Prepared for:
R.F. Binnie & Associates Ltd.
#300 – 4940 Canada Way, Burnaby BC V5G 4M5
12 June 2020
GEOTECHNICAL ASSESSMENT
AND DESIGN
Lynx Creek East Segment
Highway 29, British Columbia
Project # KX052807.11
‘Wood’ is a trading name for John Wood Group PLC and its subsidiaries
GEOTECHNICAL ASSESSMENT
AND DESIGN
Lynx Creek East Segment
Highway 29, British Columbia
Project # KX052807.11
Prepared for:
R.F. Binnie & Associates Ltd.
300 - 4940 Canada Way Burnaby BC, V5G 4M5
Prepared by:
Wood Environment & Infrastructure Solutions,
a Division of Wood Canada Limited
3456 Opie Crescent Prince George, BC V2N 2P9
12 June 2020
Copyright and non-disclosure notice
The contents and layout of this report are subject to copyright owned by Wood (© Wood Environment & Infrastructure Solutions)
save to the extent that copyright has been legally assigned by us to another party or is used by Wood under license. To the extent
that we own the copyright in this report, it may not be copied or used without our prior written agreement for any purpose other
than the purpose indicated in this report. The methodology (if any) contained in this report is provided to you in confidence and
must not be disclosed or copied to third parties without the prior written agreement of Wood. Disclosure of that information may
constitute an actionable breach of confidence or may otherwise prejudice our commercial interests. Any third party who obtains
access to this report by any means will, in any event, be subject to the Third Party Disclaimer set out below.
Third-party disclaimer
Any disclosure of this report to a third party is subject to this disclaimer. The report was prepared by Wood at the instruction of, and
for use by, our client named on the front of the report. It does not in any way constitute advice to any third party who is able to
access it by any means. Wood excludes to the fullest extent lawfully permitted all liability whatsoever for any loss or damage
howsoever arising from reliance on the contents of this report. We do not however exclude our liability (if any) for personal injury or
death resulting from our negligence, for fraud or any other matter in relation to which we cannot legally exclude liability.
Geotechnical Assessment and Design
Lynx Creek East
Project # KX052807.11 | 12 June 2020 Table of Contents
Table of Contents
Introduction ........................................................................................................................................................................... 1
General Project Description ............................................................................................................................................. 1
Background Information ................................................................................................................................................... 2
Geology ................................................................................................................................................................... 2
Quaternary Geology ........................................................................................................................................... 2
Geotechnical Site Investigations by Wood ............................................................................................... 3
Description of Highway Alignment and Site Conditions by Station ............................................................... 3
Acid Rock Drainage and Metal Leaching Potential ................................................................................................ 7
Existing Highway 29 Asphalt Thicknesses .................................................................................................................. 7
Slope Stability........................................................................................................................................................................ 8
Design Criteria ...................................................................................................................................................... 8
Slope Stability Models....................................................................................................................................... 8
7.2.1 Material Parameters .......................................................................................................................... 9
7.2.3 Groundwater Conditions ...............................................................................................................12
7.2.4 Geometry .............................................................................................................................................12
Slope Stability Assessment ............................................................................................................................12
7.3.1 Sta. 1004+300 to Sta. 1004+660 ................................................................................................12
7.3.2 Sta. 1004+900 to Sta. 1005+460 ................................................................................................13
7.3.3 Sta. 1005+500 to Sta. 1005+690 ................................................................................................14
7.3.4 Sta. 1005+690 to Sta. 1005+910 ................................................................................................14
7.3.5 Sta. 1005+910 to Sta. 1005+970 ................................................................................................15
7.3.6 Sta. 1006+120 to Sta. 1006+200 ................................................................................................16
7.3.7 Sta. 1006+200 to Sta. 1006+780 ................................................................................................16
7.3.8 Sta. 1006+860 to Sta. 1007+030 ................................................................................................17
7.3.9 Sta. 1007+030 to Sta. 1007+070 ................................................................................................17
Impact of Long-Term Reservoir Erosion ...................................................................................................................18
West of Sta. 1005+100 ....................................................................................................................................18
Between Sta. 1005+400 and 1005+800 ...................................................................................................18
Between Sta. 1005+860 and 1006+000 ...................................................................................................19
Settlement Analyses .........................................................................................................................................................19
Soil Stress History .............................................................................................................................................19
Soil Compressibility Parameters ..................................................................................................................20
Granular Soil .......................................................................................................................................20
Cohesive Soil ......................................................................................................................................20
Embankment Stress Distribution ................................................................................................................21
Settlement Estimates .......................................................................................................................................21
Time Rate of Consolidation ...........................................................................................................................24
Secondary Compression Settlements .......................................................................................................24
Settlement of Existing Fill...............................................................................................................................24
Settlement Mitigation ......................................................................................................................................................25
Instrumentation ..................................................................................................................................................................26
Slope Inclinometer Casing ............................................................................................................26
Settlement Plates ..............................................................................................................................................27
Vibrating Wire Piezometers ..........................................................................................................................27
Large Diameter Culvert Headwalls ..............................................................................................................................28
Subgrade Conditions .......................................................................................................................................28
Soil Bearing Capacity .......................................................................................................................................29
Geotechnical Assessment and Design
Lynx Creek East
Project # KX052807.11 | 12 June 2020 Table of Contents
Frost Design Considerations .........................................................................................................................29
Lateral Earth Pressures ....................................................................................................................................30
