GEF/UNDP/DOE CBRED PROJECT “Philippines: Capacity Building to Remove Barriers to Renewable Energy Development”. Market Service Center Business Planning & Development Subcontract Presentation to REIAC DOE-AVR September 27, 2005. Presentation by :. REIAC Concerns. - PowerPoint PPT Presentation
48
GEF/UNDP/DOE CBRED PROJECT “Philippines: Capacity Building to Remove Barriers to Renewable Energy Development” Presentation by : Market Service Center Business Planning & Development Subcontract Presentation to REIAC DOE-AVR September 27, 2005
Transcript
Page 1: GEF/UNDP/DOE CBRED PROJECT

GEF/UNDP/DOE CBRED PROJECT“Philippines: Capacity Building to Remove Barriers to

Renewable Energy Development”

Presentation by :

Market Service CenterBusiness Planning & Development

Subcontract

Presentation to REIACDOE-AVR

September 27, 2005

Page 2: GEF/UNDP/DOE CBRED PROJECT

REIAC Concerns1. Organizational Form of the Spin-Off Organization (SOO) a. Organizational Options

b. Fund utilization restriction/Retained Earnings c. Seed Fund

strategies for solicitation

2. Compatibility of Organizational Form of SOO with Provision of Services

Page 3: GEF/UNDP/DOE CBRED PROJECT

3. Spin-Off Trigger Indices 4. Product Mix (services offered)5. Financial Projections for SOO

Strategies for Sustainability6. Transitory Provisions7. Contingency Plan

Page 4: GEF/UNDP/DOE CBRED PROJECT

1. Organizational Form of the Spin-Off Organization

Page 5: GEF/UNDP/DOE CBRED PROJECT

a. Organizational Options1. Government Corporation with Charter2. Government Corporation under the Corporation

Code3. Private Corporation (Stock Corporation)4. Private Corporation – (Non-Stock Corporation)5. Private Corporation – (Non-Stock, Non-Profit) a. Association b. NGO c. Foundation

Page 6: GEF/UNDP/DOE CBRED PROJECT

a. Organizational Options1. Government Corporation with Charter

These corporations are created by an Act of Congress and their establishment will be a lengthy process; not a reasonable option.

2. Government Corporation under the Corporation Code

Its creation is a lengthy process as proven by the effort to establish the PNOC RE subsidiary.

It is subject to government control and political pressure and hence not attractive to target private RE sector clients.

Page 7: GEF/UNDP/DOE CBRED PROJECT

3. Private Corporation (Stock Corporation) It is primarily organized for profit, hence its

management will be focused mainly on the interests of the corporation which will redound to its stockholders.

4. Private Corporation (Non-Stock) Donors may deduct 5-10% of their

contribution/ donation to non-stock corporations from their taxable net income

Page 8: GEF/UNDP/DOE CBRED PROJECT

5. Private Corporation (Non-Stock, Non-Profit)a. Association - Organized for the benefit of its members - Will offer bias towards services that will benefit its

members - Interest of the private RE project developer may be

sacrificed and not served.

b. NGO - Organized for the advocacy of specific

ideals/interests and represent specific sector/s of society

- Interest of the private RE project developer may be sacrificed and not served.

Page 9: GEF/UNDP/DOE CBRED PROJECT

c. Foundation Established to maintain charitable,

educational, scientific, etc. activities through extending grants or endowments, but may also include undertaking projects aimed at advancing the development of these sectors.

Donations made to a foundation will be deductible in full (100%) from the donor’s gross income. This privilege could attract more donors to the foundation than to a regular non-stock corporation.

Administration expense may not exceed 30% of the total expenses.

Page 10: GEF/UNDP/DOE CBRED PROJECT
Page 11: GEF/UNDP/DOE CBRED PROJECT
Page 12: GEF/UNDP/DOE CBRED PROJECT
Page 13: GEF/UNDP/DOE CBRED PROJECT

A Foundation is the most appropriate type of organization for MSC mainly for following reasons :

Not viewed as a competitor of the RE Industry

Can accept fund donations and projects from national, bilateral and multilateral donors/sources to help support its operation

Donors can deduct 100% of their donations/contributions from their taxable income

Conclusion of Organization Study

Page 14: GEF/UNDP/DOE CBRED PROJECT

b. Fund utilization restriction/Retained Earnings

A foundation will have no retained earnings because it will use all of its funds for projects.

