FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 2
This technical memorandum presents NCC findings, conclusions, and foundation recommendations for the proposed I-15 widening over the Union Pacific Rail Road (UPRR) (Bridge No. G-941) to be located in Design Segment 1 of the I-15 North Corridor. Figure 1 shows the location of the bridge structure and the limits of I-15 North Corridor alignment (figures are presented at the end of this memorandum). As noted in Table 1, Segment 1 encompasses approximately 1.2 miles of roadway, extending from Station 863+50 US-95/ I-15 to Station 924+00 just south of Owens Avenue.
Project Description The existing bridges over the UPRR track were originally built in the late 1960s. The northbound (G-941 N) and southbound (G-941 S) bridges were constructed as three-span, cast-in-place, conventionally reinforced, concrete box girder structures. According to as-built plans, the bridges are supported by 45-ton, HP 12x74 steel H-piles at the abutment locations and by 10-foot by 10–foot spread footings at the piers. The existing bridge foundation information, as provided in the as-built plans, is summarized in Table 2. As-built elevations are provided in mean sea level (MSL) as presented in the as-built plans.
TABLE 2 Summary of Existing Structure Foundations
Location Foundation Type
Bottom of Pile Cap Elevation/Footing
Elevation (feet)
Minimum Pile tip Elevation
(feet)
Abutments A&C HP 10x57 2057.5 2027
Pier 1 (Southbound Bridge) Spread Footing (10 feet x 10 feet )
2035.5 NA1
Pier 2 (Southbound Bridge) Spread Footing (10 feet x 10 feet )
2034.0 NA1
Pier 3 (Northbound Bridge) Spread Footing (10 feet x 10 feet )
2032.5 NA1
Pier 4 (Northbound Bridge) Spread Footing (10 feet x 10 feet )
2035.5 NA1
Abutments B&D HP 10x57 2055.0 2027.5 1 Not Applicable
The I-15 widening will be constructed between the existing northbound and southbound bridge structures. The proposed widening of the I-15 over the UPRR bridge will be constructed as a three-span, post-tensioned, box girder structure. The proposed bridge will be located at “L-1” Line Station 870+80.11 (between Station 869+85.4 and Station 871+55.9). The proposed bridge will be approximately 20 feet wide and 164.5 feet long.
Figure 2 shows the approximate boring locations and the plan view of the bridge. The general plan and elevation of the proposed widening are presented in Figures 3A through 3C. The as-built general plan and elevation of the existing bridges are presented in Figure 4.
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 3
Geotechnical Investigation The scope of work for the geotechnical investigation task included the following:
• Reviewing information from previous geotechnical reports
• Drilling and sampling of three hollow-stem auger (HSA) borings (BW1-1, BW1-2 and BEN1-1) near the proposed bridge structure location to characterize the subsurface conditions
• Laboratory testing of selected soil samples to characterize the subsurface soils
• Reviewing regional geology and seismicity
• Evaluating the foundation type and pile capacity for widening and seismic retrofit of the existing bridges
• Preparing this foundation memorandum
Evaluation of potentially contaminated soils or groundwater was not part of this geotechnical investigation.
Review of Prior Geotechnical Investigations Prior to the current NCC study, geotechnical explorations in the project vicinity were performed by Black Eagle Consulting, Inc., (2006) as part of the preliminary investigation for this project. One boring (SB-05) was drilled in the vicinity of the proposed bridge structure. This boring was used only to confirm the lithology underneath the proposed bridge location. A downhole-hammer was used to obtain the blow counts in this boring. There is no known correction factor available to convert the downhole-hammer blow counts to Standard Penetration Test (SPT) blow counts.
In addition to the Black Eagle report, a geotechnical report of the static pile load test program performed by Kleinfelder (1996a) in the nearby test sites was also reviewed. Three out of four Kleinfelder load test sites are within or adjacent to the segment 1 alignment. The first test site was located at the core of I-15/US 95 interchange, west of I-15, south of US 95 and inside the loop ramp from south bound I-15 to east bound US 95. The second test site was located west of Martin Luther King Boulevard, south of US 95 and inside the loop ramp from south bound Martin Luther King Boulevard to east bound US 95. The third test site was located north of Washington Avenue, east of the Washington Avenue entrance ramp to the north bound I-15 and west of the I-15 property line fence. Results of these static pile load tests were used to evaluate the soil undrained shear strengths for the axial pile capacity analysis. The lithology observed at the test site locations are similar to the lithology observed along the Design Segment 1 of the I-15 North Corridor.
Geotechnical Investigation by North Corridor Constructors The NCC field investigations included drilling three HSA borings (BW1-1, BW1-2 and BEN1-1). These borings were drilled by Terracon Consultants, Inc., under subcontract to NCC, between December 26, 2007 and January 28, 2008. Borings BW1-1, BW1-2 and BEN1-1 were drilled to approximate depths of 95, 97 and 100.5 feet below existing ground surface
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 4
(bgs), respectively. The borings were approximately 8 inches in diameter and logged by a Terracon Consultants, Inc. engineer or geologist. Table 3 lists the locations and details of these borings. Approximate locations of the borings are shown on Figure 2 and the boring logs are included in Attachment 1.
Samples from each boring were retrieved at 5-foot intervals by means of SPT and modified California drive samplers using a 140-pound auto hammer system with a drop of 30 inches. Shelby tube samples of the clayey soils were obtained at each boring location. Samples were carefully stored and transported to the laboratory testing facilities. Elevations provided in this memorandum are based on the North American Vertical Datum (NAVD) of 1988, except where noted differently.
TABLE 3 Summary of Geotechnical Borings
Boring Type of
Exploration
Approximate Station “L1”
Line Offset (feet)
Elevation (feet)
Depth (feet bgs)
Groundwater Elevation
(feet)
BW 1-1 HSA 869+36 9 L 2066.8 95.5 2023.5
BW 1-2 HSA 872+73 7 R 2064.1 97 2020.1
BEN1-1 HSA 873+66 63 R 2,061.7 100.5 Not Measured
SB-05 HSA 871+18 119 R 2,038.5 100.75 Not Measured
Laboratory Testing Selected soil samples from the borings were tested for soil classification, strength characteristics, and corrosion potential. Results of the laboratory tests are presented in Attachment 2. Fine contents of the clayey soils vary from 51 to 80 percent and the plasticity index (PI) ranges from 4 to 50 percent. Peak undrained shear strengths (estimated from the unconsolidated undrained [UU] triaxial tests) of the clayey soils range from 1.5 to 9.6 kips per square foot (ksf). Fine contents of coarse grained soils vary from 13 to 49 percent.
Site Geology Regional Geologic Setting The Las Vegas Valley is characteristic of the Basin and Range province and consists of a faulted half graben, underlain by a pull-apart basin, with a major normal fault located along its eastern limit. By using geophysical data, Page et al. (2005) estimated the thickness of the sedimentary fill of the Las Vegas basin to be as much as 10,000 to 13,000 feet and to consist of Miocene through Holocene Age lacustrine, paludal, and alluvial deposits. Sediments in the Las Vegas Valley basin, from most recent to oldest, have been grouped into Basin Fill (Pliocene to Holocene), Muddy Creek Formation (Pliocene to late Miocene), and Horse Spring Formation (Miocene). Only the Pliocene to Holocene Basin Fill is present along the entire I-15 alignment under consideration in this Project. The Pliocene to Holocene Basin Fill sequence is characterized by three facies: coarse-grained alluvial fan, fine-grained fluvial and lacustrine basin fill, and blue lacustrine clay. The blue lacustrine clay is laterally extensive in the center of the basin, where it is reported to be present at depths that range
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 5
from 480 to 600 feet (Bell et al., 1992). Impermeable hard caliche horizons are pervasive in the uppermost portion of the basin fill. Generally, coarser-grained deposits are located near the base of the mountains, transitioning to finer-grained deposits towards the middle of the valley.
Surficial Geology According to the regional surficial geology map compiled by Page, et al (2005) and the geologic map prepared by Matti, et al (1987), the natural materials reported cropping out at the UPRR bridge site and nearby vicinity correspond to Holocene and late Pleistocene age Undivided Young Spring deposits (Qsy) (Figure 1). The soil borings advanced at the vicinity of the bridge encountered native clay materials with interbedded clayey sand, clayey gravel, and caliche/cemented soil layers. The soil borings advanced at the vicinity of the proposed bridge location confirmed the occurrence of this sequence at least to the maximum investigated depth of approximately 100 feet bgs.
Subsidence Land subsidence along the I-15 alignment has been reported to occur mainly along its southern portion, from Carey Avenue to the I-15/US-95 Interchange, associated with the Las Vegas Valley Central subsidence bowl. According to Bell, et al (2001 and 2002), the total maximum regional subsidence for the 1963 to 2000 period along the southern portion of I-15 occurs south of Washington Avenue and is reported to be 2.8 feet. The land subsidence decreases gradually towards the northeast, where 2- and 1-foot contour intervals are reported approximately at the projection of the intersection of the alignment with Williams Street and at the crossing with Lake Mead Boulevard, respectively.
Although up to 2.8 feet of regional subsidence is reported to have occurred immediately to the south of the Washington Avenue Bridge, regional groundwater subsidence is considered to be at a scale which should not cause damaging differential settlements to individual structures. Kleinfelder (1996b) indicates that although subsidence at the I-15/US-95 Intersection has been reported to be approximately 3 feet since the original construction survey, the relatively broad characteristics of the regional subsidence has had little apparent effect on the existing highway structures since their construction in the 1960s. Therefore, regional subsidence is not anticipated to represent a hazard for the proposed bridge widening.
Faulting According to Page, et al (2005) and Matti, et al (1987), a splay of the Cashman fault of the Las Vegas Valley Fault System (LVVFS), runs approximately parallel to I-15 between D Street and Washington Avenue to the south and Monroe Avenue to the north (Figure 1). In addition, Matti et al (1987) indicate an area containing subsidence-induced ground fissures at approximately 700 feet to the north of the Washington Avenue bridge. The approximate locations of the Cashman fault and the area of ground fissures were derived from Matti et al’s (1987) geologic map.
The Cashman fault is part of a series of linear and curvilinear north- to northeast-trending, east-dipping late Quaternary normal faults that exist in the central portion of the Las Vegas
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 6
Valley. A maximum date of 14,690 ± 570 years before present was determined by dePolo, et al (2006) for the most recent event of displacement along the LVVFS.
However, according to Hess and dePolo (2006), the most seismically prominent fault in the Las Vegas Valley is the Frenchman Mountain fault, located approximately 9.3 miles to the east, which is capable of producing a magnitude 6.6 seismic event. The Frenchman Mountain fault is a normal fault, approximately 13.7 miles long, and located near the base of Frenchman Mountain (Slemmons et al, 2001). There is no available data in the literature indicating that the LVVFS showed movements within the last 11,000 years.
Subsurface Conditions Subsurface conditions were determined mainly based on the results of the geotechnical explorations conducted by NCC in 2007 and 2008. According to data from the soil borings drilled at the Project site, the subsurface materials along the proposed bridge widening alignment consist of embankment fill material and native clayey soils. Fill material encountered in the soil borings consists of medium-dense to very dense silty sand, clayey sand, and sandy gravel. Up to approximately 30 feet of approach fill exists at the proposed bridge site. Below the fill, the subsurface consists of predominantly stiff to hard sandy clay and fat clay with interbedded caliche/cemented layers and occasional layers of interbedded silty sand, clayey gravel, and clayey sand.
Groundwater Groundwater was measured at two of the borings (BW1-1 and BW1-2) drilled for the proposed bridge. Groundwater was encountered at elevations 2,023.5 and 2,020.1 feet in Borings BW 1-1 and BW 1-2, respectively. A groundwater elevation of 2,025 feet was used for the engineering analysis.
Fluctuations in the groundwater level and soil moisture content variations should be anticipated during and after the rainy season. Irrigation of landscaped areas, nearby construction, and numerous other man-made and natural influences also could cause a fluctuation in local groundwater levels.
Engineering Strength Parameters Design soil strength parameters for SHAFT (to calculate axial pile capacity) analysis and LPILE (to calculate lateral pile capacity) analysis were developed for the proposed bridge alignment based on the laboratory data and field investigations. Undrained shear strength of clayey soils and Caliche/cemented soil layers was estimated based on the SPT blow counts using empirical relationship that was calibrated to the results of static load test program performed by Kleinfelder (1996a). The recommended geotechnical parameters and the lithology of the soil profile used in the drilled shaft analysis are summarized in Table 4. The table also presents the recommended P-Y curves for use in the LPILE program.
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 7
TABLE 4 Geotechnical Parameters, Abutment 1
Elevation (feet)
Soil Type
Recommended P-Y Curve
(As defined in LPILE)
Effective Unit
Weight (pcf)
φ (degree)
C (psf)
K (pci) ε50
2,060-2,041 SM Sand (Reese) 125 34 0 225 -
2,041-2,025 CL Stiff Clay without Free Water 120 - 5,000 2,000 0.004
2,025-2,018 CL Stiff Clay without Free Water 60 - 5,000 2,000 0.004
2,018-2,010 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
2,010-1,993 CL Stiff Clay without Free Water 60 - 3,500 1,000 0.005
1,993–1,989.5 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
1,989.5-1,978 CL Stiff Clay without Free Water 60 - 2,000 500 0.007
1,978-1,970 CL Stiff Clay without Free Water 60 - 4,500 2,000 0.004
Geotechnical Parameters, Pier 1
2,036-2,025 CL Stiff Clay without Free Water 120 - 5,000 2,000 0.004
2,025-2,018 CL Stiff Clay without Free Water 60 - 5,000 2,000 0.004
2,018-2,010 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
2,010-1,993 CL Stiff Clay without Free Water 60 - 3,500 1,000 0.005
1,993–1,989.5 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
1,989.5-1,978 CL Stiff Clay without Free Water 60 - 2,000 500 0.007
1,978-1,970 CL Stiff Clay without Free Water 60 - 4,500 2,000 0.004
Geotechnical Parameters, Pier 2
2,036-2,025 CL Stiff Clay without Free Water 120 - 2,500 1,000 0.005
2,025-2,020 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
2,020-2,015 CL Stiff Clay without Free Water 60 - 2,500 1,000 0.005
2,015-2,011.5 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
2,011.5-1,999 CL Stiff Clay without Free Water 60 - 3,500 1,000 0.005
1,999-1,997 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
1,997–1,950 CL Stiff Clay without Free Water 60 - 1,500 500 0.007
Geotechnical Parameters, Abut 2
2,057.5-2,036.5 SM Sand (Reese) 125 34 0 225 -
2,036.5-2,025 CL Stiff Clay without Free Water 120 - 2,500 1,000 0.005
2,025-2,020 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
2,020-2,015 CL Stiff Clay without Free Water 60 - 2,500 1,000 0.005
2,015-2,011.5 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
2,011.5-1,999 CL Stiff Clay without Free Water 60 - 3,500 1,000 0.005
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 8
TABLE 4 (CONTINUED)
Geotechnical Parameters, Abut 2
Elevation (feet)
Soil Type
Recommended P-Y Curve
(As defined in LPILE)
Effective Unit
Weight (pcf)
φ (degree)
C (psf)
K (pci) ε50
1,999-1,997 CE Stiff Clay without Free Water 65 - 10,000 2,000 0.004
1,997–1,970 CL Stiff Clay without Free Water 60 - 1,500 500 0.007 Notes: pcf = pounds per cubic foot psf = pounds per square foot pci = pounds per cubic inch CE =Caliche/cemented soil layers ε50 = Strain at which one-half of the undrained strength is developed φ=Internal friction angle Su=Undrained shear strength (cohesion) k=Soil modulus parameter
Discussion and Recommendations Seismicity Section 3.2 (Acceleration Coefficient) in Division I-A of the 17th Edition of the American Association of State Highway and Transportation Officials (AASHTO, 2002) Standard Specifications for Highway Bridges states that, ”Special studies to determine site- and structure-specific acceleration coefficients shall be performed by a qualified professional” if the bridge site is located close to an ”active fault.” However, Section 2.2.3 (Fault Movements) of the National Highway Institute Geotechnical Earthquake Engineering Reference Manual (NHI Course No. 13239-Module 9) (United States Department of Transportation [USDOT], 1998) states, ”If the fault moved in the distant geologic past, during the time of a different tectonic stress regime, and if the fault has not moved in recent (Holocene) time (generally the past 11,000 years) it may be considered inactive.” Therefore, according to NHI design guidelines, the Las Vegas Valley fault system should be considered inactive with regard to bridge designs.
NCC recommends using the standard AASHTO bridge design approaches, assuming a peak ground acceleration of 0.15g. Based on the stiff soils encountered at the project site, Soil Profile Type II (AASHTO, 2002) is appropriate for the site soil conditions. The AASHTO Response Spectrum for Soil Profile Type II is recommended for the design of the bridge structure.
Corrosion Potential The corrosion potential of soil in the vicinity of the proposed bridge was evaluated. One soil sample was tested for minimum resistivity, pH, chloride content, and sulfate content. The results of these tests are presented in Table 5. Based on the current standard-of-practice in the Las Vegas area, onsite soils are considered corrosive. Proper corrosion protection should be provided for concrete and steel reinforcement.
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 9
TABLE 5 Summary of Laboratory Corrosion Tests
Boring Sample Depth (feet) Soil Type
Minimum Resistivity (ohm-cm1) pH
Sulfate Content (ppm)
Chloride Content (ppm2)
BW 1-1 10 39 Sandy Clay 740 8.72 179 400
Notes: 1 ohm-cm = ohm-centimeters 2 ppm = parts per million
Foundation Recommendations Several foundation types were considered for support of the proposed bridge structure. These foundation types included shallow foundations and drilled shafts. Factors considered included structural demands, soil resistance capacity, differential settlement between supports, and constructability. Spread footings were considered for all support locations, but were not selected because of the anticipated differential settlement under abutment support locations and the seismic retrofit strategy at the pier locations. Therefore, NCC recommends the use of pile foundations, consisting of 36-inch-diameter drilled shafts to support the abutments and 84-inch drilled shafts to support the piers. Axial Pile Capacity The axial capacity of drilled shafts was estimated using the computer program SHAFT, Version 5.0, for Windows (Ensoft, 2003). At abutment locations, geotechnical axial capacity includes skin friction and a portion of the end bearing. End bearings developed based on pile settlement was utilized for the axial compression resistance (AASHTO, 2002). However, at pier locations, geotechnical axial capacity includes only skin friction for the large diameter piles. The allowable axial capacity is estimated with a factor of safety of 2.0 in accordance with AASHTO guidelines (AASHTO, 2002). This factor of safety can be used when a static load test is performed near or at the project site with similar soil condition. At abutment locations, axial capacity of drilled shafts was appropriately reduced in consideration of the center-to-center spacing. Approximately 60 percent of the estimated individual pile axial capacity was utilized for the maximum axial loading condition. The recommended tip elevations for each support locations are summarized in Table 6.
