+ All Categories
Home > Documents > GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE · 2017. 8. 4. · c) Connection strength For...

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE · 2017. 8. 4. · c) Connection strength For...

Date post: 16-Feb-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
35
Transcript
  • GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

    Prof. J. N. Mandal

    Department of civil engineering, IIT Bombay, Powai , Mumbai 400076, India. Tel.022-25767328email: [email protected]

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

    Module - 6LECTURE - 28

    Geosynthetics for reinforced soil retaining walls

  • Design factor of safety (FS) based on mode of failures

    Ultimate limit state

    Serviceability limit states

    External stability under static loading

    External stability under seismic loading

    Internal stability

    Recap of previous lecture…..

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Alternatively, Le can be expressed as per FHWA (1998),

    .F.C.2FS..S

    L *rv

    pullhve

    F* = coefficient of pullout interaction between soil and geotextile.

    α = scale correction factor.

    F* and α for standard backfill materials except uniformsand (Coefficient of uniformity, Cu < 4).

    Type of reinforcement Default F* Default αGeogrid 0.8 tanϕ 0.8

    Geotextile 0.67 tanϕ 0.6

    Factor of safety for pullout should be 1.5. Minimumembedment length (Le) is 1m.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Anchorage capacity of the reinforcement per unit width(P) is expressed as,

    P = 2 Le. σv. Cr. F*. α

    P ≥ FSpull . Tmax

    Tmax = Sv. σh

    For wrap-around face wall, geosynthetic overlap length(Lo) can be expressed as,

    .F.C.4FS..S

    L *rv

    pullhv0 Minimum value of overlap (L0) is 1 m

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • c) Connection strength

    For long-term creep and aging, consider a factor ofsafety = 1.5

    5.1xRFxRFTT

    CRD

    sac

    Ts = Seam strength as per ASTM D 4884 for seams

    RFD = Durability reduction factor for chemicals, stresscracking, thermal oxidation and hydrolysis,

    RFCR = Reduction factor for creep

    i) Connection testing for geosynthetic rupture (Simac etal., 1993; Elias and Christopher, 1997):

    Tac = maximum connection strength

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • ii) Connection testing for Pullout resistance ofgeosynthetic (Elias and Christopher, 1997):

    The maximum connection strength can be written as,

    5.1T

    T pac

    TP = maximum pullout load per unit width of thereinforcement or the pull out load at maximumdeformation of 20 mm, whichever occurs first

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • INTERNAL STABILITY CHECK FOR SEISMIC LOADING

    The location of maximum tensile force line does notchange due to the rupture of the reinforcement or pull outforce during seismic loading.

    Breakage failure

    RFC.T)T( rallowablestaticmax

    For dynamic case:RF75.0

    C.T)T( rallowabledynamicmax

    For static case:

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Pull-out failure

    p

    rpullmax FSx75.0

    C.PT

    rve

    *d

    rpullmax C..Lx5.1x75.0

    xFx2

    5.1x75.0C.P

    T

    Fd* (dynamic) = 0.8 F* (static)

    α = 0.6 (normally)

    F* and α = Pullout factor (default value)

    Due to seismic loading, the overall stiffness ofgeosynthetic will decrease. So, damping andamplification may increase.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Step 6: Serviceability Limit State - Internal stability

    Internal wall deformation

    Lateral displacement of wall face

    Determine the settlement of reinforced soil wall

    External wall settlement

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • COST CONSIDERATIONS

    Koerner et al. (1998) compared the cost of geosyntheticreinforced soil walls with various other retaining walls.

    The cost of geotextile is about 25 % of the wall’s totalcost (Bell et al.1983).

    In India, the cost for geosynthetics reinforced soil wall isabout 30% - 50% less than that of conventional gravityretaining walls:

    Geosynthetics and accessiroies = 35 %Panel/block facing and mould =32 %Labour =15 %Margin/profit = 18 %

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • 0

    100

    200

    300

    400

    500

    600

    700

    800

    0 2 4 6 8 10 12 14Height of wall (m)After Koerner et al., 1998

    Gravity Walls

    Crib / Bin Walls

    MSE (Metals)

    MSE (Geosynthetics)

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • The material cost depends upon the following elements:

    Modular block or Panel facia

    Gravels as drainage material

    Geosynthetics material as reinforcement (Geogrid,

    Geotextile, Geocomposite)

    Leveling pad

    Cost of design

    Soil and Geosynthetic testing

    Site preparation and site assistance

    Under drain pipe

    Placement of backfillProf. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • CONSTRUCTION PROCEDURE FOR PRECAST CONCRETE FACED WALLS

    a) Foundation subgrade

    Geogrid layers at the foundation Geocells as Foundation mattress

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • b) Leveling pad

    Leveling pad (all dimensions are in mm)

    The main objective of leveling pad is to erect the facingelements.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Plane cement concrete (P.C.C 1:2:4 lean concrete) isplaced beneath the leveling pad to minimize differentialsettlement.