Sliding Friction Coefficient ............................................................................................................................30
General Recommendations ...........................................................................................................................................30
Stripping ...............................................................................................................................................................30
Subgrade Preparation .....................................................................................................................................33
Embankment Fill Construction .....................................................................................................................33
Cut Slope Construction ...................................................................................................................................34
Temporary Excavations ...................................................................................................................................34
Culverts and Headwalls...................................................................................................................................35
Geotextile and Biaxial Geogrid Specifications .......................................................................................35
Pavement Structure ..........................................................................................................................................36
Soil Waste Disposal ..........................................................................................................................................37
Designated Soil Waste Disposal Sites........................................................................................................................37
Site B8 ....................................................................................................................................................................38
Site B9 ....................................................................................................................................................................38
Geotechnical Recommendations by Station ...........................................................................................................38
Closure ...................................................................................................................................................................................47
References ............................................................................................................................................................................48
List of Appendices
APPENDIX A FIGURES 1 TO 4, GEOTECHNICAL INVESTIGATION
FIGURE 5, SHEAR KEY STA. 1005+940
APPENDIX B FIGURES 6 TO 26, SLOPE STABILITY ANALYSES
Geotechnical Assessment and Design
Lynx Creek East
Project # KX052807.11 | 12 June 2020 Table of Contents
List of Tables
Table 6-1: Encountered Asphalt Thickness................................................................................................................................. 7
Table 7-1: Target Factors of Safety for Slope Stability Assessment ................................................................................. 8
Table 7-2: Location of Slope Stability Models .......................................................................................................................... 9
Table 7-3: Parameters used to Estimate Effective Stress Residual Friction Angle for Cohesive Soils .............. 10
Table 7-4: Total Stress Strength Parameters for Cohesive Soils ..................................................................................... 11
Table 7-5: Summary of Material Properties used in the Slope Stability Models ...................................................... 11
Table 7-6: Sta. 1004+440, Results of Slope Optimization (Optimized Slopes Shown in Figure 6) ................... 12
Table 7-7: Sta. 1004+440, Results of Slope Stability Assessment (Figure 7) ............................................................. 13
Table 7-8: Sta. 1005+260, Results of Slope Optimization (Optimized Slopes Shown in Figure 8) ................... 13
Table 7-9: Sta. 1005+260, Results of Slope Stability Assessment (Figures 9 and 10) ............................................ 13
Table 7-10: Sta. 1005+600, Results of Slope Optimization (Optimized Slope Shown in Figure 11) ................ 14
Table 7-11: Sta. 1005+600, Results of Slope Stability Assessment (Figure 11) ........................................................ 14
Table 7-12: Sta. 1005+820, Results of Slope Optimization (Optimized Slopes Shown in Figure 12) .............. 14
Table 7-13: Sta. 1005+820, Results of Slope Stability Assessment (Figures 13 and 14) ....................................... 15
Table 7-14: Sta. 1005+940, Results of Slope Stability Assessment (Figure 15 and 16) ......................................... 15
Table 7-15: Sta. 1006+200, Results of Slope Optimization (Optimized Slopes Shown in Figure 17) .............. 16
Table 7-16: Sta. 1006+200, Results of Slope Stability Assessment (Figures 18 and 19) ....................................... 16
Table 7-17: Sta. 1006+520, Results of Slope Optimization LHS (Optimized Slope Shown in Figure 20) ....... 16
Table 7-18: Sta. 1006+520, Results of Slope Stability Assessment (Figures 20 through 22) .............................. 17
Table 7-19: Sta. 1007+000, Results of Slope Stability Assessment (Figures 23 and 24) ....................................... 17
Table 7-20: Sta. 1007+060, Results of Slope Stability Assessment (Figures 25 and 26) ....................................... 17
Table 9-1: Culvert Locations and Descriptions ...................................................................................................................... 19
Table 9-2: Results of Incremental Load Consolidation Test ............................................................................................. 20
Table 9-3: Estimated Compression and Recompression Indices .................................................................................... 21
Table 9-4: Estimated Settlement at Culvert Location, below Road Centerline ......................................................... 22
Table 9-5: Estimated Differential Settlement along Culverts ........................................................................................... 23
Table 9-6: Time Rate of 95% Consolidation Considering Two-Way Drainage ......................................................... 24
Table 10-1: Estimated Differential Settlement and Settlement Criterion .................................................................... 25
Table 10-2: Settlement Mitigation .............................................................................................................................................. 26
Table 11-1: Slope Inclinometer Casings ................................................................................................................................... 27
Table 11-2: Settlement Plates ....................................................................................................................................................... 27
Table 11-3: Vibrating Wire Piezometers ................................................................................................................................... 28
Table 12-1: Headwall and Collar Locations, and Pipe Diameter ..................................................................................... 28
Table 12-2: Summary of Subsurface Conditions at Headwall and Collar Locations ............................................... 28
Table 12-3: Factored Ultimate Bearing Capacities ............................................................................................................... 29
Table 12-4: Earth Pressure Coefficients under Static Condition for Various Sloping Conditions ..................... 30
Table 13-1: Stripping Depths by Station .................................................................................................................................. 31
Table 13-2: Non-Woven Geotextile Specifications .............................................................................................................. 35
Table 13-3: Biaxial Polypropylene Geogrid Specifications ................................................................................................ 36
Table 13-4: Recommended Minimum Pavement Structure Thickness ........................................................................ 36
Table 13-5: Likely Locations for Non-Woven Geotextile Separator below SGSB .................................................... 36
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 1
Introduction
As part of BC Hydro’s proposed Site C Clean Energy Project, portions of the existing Highway 29
alignment between Hudson’s Hope and Charlie Lake, BC, will be flooded during normal reservoir
operation. Before filling of the reservoir, the affected portions of the highway will be relocated away from
the reservoir area. In support of the project, Wood Environment & Infrastructure Solutions a Division of
Wood Canada Limited (Wood), formerly Amec Foster Wheeler, was retained by R.F. Binnie & Associates
Ltd. (Binnie) to provide geotechnical engineering services in support of proposed realignment for an
approximately 2.95 km long segment (Sta. 1004+330 to Sta. 1007+280) of Highway 29, referred to herein
as Lynx Creek East. The general location of the Lynx Creek East segment is shown in Figure 1 and a plan of
the proposed realignment is provided on two plan sheets in Figure 2, both in Appendix A.