Pile settlements were evaluated using the load transfer method implemented in the SHAFT program. The settlement of the proposed drilled shafts under the service load is estimated to be less than 0.5 inch. Consolidation settlement of the pile group was estimated based on the equivalent footing situated at a depth of 2/3 D (D is pile length) below the bottom of the pile cap. The estimated settlement is less than 0.5 inch. Pile group effects for axial compressive loads should be considered in accordance with Section 4.6.5.2.4, Standard Specifications for Highway Bridges (AASHTO, 2002). The results of the axial capacity analyses are presented in Attachment 3.
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 10
Lateral Pile Capacity The lateral pile capacity can be evaluated using the software LPILE Plus, Version 5.0, for Windows (Ensoft, 2006). The recommended geotechnical parameters to be used in the analysis are summarized in Table 4.
To account for group action in the loading direction, the lateral capacities should be multiplied by an appropriate lateral group reduction factor as recommended in Section 4.6.5.6.1.4, Standard Specifications for Highway Bridges (AASHTO, 2002). Lateral capacities of the abutment drilled shafts were appropriately reduced in consideration of the center-to-center spacing. A P-Multiplier of 0.2 was used in the analysis to estimate the lateral capacity. In addition, the piles are not placed in a row in the direction of loading for lateral loads.
TABLE 6 Pile Data Table for the Allowable Axial Capacity
Location Pile Size and
Type
Pile Cut-off
Elevation (feet)
Allowable Axial Capacity in
Compression (kips)
Ultimate Axial Capacity in
Compression (kips)
Design Tip Elevation (feet) a, b
Abutment 1 36-inch drilled shaft
2055.2 290 580 2025
Pier 1 84-inch drilled shaft
2041.0 1100 2200 1986
Pier 2 84-inch drilled shaft
2038.0 1050 2100 1983
Abutment 2 36-inch drilled shaft
2052.7 270 540 2019
Notes: a Design tip elevation is controlled by the compression demand
b Pile tip elevations should be adjusted based on pile cut-off elevation to provide the minimum recommended pile length.
Slope Stability Slope stability for the proposed abutment slopes (1.5H:1V) was analyzed using the computer program SLIDE, Version 5.026 (Rocscience, Inc., 2006). Drained strength parameters, which are assumed weaker than the undrained strength parameters, were used for the analysis. In addition, the following design criteria were used:
• Permanent slopes were required to have a minimum factor of safety of 1.5 for the static condition and a minimum factor of safety of 1.1 for the pseudostatic loading condition, using a horizontal earthquake loading coefficient of 0.075 (½ x Peak Ground Acceleration).
• Traffic surcharge loads were modeled as a uniform surface load equivalent to 250 psf in the slope stability analyses.
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 11
Results of the slope stability analyses indicate that the required minimum static and pseudostatic factors of safety for global stability are satisfied. However, the 1.5H:1V abutment slopes should be concrete-paved to protect against surficial instability due to erosion. The results of the slope stability analyses are presented in Attachment 3.
Lateral Earth Pressures Active and at-rest lateral earth pressure coefficients and the equivalent fluid unit weights for horizontal backfill conditions are summarized in Table 7. The values in Table 7 are based on the assumption that the walls will be backfilled with granular backfill conforming to NDOT Standard Specifications (2001).
For seismic loading conditions, the incremental seismic/dynamic earth pressure should be added to the static active earth pressure. Seismic wall pressures for cantilever walls may be estimated by the Mononobe-Okabe Method (Kramer, 1996). The recommended incremental seismic earth pressure coefficients and equivalent fluid unit weight are provided in Table 7. The at-rest incremental seismic earth pressure was estimated applying a horizontal acceleration coefficient equal to 1.5 times the peak ground acceleration (AASHTO, 2002).
TABLE 7 Summary of Lateral Earth Pressures
Earth Pressure Coefficients Equivalent Fluid Unit Weight1 (pcf)
Condition Active At-Rest Active
Seismic At-Rest Seismic Active At-Rest
Active Seismic
At-Rest Seismic
horizontal backfill 0.28 0.44 0.04 0.15 36 55 5 18
Notes: 1 The resultant static (active and at-rest) lateral earth forces act at a height of 0.33H above the wall base, and the resultant incremental seismic lateral earth pressures may be assumed to act at a height of 0.6H above the wall base, where H is the height of the wall.
The static active and at-rest lateral earth pressures have triangular distributions, with the largest load occurring at the bottom of the wall. The incremental seismic earth pressure has an inverted triangular distribution, with the largest load occurring at the top of the wall. The resultant incremental seismic lateral force may be assumed to act at a height of 0.6 H above the wall base, where H is the height of the wall.
The values in Table 7 assume that backfill materials are free-draining and, therefore, do not include hydrostatic pressures. Adequate drainage should be provided behind the walls in accordance with NDOT Standard Plans (2007). Surcharge due to normal vehicular traffic loads should be modeled as an additional 250 psf, where applicable. Uniformly distributed vertical surcharge loads should be applied as a uniform (rectangular) distributed pressure with the appropriate corresponding lateral earth pressure coefficient (active or at-rest).
If the wall is prevented from lateral movement at the top, the horizontal earth pressure approaches the value of an at-rest condition. At-rest pressure coefficients and equivalent fluid unit weights are included in Table 7.
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 12
Construction Considerations Site Preparation The site should be prepared in accordance with Section 201 of NDOT’s Standard Specifications (2001). Vegetation, trash, and other deleterious material should be removed and disposed of prior to placement of fill.
Earthwork and Fill Material Specifications All earthwork should be performed in accordance with NDOT Standard Specifications Section 203 (2001). Granular backfill should conform to NDOT Standard Specifications (2001), Section 207.02.02. Ponding and jetting of granular fill should not be allowed.
Drilled Shafts Installation Excavation and construction of the drilled shafts should be observed by a qualified geotechnical engineer or a technician under the supervision of a geotechnical engineer. The construction of the drilled shafts should be in accordance with NDOT’s Standard Specifications (2001), Section 509. Groundwater conditions should be expected during drilled shafts construction. The construction method should not result in loose or disturbed soils or voids. If caving soil conditions occur during drilled shaft installation, temporary casing should be considered. Difficult drilling conditions should be anticipated through caliche/cemented soil layers.
Because of the close spacing of drilled shafts at the abutments, drilled shafts located closer than three times the shaft diameter should be drilled after the first pile (constructed within 3 pile diameter distance) concrete is hardened as recommended in Section 509.03.16 of NDOT Standard Specifications (2001).
The bottoms of the shaft borings should be adequately cleaned of loose or disturbed materials, using a drilling bucket or an approved alternative method. The bottom 2 feet of the shaft boring should be drilled with a cleanout bucket to provide adequate removal of loose materials. Schedule 80 polyvinyl chloride (PVC) or schedule 40 steel inspection pipes should be installed in each shaft, in accordance with NDOT standard provisions, to permit cross-hole sonic testing of drilled shafts.
Temporary Excavations and Shoring Excavations should be performed in accordance with NDOT’s Standard Specifications (2001), Section 206. Trenches and temporary excavations should be excavated in accordance with Occupational Safety and Health Administration safety requirements.
Appropriate measures should be taken to prevent damage to adjacent structures, improvements, and utilities. In areas where existing structures will be within a distance equal to the height of the shoring, lateral deflections at the top of shoring should be limited to less than 1 inch.
Measures to control the impact of surface water and groundwater on the stability of temporary excavations should be employed.
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 13
Geotechnical Observation Grading operations, including excavations and fill placement, drilled shaft installation, and excavations for utility trenches should be observed by a geotechnical engineer or a technician under the supervision of a geotechnical engineer. Variations in soil and geologic conditions might be encountered during construction. To permit correlation between exploration data and actual conditions encountered during construction, a qualified geotechnical engineer, and/or engineering geologist should perform onsite review during construction.
Limitations This technical memorandum has been prepared for the exclusive use of NDOT and the NCC design team for specific application to the design and construction of the proposed I-15 over UPRR Track (Bridge No. G-941) widening in North Las Vegas, Nevada. The findings, conclusions, and recommendations presented in this technical memorandum were prepared in accordance with generally accepted geotechnical engineering practice. No other warranty, either express or implied, is made.
The data from borings indicate subsurface conditions only at specific locations and times, and only to the depths penetrated. They do not necessarily reflect strata variation between exploration locations. Subsurface conditions and water levels at other locations might differ from those at the indicated locations. Also, the passage of time might result in changes in the conditions at these locations. If variations in subsurface conditions from those described herein are noted during construction, NCC geotechnical engineers should be notified immediately, and the recommendations in this technical memorandum should be re-evaluated.
In the event that any changes in the nature, design, or location of the planned facilities occur, the conclusions and recommendations of this technical memorandum should not be considered valid, unless the changes and conclusions of this technical memorandum are reviewed and modified or verified in writing by an NCC geotechnical engineer. NCC is not responsible for any claims, damages, or liability associated with interpretation of subsurface data by others or reuse of the subsurface data or engineering analyses without the express written authorization of NCC.
References American Association of State Highway and Transportation Officials (AASHTO). 2002. Standard Specifications for Highway Bridges, 17th Edition.
Bell, J. W., Price, J. G., and Mifflin, M. D. 1992. Subsidence-induced Fissuring Along Preexisting Faults in Las Vegas Valley, Nevada. Association of Engineering Geologists, Proceedings of the 35th Annual Meeting, Los Angeles, pp. 66-75.
dePolo, C. M., Bell, J. W., Boron, S., Slemmons, D. B., and Werle, J. L.. 2006. Latest Quaternary Fault Movement Along the Las Vegas Valley Fault System, Clark County, Nevada: Environmental & Engineering Geoscience, Volume XII, Number 2, pp 181-193.
FINAL FOUNDATION RECOMMENDATIONS, I-15 WIDENING OVER UNION PACIFIC RAIL ROAD SPUR TRACK (BRIDGE NO. G-941), I-15 NORTH, US-95 TO CRAIG ROAD DESIGN-BUILD PROJECT, NORTH LAS VEGAS, NEVADA
SCO/GEOTECH MEMO_BW1_ I-15 OVER UPRR SPUR TRACK.DOC 14
Ensoft, Inc. 2003. SHAFT, Version 5.0 for Windows.
Ensoft, Inc. 2006. LPILE Plus 5.0 for Windows.
Hess, R. H., and dePolo, C. M. 2006. Loss-Estimation Modeling of Earthquake Scenarios for Each County in Nevada Using HAZUS-MH. Nevada Bureau of Mines and Geology, Open File Report 06-1.
Hoit, M., M. McVay, and C. Hays. 2008. Documentation of Computer Program FB-MultiPier, Version 4.12b. Bridge Software Institute, University of Florida, Gainesville, Florida. 2005.
Kleinfelder. 1996a. I-15/US 95 Load Test Program, Las Vegas, Nevada, prepared for Parsons Brinckerhoff, January 26.
Kleinfelder. 1996b., Geotechnical Investigation, I-15/U.S. 95 Interchange Reconstruction Stage 2, Bridge Design Report, Clark County, Nevada, 31-215909-001. Report Prepared for Parsons Brinkerhoff, Inc., September 16.
Kramer, S. L. 1996. Geotechnical Earthquake Engineering. Prentice-Hall International Series in Civil Engineering and Engineering Mechanics. Upper Saddle River, New Jersey.
Matti, J. C., Castor, Bachhuber, F. W., Morton, S. M., and Bell, J. W.. 1987. Las Vegas NW Quadrangle Geologic Map: Prepared by the Nevada Bureau of Mines and Geology Map in Collaboration with the United States Geological Survey, Scale 1:24,000.
Nevada Department of Transportation (NDOT). 2001. Standard Specifications.
Nevada Department of Transportation (NDOT). 2007. Standard plans.
Page, W. R., Lundstrom, S. C., Harris, A. G., Langenheim, V. E., Workman, J. B., Mahan, S. A., Paces, J. B., Dixon, G. L., Rowley, P. D., Burchfiel, B. C., Bell, J. W. and Smith, E. I. 2005. Geologic and Geophysical Maps of the Las Vegas 30' x 60' Quadrangle, Clark and Nye Counties, Nevada and Inyo County, California: United States Geological Survey Scientific Investigation Map SIM-2814 and Pamphlet Accompanying the United States Geological Survey Scientific Investigation Map SIM-2814.
Rocscience, Inc. 2008. 2-D Slope Stability Program for Evaluating the Factor of Safety or Probability of Failure. SLIDE, Version 5.033
Slemmons, D. B., Bell, J. W., dePolo, C. M., Ramelli, A. R., Rasmussen, G. S., Langenheim, V. E., Jachens, R. C., Smith K., and O’Donnell, J. 2001. Earthquake Hazard in Las Vegas, Nevada in Luke, B., Jacobson, E., and Werle, J., Editors, Proceedings, 36th Annual Symposium on Engineering Geology and Geotechnical Engineering, University of Nevada, Las Vegas, pp 447-459. March 28-30.
U.S. Department of Transportation, Federal Highway Administration (FHWA). 1998. Geotechnical Earthquake Engineering, NHI Course No. 13239, Module 9, Publication No. FHWA HI-99-012.
Figures
EXPLANATION
Source: Page, W. R., Lundstrom, S. C., Harris, A. G., Langenheim, V. E., Workman, J. B., Mahan, S. A., Paces, J. B., Dixon, G. L., Rowley, P. D., Burchfiel, B. C., Bell, J. W. and Smith, E. I., 2005, Geologic and Geophysical Maps of the Las Vegas 30' x 60' Quadrangle, ClarkNye Counties, Nevada and Inyo County, California: United States Geological Survey Scientific Investigation Map SIM-2814.
Proposed Road Expansion Alignment
CH2MHILL
Figure 1Site Location and Geologic MapI-15 Over UPRR Spur Track (BW-1)Bridge No.: G-941I-15 North, US-95 Interchange to Craig RoadNorth Las Vegas, Nevada
CRAIG ROAD
ALEXANDER ROAD
GOWAN ROAD
EAST CHEYENNE ROAD
CAREY AVENUE
LAKE MEAD BOULEVARD
OWENS AVENUE
WASHINGTON AVENUE
BONANZA AVENUE
VALLEY
VIEW
FAULT
CONCORD STREET
EASTERN AVENUE
DECATUR
FAULT
LAS VEGAS VALLEY FAULT SYSTEM
I-15 OVER UPRR SPUR TRACK (G-941)
D
STREET
Attachment 1
Boring Logs
Attachment 1(a)
Boring Logs
North Corridor Constructors (2008)
GENERAL NOTES DRILLING & SAMPLING SYMBOLS: SS: Split Spoon - 1-3/8" I.D., 2" O.D., unless otherwise noted HS: Hollow Stem Auger ST: Thin-Walled Tube - 2" O.D., unless otherwise noted PA: Power Auger RS: Ring Sampler - 2.42" I.D., 3" O.D., unless otherwise noted HA: Hand Auger DB: Diamond Bit Coring - 4", N, B RB: Rock Bit BS: Bulk Sample or Auger Sample WB: Wash Boring or Mud Rotary PID: Photo Ionization Detector*
*Used mostly to detect volatile organic compounds in soil, sediment, air and water. The number of blows required to advance a standard 2-inch O.D. split-spoon sampler (SS) the last 12 inches of the total 18-inch penetration with a 140-pound hammer falling 30 inches is considered the “Standard Penetration” or “N-value”. For 3” O.D. ring samplers (RS) the penetration value is reported as the number of blows required to advance the sampler 12 inches using a 140-pound hammer falling 30 inches, reported as “blows per foot,” and is not considered equivalent to the “Standard Penetration” or “N-value”.
The following average energy transfer efficiencies are applicable to the Auto hammer used to obtain the soil samples.
1. Black Eagle’s Diedrich D-50 Drill Rig: 69% with a standard deviation of 3%
2. Terracon’s Diedrich D-120 Drill Rig: 81% with a standard deviation of 4%
3. WDC’s CME 85 Drill Rig: 76%
WATER LEVEL MEASUREMENT SYMBOLS: WL: Water Level WS: While Sampling N/E: Not Encountered WCI: Wet Cave in WD: While Drilling N/M: Not Measured DCI: Dry Cave in BCR: Before Casing Removal AB: After Boring ACR: After Casing Removal
Water levels indicated on the boring logs are the levels measured in the borings at the times indicated. Groundwater levels at other times and other locations across the site could vary. In pervious soils, the indicated levels may reflect the location of groundwater. In low permeability soils, the accurate determination of groundwater levels may not be possible with only short-term observations.
DESCRIPTIVE SOIL CLASSIFICATION: Soil classification is based on the Unified Classification System. Coarse Grained Soils have more than 50% of their dry weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand. Fine Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they are plastic, and silts if they are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents may be added according to the relative proportions based on grain size. In addition to gradation, coarse-grained soils are defined on the basis of their in-place relative density and fine-grained soils on the basis of their consistency.
CONSISTENCY OF FINE-GRAINED SOILS
RELATIVE DENSITY OF COARSE-GRAINED SOILS
Unconfined Compressive
Strength, Qu, psf
Standard Penetration or N-value (SS)
Blows/Ft.
Consistency
Standard Penetration or N-value (SS)
Blows/Ft.