Administrative expenses may not exceed 30% of total expenses

Page 15: GEF/UNDP/DOE CBRED PROJECT

b. Fund utilization restriction/Retained Earnings

Per DOST, there are accepted ways of allocating more funds for administrative costs. Specifically, this is done by considering portions of the admin cost as part of project implementation cost. Per DOST, this approach is widely used and have not encountered problems in compliance to the 30/70 restriction for funds allocation.

Page 16: GEF/UNDP/DOE CBRED PROJECT

1. Conduct donors’ meeting to solicit required seed money of Php 1 MM and pre-operating expenses

2. Offer Funds (3 Funds) monitoring services to DOE for a fee which may include a commitment from DOE to allocate a portion of interests earned by the LGF for the required seed money and pre-operating expenses of the Foundation.

c. Financial Strategies for Sourcing SEED Fund of the Foundation

Page 17: GEF/UNDP/DOE CBRED PROJECT

F in an ce an d A d m in is tra t ion

M an ag erK n ow led g e M an ag em en t

P ro jec t S u p p ort S ta ff

P ro jec t S u b c on trac to rs

P ro jec t M an ag er

M an ag erO p era tion s

M an ag erB u s in es s D eve lop m en t

E xec u tive D irec to r

B oard o f Tru s tees

Table of OrganizationDoc. No.: TO Rev. No.: 0Effective Date:Copy No.: Page 1 of 1

Controlled Copy Uncontrolled Copy

MSCF

Page 18: GEF/UNDP/DOE CBRED PROJECT

2. COMPATIBILITY OF ORGANIZATIONAL FORM WITH PROVISION OF SERVICES

Page 19: GEF/UNDP/DOE CBRED PROJECT

Type of Service Private Corporation Foundation1. Facilitation of permits,

licenses, clearances and approvals (e.g. from DOE, NWRB, DENR, ERC, NCIP)

Can be provided as a service by a private corporation.

Can be provided as a service by a foundation.

2. Information Services2.1 Information

Search/Provision of processed information

Being profit-oriented, this service may not be attractive to a private corporation since maintenance of data base is costly while fee for provision of such service is relatively low because of current practice of accessing information for free or at cost.

Regardless of profit, a foundation will offer this service since it is needed by the RE private sector and is precisely one of the reasons why the MSC was conceptualized.

2.2 Access to private data bases

Owners of private data bases may be hesitant to provide access to a private corporation because of concern on possible competition in the use of the data base.

Because a foundation carries out activities to support the development of its sector, it could have easier access to private data bases since it shall also be passed on to private RE project developers.

Page 20: GEF/UNDP/DOE CBRED PROJECT

Type of Service Private Corporation Foundation3. Project Development

Services3.1 Proposal Packaging Can be provided as a service by

a private corporation.Can be provided as a service by a foundation

3.2 Loan facilitation Can be provided as a service by a private corporation.

Can be provided as a service by a foundation.

3.3 Brokering the rehabilitation of NEA-hydro plants

Can be provided as a service by a private corporation.

Can be provided as a service by a foundation.

3.4 Conduct of FS in partnership with private consultants and project developers

A private corporation may be viewed as a competitor by private consultants offering the same service.

A foundation is less viewed as a competitor by the nature of its service personality.

3.5 Fund syndication Can be provided as a service by a private corporation.

Can be provided as a service by a foundation.

Page 21: GEF/UNDP/DOE CBRED PROJECT

Type of Service Private Corporation Foundation4. Business Systems

Process Improvement4.1 Advisory services and Conduct of Capacity Building/Enhancement Program

It is likely that the range of expertise required to provide this service to the RE industry will not be present within the private corporation and it will need to engage the services of external experts. A private corporation may not have the ability to undertake an agreement with universities and R&D institutions to tap the latter’s technical staff. There is also the issue of proprietary rights over intellectual properties.

A foundation will be in the best position to arrange manpower sharing with universities/R&D institutions, provided it is willing to provide the partner institutions some financial support.

5. Web hosting Can be provided as a service by a private corporation.

Can be provided as a service by a foundation.