General Project Description
The proposed 2.95 km long Lynx Creek East realignment segment is referenced as the L1000-Line (Binnie
Plan dated 17 April 2020) which comprises a 2-lane paved highway. The west end of the Lynx Creek
realignment starts at Sta. 1004+330 and extends in a northeasterly direction generally north (left) of and
parallel to the existing Highway 29 to approximately Sta. 1006+350, where it will cross Highway 29. East of
approximately Sta. 1006+350, the new alignment follows the left bank of the Peace River until it merges
back into Highway 29 at approximately Sta. 1007+280. A plan of the proposed L1000-Line is provided on
two map sheets in Figure 2. Figure 3 (Sheets 1 to 5) depicts a profile view along the new highway
alignment centreline. Figure 4 (Sheets 1 to 6) depicts cross-sections at various points along the alignment.
Figures 1 through 4 are in Appendix A. The terms left hand side (LHS) and right hand side (RHS) are used
to refer to the north and south sides of the alignment, respectively.
For detailed descriptions of the background topographic, geology and terrain conditions along the
project segment, the reader is referred to definition design phase reporting (AMEC, 2012).
East of approximately Sta. 1004+800 to approximately Sta. 1007+080 the L1000-Line traverses several
alluvial fan terrain features. Wood carried out an assessment of the debris flow risk associated with the
alluvial fan features and presented the results in a memo dated 04 November 2019 (Wood, 2019a).
Between approximately Sta. 1006+260 and the eastern limit of the Lynx Creek East segment, the highway
is located on an approximately 25 m high embankment that will be partially founded in the current Peace
River. An in-river Early Works platform nominally higher than the water level in the Peace River is to be
constructed in this area prior to construction of the alignment. Design RHS embankment fill slopes in this
area will be confirmed after geotechnical drilling is carried out from the surface of the in-river platform.
Beyond the eastern limit of the Lynx Creek East segment, the existing highway is tightly constrained
between a large landslide feature known as the Farrell Creek Road Slide, which is located above and to the
left of the highway, and a steep erosional slope down into the Peace River on the right. An in-stream
reservoir shoreline stability berm is proposed along the steep erosion slope. As part of the Lynx Creek East
segment design work, Wood carried out an assessment of the Farrell Creek Road Slide and the proposed
in-stream reservoir shoreline stability berm and presented the results in a memo dated 17 December 2019
(Wood, 2019b).
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 2
Background Information
Geology
The Peace region of British Columbia is part of the Peace River Lowland, of the Alberta Plateau sub-
province of the Northern Interior Plains (Bidwell, 1999, Hartman and Clague, 2008). It has plateaus and
gently rolling upland areas that have been deeply incised into the underlying soil and bedrock by the
Peace River and its tributaries. Within this region are found uplands, river valleys, and raised terraces. The
uplands can be characterized as steep to gently rolling ridges with bedrock typically near ground surface.
The top of the terrace features have little relief, although scarps are located between the terrace levels.
The terraces are located within and adjacent to river valleys. The area has undergone many stages of
glacial advance and retreat. Since the last glaciation, the Peace River rapidly eroded the current valley
(Hartman and Clague, 2008).
Bedrock geology is summarized from Geological Survey of Canada Bulletin 328 (Stott, 1982), the Lynx
Creek East segment is underlain by gently northeast-dipping sedimentary beds of the Lower Cretaceous
age. Mapping identifies the site as near the contact between the overlying Shaftesbury Formation and the
underlying Boulder Creek, Hulcross and Gates Formations.
The Boulder Creek Formation is described as consisting of fine-grained, laminated sandstone with
interbedded mudstone, and the formation is described as laying gradationally on the underlying marine
shales and siltstones of the Hulcross Formation.
The Hulcross Formation is described as consisting of rubbly, silty dark grey to black shale or mudstones.