Relative Density
< 500 <2 Very Soft 0 – 4 Very Loose 500 – 1,000 2-4 Soft 5 – 10 Loose 1,001 – 2,000 4-8 Medium Stiff 11 – 30 Medium Dense 2,001 – 4,000 8-15 Stiff 31 – 50 Dense 4,001 – 8,000 15-30 Very Stiff 50+ Very Dense 8,000+ 30+ Hard
UNIFIED SOIL CLASSIFICATION SYSTEM Criteria for Assigning Group Symbols and Group Names Using Laboratory TestsA Soil Classification
Group Symbol
Group NameB
Cu ≥ 4 and 1 ≤ Cc ≤ 3E GW Well-graded gravelF Clean Gravels Less than 5% finesC Cu < 4 and/or 1 > Cc > 3E GP Poorly graded gravelF
Fines classify as ML or MH GM Silty gravelF,G, H
Coarse Grained Soils
More than 50% retained
on No. 200 sieve
Gravels More than 50% of coarse fraction retained on No. 4 sieve Gravels with Fines More
than 12% finesC Fines classify as CL or CH GC Clayey gravelF,G,H
Cu ≥ 6 and 1 ≤ Cc ≤ 3E SW Well-graded sandI Clean Sands Less than 5% finesD Cu < 6 and/or 1 > Cc > 3E SP Poorly graded sandI
Fines classify as ML or MH SM Silty sandG,H,I
Sands 50% or more of coarse fraction passes No. 4 sieve Sands with Fines
More than 12% finesD Fines Classify as CL or CH SC Clayey sandG,H,I
PI > 7 and plots on or above “A” lineJ CL Lean clayK,L,M Silts and Clays Liquid limit less than 50
inorganic
PI < 4 or plots below “A” lineJ ML SiltK,L,M
Liquid limit - oven dried Organic clayK,L,M,N
Fine-Grained Soils 50% or more passes the No. 200 sieve
organic
Liquid limit - not dried < 0.75 OL
Organic siltK,L,M,O
inorganic PI plots on or above “A” line CH Fat clayK,L,M
Silts and Clays Liquid limit 50 or more
PI plots below “A” line MH Elastic SiltK,L,M
Liquid limit - oven dried Organic clayK,L,M,P organic
Liquid limit - not dried < 0.75 OH
Organic siltK,L,M,Q
Highly organic soils Primarily organic matter, dark in color, and organic odor PT Peat
A Based on the material passing the 3-in. (75-mm) sieve B If field sample contained cobbles or boulders, or both, add “with cobbles
or boulders, or both” to group name. C Gravels with 5 to 12% fines require dual symbols: GW-GM well-graded
gravel with silt, GW-GC well-graded gravel with clay, GP-GM poorly graded gravel with silt, GP-GC poorly graded gravel with clay.
D Sands with 5 to 12% fines require dual symbols: SW-SM well-graded sand with silt, SW-SC well-graded sand with clay, SP-SM poorly graded sand with silt, SP-SC poorly graded sand with clay
E Cu = D60/D10 Cc = 6010
230
DxD)(D
F If soil contains ≥ 15% sand, add “with sand” to group name. G If fines classify as CL-ML, use dual symbol GC-GM, or SC-SM.
HIf fines are organic, add “with organic fines” to group name. I If soil contains ≥ 15% gravel, add “with gravel” to group name. J If Atterberg limits plot in shaded area, soil is a CL-ML, silty clay. K If soil contains 15 to 29% plus No. 200, add “with sand” or “with
gravel,” whichever is predominant. L If soil contains ≥ 30% plus No. 200 predominantly sand, add
“sandy” to group name. M If soil contains ≥ 30% plus No. 200, predominantly gravel, add
“gravelly” to group name. N PI ≥ 4 and plots on or above “A” line. O PI < 4 or plots below “A” line. P PI plots on or above “A” line. Q PI plots below “A” line.
Form 111—6/98
TEST ABBREVIATIONS
M Moisture content
D Dry density
G Gradation
A Atterberg limits
DS Consolidated drained direct shear
T Unconsolidated undrained triaxial
U Unconfined compression
Co 1-D consolidation
S Swell potential
P Modifed proctor
R R-value
HM Harvard miniature compaction
Ch Chemical tests
CL
36
29
23
24
8
7
6
5
4
3
9.00
1
37
FILL
FILL
FILL
FILL
FILL
FILL
FILL
29.00
24.00
19.00
2
22.00
FILL - SANDY CLAY - moist, brown
FILL - SILTY SAND - trace gravel, moist, lightbrown
FILL - CLAYEY SAND - trace gravel, moist,brown
FILL - SILTY SAND - trace gravel, moist,brown
FILL - SILTY, CLAYEY SAND - with gravel,moist, light brown
- with clayey sand lenses, moist
FILL - SILTY SAND - with gravel, dry, brown
FILL - SILTY GRAVEL - with sand, dry, brown
30.0029.50
50/6"
24.5050/6"
17.00
14.50
3.50
25.50
20.00
15.50
10.50
5.505.00
3.504.00
26.00
SS
14.00
RS
RS
SS
RS
SSBS
SS
12
2.00
0.00
50/6"
9
17
11
12
10
34
50/6"
27
12
9
19
29
21
10
11
14
12
TYPE
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
REMARKS
DATE 8-inch Hollow Stem Auger64075084
12/27/07
LAB TESTS6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
SHEET 1 OF 4
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
2023.5
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
SANDY CLAY - moist, hard, brown
I-15/US 95 Interchange to Craig RoadJOB DESCRIPTION
BLOW COUNT
2066.8 ft. (NAVD88)12/27/07
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
PLATE No. A-1
NO.
HAMMER DROP SYSTEM
GROUND ELEV.
USCSGroup
LOCATION
Last1 foot
END DATE
Yes
BW1-1
PROJECT No.
12/26/07
SAMPLE
Auto Hammer
869+36LT 9Wendy MontesDiedrich D-120Tim Thompson
START DATE
43.3
BORING
M
2061.8
2056.8
2051.8
2046.8
2041.8 M, D
M, D, G, A,DS
M
M, G, A
MR, P
M
12/27/07DRILLINGMETHOD
ELEV. (ft)
Interstate-15 Design Build
DATE
DEPTH(ft)
ELEV.(ft)
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/1
9/08
DEPTH (ft)
40
SC-SM
54.00
49.50
45.50
40.50
35.50
30.50
29
50/0"
32.50
68
34.00
39
14
13
12
11
10
9
SC
CALICHE
50/6"
SILTY, CLAYEY SAND - with gravel, moist,dense
CLAYEY SAND - with caliche gravel, verymoist, medium dense, white
CALICHE - dry, hard, white
- occasional partially cemented lenses, hard,light green
SANDY CLAY - moist, hard
CL
- with partially cemented lenses
- occasional partially cemented lenses, hard
SANDY LEAN CLAY - moist, very stiff, whiteto light brown
FAT CLAY - with sand, moist, stiff, brown
SANDY CLAY - moist, very stiff, light brown
60.00
57.00
54.00
47.00
43.00
- thin caliche lenses
SS
CL
RS
SS
RS
SS
RS
27
CH
CL
59.00
54.00
49.00
44.00
39.00
34.00
25
25M, D, G, A,
Co
15
43
17
14
18
50/0"
50/6"
24
10
7
23
8-inch Hollow Stem Auger
Last1 foot
USCSGroup
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
43.3DATE
START DATE
64075084
I-15/US 95 Interchange to Craig Road
12/27/07
TYPE 6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
SHEET 2 OF 4
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
REMARKS
BORING
BLOW COUNT
2066.8 ft. (NAVD88)12/27/07
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
PLATE No. A-2
NO. LAB TESTS
GROUND ELEV.
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
LOCATION
JOB DESCRIPTION
END DATE
Yes
BW1-1
PROJECT No.
12/26/07
SAMPLE
Auto Hammer
869+36LT 9Wendy MontesDiedrich D-120Tim Thompson
HAMMER DROP SYSTEM2023.5
2031.8
2026.8
2021.8
2016.8
2011.8
M, G, A
M
M, G, A, T
M, Ch
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/1
9/08
DRILLINGMETHOD
ELEV. (ft)DEPTH (ft)
Interstate-15 Design Build
12/27/07DATE
DEPTH(ft)
ELEV.(ft)
16
27
19
50/6"
38
42
22
21
20
19
17
65.5015
CH
CL
CALICHE
GC
CL
CH
89.00
86.00
84.00
18
77.50
FAT CLAY - with sand, moist, stiff
- with caliche gravel
SANDY CLAY - with cemented lenses, moist,stiff, white
CALICHE - dry, hard, white
- with caliche lenses, very dense
- with partially cemented lenses
CLAYEY GRAVEL - with sand, very moist,medium dense
- non-cemented, stiff
SANDY CLAY - with partially cementedlenses, very moist, very stiff, white
FAT CLAY - with sand, very moist, very stiff,light green
43
83.00
60.50
74.50
68.00
62.50
87.50
86.00
80.50
74.50
71.50
70.0070.00
90.00
SS
79.00
SS
RS
RS
RS
ST
RS
ST
24
69.00
64.00
23
11
20
18
14
8
4
18
74.00
5
5
11
50/6"
12
19
8
I-15/US 95 Interchange to Craig Road
USCSGroup
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
REMARKS
DATE
LAB TESTS
64075084
43.3
12/27/07
TYPE 6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
SHEET 3 OF 4
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
2023.5
- occasional partially cemented lenses, verystiff
8-inch Hollow Stem Auger
LOCATION
BLOW COUNT
2066.8 ft. (NAVD88)12/27/07
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
PLATE No. A-3
NO.
HAMMER DROP SYSTEM
Last1 foot
BORING
JOB DESCRIPTION
END DATE
Yes
BW1-1
PROJECT No.
12/26/07
SAMPLE
Auto Hammer
869+36LT 9Wendy MontesDiedrich D-120Tim Thompson
START DATE
GROUND ELEV.
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
2001.8
1996.8
1991.8
1986.8
1981.8 M, G, A
M, G, A, T
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/1
9/08
DRILLINGMETHOD
- trace caliche gravel, stiff
ELEV. (ft)DEPTH (ft)
Interstate-15 Design Build
12/27/07DATE
DEPTH(ft)
ELEV.(ft)
ELEV.(ft)
DEPTH(ft)
DATE12/27/07
Interstate-15 Design Build
DEPTH (ft) ELEV. (ft) DRILLINGMETHOD
90.50
RS118
35
33
94.00
MH
CL
4195.50
92.50
95.50
ELASTIC SILT - with sand, very moist, hard,white
SANDY CLAY - very moist, very stiff, lightbrown
- with partially cemented lenses, hard1971.8
1966.8
1961.8
1956.8
1951.8
23
LOCATION
Last1 foot
LAB TESTS
43.3
START DATE
869+36LT 9Wendy MontesDiedrich D-120Tim Thompson
Auto Hammer
SAMPLE
12/26/07
PROJECT No.
BW1-1
Yes
JOB DESCRIPTION
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
BORING
GROUND ELEV.
HAMMER DROP SYSTEM
NO.
PLATE No. A-4
PercentRecov'd
GROUNDWATER LEVEL
EXPLORATION LOG
12/27/072066.8 ft. (NAVD88)
BLOW COUNT
END DATE
BACKFILLED
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/1
9/08
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
2023.5
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
USCSGroup MATERIAL DESCRIPTION6 inch
IncrementsTYPE
12/27/07
I-15/US 95 Interchange to Craig Road
640750848-inch Hollow Stem AugerDATE
REMARKS
SHEET 4 OF 4
4
2.90
15
50/5"
50/6"
50/6"
50/6"
50/6"
50/4"
8
7
5
9.50
3
1
2
FILL
FILL
FILL
FILL
FILL
FILL
FILL
6
30.00
FILL - SANDY CLAY - very moist, brown todark brown
- with gravel, red brown
- occasional clay lenses
FILL - SILTY SAND - trace gravel, moist,yellow brown
FILL - SILTY SAND - with gravel, moist, redbrown
FILL - SILTY SAND - with gravel, moist, redbrown
FILL - SILTY SAND - with gravel, moist, whiteto light brown
FILL - SILTY SAND - with gravel, dry, redbrown
- white to light brown
5.00
CONCRETE - 8.5 inches
5.00
27.50
22.00
15.00
11.00
7.50
4.50
0.70
25.45
20.00
14.50
24.00
FILL - SILTY SAND - with gravel, moist,brown
SS
CONC
RS
RS
SS
RS
BS
SS
SS
50/4"
19.00
14.00
9.00
4.00
2.002.00
50/5"
6
42
50/6"
29.005
12
46
50/6"
50/6"
36
24
50/6"
1/28/08
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
REMARKS
DATE 8-inch Hollow Stem Auger
Last1 foot
I-15/US 95 Interchange to Craig Road
LAB TESTSTYPE 6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
SHEET 1 OF 4
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
2020.1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
64075084
LOCATION
BLOW COUNT
2064.1 ft. (NAVD88)01/28/08
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
PLATE No. A-1
NO.
HAMMER DROP SYSTEM
USCSGroup
BORING
JOB DESCRIPTION
END DATE
Yes
BW1-2
PROJECT No.
1/27/08
SAMPLE
Auto Hammer
872+73RT 7Rick EricksonDiedrich D-120Tim Thompson
START DATE
44.0GROUND ELEV.
M
2059.1
2054.1
2049.1
2044.1
2039.1M, D
M, G, A
M, G, A
M, D
HM
M, G, A
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/2
3/08
DEPTH (ft) ELEV. (ft)
Interstate-15 Design Build
01/28/08DATE
DEPTH(ft)
ELEV.(ft)
DRILLINGMETHOD
27
55.50
49.25
45.50
39.50
35.50
30.50
25
41.00
50/3"
43.50
50/6"
32
14
13
12
11
10
9
CL
SC-SM
42
SILTY SAND - with partially cemented lenses,very moist, medium dense, light green
- occasional partially cemented lenses
SANDY CLAY - with partially cementedlenses, very moist, hard, white to light green
SILTY CLAYEY SAND - very moist, mediumdense, light green
32.50
CLAYEY SAND - with gravel, partiallycemented lenses, very moist, medium dense,light green
CALICHE
CALICHE - dry, hard, white
- partially cemented, moist, hard, white
- with partially cemented lenses
- very stiff, white to light green
LEAN CLAY - with sand, trace salts, moist,very stiff, brown
FILL - SANDY CLAY - very moist, brown todark brown
60.00
55.00
52.50
44.50
- partially cemented, moist, very dense, white
SS
SC
9
RS
SS
RS
SS
RS
9
M, D, G, A,Co
CL
FILL
59.00
54.00
49.00
44.00
39.00
34.00
28
18
9
14
11
14
11
14
50/3"
9
50/6"
SM
16
8-inch Hollow Stem Auger
Last1 foot
USCSGroup
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
44.0DATE
START DATE
64075084
I-15/US 95 Interchange to Craig Road
1/28/08
TYPE 6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
SHEET 2 OF 4
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
2020.1
REMARKS
BORING
BLOW COUNT
2064.1 ft. (NAVD88)01/28/08
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
PLATE No. A-2
NO. LAB TESTS
GROUND ELEV.
LOCATION
JOB DESCRIPTION
END DATE
Yes
BW1-2
PROJECT No.
1/27/08
SAMPLE
Auto Hammer
872+73RT 7Rick EricksonDiedrich D-120Tim Thompson
HAMMER DROP SYSTEM
2029.1
2024.1
2019.1
2014.1
2009.1
M
M, G, A, T
M
M, G, A, T
M
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/2
3/08
DRILLINGMETHOD
ELEV. (ft)DEPTH (ft)
Interstate-15 Design Build
01/28/08DATE
DEPTH(ft)
ELEV.(ft)
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
21
75.50
70.50
65.4565.00
60.50
3
20
12
16
M, G, A
50/5"
67.00
20
19
18
17
16
15
CH
CL
SC
8
SANDY LEAN CLAY - with caliche gravel,very moist, stiff, brown to light brown
M, G, A
SANDY FAT CLAY - very moist, soft, brown
- caliche gravel and partially cemented lenses,very moist, stiff, brown
- very moist, light brown to brown80.50
- with partially cemented lenses
85.50
- with caliche gravel, very moist, light brown tobrown
- partially cemented, very moist, very dense,white
- with partially cemented lenses
CLAYEY SAND - with gravel, occasionalpartially cemented lenses, very moist, loose,light green
- partially cemented, very moist, hard
SANDY FAT CLAY - with gravel, occasionalpartially cemented lenses, very moist, hard,white
90.00
87.00
75.00
84.00
- partially cemented, moist, white
SS
CH
RS
RS
SS
RS
ST
SS 2
M, D
79.00
74.00
69.00
65.00
64.00
8
5
8
16
89.00
12
7
8
5
1
36
48
7
7
50/5"
3
8-inch Hollow Stem Auger
LAB TESTSLast1 foot
USCSGroup
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
M
DATE
872+73RT 7Rick EricksonDiedrich D-120Tim Thompson64075084
I-15/US 95 Interchange to Craig Road
1/28/08
TYPE 6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
SHEET 3 OF 4
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
REMARKS
BORING
BLOW COUNT
2064.1 ft. (NAVD88)01/28/08
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
PLATE No. A-3
NO.
44.0GROUND ELEV.
START DATE
LOCATION
JOB DESCRIPTION
END DATE
Yes
BW1-2
PROJECT No.
1/27/08
SAMPLE
Auto Hammer
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
HAMMER DROP SYSTEM2020.1
ELEV.(ft)
1999.1
1994.1
1989.1
1984.1
1979.1
M, G, A
M
M, G, A
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/2
3/08
DRILLINGMETHOD
ELEV. (ft)DEPTH (ft)
Interstate-15 Design Build
01/28/08DATE
DEPTH(ft)
1969.1
1964.1
1959.1
1954.1
1949.1
M
ELEV.(ft)
ELEV. (ft)DEPTH (ft)
Interstate-15 Design Build
01/28/08
DEPTH(ft)
DATE
CLST
RS3613
1
9
94.00
M97.00
- stiff
- with partially cemented lenses, very stiff
SANDY CLAY - trace caliche gravel, verymoist, stiff, light brown
FAT CLAY - with sand, very moist, soft, brown
95.50
93.00
CH
95.50
90.50
2223
22
97.00
JOB DESCRIPTION
DRILLINGMETHOD
USCSGroupLast
1 footLAB TESTS
44.0
START DATE
872+73RT 7Rick EricksonDiedrich D-120Tim Thompson
Auto Hammer
SAMPLE
1/27/08
PROJECT No.