    Leveling pad should be constructed continuously up to20 m in length with a gap of 20 mm.

    Curing for at least 24 hours prior to the placement ofthe blocks / panels.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • c) Erection of facing elements

    Sequence of erection of panels

    Cast with M-35 gradeconcrete.

    Erection of panel after curingfor 28 days.

    The minimum thickness ofpanel is 140 mm.

    The Panels are square,rectangular, hexagonal, cruciformand diamond in shape.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Panel dimension of precast faciaProf. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Face length = 200 mm-450 mm,

    width = 200 mm-600 mm and

    height = 150 mm - 200 mm.

    weight of the block = 250 N to 500 N.

    Precast concrete modular blocks (After Bathurst and Simac, 1994)

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • The facing batter is not less than 1 in 40 but 6 degreeis preferable.

    Minimum M 25 grade concrete should be used.

    The facing units should be connected with the help ofshear keys, shear pins or shear lips.

    The spacing between reinforcement should not bemore than 600 mm.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Standard design of MSEW (After FHWA, 2009)

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • d) Placement of backfill and compaction

    The backfill materials are compacted with a rollercompactor to achieve at least 95% modified Proctordensity. The lift thickness should not be more than 200 mm.

    The light weight hand compactor not exceeding 75 kgshould be used to compact near to the facing elements.

    Vibroplate compactor of maximum weight 1000 kgshould be used to compact within 1.5 m from the edge ofthe facing elements.

    No heavy equipment should be kept near to the face ofthe walls.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • e) Placement of reinforcement

    After filling and compaction up to desired height,geogrid reinforcement is connected with the facingelements and placed horizontally.

    The geogrid should be placed in the machinedirection perpendicular to the face of the wall.

    It is very important that during the compaction, bothhorizontal and vertical alignment of facia panel or blockmust be observed regularly.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • e) Drainage (DDD………)

    Most of the reinforced soil structures fail (or collapse)due to the development of excess hydrostatic pressureat the back of the retaining walls.

    Koerner and Soong (2001) documented that 20 outof 26 mechanically stabilized earth walls fail either byexcessive deformation or collapse.

    Therefore, proper design of drainage system isneeded.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Drainage using a blanket with chimney drains (After Collin et al. 2002)

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Drainage system and geomembrane barrier for reinforced soil wall (After FHWA, 2009)Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • f) Submission of materials and test reports bymanufacturer

    The contractor should submit the following information tothe engineer,

    Name of the manufacturer

    Current full address

    Polymer type for Geosynthetics

    yarn/Fiber tie for Geosynthetic structure

    Roll no of Geosynthetics, and

    Certified test result.Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • g) Design critique

    The mobilized strain in reinforced soil walls may berelatively high because of the extensibility ofreinforcement.

    It is recommended to use critical state shearingresistance angle instead of peak friction angle of the soilfor design (Jewell, 1991).

    At the end of construction, the serviceability straincriteria for long design life of reinforced soil wall,

    - 1.0 % for walls, and

    - 0.5 % for bridge abutmentsProf. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Most of the reinforced soil structures fail due to thelateral deformation at the top and bulging of the wall.

    It is recommended to provide longer lengthreinforcements at the top, middle and bottom of thereinforced wall

    For the remaining height of the wall, shorter lengthreinforcements can be used.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • FAILURES OF STRUCTURES

    The geosynthetic reinforced soil walls fail or collapse due toseveral reasons:

    Excess hydrostatic pressure Excessive lateral deformation; Improper selection of backfill materials Local instability (distortion) of modular blocks or panels, Contractor’s lack of workmanships for quality control, Bearing capacity and deep-seated failure Global failure also causing formation of huge heave in frontof the facia elements No site-specific design and also Copycat and paste

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Heavy compaction within 1 to 1.5 m of wall face

    No outlet drainage provided for internal drainage

    Geogrid tension failure

    Geogrid connection failure

    Geogrid slippage or block wall failure

    Poor attention to facing connection,

    poor inspection,

    Improper compaction

    poor quality control and assurance

    Inadequate design of the backfill slope and the foundation

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Codes and design Standards

    Strengthened / reinforced soil and other fills, BSI (1995)

    Mechanically stabilized earth walls and reinforced soil slopes: Design and construction guidelines. FHWA, 2001.

    Design manual for segmental retaining walls, NCMA Design manual, 1996.

    Segmental retaining walls – seismic design manual, Dr. R. J. Bathurst.

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Please let us hear from you

    Any question?

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay

  • Prof. J. N. Mandal

    Department of civil engineering, IIT Bombay, Powai , Mumbai 400076, India. Tel.022-25767328email: [email protected]

    Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay


Recommended