The silt content is noted to increase upward through the member with thin beds of argillaceous siltstone
and sandstone occurring in the uppermost part of the member.
In the vicinity of Gates Island, the Gates Formation is described as consisting of massive, thick-bedded,
fine-grained, well-sorted sandstone that often forms overhanging cliffs.
Bedrock exposed in a gully (colloquially known as the amphitheater) on the left bank of the river across
from Gates Island is identified as the Hulcross Formation overlying the Gates Formation, and the Boulder
Creek Formation is noted to be possibly exposed near the top of the gully.
Quaternary Geology
The quaternary geology upstream of Halfway River, as described by BGC (2012), suggests that the
overburden soils comprising the valley wall of the Peace River likely consist of the following units:
1. Glacial Lake Peace (Interbedded Sand, Silt and Clay), over
2. Laurentide Till, over
3. Interbedded layers of valley infill sediments including glaciolacustrine deposits (e.g. Glacial Lake
Mathews) and granular fluvial deposits.
Glacial Lake Peace and Laurentide Till are located on the plain above the Peace River Valley, and valley
infill sediments are located within the Peace River Valley. Due to down cutting of the modern Peace River,
there may only be remnants of the older valley infill sediments within the Peace River Valley. The valley
bottom sediments in the vicinity of Lynx Creek are more likely to consist of younger, post-glacial, granular
fluvial channel, terrace deposits, fine-grained (silt/clay) over-bank flood plain deposits, and colluvial
sediments derived from adjacent valley slopes.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 3
Geotechnical Site Investigations by Wood
To support design for the Lynx Creek East segment, Wood carried out geotechnical site investigations in
2018 and 2019. The bulk of the geotechnical investigation work was carried out in 2018 for the original
definition design alignment; however, in January 2019, a significant northerly alignment shift away from
the definition design was proposed and subsequently a supplemental geotechnical investigation specific
to the new alignment was carried out in 2019. Information from the investigations is presented in a
geotechnical data report (Wood, 2019c). The boundary of the west end of the Lynx Creek East segment
was subsequently shifted 370 m west, information from the Lynx Creek West geotechnical data report
(Wood, 2020) was used for analyses in that area.
Description of Highway Alignment and Site Conditions by
Station
For the purposes of geotechnical assessment and design, the L1000-Line was divided into sections having
similar topographic, geological and geometric design geometries. These sections are described below.
Subsurface conditions along the alignment centerline are summarized in Figure 3 (Sheets 1 to 5) and in
cross sections at various points along the alignment, shown in Figure 4 (Sheets 1 to 6), all in Appendix A.
Sta. 1004+330 to Sta. 1004+660: The alignment transitions from an upper to a lower terrace largely on
an embankment. The section includes cuts approximately 5 m deep and an embankment up to 5 m high.
A culvert goes through the embankment at Sta. 1004+430. The culvert is corrugated steel pipe, with a
diameter of 0.9 m, a length of 61.5 m, a gradient of 1.4% and a skew of 135°.
Subsurface conditions below the upper terrace (area of cut) generally consisted of gravel with variable
amounts of sand and silt, over bedrock. The bedrock surface elevation is variable and was encountered at
470.1 and 473.1 m elevations. The cut slope may encounter bedrock. Subsurface conditions below the
lower terrace (area of fill) generally consisted of clay between 3.6 m depth to greater than 5 m depth. In
two test holes sand was located below the clay. Groundwater was inferred at 6.2 m depth at
CPT18-LX-008.
Sta. 1004+660 to Sta. 1004+780: The alignment is scratch grade. The section includes shallow fills of
less than 2 m and ditch cuts of up to 1 m. TP18-LX-039 encountered clayey sand to 2.4 m depth, over
gravel to 2.7 m depth, over silt and clay. Bedrock and groundwater were not encountered within the
depth of the investigation.
Sta. 1004+780 to Sta. 1004+840: The alignment crosses an entrenched drainage channel and is located
near the distal edge of an alluvial fan. The entrenched drainage channel is crossed by a culvert at Sta.
1004+812. The culvert is corrugated steel pipe, has a diameter of 2.4 m, a length of 27.5 m, a gradient of
4%, a skew of 105° and headwalls at the inlet and outlet. Riprap check dams are proposed upstream of
the inlet and a riprap basin is proposed downstream of the inlet. Subsurface conditions below the culvert
generally consisted of silt and sand.
Subsurface conditions along the highway section generally consisted of sand and gravel, interbedded with
silt and clay, over shale bedrock. Bedrock was encountered at approximate 460 m elevation
(approximately 10 m below the proposed alignment grade). Groundwater was not encountered at the
investigation locations in this section.
Sta. 1004+840 to Sta. 1004+900: The alignment is scratch grade. The section includes shallow fills of
less than 2 m and ditch cuts of up to 1 m. TP18-LX-041 encountered sand and gravel to 1.4 m depth, over
silt to the bottom of the test pit at 4.9 m depth. Groundwater was not encountered.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 4
Sta. 1004+900 to Sta. 1005+460: The alignment is on an embankment up to 9 m high. Subsurface
conditions generally consisted of a mixture of silt and clay, interbedded with sand and gravel, over shale
bedrock. Bedrock was encountered between 3.1 and 7.6 m below ground surface. Groundwater was
inferred in CPT19-LX-202 and 204 at 2.4 and 2.7 m depths, respectively.