BW1-2
NO.BLOW COUNT
2064.1 ft. (NAVD88)01/28/08
EXPLORATION LOG
GROUNDWATER LEVEL
Yes
PLATE No. A-4
END DATE
HAMMER DROP SYSTEM
GROUND ELEV.
BORING
LOCATION
PercentRecov'd
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
1/28/08
REMARKS
DATE 8-inch Hollow Stem Auger
I-15/US 95 Interchange to Craig Road
2020.1
TYPE 6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
SHEET 4 OF 4
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/2
3/08
64075084
2
80
50/4"
50/5"
50/4"
50
8
7
6
5
4
19.00
13.50
CH
ML
FILL
FILL
FILL
FILL
FILL
FILL
CONC
29.00
FAT CLAY - with sand, moist, stiff, brown
3
19.50
FILL - SILTY SAND with gravel, slightly moist,light brown to brown
FILL - SILTY GRAVEL with sand, dry toslightly moist, red brown
- red brown
FILL - SILTY SAND with gravel, dry to slightlymoist, brown
FILL - SILTY GRAVEL with sand, dry toslightly moist, brown
FILL - SILTY SAND with gravel, dry to slightlymoist, light brown
FILL - SILTY GRAVEL with sand, slightlymoist, brown
CONCRETE- 9 inches
30.0029.50
50/6"
22.00
10
8.50
6.00
4.00
0.75
25.00
20.50
14.80
9.85
5.004.80
14.00
28.00
SS
24.00
RS
RS
SS
RS
BS
SS
SS3
9.00
4.00
2.002.00
42
26
4
50/6"
38
50/4"
50/5"
24
8
38
17
26
25
11
50/4"
TYPE
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
REMARKS
DATE 8-inch Hollow Stem Auger64075084
1/23/08
LAB TESTS6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
SHEET 1 OF 4
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
SANDY SILT - moist, stiff, dark brown
I-15/US 95 Interchange to Craig RoadJOB DESCRIPTION
BLOW COUNT
2061.7 ft. (NAVD88)01/23/08
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
PLATE No. A-1
NO.
HAMMER DROP SYSTEM
GROUND ELEV.
USCSGroup
LOCATION
Last1 foot
END DATE
Yes
BEN1-1
PROJECT No.
1/22/08
SAMPLE
Auto Hammer
873+66RT 63Rick EricksonDiedrich D-120Tim Thompson
START DATE
N/M
BORING
M, G, A
2056.7
2051.7
2046.7
2041.7
2036.7
M
M
M
M, G, A
M, DS
M, D, G, A
DATE
DRILLINGMETHOD
ELEV. (ft)DEPTH (ft)
01/23/08
DEPTH(ft)
ELEV.(ft)
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/2
1/08
Interstate-15 Design Build
50/5"
CL-ML
45.50
39.40
34.9534.50
30.50
50/6"
50/6"
50/4"
55.00
50/4"
60.00 15
14
13
12
11
109
CL
M
12
- with caliche lenses
M
M, DM, G, A
- trace caliche gravel, white to light green
49.40
- With trace caliche gravel, very moist, mediumstiff, white to light green
CH
SANDY LEAN CLAY - partially cemented,slightly moist, hard, white
CALICHE - dry, hard, white
- partially cemented, hard, white
SANDY SILTY CLAY with trace gravel, moist,very stiff, white to light brown
FAT CLAY - with sand, moist, stiff, brown
60.00
37.00
35.50
32.50
- with partially cemented lenses, hard, white
SS
CALICHE
SS
RS
RS
RSST
SS
6
59.00
54.00
49.00
44.00
39.00
34.5034.00
6
6
50/6" M, G, A, T
50/4"
10
9
50/4"
6
6
50/5"
50/6"
DATE
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
LAB TESTSLast1 foot
USCSGroup
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
START DATE
REMARKS
873+66RT 63Rick EricksonDiedrich D-120Tim Thompson
8-inch Hollow Stem Auger64075084
I-15/US 95 Interchange to Craig Road
1/23/08
TYPE 6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
M, G, A, Co
BORING
BLOW COUNT
2061.7 ft. (NAVD88)01/23/08
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
PLATE No. A-2
NO.
N/MGROUND ELEV.
LOCATION
JOB DESCRIPTION
END DATE
Yes
BEN1-1
PROJECT No.
1/22/08
SAMPLE
Auto HammerHAMMER DROP SYSTEM
SHEET 2 OF 4
ELEV.(ft)
DEPTH(ft)
2026.7
2021.7
2016.7
2011.7
2006.7
M
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/2
1/08
DRILLINGMETHOD
ELEV. (ft)DEPTH (ft)
Interstate-15 Design Build
01/23/08DATE
21
80.50
75.50
70.50
65.50
6
50/5"
3
21
9
CL
22
64.00
20
19
18
17
16
CH
CL
CH
CL
51
- very moist, green brown
- trace caliche gravel
FAT CLAY - with sand, very moist, mediumstiff, red brown
- with partially cemented lenses, hard
SANDY CLAY - very moist, stiff, light brown
FAT CLAY - with sand, very moist, soft, greenbrown
- very moist, soft, red brown
SANDY CLAY - with partially cementedlenses, very moist, stiff, brown
- with partially cemented lenses, mediumdense, brown
- partially cemented, white
84.50
- occasional partially cemented lenses, white
85.35
CLAYEY GRAVEL - with sand, occasional thincaliche lenses, moist, dense
- occasional non-cemented lenses
- partially cemented, white
SANDY LEAN CLAY with occasional partiallycemented lenses, very moist, hard, white tolight brown
90.00
86.50
82.50
79.00
75.00
89.00
- loose
RS
GC
SS
ST
SS
RS
SS
RS
1
84.5084.00
79.00
74.00
69.00
64.00
2
8
6
14
50/5"
13
3
37
3
13
2
8
2
13
3
64075084
Last1 foot
USCSGroup
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
REMARKS
8-inch Hollow Stem Auger
START DATE
I-15/US 95 Interchange to Craig Road
1/23/08
TYPE 6 inchIncrements
BACKFILLED
MATERIAL DESCRIPTION
SHEET 3 OF 4
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
DATE
LOCATION
BLOW COUNT
2061.7 ft. (NAVD88)01/23/08
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
PLATE No. A-3
NO.
HAMMER DROP SYSTEM
LAB TESTS
BORING
N/M
JOB DESCRIPTION
END DATE
Yes
BEN1-1
PROJECT No.
1/22/08
SAMPLE
Auto Hammer
873+66RT 63Rick EricksonDiedrich D-120Tim Thompson
GROUND ELEV.
1996.7
1991.7
1986.7
1981.7
1976.7
M, G, A
M
M, G, A
M
M, G, A, T
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/2
1/08
DRILLINGMETHOD
ELEV. (ft)DEPTH (ft)
Interstate-15 Design Build
01/23/08DATE
DEPTH(ft)
ELEV.(ft)
M
1966.7
1961.7
1956.7
1951.7
1946.7
M, D
FAT CLAY - with sand, very moist, mediumstiff, red brown
- partially cemented, white to light brown
DATE
DEPTH(ft)
ELEV.(ft)
100.50
3
4
8
4
8SANDY CLAY - very moist, very stiff, light redbrown
94.00
SS
RS
24
DEPTH (ft)
96.50
93.50
100.50
95.50
90.50
1826
4
23
CH
CL
CH
99.00
FAT CLAY - with sand, very moist, mediumstiff, red brown
8
LAB TESTS
PROJECT No.
1/22/08
SAMPLE
Auto Hammer
873+66RT 63Rick EricksonDiedrich D-120Tim Thompson
N/M
END DATE
Last1 foot
USCSGroup
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
01/23/08
START DATE
BLOW COUNT
2061.7 ft. (NAVD88)01/23/08
EXPLORATION LOG
GROUNDWATER LEVEL
PercentRecov'd
BEN1-1
NO.
YesHAMMER DROP SYSTEM
GROUND ELEV.
BORING
LOCATION
JOB DESCRIPTION
PLATE No. A-4
DRILLINGMETHOD
ELEV. (ft)
NV
_DO
T 7
5084
_UP
DA
TE.G
PJ
NV
_DO
T.G
DT
5/2
1/08
BACKFILLED
REMARKS
DATE 8-inch Hollow Stem Auger64075084
I-15/US 95 Interchange to Craig Road
1/23/08
6 inchIncrements
MATERIAL DESCRIPTION
SHEET 4 OF 4
STATIONOFFSETENGINEEREQUIPMENTOPERATOR
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
Interstate-15 Design Build
TYPE
Attachment 1(b)
Boring Logs
Black Eagle Consultants, Inc. (2006)
Attachment 2
Laboratory Results
Attachment 2(a)
Laboratory Results
North Corridor Constructors (2008)
SUMMARY OF LABORATORY RESULTSI-15 OVER UPRR SPUR TRACK (G-941)
I-15 NORTH, US-95 INTERCHANGE TO CRAIG ROAD DESIGN BUILD PROJECT
S.NO Exploration No.
Depth1
(ft)Elevation
(ft) Geologic Formation Soil2 or Rock DescriptionType of
SamplingBlowCount
Field Dry Density
(pcf)
Field Moisture Content
(%)
Compaction
Grain Size (GR:SD:FN)3
(%)
Percent PassingNo. 200
Sieve
Atterberg Limits
Expansion Index
Consolidation
R-Value Sand Eq.
Corrosivity Direct Shear Test UU test
Max. Dy Density
(pcf)OMC (%)
Liquid Limit (%)
Plastic Limit (%)
Plasticity Index (%)
Undisturbed
pHMinimum Resistivity (Ohm-cm)
Sulfate Content (ppm)
Chloride Content (ppm)
Ultimate Cohesion
(psf)
Ultimate Friction Angle (deg)
Sample Type
Undrained Shear Strength
Cce Cre Peak(ksf)
Ultimate(ksf)
1
BW
1-1
0-5 2066.8 Fill Silty gravel with sand BS 362-3.5 Fill Silty gravel with sand SPT 24 1.44-5.5 Fill Silty sand with gravel Ring 23 2.9 43:44:13 13 NP NP NP
9-10.5 Fill Silty sand with gravel SPT 29 6.614-15.5 Fill Silty, clayey sand with gravel Ring 36 112.9 7.1 18:52:30 30 19 15 4 1,258 25 Ring Sample19-20 Fill Silty sand SPT 50/6" 6.1
24-25.5 Fill Silty sand Ring 84/11.5" 118.1 4.829-30.5 CL Sandy clay SPT 37 2134-35.5 CL Sandy lean clay Ring 39 106.8 12.2 1:32:67 67 45 15 30 √ √39-40.5 CL Sandy lean clay SPT 40 11.7 8.72 740 179 40044-45.5 SC-SM Silty, clayey sand with gravel Ring 68 11.5 20:41:39 39 18 14 4 5.5 5.549-49.5 CL Sandy clay SPT 50/6" 9.2
54 Caliche Ring 50/0"59-60.5 SC Clayey sand with caliche gravel SPT 29 20.8 19:32:49 49 49 22 2764-65.5 CL Sandy clay Ring 4269-70 GC Clayey gravel with sand Shelby
70-71.5 GC Clayey gravel with sand Ring 38 16.9 34:22:44 44 32 15 17 2.7 2.774-74.5 GC Clayey gravel with sand SPT 50/6"79-80.5 CL Sandy clay Ring 1984-86 CH Fat clay with sand Shelby 50.9 7:19:74 74 71 30 41
86-87.5 CH Fat clay with sand Ring 2789-90.5 CH Fat clay with sand SPT 4394-95.5 CL Sandy clay Ring 41
2
BW
1-2
2-5 2064.1 Fill Silty sand with gravel BS 129.5 9.0 782-3 Fill Silty sand with gravel SPT 50/4" 5.3 31:54:15 15 NP NP NP4-5 Fill Sandy silt with gravel Ring 50/6" 121.4 1.9
9-9.5 Fill Silty sand with gravel SPT 50/6" 4.3 19:57:24 24 NP NP NP14-14.5 Fill Sandy silt with gravel Ring 50/6"19-20 Fill Silty sand with gravel SPT 50/6" 3.2 33:52:15 15 NP NP NP
24-25.5 Fill Silty sand Ring 50/5" 112.2 11.229-30.5 Fill Sandy clay SPT 15 23.634-35.5 CL Lean clay with sand Ring 32 112.8 16.3 4:21:75 75 30 18 12 √ √39-39.5 CL Lean clay with sand SPT 50/6" 12.744-45.5 SC Clayey sand with gravel Ring 27 17.4 19:39:42 42 24 13 11 1.5 1.5
49-49.25 SC Clayey sand with gravel SPT 50/3" 5.654-55.5 SC-SM Silty clayey sand Ring 42 16.2 0:53:47 47 21 15 6 1.8 1.859-60.5 CL Sandy clay SPT 25 18.464-65 CH Sandy fat clay with gravel Shelby 32.6 15:29:56 56 51 23 28
65-65.5 CH Sandy fat clay with gravel Ring 50/5" 20.269-70.5 SC Clayey sand with gravel SPT 8 43.1 21:38:41 41 53 21 3274-75.5 SC Clayey sand with gravel Ring 16 81.5 38.279-80.5 CL Sandy lean clay with caliche gravel SPT 12 20.3 2:32:66 66 35 20 1584-85.5 CL Sandy lean clay with caliche gravel Ring 20 28.289-90.5 CH Sandy fat clay SPT 3 69.8 5:44:51 51 77 27 5094-95.5 CL Sandy clay Shelby 33.695.5-97 CL Sandy clay Ring 22 24.6
3
BE
N1-
1
2-5 2061.7 Fill Silty gravel with sand BS2-3.5 Fill Silty gravel with sand SPT 50 4.3 428 30 Remolded, Saturated4-5 Fill Silty sand Ring 50/4" 1.4 5:59:36 36 16 13 3
9-10 Fill Silty sand SPT 50/5" 1.414-15 Fill Silty sand Ring 50/4" 1.5 26:52:22 22 NP NP NP
19-20.5 Fill Silty gravel with sand SPT 80 3.124-25 Fill Silty sand with gravel Ring 50/6" 117.1 6.5 18:59:23 23 17 14 3
29-30.5 CH Fat clay with sand SPT 10 22.834-34.5 CL-ML Sandy silty clay Shelby 12.2 11:37:52 52 21 17 434.5-35 CL-ML Sandy silty clay Ring 50/5" 104.1 9.539-40.5 CL Sandy lean clay SPT 50/4" 15.244-45.5 CL Sandy lean clay Ring 12 99.3 26.4 11:27:62 62 37 23 14 √ √49-49.5 CL Sandy lean clay SPT 50/4" 11.854-55.5 CL Sandy lean clay Ring 50/6" 109.6 18.4 0:38:62 62 35 14 21 2.5 2.559-60.5 CL Sandy lean clay SPT 50/6" 17.764-65.5 GC Clayey gravel with sand Ring 51 117.5 13.7 46:32:22 22 29 18 11 9.6 9.369-70.5 GC Clayey gravel with sand SPT 9 90.474-75.5 GC Clayey gravel with sand Ring 2179-80.5 CH Fat clay with sand SPT 3 67.0 2:23:75 75 70 25 4584-84.5 CL Sandy clay Shelby 98.0 21.6
84.5-85.5 CL Sandy clay Ring 50/5"89-90.5 CH Fat clay with sand SPT 6 51.6 1:19:80 80 63 20 4394-95.5 CL Sandy clay Ring 26 63.4 45.4
99-100.5 CH Fat clay with sand SPT 8 71.5
34.0
49.0
CL679.530 106.845 60BW1-121.029.0BW1-1
0.38532
15
18
BW1-1
11.5SC-SM3937.5
12.2
14
24.0
44.0BW1-111.739.0BW1-1
0.531
4
NP6.69.0BW1-12.9SM
118.1
50.8
19
NPNP4.0BW1-11.42.0
13
7.1
9.2
BW1-16.119.0BW1-1
0.448BW1-1 112.914.0 SC-SM3019415
4.8
42
BW1-1
Borehole LiquidLimit
WaterContent
(%)
MaximumSize(mm)
Sheet 1 of 1
Dry UnitWeight(pcf)
Client: North Corridor ConstructorsProject: Interstate-15 Design BuildSite: I-15/US 95 Interchange to Craig RoadJob #: 64075084 PLATE: B-1
Depth(ft)
DerivedSaturation
(%)
DerivedVoidRatio
SUMMARY OF LABORATORY RESULTS
PlasticLimit
USCSClass-ification
4917153270.0BW1-1
SCGC
25.427224959.0BW1-1 20.8
41
TC_L
AB
_SU
MM
AR
Y 7
5084
.GP
J T
ER
RA
CO
N.G
DT
4/2
/08
%<#200Sieve
PlasticityIndex
50.9CH37.519
44307184.0BW1-1
16.974
95
1911132444.0BW1-212.739.0
34.0 0.449
17.4
112.816.3CL7612.51218
28
BW1-2
4.75
BW1-2
5164.0BW1-218.459.0BW1-216.2
42
47
SC
6152154.0BW1-25.649.0BW1-2
BW1-2
SC-SM
BW1-2NPNPNP9.0BW1-2
0.34715121.4
30
4.0SM
5.3SM1525.4NPNPNP2.01.9
SM
23.629.0BW1-20.45664112.211.224.0
193.2
241525.4NPNPNP19.0BW1-2
4.3
25.4
BW1-2
WaterContent
(%)
MaximumSize(mm)
Sheet 1 of 1
Dry UnitWeight(pcf)
BW1-2
LiquidLimit
%<#200Sieve
PlasticityIndex
24.695.5BW1-233.6
23
DerivedVoidRatio
Client: North Corridor ConstructorsProject: Interstate-15 Design BuildSite: I-15/US 95 Interchange to Craig RoadJob #: 64075084 PLATE: B-1
DerivedSaturation
(%)
SUMMARY OF LABORATORY RESULTS
PlasticLimit
USCSClass-ification
Depth(ft)Borehole
69.8
5381.538.274.0BW1-2
43.1SC4125.4
94.0
21
BW1-2
69.0BW1-220.265.0BW1-232.6CH56
32
BW1-2CH511950277789.0BW1-2
100
84.0
1.00520.3CL6612.515203579.0
TC_L
AB
_SU
MM
AR
Y 7
5084
.GP
J T
ER
RA
CO
N.G
DT
4/2
/08
28.2
BEN1-1
BEN1-115.239.0BEN1-1
0.57143104.1
BEN1-1
34.5
23
12.2CL-ML5212.54172134.09.5
49.018.4CL629.521143554.0
44.011.8
37BEN1-1
99.326.4CL6212.514
29.0
BEN1-1
36
BEN1-1
NPNP14.0BEN1-11.49.0BEN1-1
19
SM
22
12.5313164.0BEN1-14.32.01.4
14
17.7
BEN1-10.39643117.16.5SM23
NP
322.8
1724.0BEN1-13.119.0BEN1-11.5SM
19
75
WaterContent
(%)
MaximumSize(mm)
Sheet 1 of 1
LiquidLimit
%<#200Sieve
PlasticityIndex
71.599.0BEN1-1
BEN1-1
Dry UnitWeight(pcf)
DerivedVoidRatio
Client: North Corridor ConstructorsProject: Interstate-15 Design BuildSite: I-15/US 95 Interchange to Craig RoadJob #: 64075084 PLATE: B-1
DerivedSaturation
(%)
63.4
SUMMARY OF LABORATORY RESULTS
PlasticLimit
USCSClass-ification
Depth(ft)Borehole
GC
1.577
45257079.0BEN1-190.469.0
75
13.7
CH
227511182964.0BEN1-1
TC_L
AB
_SU
MM
AR
Y 7
5084
.GP
J T
ER
RA
CO
N.G
DT
4/2
/08
BEN1-1
89.045.494.0BEN1-151.6CH809.543
9.5
63
59.0
BEN1-10.6688598.021.684.0BEN1-1
67.0
20
0.1702.995
864
0.081
100SANDGRAVELCOBBLES
50
fine
0.216
%Sand
3
Classification WC%
4 2
10 1 0.1 0.01 0.001
20
100
80
70
60
50
30
10
0
40
90
32.2
1.5
38.765.610.376.376.08
52.6
1/2
41.132.2
PI Cc
43.7
CuPL
coarse
19.00
LL
49
4.0 ft.14.0 ft.34.0 ft.44.0 ft.59.0 ft.
