems test results
Produce the commissioning report
Review and coordinate O&M team training
Deliverables
✓ Tested and validated building and systems
✓ Documented building performance
✓ Fully operational & optimized building
✓ Timely completion of commissioning
✓ High quality environmental conditions
✓ Low levels of deficiencies
✓ Low levels of call backs
✓Set trend logs to monitor building
performance
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Commissioning Process Acceptance Phase - Post Occupancy = Quality Control & Fine tuning
Occupancy
Deferred FTP testing
Deferred seasonal testing
Systems optimization
Post occupancy adjustments
Review of outstanding defects
Lessons learned workshop
Deliverables
✓Up-dated commissioning report
✓Lessons learned report / workshop
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Cause of Defects in Construction
Product/
Equipment
Failures, 10%
Construction
Problems, 40%
Design
Problems, 50%
Cost of NOT Commissioning
Commissioning exposes deficiencies in design and installation
M Billington. (2001). Defects in Buildings: Symptoms, Investigation, Diagnosis and Cure. www.BRE.co.uk
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Cost of NOT Commissioning
Cost of rectifying quality failures increases as the project progresses:
Cost
Rectified at design stage 1.00 (Zero)
Rectified during construction 3 times design stage
Rectified at completion 8 times design stage
Rectified in use unlimited!
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Cost of NOT Commissioning
Energy Costs at Differing RTU Minimum Outside Air Settings
$46,488
$61,349
$80,820
$99,315
$0
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
21% (Design) 30% 40% 50%
% OA During Occupied Hours
An
nu
al C
os
t ($
)
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Costs of Commissioning
PECI. (2002). New Construction Commissioning Costs. www.PECI.org
Estimates of Construction Phase Commissioning Costs
(Costs from the commission authority in new construction, per square foot)
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Benefits of Commissioning
• Increased occupant thermal comfort
with improved environmental control
• Improved indoor air quality
• Smoother turnover from contractor to
owner
• Optimized Energy Performance
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Benefits of Commissioning
• Reduced construction, operating and
maintenance costs
• Reduced energy consumption
• Reduced RFI’s and change orders
• Reduced contractor and vender call
backs
Presented by:
Adam Muggleton, MSc, LEED® AP
Managing Partner Toronto
September 10, 2008
Commissioning & Sustainability: Ensuring your ROI
Thank You