Culverts are located and Sta. 1005+075 and 1005+285. The culvert at Sta. 1005+075 is corrugated steel
pipe, has a diameter of 1.2 m, a length of 42.5 m, a gradient of 2.7% and a skew of 90°. The culvert at
Station 1005+285 is corrugated steel pipe, has a diameter of 1.2 m, a length of 57.0 m, a gradient of 0.8%
and a skew of 90°.
Sta. 1005+460 to Sta. 1005+500: The alignment crosses a drainage channel and is located near the
distal edge of an alluvial fan. The drainage channel is crossed by a culvert at Sta. 1005+487. The culvert is
corrugated steel pipe, has a diameter of 2.0 m, a length of 54.5 m, a gradient of 5.9%, a skew of 122° and
headwalls at the inlet and outlet. Riprap check dams are proposed upstream of the inlet and a riprap
armored drainage channel is proposed downstream of the outlet. Ground conditions below the culvert
generally consisted of interbedded layers of silt and sand, and clay and silt.
General subsurface conditions along the highway section consisted of a mixture of silt and clay over shale
bedrock. Based on CPTu data, bedrock is inferred at approximately 12 m below ground surface.
Groundwater was encountered at 9.4 m depth in TH19-LX-207 and inferred at 6.1 m depth in
CPT19-LX-206.
Sta. 1005+500 to Sta. 1005+690: The alignment has a cut up to 10 m deep into the edge of an alluvial
fan. Subsurface conditions consisted of a mixture of silt and clay interbedded with sand and gravel, over
shale bedrock. Bedrock was encountered between 12.3 and 18.7 m below ground surface but is not
anticipated in the cut slope. Groundwater was encountered at 9.1 m depth in TH19-LX-210 and inferred at
6.1 m depth in CPT19-LX-211.
Sta. 1005+690 to Sta. 1005+910: The alignment is on an embankment up to 13 m high. Subsurface
conditions generally consisted of clay up to 13.7 m depth, over shale bedrock. Bedrock was encountered
between 7.8 and 14.6 m below ground surface. Groundwater was encountered at 3.7 m depth in
TP18-LX-044 and inferred at 8.5 m depth in CPT19-LX-215.
A culvert is located at Sta. 1005+820. The culvert is corrugated steel pipe, has a diameter of 1.6 m, a
length of 37.5 m, a gradient of 2.1%, a skew of 90° and a headwall at the inlet. Ground conditions below
the headwall generally consisted of clay and silt, ground conditions below the culvert will transition to
embankment fill that becomes increasing thicker (up to 3 m) towards the outlet.
Sta. 1005+910 to Sta. 1005+970: The alignment has a cut up to 7 m deep into the edge of an alluvial
fan. Subsurface conditions consisted of a mixture of silt and clay, over sand, over bedrock. Bedrock was
encountered between 12.8 and 23.3 m below ground surface and is not anticipated in the cut slope.
Groundwater was not encountered at the investigation locations in this section.
Sta. 1005+970 to Sta. 1006+200: The alignment is on an embankment up to 15 m high. Waste soil is
proposed to be placed adjacent to the LHS embankment slope up to elevation 465 m. Subsurface
conditions generally consisted of clay or gravel over shale bedrock. Bedrock was encountered between 2.4
and 3.8 m below ground surface. Groundwater was encountered at 1.5 m depth in TH18-LX-029 and
inferred at 5.6 m depth in CPT19-LX-219.
A culvert is located at Sta. 1006+180. The culvert is corrugated steel pipe, has a diameter of 1.2 m, a
length of 41.0 m, a gradient of 1.5% and a skew of 90°. The culvert invert will be located approximately
5 m below highway surface (465 m elevation), and between 4 and 5 m above current ground surface.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 5
Sta. 1006+200 to Sta. 1006+400: The alignment is on an embankment up to 15 m high and crosses over
the existing highway. Subsurface conditions generally consisted of clay, over sand and gravel, over
bedrock. Clay was up to 8.5 m thick and bedrock was encountered at 9.5 m depth. Groundwater was not
encountered at the investigation locations in this section.
Sta. 1006+400 to Sta. 1006+780: The alignment is on an embankment 15 m high on the left side of
highway and 25 m high on the right side of the highway. Waste soil is proposed to be placed up to
approximately 465 m elevation. The toe of RHS embankment slope is on the in-river Early Works platform
which is the granular fill placed in the Peace River prior to construction of the balance of the Lynx Creek
East highway segment. Subsurface conditions left of and below the existing highway generally consisted
of silt and clay over shale bedrock, in some areas layers of gravel and silt were encountered. Subsurface
conditions right of the highway generally consisted of sand and gravel with varying silt content, over shale
bedrock. It is anticipated that the existing highway and RHS slope beside the existing highway may be
underlain by fill of variable composition and density. An existing slide is located on the RHS slope below
the highway between Sta. 1006+380 to Sta. 1006+460. Groundwater was inferred at 10.5 m depth in
CPT19-LX-222, and 4.1 m depth in CPT19-LX-227.