NP19
D15
18
30
NP15151422
2.97.117.911.520.8
45
HYDROMETER
19.89.5037.5025.40
%Gravel
U.S. STANDARD SIEVE NUMBERS
50.80
PE
RC
EN
T FI
NE
R B
Y W
EIG
HT
GRAIN SIZE IN MILLIMETERS
NP430427
14 16 20U.S. STANDARD SIEVE OPENING IN INCHES
4.0 ft.
49.1Client:
Date
100
BW1-1 @BW1-1 @BW1-1 @BW1-1 @BW1-1 @
I-15/US 95 Interchange to Craig Road
14.0 ft.34.0 ft.44.0 ft.59.0 ft.
Project No. 64075084
13.229.667.2
Project Site
6
SILTY SAND with GRAVEL SMSILTY, CLAYEY SAND with GRAVEL SC-SM
SANDY LEAN CLAY CLSILTY, CLAYEY SAND with GRAVEL SC-SM
CLAYEY SAND with GRAVEL SC
B-2
fine
PE
RC
EN
T C
OA
RS
ER
BY
WE
IGH
T
Specimen Identification
Specimen Identification
1 3/4
SIEVE ANALYSES
medium
39.1
Interstate-15 Design Build
D85 D50
10
0.0863
North Corridor Constructors
SILT OR CLAY
0
10
20
30
40
50
60
70
80
90
70 100 14040
43.117.80.6
March 2008
BW1-1 @BW1-1 @BW1-1 @BW1-1 @BW1-1 @
%Silt
Project:
18.7
20033/8
coarse
%Clay
D100
3
0.169
6 82
SAND
4
COBBLES
50
GRAVEL
4
WC%Classification
%Sand
fine
30
40
50
60
70
80
10
100
0100 10 1 0.1 0.01 0.001
90
20
1/21.5
10.810.49
21.9
coarse
7.1
LL PL Cu70.0 ft.
40
14 16 20 30
D15
18.7
PE
RC
EN
T FI
NE
R B
Y W
EIG
HT
84.0 ft.3271
1530
16.950.9
PI Cc
37.50
17
GRAIN SIZE IN MILLIMETERS
%Gravel
U.S. STANDARD SIEVE OPENING IN INCHES U.S. STANDARD SIEVE NUMBERS HYDROMETER40
19.00
100
3/4
SIEVE ANALYSES64075084 Date
BW1-1 @BW1-1 @
Project Site I-15/US 95 Interchange to Craig Road
70.0 ft.84.0 ft.
33.6
Client:
March 2008
6
CLAYEY GRAVEL with SAND GC
1
Specimen Identification
Specimen Identification
fine
PE
RC
EN
T C
OA
RS
ER
BY
WE
IGH
T
44.5
FAT CLAY with SAND CH
SILT OR CLAY
Project: Interstate-15 Design Build
D85 D50
10
Project No.
North Corridor Constructors
%Clay
0
10
20
30
40
50
60
70
80
90
medium
70 100 140
74.2
B-3
BW1-1 @BW1-1 @
D100
20033/8
coarse
%Silt
6 8
1.5920.6011.076
SAND
4
COBBLES
50
fine
0.100
3 2
%Sand
Classification WC%
4
GRAVEL100 10 1 0.1 0.01 0.001
20
90
80
70
60
50
30
10
0
40
100
52.2
1.5
8.825.8810.030.156.26
56.5
1/2
20.838.8
PI Cc
53.9
CuPL
coarse
19.00
LL
24
2.0 ft.9.0 ft.
19.0 ft.34.0 ft.44.0 ft.
NPNP
D15
30
30
NPNPNP1813
5.34.33.216.517.4
NP
HYDROMETER
3.725.4012.5019.00
%Gravel
U.S. STANDARD SIEVE NUMBERS
25.40
PE
RC
EN
T FI
NE
R B
Y W
EIG
HT
GRAIN SIZE IN MILLIMETERS
NPNPNP1211
14 16 20U.S. STANDARD SIEVE OPENING IN INCHES
9.0 ft.
B-2Date
100
BW1-2 @BW1-2 @BW1-2 @BW1-2 @BW1-2 @
Project Site
2.0 ft.
19.0 ft.34.0 ft.44.0 ft.
Project No. 64075084
14.724.214.875.5
I-15/US 95 Interchange to Craig RoadMarch 2008
6
SILTY SAND with GRAVEL SMSILTY SAND with GRAVEL SMSILTY SAND with GRAVEL SM
LEAN CLAY with SAND CLCLAYEY SAND with GRAVEL SC
Client:
BW1-2 @
fine
PE
RC
EN
T C
OA
RS
ER
BY
WE
IGH
T
Specimen Identification
Specimen Identification
1 3/4
SIEVE ANALYSES
medium
41.7
D85 D50
10
0.0767
0.0757
North Corridor ConstructorsProject:
0
10
20
30
40
50
60
70
80
90
SILT OR CLAY
70 100 14040
31.319.333.0
200
BW1-2 @BW1-2 @BW1-2 @BW1-2 @
%SiltD100
Interstate-15 Design Build
19.6
33/8
coarse
%Clay
Classification WC%
%Sand
4
GRAVELfine
50
COBBLES
0.01SAND
4 6 8
2
0.080
0.122
3
1
80
0
10
20
30
40
50
70
90
100
0.0010.110
60
100
28.7
1.5
0.184.868.210.46
coarse
53.4
1/2
38.131.844.2
PI Cc
4.60.50
PLLL
4.75
Cu
77
54.0 ft.64.0 ft.69.0 ft.79.0 ft.89.0 ft.
2151
D15
35
30
1523212027
16.232.643.120.369.8
53
HYDROMETER
25.4025.4012.5019.00
%Gravel
U.S. STANDARD SIEVE NUMBERS
2.5
PE
RC
EN
T FI
NE
R B
Y W
EIG
HT
GRAIN SIZE IN MILLIMETERS
628321550
14 16 20U.S. STANDARD SIEVE OPENING IN INCHES
Project Site
41.4
Client:
Date
100
BW1-2 @BW1-2 @BW1-2 @
SIEVE ANALYSESBW1-2 @
I-15/US 95 Interchange to Craig Road
54.0 ft.64.0 ft.69.0 ft.79.0 ft.89.0 ft.
Project No. 64075084
46.6
BW1-2 @
March 2008
6
SILTY, CLAYEY SAND SC-SMSANDY FAT CLAY with GRAVEL CH
CLAYEY SAND with GRAVEL SCSANDY LEAN CLAY CL
65.7
fine
PE
RC
EN
T C
OA
RS
ER
BY
WE
IGH
T
Specimen Identification
Specimen Identification
1 3/4
SANDY FAT CLAY CH
0
10
20
30
40
50
60
70
80
90
56.1
SILT OR CLAY
Project: Interstate-15 Design Build
D85 D50
10
North Corridor Constructors
medium
70 100 14040
0.015.220.5
D100
51.2
B-3
BW1-2 @BW1-2 @BW1-2 @BW1-2 @BW1-2 @
%Silt
20033/8
coarse
%Clay
SAND
0.2190.3320.167
84 6
COBBLES
50
Classification
3 2
fine
WC%
4
GRAVEL
%Sand
6
100 10 1 0.1 0.01 0.0010
10
20
30
40
50
60
70
80
90
100
36.4
1.5
2.308.916.042.542.82
58.912.50
58.7
coarse
26.8
PI Cc
52.2
LL Cu
1/2
19.00
PL134.0 ft.
14.0 ft.24.0 ft.34.0 ft.44.0 ft.
16NP17
37
30
NP141723
1.41.56.512.226.4
21
PE
RC
EN
T FI
NE
R B
Y W
EIG
HT
19.0012.5012.50
%Gravel
U.S. STANDARD SIEVE OPENING IN INCHES HYDROMETER
D15
GRAIN SIZE IN MILLIMETERS
3NP3514
14 16 20U.S. STANDARD SIEVE NUMBERS
24.0 ft.
Date
100
BEN1-1 @BEN1-1 @BEN1-1 @BEN1-1 @BEN1-1 @
Project Site I-15/US 95 Interchange to Craig RoadB-2
14.0 ft.
34.0 ft.44.0 ft.
Project No. 64075084
35.921.823.552.3
4.0 ft.
March 2008
SILTY SAND SMSILTY SAND with GRAVEL SMSILTY SAND with GRAVEL SM
SANDY SILTY CLAY CL-MLSANDY LEAN CLAY CL
Client:
fine
PE
RC
EN
T C
OA
RS
ER
BY
WE
IGH
T
Specimen Identification
Specimen Identification
1 3/4
SIEVE ANALYSES
BEN1-1 @
100
Interstate-15 Design Build
D85 D50
10
North Corridor Constructors
0
10
20
30
40
50
60
70
80
90
61.8
70
14040
5.226.017.811.211.4
medium
200
BEN1-1 @BEN1-1 @BEN1-1 @BEN1-1 @
%SiltD100
Project:
SILT OR CLAY
33/8
coarse
%Clay
GRAVEL
Classification WC%
4
%Sand
1432.9
fine
3.253
50
1SAND
4 6 8
2
0.043
3
100
90
10
20
30
40
50
60
80
100
0.0010.010.110
70
0
COBBLES
0.12
1/2
coarse
1.5
37.84
0.11
38.132.323.018.6
PI
0.15
1.81.6
LL PL Cu
70
Cc
30
D15
54.0 ft.64.0 ft.79.0 ft.89.0 ft.
16
29
14
63
14182520
18.413.767.051.6
35
9.5075.009.509.50
5.15
20U.S. STANDARD SIEVE OPENING IN INCHES U.S. STANDARD SIEVE NUMBERS HYDROMETER
PE
RC
EN
T FI
NE
R B
Y W
EIG
HT
GRAIN SIZE IN MILLIMETERS
21104543
%Gravel
BEN1-1 @
11.8
SIEVE ANALYSESClient:
Date
100
BEN1-1 @
3/4
BEN1-1 @
1
Project Site I-15/US 95 Interchange to Craig Road
54.0 ft.64.0 ft.79.0 ft.89.0 ft.
Project No. 64075084
45.8BEN1-1 @
6
SANDY LEAN CLAY CLCLAYEY GRAVEL with SAND GC
FAT CLAY with SAND CH
75.3
fine
PE
RC
EN
T C
OA
RS
ER
BY
WE
IGH
T
Specimen Identification
Specimen Identification
FAT CLAY with SAND CH
27.8
Project: Interstate-15 Design Build
D85 D50
10
0.020133.7
North Corridor Constructors
0
10
20
30
40
50
60
70
80
90
medium
70 100 14040
March 2008
10.1
79.9
B-3
BEN1-1 @BEN1-1 @BEN1-1 @BEN1-1 @
SILT OR CLAY
D1000.4
20033/8
coarse
%Clay
%Silt
CH
Specimen Identification PI
LIQUID LIMIT
CL-ML
PL
60
40
20
0
100
120
LL
80
140
100806040200
SILTY, CLAYEY SAND with GRAVEL(SC-SM)
BW1-1
PLASTICITY
INDEX
FAT CLAY with SAND(CH)
CLAYEY GRAVEL with SAND(GC)
CLAYEY SAND with GRAVEL(SC)
13
SANDY LEAN CLAY(CL)
BW1-1
SILTY SAND with GRAVEL(SM)
74
44
49
39
67
SILTY, CLAYEY SAND with GRAVEL(SC-SM)
MH
Client: North Corridor ConstructorsProject: Interstate-15 Design BuildSite: I-15/US 95 Interchange to Craig RoadJob #: 64075084 PLATE: B-4
BW1-1
BW1-1
ML
CL
BW1-1
BW1-1
BW1-1
41
44.0ft
32
49
18
45
19
NP
84.0ft
30
59.0ft
34.0ft
14.0ft
4.0ft
ATTERBERG LIMITS RESULTS
Classification%Fines
TC_A
TTE
RB
ER
G_L
IMIT
S 7
5084
.GP
J T
ER
RA
CO
N.G
DT
3/2
5/08
70.0ft
14
17
27
4
30
4
NP
3071
22
15
15
NP
15
CL-ML
CH
2.0ft
ATTERBERG LIMITS RESULTS
Classification%FinesSpecimen Identification
LIQUID LIMIT
PI
80
60
40
20
0
0
19.0ft
34.0ft
PL
100
14012010080604020
LL
LEAN CLAY with SAND(CL)
BW1-2
PLASTICITY
INDEX
SANDY FAT CLAY(CH)
SANDY LEAN CLAY(CL)
CLAYEY SAND with GRAVEL(SC)
SANDY FAT CLAY with GRAVEL(CH)
9.0ft
CLAYEY SAND with GRAVEL(SC)
BW1-2
SILTY SAND with GRAVEL(SM)
SILTY SAND with GRAVEL(SM)
SILTY SAND with GRAVEL(SM)
51
66
41
56
47
42
SILTY, CLAYEY SAND(SC-SM)
Client: North Corridor ConstructorsProject: Interstate-15 Design BuildSite: I-15/US 95 Interchange to Craig RoadJob #: 64075084 PLATE: B-4
BW1-2
ML
BW1-2
CL
BW1-2
BW1-2
BW1-2
BW1-2
BW1-2
BW1-2
24
MH
30 76
77
35
53
51
24
NP
NP
NP
NP
89.0ft
79.0ft
69.0ft
64.0ft
54.0ft
44.0ft
21
NP
TC_A
TTE
RB
ER
G_L
IMIT
S 7
5084
.GP
J T
ER
RA
CO
N.G
DT
3/2
5/08
15
50
15
32
28
6
11
12
NP
15
27
20
21
23
15
13
18
NP
NP
NP
CL-ML
CH
Classification%FinesSpecimen Identification PI
LIQUID LIMIT
60
40
20
0
100
140
14.0ft
PLLL
80
120100806040200
SILTY SAND with GRAVEL(SM)
BEN1-1
PLASTICITY
INDEX
FAT CLAY with SAND(CH)
FAT CLAY with SAND(CH)
CLAYEY GRAVEL with SAND(GC)
SANDY LEAN CLAY(CL)
ATTERBERG LIMITS RESULTS
SANDY SILTY CLAY(CL-ML)BEN1-1
SILTY SAND with GRAVEL(SM)
SILTY SAND(SM)
80
75
22
62
62
52
SANDY LEAN CLAY(CL)
ML
Client: North Corridor ConstructorsProject: Interstate-15 Design BuildSite: I-15/US 95 Interchange to Craig RoadJob #: 64075084 PLATE: B-4
BEN1-1
MH
BEN1-1
CL
BEN1-1
BEN1-1
BEN1-1
BEN1-1
BEN1-1
36
NP
23
63
70
29
35
37
17
16
89.0ft
79.0ft
64.0ft
54.0ft
44.0ft
34.0ft
24.0ft
TC_A
TTE
RB
ER
G_L
IMIT
S 7
5084
.GP
J T
ER
RA
CO
N.G
DT
3/2
5/08
21
20
4.0ft
43
45
11
21
14
4
3
3
22
25
18
14
23
17
14
NP
13
NP
Project Name: Tested by: A. Santos Date: 01/20/08Project No: 64075084 Checked by: J. Ward Date: 01/29/08Boring No.: BW1-1 @ 45 ft. Sample Type: RingsSample No.: N/A Depth(ft): 44Sample Description:
1 2.4082 2.4103 2.414
Average 2.4111 5.0152 5.0353 5.027
Average 5.026
829.500.00
1076.60976.40108.102.7020.150.045
11.54 76.47123.5 20.150.364 96.6285.6 14.53
* Stress values have been corrected for membrane effects
Minor principal total stress (psi) Major principal total stress (psi) Axial strain (%)
Moisture Content (%)Dry Density (pcf)Void Ratio% Saturation
Specific Gravity (assumed)Confining Pressure (psi)Rate of Deformation (in/min)
Deviator stress (psi)
Diameter (in)
Height (in)
Sample Properties At Failure*
Weight of Container (g)
I-15 Design Build
Weight of Sample + Tube / Rings (g)Weight of Tube / Rings (g)Weight of Wet Sample + Container (g)Weight of Dry Sample + Container (g)
Unconsolidated-Undrained TriaxialCompression Test on Cohesive Soils
ASTM D 2850
White silty, clayey sand with gravel (SC-SM)g (with CaCO3, strong reaction to HCl)
Stress - Strain Curve
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0Axial Strain (%)
Dev
iato
r St
ress
(ps
i)
At end of test x = 14.92, y = 76.31
PLATE: B-8
Project Name: Tested by: A. Santos Date: 01/20/08Project No: 64075084 Checked by: J. Ward Date: 01/29/08Boring No.: BW1-1 @ 70 ft. Sample Type: RingsSample No.: N/A Depth(ft): 70Sample Description:
1 2.4202 2.4183 2.421
Average 2.4201 5.3082 5.3033 5.304
Average 5.305
848.300.00
1055.90919.40110.402.7031.250.045
16.87 37.04113.4 31.250.486 68.2993.7 15.08
* Stress values have been corrected for membrane effects
Minor principal total stress (psi) Major principal total stress (psi) Axial strain (%)
