Date post: | 01-Apr-2015 |
Category: |
Documents |
Upload: | dylan-hodgkiss |
View: | 216 times |
Download: | 2 times |
Generation Use of System Charges
Nigel Turvey
Background
• Regulatory incentive allows:• Recovery of a percentage of any reinforcement costs• A value per kW of generation connected• An allowance for the O&M costs on the sole use and
reinforcement assets
• The incentive applies to generation connected post April 2005 or to incremental additions to existing generators made post April 2005
• This results in a positive allowed revenue from generation
Existing Position
• For generators connected at EHV:• LRIC methodology applies • which can result in positive or negative charges • Continue to be cost reflective and do not need further amendment
• For generators connected at HV/LV:• Charges calculated from yardsticks which have characteristics
derived from demand data• Originally set using cost data used in the last price control settlement• Concerns raised whether this approach is cost reflective and whether
there are benefits not being reflected in the charges• For microgeneration:
• Charges set to zero• At existing low level of activity neither costs nor benefits have been
identified and zero charge continue to be appropriate
Proposed method for HV/LV generator charges - Data
Scatter graph of West HV Coincidences 0607
0
0.2
0.4
0.6
0.8
1
1.2
0 5 10 15 20 25 30 35 40 45 50
coin
cid
ence
Coincidence range across technology typeHV connections
0.00
0.20
0.40
0.60
0.80
1.00
1.20
landfill chp wind waste tmt other
Proposed method for HV/LV generator charges - Data
Proposed method for HV/LV generator charges - principles
• Generation tends to be widely dispersed• Unlikely that benefits (or cost not recovered in connection charges)
will be seen at voltage of connection• Some benefit likely at higher voltage levels due to the impact of
multiple higher load factor generators• For consistency with security standards, benefits will not be applied to
intermittent generation• Yardstick constructed including:
• negative coincidences at voltage levels above the voltage of connection (for high load factor generators)
• zero coincidence at the voltage level of connection• Positive service connection costs
Proposed method for HV/LV generator charges - scaling
• Proposed method will result in negative export yardsticks whilst allowed revenue is positive
• Whilst scaling to a positive allowed income will reduce the pricing signals it will reflect a recovery of other costs not in DRM yardsticks
• Scaling by a £/kW adder will be required• Scaling to required revenue will result in low load factor
generators (generally renewable) having higher UoS charges than at present
• The only way to prevent this would be to recover some allowed generation revenue from demand – this would require Ofgem’s agreement
Proposed method for HV/LV generator charges – resulting charges
South Wales South West
Existing Charge Proposed Charge Existing Charge Proposed Charge
Microgeneration £0 No Change £0 No Change
Profiles 5 to 8 7.85p/MPAN/day ?? 6.49p/MPAN/day ??
LV > 60% Load Factor
2.01p/kVA/day
-11.91p/kVA/day
1.67p/kVA/day
-12.63p/kVA/day
LV < 60% Load Factor
5.85p/kVA/day 4.43p/kVA/day
HV > 60% Load Factor
2.49p/kVA/day
0.37p/kVA/day
1.74p/kVA/day
-2.68p/kVA/day
HV < 60% Load Factor
5.75p/kVA/day 4.14p/kVA/day
EHV -4.51 to +2.25p/kVA/day
No Change-1.67 to
+1.77p/kVA/dayNo Change
Some examples – low voltage connections
South Wales South West
Existing annual charge
Proposed annual Charge
Existing annual Charge
Proposed annual Charge
250kVA Demand, 30%LF 20% of units at night
£11,104 No change £9,810 No Change
250kVA landfill generator operating at 70% LF
£1,834 £-10,870 £1,524 £-11,526
250kVA windfarm operating at 30% LF
£1,834 £5,340 £1,524 £4,044
Some examples – high voltage connections
South Wales South West
Existing annual charge
Proposed annual Charge
Existing annual Charge
Proposed annual Charge
1MVA Demand, 30%LF 20% of units at night
£25,313 No change £22,627 No change
1MVA landfill generator operating at 70% LF
£9,089 £1,340 £6,351 £-9,794
1MVA windfarm operating at 30% LF
£9,089 £20,987 £6,351 £15,117
Proposed method for HV/LV generator charges - timetable
• Draft modification report prepared• Expecting to issue a WPD consultation to get
users views shortly• Modification request to Ofgem June/July• Implementation April 09