Between approximately Sta. 1006+200 and Sta. 1006+670 the LHS of the embankment is located on the
distal edge of three separate but coalesced/overlapping alluvial fans. Culverts are located at Sta.
1006+450, 1006+500 and 1006+658.
The culvert at Sta. 1006+450 is corrugated steel pipe, has a diameter of 1.2 m, a length of 43.0 m, a
gradient of 2.5% and a skew of 90°. The culvert invert will be located approximately 5 m below highway
surface (at 465 m elevation) and between 7 and 15 m above current ground surface.
The culvert at Sta. 1006+500 is corrugated steel pipe, has a diameter of 2.7 m, a length of 42.0 m, a
gradient of 2.0%, a skew of 90° and headwalls at the inlet and outlet. The culvert invert will be located
approximately 7 m below highway surface (at 465 m elevation) and between 8 and 20 m above current
ground surface. Riprap check dams are proposed upstream of the inlet.
The culvert at Sta. 1006+658 is corrugated steel pipe, has a diameter of 0.9 m, a length of 36.0 m, a
gradient of 2.4% and a skew of 90°. The culvert invert will be located approximately 4 m below highway
surface (at 465 m elevation) and between 10 and 20 m above current ground surface.
Sta. 1006+780 to Sta. 1006+860: The alignment is on an embankment 8 m high on the left side of
highway and 25 m high on the right side of highway. Waste soil is proposed to be placed up to
approximately 465 m elevation between the LHS embankment slope and the natural ground surface to
the north. The toe of the RHS embankment slope is on the in-river platform. Subsurface conditions below
the existing highway generally consisted of highway fill, over clay and silt, over gravel, over shale bedrock.
Highway fill is likely variable in composition and density, with zones of potentially loose fill. Subsurface
conditions right of the highway generally consisted of sand and gravel interbedded with silt and clay, over
bedrock. Fill may have been side cast over the RHS of the highway. A historic highway fill slope failure (i.e.
slide) is located between 1006+780 and 1006+930. The slide was remediated, likely in 1979-1980;
however the current condition of the remediation works and the current stability of the slide is unknown.
Groundwater was not encountered at the investigation locations in this section, but groundwater is likely
at a depth comparable to the elevation of the Peace River.
Sta. 1006+860 to Sta. 1007+030: The alignment begins to merge back into the existing highway. The
left side embankment slope becomes progressively shorter. Between Sta. 1006+860 and 1006+900 waste
soil is proposed to be placed up to approximately 465 m elevation between the LHS embankment slope
and the natural ground surface to the north. The right side embankment slope is 25 m high with the toe
of the slope on the in-river platform. Subsurface conditions generally consisted of highway fill, over silt
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 6
and clay interbedded with sand and gravel, over shale bedrock. The highway fill is likely variable in
composition and density, with zones of potentially loose fill. A relatively recent existing slide is located on
the RHS between approximately Sta. 1006+900 and Sta. 1007+030. The slide could not be accessed
during the site investigation, it is anticipated that the slide is in colluvium and/or side cast fill or waste soil.
Groundwater was not encountered at the investigation locations in this section, but groundwater is likely
at a depth comparable to the elevation of the Peace River.
A culvert is located at Sta. 1006+900. The culvert is corrugated steel pipe, has a diameter of 0.9 m, a
length of 31.5 m, a gradient of 1.8% and a skew of 90°. The culvert invert will be located approximately
3 m below the highway surface (at 465 m elevation) and between 1 and 13 m above current ground
surface.
Sta. 1007+030 to Sta. 1007+070: The alignment crosses a relatively well known debris flow and flood
site. The alignment is on an embankment 2 m high on the left side of highway and 28 m high on the right
side of highway. The toe of the RHS embankment slope is on the in-river platform. Subsurface conditions
generally consisted of layers of silty sand, sand, sand and gravel, over shale bedrock. A test pit located in
the debris flow deposit at the toe of the slope encountered sand and gravel; however, it is anticipated that
the deposit will be variable. The existing RHS slope below the highway is likely covered by poorly
compacted end-dumped fill, over colluvium. Groundwater was not encountered at the investigation
locations in this section, but groundwater is likely at a depth comparable to the elevation of the Peace
River.
Left and upslope of the alignment is a large erosional basin, colloquially referred to by various BCMoTI
geotechnical practitioners as the ‘amphitheater’. Periodic precipitation events and diverted road drainage
from Farrell Creek Road (located above the amphitheater) can result in debris flow and flood events that
reach and cross the existing highway at the current culvert location. The new culvert, located at Sta.
1007+055 is corrugated steel pipe, has a diameter of 2.4 m, a length of 33.5 m, a gradient of 9.5% and a
skew of 98°. Head walls are located at the culvert inlet and outlet. The culvert invert will be located
approximately 3 m below highway surface. The inlet headwall and upper 2/3 of the culvert will likely be
founded on granular colluvium and the lower 1/3 and outlet headwall will be founded on embankment fill
up to 3 m thick. Riprap check dams are proposed upstream of the inlet.