Moisture Content (%)Dry Density (pcf)Void Ratio% Saturation
Specific Gravity (assumed)Confining Pressure (psi)Rate of Deformation (in/min)
Deviator stress (psi)
Diameter (in)
Height (in)
Sample Properties At Failure*
Weight of Container (g)
I-15 Design Build
Weight of Sample + Tube / Rings (g)Weight of Tube / Rings (g)Weight of Wet Sample + Container (g)Weight of Dry Sample + Container (g)
Unconsolidated-Undrained TriaxialCompression Test on Cohesive Soils
ASTM D 2850
Yellowish white clayey gravel with sand (GC)s (with CaCO3, strong reaction to HCl)
Stress - Strain Curve
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0Axial Strain (%)
Dev
iato
r St
ress
(ps
i) At end of test x = 15.08,y = 37.04
PLATE: B-9
Project Name: Tested by: A. Santos Date: 02/18/08Project No: 64075084 Checked by: J. Ward Date: 02/20/08Boring No.: BW1-2 @ 45 ft. Sample Type: RingsSample No.: N/A Depth(ft): 45Sample Description:
1 2.4152 2.4123 2.411
Average 2.4131 4.9492 4.9453 4.947
Average 4.947
785.400.00
1021.20885.80108.802.7020.10.045
17.43 20.38112.7 20.100.495 40.4895.0 15.16
* Stress values have been corrected for membrane effects
Minor principal total stress (psi) Major principal total stress (psi) Axial strain (%)
Moisture Content (%)Dry Density (pcf)Void Ratio% Saturation
Specific Gravity (assumed)Confining Pressure (psi)Rate of Deformation (in/min)
Deviator stress (psi)
Diameter (in)
Height (in)
Sample Properties At Failure*
Weight of Container (g)
I-15 Design Build
Weight of Sample + Tube / Rings (g)Weight of Tube / Rings (g)Weight of Wet Sample + Container (g)Weight of Dry Sample + Container (g)
Unconsolidated-Undrained TriaxialCompression Test on Cohesive Soils
ASTM D 2850
Very light olive clayey sand with gravel (SC)g (with CaCO3, strong reaction to HCl)
Stress - Strain Curve
0.0
5.0
10.0
15.0
20.0
25.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0Axial Strain (%)
Dev
iato
r St
ress
(ps
i)
At end of testx = 15.16,y = 20.38
PLATE: B-7
Project Name: Tested by: A. Santos Date: 02/25/08Project No: 64075084 Checked by: J. Ward Date: 02/28/08Boring No.: BEN1-1 @ 55 ft. Sample Type: RingsSample No.: N/A Depth(ft): 55Sample Description:
Note: height-to-diameter ratio = 1.891 2.4002 2.4023 2.403
Average 2.4021 4.5432 4.5433 4.546
Average 4.544
701.400.00
1006.20866.50107.702.7025.00.045
18.41 34.60109.6 25.000.537 59.6092.6 15.41
* Stress values have been corrected for membrane effects
Minor principal total stress (psi) Major principal total stress (psi) Axial strain (%)
Moisture Content (%)Dry Density (pcf)Void Ratio% Saturation
Specific Gravity (assumed)Confining Pressure (psi)Rate of Deformation (in/min)
Deviator stress (psi)
Diameter (in)
Height (in)
Sample Properties At Failure*
Weight of Container (g)
I-15 Design Build
Weight of Sample + Tube / Rings (g)Weight of Tube / Rings (g)Weight of Wet Sample + Container (g)Weight of Dry Sample + Container (g)
Yellow sandy lean clay s(CL) (with CaCO3, strong reaction to HCl)
Unconsolidated-Undrained TriaxialCompression Test on Cohesive Soils
ASTM D 2850
Stress - Strain Curve
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0Axial Strain (%)
Dev
iato
r St
ress
(ps
i)
At end of testx = 15.41,y = 34.60
PLATE: B-8
Project Name: Tested by: A. Santos Date: 02/25/08Project No: 64075084 Checked by: J. Ward Date: 02/28/08Boring No.: BEN1-1 @ 65 ft. Sample Type: RingsSample No.: N/A Depth(ft): 65Sample Description:
Note: height-to-diameter ratio = 1.9151 2.3992 2.3983 2.400
Average 2.3991 4.5962 4.5963 4.596
Average 4.596
1211.70483.40928.00829.40106.902.7029.20.045
13.65 133.02117.5 29.200.434 162.2285.0 8.49
* Stress values have been corrected for membrane effects
Unconsolidated-Undrained TriaxialCompression Test on Cohesive Soils
ASTM D 2850
Yellow clayey gravel with sand (GC)s (with CaCO3, strong reaction to HCl)
Weight of Container (g)
I-15 Design Build
Weight of Sample + Tube / Rings (g)Weight of Tube / Rings (g)Weight of Wet Sample + Container (g)Weight of Dry Sample + Container (g)
Specific Gravity (assumed)Confining Pressure (psi)Rate of Deformation (in/min)
Deviator stress (psi)
Diameter (in)
Height (in)
Sample Properties At Failure*
Minor principal total stress (psi) Major principal total stress (psi) Axial strain (%)
Moisture Content (%)Dry Density (pcf)Void Ratio% Saturation
Stress - Strain Curve
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0Axial Strain (%)
Dev
iato
r St
ress
(ps
i) At end of testx = 15.23,y = 129.84
PLATE: B-9
Project Name: Tested by: A. Santos Date: 02/26/08Project No: 64075084 Checked by: J. Ward Date: 02/28/08Boring No.: BW1-2 @ 55 ft. Sample Type: RingsSample No.: N/A Depth(ft): 55Sample Description:
1 2.4002 2.4013 2.405
Average 2.4021 5.0222 5.0223 5.020
Average 5.021
809.900.00
1057.50925.80110.202.7025.00.045
16.15 25.59116.8 25.000.443 50.5998.4 15.14
* Stress values have been corrected for membrane effects
Unconsolidated-Undrained TriaxialCompression Test on Cohesive Soils
ASTM D 2850
White silty, clayey sand (SC-SM) (with CaCO3, strong reaction to HCl)
Weight of Container (g)
I-15 Design Build
Weight of Sample + Tube / Rings (g)Weight of Tube / Rings (g)Weight of Wet Sample + Container (g)Weight of Dry Sample + Container (g)
Specific Gravity (assumed)Confining Pressure (psi)Rate of Deformation (in/min)
Deviator stress (psi)
Diameter (in)
Height (in)
Sample Properties At Failure*
Minor principal total stress (psi) Major principal total stress (psi) Axial strain (%)
Moisture Content (%)Dry Density (pcf)Void Ratio% Saturation
Stress - Strain Curve
0.0
5.0
10.0
15.0
20.0
25.0
30.0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0Axial Strain (%)
Dev
iato
r St
ress
(ps
i)
At end of testx = 15.14,y = 25.59
PLATE: B-8
2,500 3,000 3,500 4,000
DIRECT SHEAR TEST
2,000
ULT
IMA
TE S
HEA
R S
TREN
GTH
, psf 2,500
0
500
1,000
500
2,000
1,500
3,000
3,500
4,000
0 1,000
1,500
Sample Condition
Specimen Identification
14.0 ft
NORMAL STRESS, psf
BW1-1 @
Project: Interstate-15 Design BuildLocation: I-15/US 95 Interchange to Craig RoadClient: North Corridor ConstructorsProject No.: 64075084 PLATE: B-5
4.3 1382 1258
Initial DryDensity (pcf)
Final MoistureContent (%)
Peak FrictionAngle (degree)
PeakCohesion (psf)
UltimateCohesion (psf)
Ring sample 112.9 2524
TC_D
IRE
CT_
SH
EA
R 7
5084
.GP
J T
ER
RA
CO
N.G
DT
4/1
/08
Ultimate FrictionAngle (degree)
2,500 3,000 3,500 4,000
DIRECT SHEAR TEST
2,000
ULT
IMA
TE S
HEA
R S
TREN
GTH
, psf 2,500
0
500
1,000
500
2,000
1,500
3,000
3,500
4,000
0 1,000
1,500
Sample Condition
Specimen Identification
2.0 ft
NORMAL STRESS, psf
BEN1-1 @
Project: Interstate-15 Design BuildLocation: I-15/US 95 Interchange to Craig RoadClient: North Corridor ConstructorsProject No.: 64075084 PLATE: B-5
14.3 428 428
Initial DryDensity (pcf)
Final MoistureContent (%)
Peak FrictionAngle (degree)
PeakCohesion (psf)
UltimateCohesion (psf)
Remolded, Saturated 115.7 3030
TC_D
IRE
CT_
SH
EA
R 7
5084
.GP
J T
ER
RA
CO
N.G
DT
4/1
/08
Ultimate FrictionAngle (degree)
BW1-1 @
8
9
10
psf2000
6
106.8
5
Ring sample19.3112.612.2
10 100
Inundation at
7
105
0
1
2
3
4
TC_C
ON
SO
L_S
TRA
IN 7
5084
.GP
J T
ER
RA
CO
N.G
DT
4/1
/08
Project: Interstate-15 Design BuildLocation: I-15/US 95 Interchange to Craig RoadClient: North Corridor ConstructorsProject No.: 64075084 PLATE: B-6
1,000
Initial DryDensity (pcf)
CONSOLIDATION TEST
AX
IAL
STR
AIN
, %
PRESSURE, psf
34 ft.
Specimen ID NotesFinal WaterContent (%)
Final DryDensity (pcf)
Initial WaterContent (%)
10,000
0.425
0.430
0.435
0.440
0.445
0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0
Square Root of Time (min^0.5)
Dia
l Rea
ding
(inc
h)
Time Reading @ 4.0 ksfBW1-1 @ 34.0 ft.
PLATE: B-7
BW1-2 @
8
9
10
psf2000
6
112.9
5
Ring Sample15.5119.516.3
10 100
Inundation at
7
105
0
1
2
3
4
TC_C
ON
SO
L_S
TRA
IN 7
5084
.GP
J T
ER
RA
CO
N.G
DT
4/1
/08
Project: Interstate-15 Design BuildLocation: I-15/US 95 Interchange to Craig RoadClient: North Corridor ConstructorsProject No.: 64075084 PLATE: B-5
1,000
Initial DryDensity (pcf)
CONSOLIDATION TEST
AX
IAL
STR
AIN
, %
PRESSURE, psf
34 ft.
Specimen ID NotesFinal WaterContent (%)
Final DryDensity (pcf)
Initial WaterContent (%)
10,000
0.390
0.395
0.400
0.405
0.410
0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0
Square Root of Time (min^0.5)
Dia
l Rea
ding
(inc
h)
Time Reading @ 4.0 ksfBW1-2 @ 34.0 ft.
PLATE: B-6
BEN1-1 @
16
18
20
psf2000
12
99.3
10
Ring Sample21.8109.026.4
10 100
Inundation at
14
105
0
2
4
6
8
TC_C
ON
SO
L_S
TRA
IN 7
5084
.GP
J T
ER
RA
CO
N.G
DT
4/1
/08
Project: Interstate-15 Design BuildLocation: I-15/US 95 Interchange to Craig RoadClient: North Corridor ConstructorsProject No.: 64075084 PLATE: B-6
1,000
Initial DryDensity (pcf)
CONSOLIDATION TEST
AX
IAL
STR
AIN
, %
PRESSURE, psf
44 ft.
Specimen ID NotesFinal WaterContent (%)
Final DryDensity (pcf)
Initial WaterContent (%)
10,000
0.280
0.285
0.290
0.295
0.300
0.305
0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0
Square Root of Time (min^0.5)
Dia
l Rea
ding
(inc
h)
Time Reading @ 4.0 ksfBEN1-1 @ 44.0 ft.
PLATE: B-7
I-15 Design Build Project
Terracon Project No.: 64075084
R-Value Test Results
Segment 1
Boring No. R Value
BW1-1 36
BW1-2 78
144
126
128
130
132
134
136
138
146
150
Client: North Corridor ConstructorsProject: Interstate-15 Design BuildSite: I-15/US 95 Interchange to Craig RoadJob #: 64075084 PLATE: B-3
148
142
102
124
140
104
106
122
108
110
112
114
116
118
120
100
pcf
Test Method
Optimum Water Content
Source of MaterialDescription of Material
Curves of 100% Saturationfor Specific Gravity Equal to:
TEST RESULTS
Maximum (optimum) Dry Unit Weight
HA
RV
AR
D M
INIA
TUR
E 7
5084
SW
ELL
.GP
J T
ER
RA
CO
N.G
DT
5/5
/08
0 5 10 15 20 25
BW1- 2 2.0 ft
9.0
MOISTURE-DENSITY RELATIONSHIP
Silty Sand with Gravel
%
WATER CONTENT, %
DR
Y U
NIT
WE
IGH
T, p
cf
2.80
2.70
2.60
Nev T101 E
129.5
Attachment 2(b)
Laboratory Results
Black Eagle Consultants, Inc. (2006)
Attachment 3
Results of Analyses
Axial Pile Capacity Analyses
Foundation Recommendation BW1, I-15 Widening over UPRR Spur Track
Pile Data Table (10/17/08)
Location Pile Size and
Type
Pile Cut-off
Elevation (feet)
Allowable Axial Capacity in
Compression (kips)
Ultimate Axial Capacity in
Compression (kips)
Design Tip Elevation
(feet) a
Abutment 1 36-inch drilled shaft
2054.9 290 580 2025
Pier 1 84-inch drilled shaft
2041.0 1100 2200 1986
Pier 2 84-inch drilled shaft
2038.0 1050 2100 1983
Abutment 2 36-inch drilled shaft
2052.4 270 540 2019
Notes: a Pile tip elevations should be adjusted based on pile cut-off elevation to provide the minimum recommended pile length.