Page 22: GEF/UNDP/DOE CBRED PROJECT

3. Spin-off Trigger Indices MSC staff has completed the proposed

capacity building program

Page 23: GEF/UNDP/DOE CBRED PROJECT

Capacity Building for MSC Staff Loan Proposal Packaging Permits/Licenses Processing Understanding ISO 9001 Operation of the MSC’s Management System Project/Quality Planning Management System Auditing Document Control Permits/Licenses Processing

COMPLETED HAVE NOT BEEN COMPLETED

Page 24: GEF/UNDP/DOE CBRED PROJECT

Fundamentals of RE RE Project Development & Management RE Project Financing RE Database Management System Dynamics of RE Market Entrepreneurial Skills RE Technology Design, Installation and

Maintenance CDM

COMPLETED HAVE NOT BEEN COMPLETED

Page 25: GEF/UNDP/DOE CBRED PROJECT

3. Spin-off Trigger Indices MSC staff has completed the proposed

capacity building program

Organized and conducted 2 Donors’ meeting 1 for potential private donors 1 for potential bilateral/multilateral donors

Page 26: GEF/UNDP/DOE CBRED PROJECT

Spin-off Trigger Indices (cont’d.)

Relationships built with at least 6 potential subcontractors

Relationships built with at least 6 financial institutions

Relationships built with at least 8 potential customers/companies

Signed MOA with donor of PhP1M endowment fund and pre-operating expenses

Page 27: GEF/UNDP/DOE CBRED PROJECT

4. Provided the following services/product mix:

Information services Permits/Clearances/Licenses Facilitation Project Development Services Web Hosting Project Finance and Fund Syndication-

related services Advisory Services/Training & Workshops

on Business Systems Process Improvement

Spin-off Trigger Indices (cont’d.)

Page 28: GEF/UNDP/DOE CBRED PROJECT

Provided the following number of services:

Information services 24 Permits/Clearances/Licenses Facilitation 20 Project Development Services 8 Web Hosting 8 Project Finance and Fund Syndication- 0

related services Advisory Services/Training & Workshops 0

on Business Systems Process Improvement

TOTAL 60

Spin-off Trigger Indices (cont’d.)

Page 29: GEF/UNDP/DOE CBRED PROJECT

5. Financial Projections for Foundation

Strategies for Sustainability

Page 30: GEF/UNDP/DOE CBRED PROJECT
Page 31: GEF/UNDP/DOE CBRED PROJECT
Page 32: GEF/UNDP/DOE CBRED PROJECT
Page 33: GEF/UNDP/DOE CBRED PROJECT
Page 34: GEF/UNDP/DOE CBRED PROJECT
Page 35: GEF/UNDP/DOE CBRED PROJECT
Page 36: GEF/UNDP/DOE CBRED PROJECT
Page 37: GEF/UNDP/DOE CBRED PROJECT
Page 38: GEF/UNDP/DOE CBRED PROJECT
Page 39: GEF/UNDP/DOE CBRED PROJECT
Page 40: GEF/UNDP/DOE CBRED PROJECT
Page 41: GEF/UNDP/DOE CBRED PROJECT
Page 42: GEF/UNDP/DOE CBRED PROJECT
Page 43: GEF/UNDP/DOE CBRED PROJECT
Page 44: GEF/UNDP/DOE CBRED PROJECT

1. Conduct donors’ meetings to solicit donations/grants to help support its operating expenses

2. Offer Funds (3 Funds) monitoring services to DOE for an annual fee which may come from the unused portion of interests earned by the LGF.

Financial Strategies for Sourcing Supplementary Fund for the Foundation

Page 45: GEF/UNDP/DOE CBRED PROJECT

6. Transitory Provisions1. Phasing-in Strategy – Interim MSC simulates

the operation of the SOO by providing services to the RE industry

2. Asset Transfer – All equipment purchased for the MSC shall be transferred to the Foundation through a Deed of Donation from UNDP.

3. Personnel Transfer – Services of IMSC staff shall be terminated at the end of operation of IMSC. They will however be given priority in hiring personnel for the MSCF, if they qualify. Years of service with the IMSC shall not be transferred to the Foundation.

Page 46: GEF/UNDP/DOE CBRED PROJECT

7. Contingency PlanIf the MSCF is not sustainable, the following

are fallback options:

1. Continue to operate as a Foundation with scaled-down operation aimed at sustainability

2. Dissolve the Foundation – Transfer all MSCF assets to the DOE and DOE continues the functions of the MSCF

Page 47: GEF/UNDP/DOE CBRED PROJECT

Cost Benefit AnalysisRenewable Energy Policy Framework Target

= 10 MMBFOE= 4,697 MW

Assuming MSC provides services to 10% of the projects:Total MW = 469 MWMMBFOE = 1 MMBFOEForex Savings = 50 million USD or equivalent to 2.75 Billion Pesos

Potential MT CO2 emissions avoided = 310,440At 7 USD per MT CO2 = 2.2 USD million