Sta. 1007+070 to Sta. 1007+280: The alignment merges back into the existing highway. The left side
embankment slope is a nominal height and the right side embankment slope is 28 m high with the toe of
the slope on the in-river platform. Subsurface conditions generally consisted of silty sand interbedded
with clay, over shale bedrock. The existing RHS slope below the highway is likely covered by poorly
compacted end-dumped fill or waste soil, over colluvium. Groundwater was not encountered at the
investigation locations in this section, but groundwater is likely at a depth comparable to the elevation of
the Peace River. A relatively recent existing slide is located on the RHS between approximately Sta.
1007+140 and 1007+230.
Beyond the eastern limit of the Lynx Creek East segment (Sta. 1007+280) an in-stream reservoir shoreline
stability berm is located along the toe of a steep erosional slope which forms the north bank of the Peace
River. The in-stream reservoir shoreline stability berm is designated the L2 alignment. The western limit of
the L2 alignment (Sta. 2+380) coincides approximately with Sta. 1007+130 of the L1000 alignment. The in-
stream stability berm is located below a relatively recent existing slide located between approximately Sta.
2+390 and 2+490 (Sta. 1007+140 and 1007+230, noted above). The instream stability berm is also located
below existing slope instability features between approximately Sta. 2+610 and 2+800. East of Sta. 2+800
the in-stream stability berm is located below a steep gradient and eroded slope.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 7
Acid Rock Drainage and Metal Leaching Potential
Planned earthworks for the highway alignment may encounter shale bedrock in a cut slope between Sta.
1004+300 and 1004+380, elsewhere bedrock is not anticipated to be encountered.
Acid Rock Drainage (ARD) and Metal Leaching (ML) testing has not been carried out on bedrock samples
collected within the Lynx Creek East project area. ARD and ML testing on primarily sandstone bedrock
samples collected west of the project area were classified according to BCMoTI Technical Circular T-04/13
as non-acid generating with low potential to produce ARD; however, testing on shale samples east of the
project area were classified as potentially acid generating (PAG). The boundary between the PAG bedrock
to the east and the non-acid generating bedrock to the west is unknown. It is therefore recommended
that, unless proven otherwise, all bedrock encountered during construction be considered PAG. Excavated
bedrock should be disposed of in an environmentally appropriate manner and should any surface
exposures of bedrock remain after excavation, the exposures should be appropriately treated with a cover
(e.g. backfill) as needed.
Existing Highway 29 Asphalt Thicknesses
An asphalt drilling program was carried out along the existing pavement surface of Highway 29. The
program consisted of 12 boreholes spaced at approximately 180 m. The boreholes are designated with
the prefix PV. Near the east end of the project, asphalt thickness was determined as part of deeper site
investigation boreholes that are designated with the prefix TH. The locations of the holes are shown on
Figure 2. The encountered thickness of asphalt is provided in Table 6-1.
Table 6-1: Encountered Asphalt Thickness
Hole Identification Asphalt Thickness (m)
PV18-LX-025 0.15
PV18-LX-026 0.17
PV18-LX-027 0.12
PV18-LX-028 0.11
PV18-LX-029 0.17
PV18-LX-030 0.18
PV18-LX-031 0.12
PV18-LX-032 0.26
PV18-LX-033 0.081
PV18-LX-034 0.231
PV18-LX-035 0.101
PV18-LX-036 0.141
PV18-LX-037 0.141
TH18-LX-037 0.101
TH18-LX-039 0.101
TH18-LX-041 0.101
TH18-LX-044 0.101 Note: 1 Asphalt layer would be covered by the new highway embankment.
New highway embankments are located above the existing highway pavement surface between
approximately Sta. 1006+040 and the east end of the segment (Sta. 1007+280). If the new embankment is
constructed over the asphalt surface, the relatively smooth asphalt surface can become a potentially weak
layer and reduce the stability of the embankment. Where the relatively impermeable asphalt layer is
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 8
located below the MNRL, the layer can also disrupt internal drainage of the embankment during a
reservoir rapid drawdown event. For those reasons, it is recommended that the asphalt surface be
removed below the footprint of new embankments and that the underlying gravel surface be scarified
prior to construction of the new embankment. Note that the slope stability assessments described in
Section 7.3 assume the asphalt layer is removed and the underlying gravel surface scarified and, therefore,
the corresponding recommended fill slope angles also assume the asphalt layer is removed and underling
gravel surface scarified.
At the tie-in between the new alignment and existing highway at the east end of the project (Sta.
1007+280) the existing asphalt thickness is unknown. For design purposes it is recommended to assume
an existing asphalt thickness of 0.10 m.
Slope Stability
To assess the stability of the proposed cut and fill slopes, slope stability analyses were carried out using
the Slope/W computer program included in the GeoStudio 2016 package by GEO-SLOPE International
Ltd. (GEO-SLOPE, 2016). The analyses were carried out using limit equilibrium methods.
Design Criteria
The design criteria used for the slope stability assessment is described in the document ‘BC Hydro Site C –
Highway 29 Relocation, Geotechnical Design Criteria (Version 2.8)’, dated 20 February 2020. Based on that
document, the slope stability assessment used the target factors of safety noted Table 7-1, which consider
a typical understanding and typical consequence of failure.
Table 7-1: Target Factors of Safety for Slope Stability Assessment
Scenario Limit State Target Factor of
Safety
Maximum Normal Reservoir Level (elev. 461.8 m) Global Stability – Permanent 1.54
Emergency Reservoir Drawdown Event Global Stability - Temporary 1.24
The maximum normal reservoir level and emergency reservoir drawdown event scenarios were analyzed
using effective stress conditions, and as described in the design criteria document.