VERTICALLY LOADED DRILLED SHAFT ANALYSIS PROGRAM SHAFT VERSION 5.0 (C) COPYRIGHT ENSOFT,INC. 1989,1995,1998,2001,2003 I-15 D/B, BW-1, UPRR Over Track 801, Piles @ Abutment 1, D=3 ft PROPOSED DEPTH = 35.0 FT ---------------- NUMBER OF LAYERS = 4 ------------------ WATER TABLE DEPTH = 35.0 FT. ------------------- FACTOR OF SAFETY APPLIED TO THE TOTAL ULTIMATE CAPACITY = 2.00 ------------------------------------------------------- FACTOR OF SAFETY APPLIED TO THE ULTIMATE BASE CAPACITY = 2.00 ------------------------------------------------------ SOIL INFORMATION --------------- LAYER NO 1----SAND AT THE TOP SKIN FRICTION COEFFICIENT- BETA = 0.120E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.000E+00 INTERNAL FRICTION ANGLE, DEG. = 0.340E+02 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.000E+00 AT THE BOTTOM SKIN FRICTION COEFFICIENT- BETA = 0.912E+00 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.000E+00 INTERNAL FRICTION ANGLE, DEG. = 0.340E+02 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.190E+02 LAYER NO 2----CLAY AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.464E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.500E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.190E+02 AT THE BOTTOM STRENGTH REDUCTION FACTOR-ALPHA = 0.464E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.500E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.420E+02 LAYER NO 3----CLAY AT THE TOP STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.420E+02 AT THE BOTTOM STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.500E+02 LAYER NO 4----CLAY AT THE TOP STRENGTH REDUCTION FACTOR-ALPHA = 0.535E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.350E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00
SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.500E+02 AT THE BOTTOM STRENGTH REDUCTION FACTOR-ALPHA = 0.535E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.350E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.670E+02 DRILLED SHAFT INFORMATION ------------------------- DIAMETER OF STEM = 3.000 FT. DIAMETER OF BASE = 3.000 FT. END OF STEM TO BASE = 0.000 FT. ANGLE OF BELL = 0.000 DEG. IGNORED TOP PORTION = 5.000 FT. IGNORED BOTTOM PORTION = 3.000 FT. AREA OF ONE PERCENT STEEL = 10.180 SQ.IN. ELASTIC MODULUS, Ec = 0.360E+07 LB/SQ IN VOLUME OF UNDERREAM = 0.000 CU.YDS. PREDICTED RESULTS ----------------- QS = ULTIMATE SIDE RESISTANCE; QB = ULTIMATE BASE RESISTANCE; WT = WEIGHT OF DRILLED SHAFT (FOR UPLIFT CAPACITY ONLY); QU = TOTAL ULTIMATE RESISTANCE; QBD = TOTAL ALLOWABLE LOAD USING A FACTOR OF SAFETY APPLIED TO THE ULTIMATE BASE RESISTANCE; QDN = TOTAL ALLOWABLE LOAD USING FACTORS OF SAFETY APPLIED TO THE ULTIMATE SIDE RESISTANCE AND THE ULTIMATE BASE RESISTANCE. LENGTH VOLUME QS QB QU QBD QDN QU/VOLUME (FEET) (CU.YDS) (TONS) (TONS) (TONS) (TONS) (TONS) (TONS/CU.YDS) 9.0 2.36 4.13 33.44 37.58 20.85 18.79 15.95 10.0 2.62 8.85 35.96 44.80 26.82 22.40 17.11 11.0 2.88 14.12 38.47 52.59 33.35 26.29 18.26 12.0 3.14 19.92 40.98 60.91 40.41 30.45 19.38 13.0 3.40 26.24 43.50 69.74 47.99 34.87 20.49 14.0 3.67 33.06 69.09 102.15 67.61 51.08 27.87 15.0 3.93 40.36 97.44 137.80 89.08 68.90 35.09
16.0 4.19 48.12 128.48 176.60 112.36 88.30 42.16 17.0 4.45 56.33 148.95 205.27 130.80 102.64 46.12 18.0 4.71 64.96 159.06 224.03 144.49 112.01 47.53 19.0 4.97 74.01 159.06 233.07 153.54 116.54 46.85 20.0 5.24 83.46 159.06 242.52 162.99 121.26 46.31 21.0 5.50 93.29 159.06 252.35 172.82 126.18 45.90 22.0 5.76 103.49 159.06 262.56 183.03 131.28 45.58 23.0 6.02 114.42 159.06 273.49 193.96 136.74 45.41 24.0 6.28 125.35 159.06 284.42 204.88 142.21 45.26 25.0 6.55 136.28 159.06 295.35 215.81 147.67 45.12 26.0 6.81 147.21 159.06 306.28 226.74 153.14 44.99 27.0 7.07 158.14 159.06 317.20 237.67 158.60 44.87 28.0 7.33 169.07 159.06 328.13 248.60 164.07 44.76 29.0 7.59 180.00 159.06 339.06 259.53 169.53 44.65 30.0 7.86 190.93 159.06 349.99 270.46 175.00 44.56 31.0 8.12 201.86 159.06 360.92 281.39 180.46 44.47 32.0 8.38 212.79 159.06 371.85 292.32 185.93 44.38 33.0 8.64 223.72 159.06 382.78 303.25 191.39 44.30 34.0 8.90 234.65 159.06 393.71 314.18 196.86 44.23 35.0 9.16 245.58 159.06 404.64 325.11 202.32 44.15 TOP LOAD TOP MOVEMENT TIP LOAD TIP MOVEMENT ton IN. ton IN. 0.3403E+00 0.1510E-03 0.3491E-01 0.1000E-03 0.3403E+01 0.1510E-02 0.3491E+00 0.1000E-02 0.8508E+01 0.3776E-02 0.8726E+00 0.2500E-02 0.1702E+02 0.7551E-02 0.1745E+01 0.5000E-02 0.2554E+02 0.1133E-01 0.2618E+01 0.7500E-02 0.3413E+02 0.1511E-01 0.3491E+01 0.1000E-01 0.8558E+02 0.3781E-01 0.8726E+01 0.2500E-01 0.1454E+03 0.7191E-01 0.1745E+02 0.5000E-01 0.1870E+03 0.1034E+00 0.2618E+02 0.7500E-01 0.2217E+03 0.1342E+00 0.3491E+02 0.1000E+00 0.2882E+03 0.2962E+00 0.7304E+02 0.2500E+00 0.3181E+03 0.5531E+00 0.1064E+03 0.5000E+00 0.3276E+03 0.8060E+00 0.1267E+03 0.7500E+00 0.3415E+03 0.1059E+01 0.1407E+03 0.1000E+01 0.3577E+03 0.3663E+01 0.1576E+03 0.3600E+01
Ultimate Skin Friction (tons)
I-15 D/B, BW-1, UPRR Over Track 801, Piles @ Abutment 1, D=3 ft
Dep
th (
ft)
0 20 40 60 80 100 120 140 160 180 200 220 2400
24
68
1012
1416
1820
2224
2628
3032
3436
38
Dia=3 ft
Axial Load (tons)
I-15 D/B, BW-1, UPRR Over Track 801, Piles @ Abutment 1, D=3 ft
Settl
emen
t (in
)
0 50 100 150 200 250 300 350 4000
0.2
0.4
0.6
0.8
11.
21.
41.
61.
82
2.2
2.4
2.6
2.8
33.
23.
43.
63.
84
Curve #1
Calculations for Allowable Base Resistance:
1. Ultimate Base Resistance = 159 tons (Based on SHAFT Analysis) 2. Mobilized settlement at Ultimate Load of (245 tons) 490 Kips =0.18 inch
(Based on SHAFT) 3. The CIDH pile is assumed to be rigid and deformations are neglected for this
calculation.
ofbaseSettlement4. (0.18/36)* 100 =0.5%
Diaofbase 5. Normalized Base Transfer =0.3
(Based on Figure 11.9, FHWA-IF-99-025; Shown below) 6. End Bearing = 0.3 * Ultimate End Bearing
= 0.3*159 = 47.7 tons 7. End Bearing =47.7 tons 8. Total Allowable Axial Capacity = (245+47.7)=292.7~290 kips
Settlement of Base
Dia ase meter of B
Note:- Pile is modeled in SHAFT from the ground surface. Based on design plans, the pile cut-off elevation is 5 feet below ground surface; hence this length should be deducted from the estimated pile length by SHAFT program.
BW-1_Pier1_Sfit.sfo VERTICALLY LOADED DRILLED SHAFT ANALYSIS PROGRAM SHAFT VERSION 5.0 (C) COPYRIGHT ENSOFT,INC. 1989,1995,1998,2001,2003
I-15 D/B_BW-1_Pier 1_D=7 ft
PROPOSED DEPTH = 55.0 FT ----------------
NUMBER OF LAYERS = 6 ------------------
WATER TABLE DEPTH = 16.0 FT. -------------------
FACTOR OF SAFETY APPLIED TO THE TOTAL ULTIMATE CAPACITY = 2.00 ------------------------------------------------------- FACTOR OF SAFETY APPLIED TO THE ULTIMATE BASE CAPACITY = 2.00 ------------------------------------------------------
SOIL INFORMATION ---------------
LAYER NO 1----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.464E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.500E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.000E+00
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.464E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.500E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.230E+02
LAYER NO 2----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00
Page 1
BW-1_Pier1_Sfit.sfo BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.230E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.310E+02
LAYER NO 3----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.535E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.350E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.310E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.535E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.350E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.480E+02
LAYER NO 4----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.480E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05
Page 2
BW-1_Pier1_Sfit.sfo INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.515E+02
LAYER NO 5----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.200E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.515E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.200E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.630E+02
LAYER NO 6----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.487E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.450E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.630E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.487E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.450E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.800E+02
DRILLED SHAFT INFORMATION -------------------------
Page 3
BW-1_Pier1_Sfit.sfo
DIAMETER OF STEM = 7.000 FT. DIAMETER OF BASE = 7.000 FT. END OF STEM TO BASE = 0.000 FT. ANGLE OF BELL = 0.000 DEG. IGNORED TOP PORTION = 10.000 FT. IGNORED BOTTOM PORTION = 7.000 FT. AREA OF ONE PERCENT STEEL = 55.425 SQ.IN. ELASTIC MODULUS, Ec = 0.360E+07 LB/SQ IN VOLUME OF UNDERREAM = 0.000 CU.YDS.
PREDICTED RESULTS -----------------
QS = ULTIMATE SIDE RESISTANCE; QB = ULTIMATE BASE RESISTANCE; WT = WEIGHT OF DRILLED SHAFT (FOR UPLIFT CAPACITY ONLY); QU = TOTAL ULTIMATE RESISTANCE; QBD = TOTAL ALLOWABLE LOAD USING A FACTOR OF SAFETY APPLIED TO THE ULTIMATE BASE RESISTANCE; QDN = TOTAL ALLOWABLE LOAD USING FACTORS OF SAFETY APPLIED TO THE ULTIMATE SIDE RESISTANCE AND THE ULTIMATE BASE RESISTANCE.
LENGTH VOLUME QS QB QU QBD QDN QU/VOLUME (FEET) (CU.YDS) (TONS) (TONS) (TONS) (TONS) (TONS) (TONS/CU.YDS) 18.0 25.66 25.50 634.63 660.13 342.81 330.06 25.73 19.0 27.09 51.00 619.99 670.99 361.00 335.50 24.77 20.0 28.51 76.51 599.81 676.31 376.41 338.16 23.72 21.0 29.94 102.01 574.02 676.03 389.02 338.01 22.58 22.0 31.36 127.51 542.58 670.09 398.80 335.04 21.37 23.0 32.79 153.01 505.44 658.45 405.73 329.23 20.08 24.0 34.21 178.51 466.60 645.11 411.81 322.55 18.86 25.0 35.64 204.01 433.36 637.38 420.70 318.69 17.88 26.0 37.06 229.52 405.68 635.20 432.36 317.60 17.14 27.0 38.49 255.02 383.54 638.56 446.79 319.28 16.59 28.0 39.92 280.52 366.93 647.45 463.99 323.73 16.22 29.0 41.34 306.02 355.86 661.88 483.95 330.94 16.01 30.0 42.77 331.52 350.33 681.85 506.69 340.93 15.94 31.0 44.19 392.01 350.33 742.33 567.17 371.17 16.80 32.0 45.62 452.49 350.33 802.82 627.65 401.41 17.60 33.0 47.04 512.97 350.33 863.30 688.14 431.65 18.35 34.0 48.47 573.46 350.33 923.78 748.62 461.89 19.06 35.0 49.89 633.94 378.01 1011.95 822.94 505.97 20.28 36.0 51.32 694.42 407.53 1101.95 898.19 550.98 21.47 37.0 52.74 754.91 438.90 1193.81 974.36 596.90 22.63 38.0 54.17 815.39 472.11 1287.50 1051.45 643.75 23.77 39.0 55.60 835.97 470.44 1306.41 1071.19 653.20 23.50 40.0 57.02 856.55 468.16 1324.71 1090.63 662.36 23.23 41.0 58.45 877.13 465.28 1342.41 1109.77 671.21 22.97 42.0 59.87 897.71 454.42 1352.13 1124.92 676.06 22.58 43.0 61.30 918.28 435.57 1353.86 1136.07 676.93 22.09 44.0 62.72 938.86 408.74 1347.60 1143.23 673.80 21.48 45.0 64.15 959.44 373.92 1333.36 1146.40 666.68 20.79 46.0 65.57 980.02 340.92 1320.94 1150.48 660.47 20.14 47.0 67.00 1000.60 309.72 1310.32 1155.46 655.16 19.56 48.0 68.43 1021.18 280.33 1301.51 1161.34 650.76 19.02 49.0 69.85 1041.76 258.30 1300.05 1170.90 650.03 18.61 50.0 71.28 1062.33 257.84 1320.17 1191.25 660.09 18.52 51.0 72.70 1082.91 265.68 1348.59 1215.75 674.29 18.55
Page 4
BW-1_Pier1_Sfit.sfo 52.0 74.13 1103.49 281.81 1385.30 1244.40 692.65 18.69 53.0 75.55 1124.07 298.89 1422.96 1273.52 711.48 18.83 54.0 76.98 1144.65 316.92 1461.57 1303.11 730.78 18.99 55.0 78.40 1165.23 335.90 1501.13 1333.18 750.56 19.15
RESULT FROM TREND (AVERAGED) LINE
TOP LOAD TOP MOVEMENT TIP LOAD TIP MOVEMENT ton IN. ton IN. 0.8025E+00 0.1281E-03 0.3159E-01 0.1000E-03 0.8025E+01 0.1281E-02 0.3159E+00 0.1000E-02 0.2006E+02 0.3204E-02 0.7898E+00 0.2500E-02 0.4012E+02 0.6407E-02 0.1580E+01 0.5000E-02 0.6018E+02 0.9611E-02 0.2369E+01 0.7500E-02 0.8025E+02 0.1281E-01 0.3159E+01 0.1000E-01 0.2010E+03 0.3204E-01 0.7898E+01 0.2500E-01 0.4024E+03 0.6410E-01 0.1580E+02 0.5000E-01 0.6006E+03 0.9612E-01 0.2369E+02 0.7500E-01 0.7076E+03 0.1252E+00 0.3159E+02 0.1000E+00 0.1158E+04 0.2924E+00 0.7898E+02 0.2500E+00 0.1275E+04 0.5485E+00 0.1432E+03 0.5000E+00 0.1310E+04 0.8008E+00 0.1762E+03 0.7500E+00 0.1313E+04 0.1052E+01 0.2060E+03 0.1000E+01 0.1333E+04 0.8457E+01 0.3329E+03 0.8400E+01
Page 5
Ultimate Skin Friction (tons)D
epth
(ft
)
0 100 200 300 400 500 600 700 800 900 1000 1100 12000
510
1520
2530
3540
4550
5560
Dia=7 ft
Ultimate Skin Friction (tons)D
epth
(ft
)
0 100 200 300 400 500 600 700 800 900 1000 1100 120
510
1520
2530
3540
4550
550 Dia=7 ft
Axial Load (tons)Se
ttle
men
t (in
)
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 14000
0.5
11.
52
2.5
33.
54
4.5
55.
56
6.5
77.
58
8.5
9
Curve #1
BW-1Pier 2_s retro.sfo VERTICALLY LOADED DRILLED SHAFT ANALYSIS PROGRAM SHAFT VERSION 5.0 (C) COPYRIGHT ENSOFT,INC. 1989,1995,1998,2001,2003
I-15 Over UPRR _Pier 2, Pile Dia = 7 ft
PROPOSED DEPTH = 55.0 FT ----------------
NUMBER OF LAYERS = 8 ------------------
WATER TABLE DEPTH = 13.0 FT. -------------------
FACTOR OF SAFETY APPLIED TO THE TOTAL ULTIMATE CAPACITY = 2.00 ------------------------------------------------------- FACTOR OF SAFETY APPLIED TO THE ULTIMATE BASE CAPACITY = 2.00 ------------------------------------------------------
SOIL INFORMATION ---------------
LAYER NO 1----SAND
AT THE TOP
SKIN FRICTION COEFFICIENT- BETA = 0.120E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.000E+00 INTERNAL FRICTION ANGLE, DEG. = 0.340E+02 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.000E+00
AT THE BOTTOM
SKIN FRICTION COEFFICIENT- BETA = 0.120E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.000E+00 INTERNAL FRICTION ANGLE, DEG. = 0.340E+02 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.150E+01
LAYER NO 2----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.250E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03
Page 1
BW-1Pier 2_s retro.sfo MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.150E+01
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.250E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.130E+02
LAYER NO 3----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.130E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.180E+02
LAYER NO 4----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.250E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.180E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.250E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00
Page 2
BW-1Pier 2_s retro.sfo SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.230E+02
LAYER NO 5----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.230E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.265E+02
LAYER NO 6----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.535E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.350E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.265E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.535E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.350E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.390E+02
LAYER NO 7----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01
Page 3
BW-1Pier 2_s retro.sfo UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.390E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.410E+02
LAYER NO 8----CLAY
AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.150E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.410E+02
AT THE BOTTOM
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.150E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.800E+02
DRILLED SHAFT INFORMATION -------------------------
DIAMETER OF STEM = 7.000 FT. DIAMETER OF BASE = 7.000 FT. END OF STEM TO BASE = 0.000 FT. ANGLE OF BELL = 0.000 DEG. IGNORED TOP PORTION = 7.000 FT. IGNORED BOTTOM PORTION = 7.000 FT. AREA OF ONE PERCENT STEEL = 55.425 SQ.IN. ELASTIC MODULUS, Ec = 0.360E+07 LB/SQ IN VOLUME OF UNDERREAM = 0.000 CU.YDS.
Page 4
BW-1Pier 2_s retro.sfo
PREDICTED RESULTS -----------------
QS = ULTIMATE SIDE RESISTANCE; QB = ULTIMATE BASE RESISTANCE; WT = WEIGHT OF DRILLED SHAFT (FOR UPLIFT CAPACITY ONLY); QU = TOTAL ULTIMATE RESISTANCE; QBD = TOTAL ALLOWABLE LOAD USING A FACTOR OF SAFETY APPLIED TO THE ULTIMATE BASE RESISTANCE; QDN = TOTAL ALLOWABLE LOAD USING FACTORS OF SAFETY APPLIED TO THE ULTIMATE SIDE RESISTANCE AND THE ULTIMATE BASE RESISTANCE.
LENGTH VOLUME QS QB QU QBD QDN QU/VOLUME (FEET) (CU.YDS) (TONS) (TONS) (TONS) (TONS) (TONS) (TONS/CU.YDS) 15.0 21.38 15.12 482.22 497.34 256.23 248.67 23.26 16.0 22.81 30.24 482.33 512.57 271.41 256.28 22.47 17.0 24.23 45.36 480.97 526.34 285.85 263.17 21.72 18.0 25.66 60.48 478.18 538.66 299.57 269.33 20.99 19.0 27.09 75.60 467.10 542.70 309.15 271.35 20.04 20.0 28.51 90.73 447.71 538.44 314.58 269.22 18.89 21.0 29.94 151.21 427.37 578.58 364.90 289.29 19.33 22.0 31.36 211.69 406.04 617.73 414.71 308.86 19.70 23.0 32.79 272.18 383.66 655.83 464.00 327.92 20.00 24.0 34.21 332.66 366.95 699.61 516.14 349.81 20.45 25.0 35.64 393.14 355.86 749.01 571.07 374.50 21.02 26.0 37.06 408.26 378.01 786.27 597.27 393.13 21.21 27.0 38.49 423.38 407.53 830.91 627.15 415.46 21.59 28.0 39.92 438.51 398.62 837.12 637.81 418.56 20.97 29.0 41.34 453.63 388.86 842.49 648.06 421.24 20.38 30.0 42.77 468.75 378.27 847.01 657.88 423.51 19.81 31.0 44.19 529.23 366.83 896.06 712.65 448.03 20.28 32.0 45.62 589.71 354.56 944.27 766.99 472.14 20.70 33.0 47.04 650.20 334.06 984.26 817.23 492.13 20.92 34.0 48.47 710.68 305.34 1016.02 863.35 508.01 20.96 35.0 49.89 731.26 279.15 1010.41 870.83 505.20 20.25 36.0 51.32 751.84 255.47 1007.31 879.57 503.65 19.63 37.0 52.74 772.42 234.31 1006.73 889.57 503.37 19.09 38.0 54.17 793.00 215.68 1008.68 900.84 504.34 18.62 39.0 55.60 813.57 199.57 1013.14 913.36 506.57 18.22 40.0 57.02 834.15 191.51 1025.66 929.91 512.83 17.99 41.0 58.45 854.73 191.51 1046.24 950.49 523.12 17.90 42.0 59.87 875.31 191.51 1066.82 971.07 533.41 17.82 43.0 61.30 895.89 191.51 1087.40 991.64 543.70 17.74 44.0 62.72 916.47 191.51 1107.98 1012.22 553.99 17.66 45.0 64.15 937.05 191.51 1128.56 1032.80 564.28 17.59 46.0 65.57 957.63 191.51 1149.14 1053.38 574.57 17.52 47.0 67.00 1018.11 191.51 1209.62 1113.86 604.81 18.05 48.0 68.43 1078.59 191.51 1270.10 1174.35 635.05 18.56 49.0 69.85 1087.66 191.51 1279.18 1183.42 639.59 18.31 50.0 71.28 1096.74 191.51 1288.25 1192.49 644.12 18.07 51.0 72.70 1105.81 191.51 1297.32 1201.57 648.66 17.84 52.0 74.13 1114.88 191.51 1306.39 1210.64 653.20 17.62 53.0 75.55 1123.95 191.51 1315.47 1219.71 657.73 17.41 54.0 76.98 1133.03 191.51 1324.54 1228.78 662.27 17.21 55.0 78.40 1142.10 191.51 1333.61 1237.86 666.81 17.01
RESULT FROM TREND (AVERAGED) LINE
TOP LOAD TOP MOVEMENT TIP LOAD TIP MOVEMENTPage 5
BW-1Pier 2_s retro.sfo ton IN. ton IN. 0.6721E+00 0.1228E-03 0.1801E-01 0.1000E-03 0.6721E+01 0.1228E-02 0.1801E+00 0.1000E-02 0.1680E+02 0.3071E-02 0.4503E+00 0.2500E-02 0.3361E+02 0.6142E-02 0.9006E+00 0.5000E-02 0.5041E+02 0.9213E-02 0.1351E+01 0.7500E-02 0.6721E+02 0.1228E-01 0.1801E+01 0.1000E-01 0.1682E+03 0.3071E-01 0.4503E+01 0.2500E-01 0.3368E+03 0.6143E-01 0.9006E+01 0.5000E-01 0.5044E+03 0.9215E-01 0.1351E+02 0.7500E-01 0.5955E+03 0.1205E+00 0.1801E+02 0.1000E+00 0.9714E+03 0.2840E+00 0.4503E+02 0.2500E+00 0.1054E+04 0.5380E+00 0.8167E+02 0.5000E+00 0.1075E+04 0.7894E+00 0.1005E+03 0.7500E+00 0.1069E+04 0.1040E+01 0.1175E+03 0.1000E+01 0.1049E+04 0.8441E+01 0.1898E+03 0.8400E+01
Page 6
Ultimate Skin Friction (tons)D
epth
(ft
)
0 100 200 300 400 500 600 700 800 900 1000 1100 12000
510
1520
2530
3540
4550
5560
Dia=7 ft
Axial Load (tons)Se
ttle
men
t (in
)
0 100 200 300 400 500 600 700 800 900 1000 11000
0.5
11.
52
2.5
33.
54
4.5
55.
56
6.5
77.
58
8.5
9
Curve #1
VERTICALLY LOADED DRILLED SHAFT ANALYSIS PROGRAM SHAFT VERSION 5.0 (C) COPYRIGHT ENSOFT,INC. 1989,1995,1998,2001,2003 I-15 Over UPRR Track 801 (Bridge No. G-941), Abutment 2, Pile Dia = 3 fe PROPOSED DEPTH = 38.5 FT ---------------- NUMBER OF LAYERS = 7 ------------------ WATER TABLE DEPTH = 32.5 FT. ------------------- FACTOR OF SAFETY APPLIED TO THE TOTAL ULTIMATE CAPACITY = 2.00 ------------------------------------------------------- FACTOR OF SAFETY APPLIED TO THE ULTIMATE BASE CAPACITY = 2.00 ------------------------------------------------------ SOIL INFORMATION --------------- LAYER NO 1----SAND AT THE TOP SKIN FRICTION COEFFICIENT- BETA = 0.120E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.000E+00 INTERNAL FRICTION ANGLE, DEG. = 0.340E+02 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.000E+00 AT THE BOTTOM SKIN FRICTION COEFFICIENT- BETA = 0.881E+00 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.000E+00 INTERNAL FRICTION ANGLE, DEG. = 0.340E+02 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.210E+02 LAYER NO 2----CLAY AT THE TOP
STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.250E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.210E+02 AT THE BOTTOM STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.250E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.325E+02 LAYER NO 3----CLAY AT THE TOP STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.325E+02 AT THE BOTTOM STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.375E+02 LAYER NO 4----CLAY AT THE TOP STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.250E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00
SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.375E+02 AT THE BOTTOM STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.250E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.425E+02 LAYER NO 5----CLAY AT THE TOP STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.425E+02 AT THE BOTTOM STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.460E+02 LAYER NO 6----CLAY AT THE TOP STRENGTH REDUCTION FACTOR-ALPHA = 0.535E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.350E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.460E+02
AT THE BOTTOM STRENGTH REDUCTION FACTOR-ALPHA = 0.535E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.350E+04 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.120E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.585E+02 LAYER NO 7----CLAY AT THE TOP STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.585E+02 AT THE BOTTOM STRENGTH REDUCTION FACTOR-ALPHA = 0.550E+00 END BEARING COEFFICIENT-Nc = 0.700E+01 UNDRAINED SHEAR STRENGTH, LB/SQ FT = 0.100E+05 INTERNAL FRICTION ANGLE, DEG. = 0.000E+00 BLOWS PER FOOT FROM STANDARD PENETRATION TEST = 0.000E+00 SOIL UNIT WEIGHT, LB/CU FT = 0.125E+03 MAXIMUM LOAD TRANSFER FOR SOIL, LB/SQ FT = 0.100E+11 DEPTH, FT = 0.605E+02 DRILLED SHAFT INFORMATION ------------------------- DIAMETER OF STEM = 3.000 FT. DIAMETER OF BASE = 3.000 FT. END OF STEM TO BASE = 0.000 FT. ANGLE OF BELL = 0.000 DEG. IGNORED TOP PORTION = 5.000 FT. IGNORED BOTTOM PORTION = 3.000 FT. AREA OF ONE PERCENT STEEL = 10.180 SQ.IN. ELASTIC MODULUS, Ec = 0.360E+07 LB/SQ IN VOLUME OF UNDERREAM = 0.000 CU.YDS. PREDICTED RESULTS
----------------- QS = ULTIMATE SIDE RESISTANCE; QB = ULTIMATE BASE RESISTANCE; WT = WEIGHT OF DRILLED SHAFT (FOR UPLIFT CAPACITY ONLY); QU = TOTAL ULTIMATE RESISTANCE; QBD = TOTAL ALLOWABLE LOAD USING A FACTOR OF SAFETY APPLIED TO THE ULTIMATE BASE RESISTANCE; QDN = TOTAL ALLOWABLE LOAD USING FACTORS OF SAFETY APPLIED TO THE ULTIMATE SIDE RESISTANCE AND THE ULTIMATE BASE RESISTANCE. LENGTH VOLUME QS QB QU QBD QDN QU/VOLUME (FEET) (CU.YDS) (TONS) (TONS) (TONS) (TONS) (TONS) (TONS/CU.YDS) 9.0 2.36 3.97 33.44 37.41 20.69 18.71 15.88 10.0 2.62 8.49 35.96 44.45 26.47 22.22 16.98 11.0 2.88 13.55 38.47 52.02 32.79 26.01 18.06 12.0 3.14 19.12 40.98 60.11 39.62 30.05 19.13 13.0 3.40 25.19 43.50 68.69 46.94 34.35 20.18 14.0 3.67 31.74 46.01 77.75 54.75 38.88 21.21 15.0 3.93 38.75 48.53 87.27 63.01 43.64 22.22 16.0 4.19 46.20 56.18 102.38 74.29 51.19 24.44 17.0 4.45 54.07 64.03 118.11 86.09 59.05 26.53 18.0 4.71 62.36 72.01 134.37 98.37 67.19 28.51 19.0 4.97 71.05 77.10 148.15 109.60 74.08 29.78 20.0 5.24 80.12 79.53 159.65 119.89 79.83 30.49 21.0 5.50 89.56 79.53 169.09 129.33 84.55 30.75 22.0 5.76 99.35 79.53 178.89 139.12 89.44 31.05 23.0 6.02 109.49 79.53 189.02 149.26 94.51 31.39 24.0 6.28 119.96 79.53 199.49 159.73 99.75 31.75 25.0 6.55 126.44 79.53 205.97 166.21 102.99 31.47 26.0 6.81 132.92 79.53 212.45 172.69 106.23 31.21 27.0 7.07 139.40 79.53 218.93 179.17 109.47 30.97 28.0 7.33 145.88 122.65 268.53 207.20 134.26 36.63 29.0 7.59 152.36 171.92 324.28 238.32 162.14 42.71 30.0 7.86 158.84 227.35 386.19 272.52 193.10 49.16 31.0 8.12 165.32 264.30 429.63 297.47 214.81 52.93 32.0 8.38 171.80 282.78 454.58 313.19 227.29 54.25 33.0 8.64 178.28 239.67 417.95 298.12 208.98 48.37 34.0 8.90 184.76 190.39 375.16 279.96 187.58 42.14 35.0 9.16 191.24 134.96 326.21 258.73 163.10 35.60 36.0 9.43 197.72 98.01 295.73 246.73 147.87 31.37 37.0 9.69 223.65 79.53 303.18 263.41 151.59 31.29 38.0 9.95 249.57 122.65 372.21 310.89 186.11 37.41 39.0 10.21 275.49 171.92 447.41 361.45 223.70 43.81 TOP LOAD TOP MOVEMENT TIP LOAD TIP MOVEMENT ton IN. ton IN. 0.3332E+00 0.1533E-03 0.3773E-01 0.1000E-03 0.3332E+01 0.1533E-02 0.3773E+00 0.1000E-02 0.8329E+01 0.3831E-02 0.9432E+00 0.2500E-02 0.1666E+02 0.7663E-02 0.1886E+01 0.5000E-02 0.2499E+02 0.1149E-01 0.2829E+01 0.7500E-02 0.3340E+02 0.1533E-01 0.3773E+01 0.1000E-01 0.8373E+02 0.3836E-01 0.9432E+01 0.2500E-01
0.1429E+03 0.7299E-01 0.1886E+02 0.5000E-01 0.1845E+03 0.1050E+00 0.2829E+02 0.7500E-01 0.2188E+03 0.1362E+00 0.3773E+02 0.1000E+00 0.2895E+03 0.3003E+00 0.7894E+02 0.2500E+00 0.3229E+03 0.5589E+00 0.1150E+03 0.5000E+00 0.3355E+03 0.8128E+00 0.1369E+03 0.7500E+00 0.3506E+03 0.1067E+01 0.1521E+03 0.1000E+01 0.3680E+03 0.3671E+01 0.1704E+03 0.3600E+01
Ultimate Skin Friction (tons)
I-15 D/B, BW-1, UPRR Over Track 801, Piles @ Abutment 2, D=3 ft
Dep
th (
ft)
0 20 40 60 80 100 120 140 160 180 200 220 2400
24
68
1012
1416
1820
2224
2628
3032
3436
38
Dia=3 ft
Axial Load (tons)
I-15 D/B, BW-1, UPRR Over Track 801, Piles @ Abutment 2, D=3 ft
Settl
emen
t (in
)
0 50 100 150 200 250 300 350 4000
0.2
0.4
0.6
0.8
11.
21.
41.
61.
82
2.2
2.4
2.6
2.8
33.
23.
43.
63.
84
Curve #1
Calculations for Allowable Base Resistance:
1. Ultimate Base Resistance = 79 tons (Based on SHAFT Analysis) 2. Mobilized settlement at Ultimate Load of (245 tons) 490 Kips =0.28 inch
(Based on SHAFT) 3. The CIDH pile is assumed to be rigid and deformations are neglected for this
calculation.
ofbaseSettlement4. (0.28/36)* 100 =0.77%
Diaofbase
5. Normalized Base Transfer =0.45
(Based on Figure 11.9, FHWA-IF-99-025; Shown below) 6. End Bearing = 0.45* Ultimate End Bearing
= 0.45*79 = 35.55 tons 7. End Bearing =35.55 tons 8. Total Allowable Axial Capacity = (245+35.55)*(2/2)=280 kips~270 kips
Settlement of Base
Dia ase meter of B
Note:-
Pile is modeled in SHAFT from the ground surface. Based on design plans, the pile cut-off elevation is 5 feet
below ground surface; hence this length should be deducted from the estimated pile length by SHAFT program.
Lateral Earth Pressures
Project: I-15 Design/BuildSegment 1:UPRR Spur Track 213 (Bridge No. G-941)Project No.: 362104.DE.GT.S1.FC
Performed By: J. BarkerDate: 5/20/2008
Page 1 of 2
Lateral Earth Pressure - Flat Backfill
Back slope β 0deg:= Wall Batter θ 90deg:= Angle of Wall Friction δ 0deg:=
Internal friction of granular backfill φ' 34deg:=
Unit weight of granular backfill γbackfill 125pcf:=
At-rest earth pressure coefficient Ko 1 sin φ'( )−:= Ko 0.44=
Active earth pressure coefficient
Kasin θ φ'+( )2
sin θ( )2 sin θ δ−( )⋅ 1sin φ' δ+( ) sin φ' β−( )⋅
sin θ δ−( ) sin θ β+( )⋅+
⎛⎜⎝
⎞⎟⎠
2
⋅
:= Ka 0.28=
Passive earth pressure coefficient Kp 3.45:= (AASHTO 2002, Figure 5.5.2C)
Active Dynamic Pressure Coefficients
Horizontal acceleration coefficient kh 0.075:= (1/2*PGA)
(AASHTO 2002, 6.4-3)Vertical acceleration coefficient kv 0:=
ψ atankh
1 kv−
⎛⎜⎝
⎞⎟⎠
:= ψ 4.289 deg= Wall Slope θ 0deg:=
Dynamic and static active earth pressure coefficient
KAEcos φ' θ− ψ−( )2
cos ψ( ) cos θ( )2⋅ cos δ θ+ ψ+( )⋅ 1sin δ φ'+( ) sin φ' β− ψ−( )⋅
cos δ θ+ ψ+( ) cos β θ−( )⋅+
⎛⎜⎝
⎞⎟⎠
2
⋅
:= KAE 0.33=
Dynamic active earth pressure coefficient
ΔKAE KAE 1 kv−( )⋅ Ka−:= ΔKAE 0.04=
Project: I-15 Design/BuildSegment 1:UPRR Spur Track 213 (Bridge No. G-941)Project No.: 362104.DE.GT.S1.FC
Performed By: J. BarkerDate: 5/20/2008
Page 2 of 2
At-Rest Dynamic Pressure Coefficients
Horizontal acceleration coefficient kh 0.225:= (1.5*PGA)
(AASHTO 2002, 6.4-3)Vertical acceleration coefficient kv 0:=
ψ atankh
1 kv−
⎛⎜⎝
⎞⎟⎠
:= ψ 12.68 deg= Wall Slope θ 0deg:=
Dynamic and static at-rest earth pressure coefficient
KAEcos φ' θ− ψ−( )2
cos ψ( ) cos θ( )2⋅ cos δ θ+ ψ+( )⋅ 1sin δ φ'+( ) sin φ' β− ψ−( )⋅
cos δ θ+ ψ+( ) cos β θ−( )⋅+
⎛⎜⎝
⎞⎟⎠
2
⋅
:= KAE 0.43=
Dynamic at-rest earth pressure coefficient
ΔKAE KAE 1 kv−( )⋅ Ka−:= ΔKAE 0.15=
1.5201.520
W
250.00 lb/ft2
1.5201.520
Material: CalicheUnit Weight: 125 lb/ft3Cohesion: 200 psfFriction Angle: 32 degreesWater Surface: Water Table
Material: Clay1Unit Weight: 120 lb/ft3Cohesion: 200 psfFriction Angle: 28 degreesWater Surface: Water Table
Material: Clay2Unit Weight: 120 lb/ft3Cohesion: 200 psfFriction Angle: 28 degreesWater Surface: Water Table
Abutment 1 Slope Stability Analysis; I-15 Design-Build. I-15 Over UPRR Spur Track
Material: FillUnit Weight: 120 lb/ft3Cohesion: 100 psfFriction Angle: 34 degrees
Safety Factor0.0000.2500.5000.7501.0001.2501.5001.7502.0002.2502.5002.7503.0003.2503.5003.7504.0004.2504.5004.7505.0005.2505.5005.7506.000+
2175
2150
2125
2100
2075
2050
2025
2000
-75 -50 -25 0 25 50 75 100 125 150 175
1.3291.329
W
250.00 lb/ft2
1.3291.329
Material: FillUnit Weight: 120 lb/ft3Cohesion: 100 psfFriction Angle: 34 degrees
Material: Clay1Unit Weight: 120 lb/ft3Cohesion: 200 psfFriction Angle: 28 degreesWater Surface: Water TableMaterial: Caliche
Unit Weight: 125 lb/ft3Cohesion: 200 psfFriction Angle: 32 degreesWater Surface: Water Table
Material: Clay2Unit Weight: 120 lb/ft3Cohesion: 200 psfFriction Angle: 28 degreesWater Surface: Water Table
Abutment 1 Pseudostatic Slope Stability Analysis; I-15 Design-Build, I-15 Over UPRR Spur Track
Safety Factor0.0000.2500.5000.7501.0001.2501.5001.7502.0002.2502.5002.7503.0003.2503.5003.7504.0004.2504.5004.7505.0005.2505.5005.7506.000+
2175
2150
2125
2100
2075
2050
2025
2000
-75 -50 -25 0 25 50 75 100 125 150 175
0.075