Temporary stability during construction of cut and fill slopes was analyzed using total stress strength
parameters (i.e. undrained shear strength) for cohesive soils For cases where the total stress analyses
resulted in a factor of safety less than 1.24, instrumented staged construction can be implemented to
monitor and control groundwater pressure generation during construction in order to maintain required
stability.
Slope Stability Models
Slope stability models were developed based on the subsurface information noted in the geotechnical
data reports (Wood, 2019c and Wood, 2020) and the proposed geometry for the L1000-Line. Note that
slope stability models are a simplification of actual ground conditions. Slope stability models were
developed at the locations noted in Table 7-2.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 9
Table 7-2: Location of Slope Stability Models
Location Description
Sta. 1004+440 Embankment Fill, 5 m high LHS & RHS
Sta. 1005+260 Embankment Fill, 5 m high LHS, 9 m high RHS
Sta. 1005+600 Cut Slope, 8 m deep LHS
Sta. 1005+820 Embankment Fill, 4 m high LHS, 13 m high RHS
Sta. 1005+940 Cut Slope, 5 m deep LHS
Sta. 1006+200 Embankment Fill, 8 m high LHS, 14 m high RHS
Sta. 1006+520 Embankment Fill, 13 m high LHS, 26 m high RHS
Sta. 1007+000 Embankment Fill, 2 m high LHS, 28 m high RHS
Sta. 1007+060 Embankment Fill, 2 m high LHS, 28 m high RHS
Slope stability models relating to the in-stream stability berm, located beyond the eastern limit of the
Lynx Creek East segment, can be found in the Farrell Creek Road Slide and In-Stream Reservoir Shoreline
Stability Berm memo, dated 17 December 2019 (Wood, 2019b). The in-stream stability berm is proposed
along a steep erosion slope along the Peace River below a section of the existing Highway 29 alignment
which is to remain in place upon reservoir filling. The memo describes slope stability analyses carried out
at Sta. 1007+316 and 1007+490.
7.2.1 Material Parameters
Material parameters were determined based on several sources of information including observations
made during drilling, CPTu data, laboratory testing, and correlations between soil index properties and
soil strengths presented in published literature. It is anticipated that stability of the cut and fill slopes will
be largely dependent on the relatively low shear strength of underlying cohesive soil layers (e.g. clay and
silt).
Effective Stress Strength Parameters for Cohesive Soil
Based on Wood’s experience in the Peace Region, fissures can be present within cohesive soil indicating
that regions within the soil mass could be at a state of residual effective strength. For the purpose of the
effective stress stability analyses cohesive soil is assumed to be at a residual strength with no cohesion.
The residual effective strength of the cohesive soil was estimated using an empirical correlation relating
the Atterberg liquid limit, clay size fraction (particles smaller than 0.002 mm) and effective normal stress to
the residual friction angle (Stark and Eid, 1994). The residual shear strength values obtained from the
correlation are for an assumed effective normal stress of 100 kPa.
The Atterberg liquid limit and clay size fractions were obtained from the geotechnical data report (Wood,
2019c and Wood, 2020) and grouped by station segment, as noted in Section 4.0. A summary of the
parameters input into the Stark and Eid correlation and the corresponding residual friction angle for the
model locations noted in Table 7-2 is included in Table 7-3, below.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 10
Table 7-3: Parameters used to Estimate Effective Stress Residual Friction Angle for Cohesive Soils
Location Unit Name
Liquid
Limit
(%)
Clay
Fraction
(%)
Effective
Normal
Stress
(kPa)
Residual
Effective
Friction
Angle
(Degrees)
Sta. 1004+440 Clay (CL) 47 53 100 18
Sta. 1005+260 Clay (CL) 50 50 100 18
Sta. 1005+600 Clay (CL) 41 24 100 23
Sta. 1005+820 Clay (CL) 44 41 100 22
Sta. 1005+940 Clay (CL) 43 40 100 22
Sta. 1006+200 Clay (CL) 44 39 100 22
Sta. 1006+520 Clay (CL) 55 57 100 17
Sta. 1007+000 Clay/Colluvium (CL) 38 19 100 28
Sta. 1007+060 Clay/Colluvium (CL) 38 10 100 28
Total Stress Strength Parameters for Cohesive Soil
During construction of the embankments the underlying cohesive soils will develop positive pore
pressures during consolidation, reducing the effective stress within the soil (Φ’ = 0), and stability becomes
a function of the immediate strength (undrained shear strength) of the cohesive soil. To gauge the
stability of an embankment during construction a total stress analysis was carried out at the locations
noted in Table 7-2.
The undrained shear strength of cohesive soils was estimated based on the CPT tip resistance using the
following equation (Lunne, et. al., 1997).
𝑆𝑢𝐶𝑃𝑇=
𝑞𝑡 − 𝜎𝑣𝑜
𝑁𝑘𝑡
Where:
𝑆𝑢𝐶𝑃𝑇 = undrained shear strength estimated from CPTu
𝑞𝑡 = cone tip resistance
𝜎𝑣𝑜 = total vertical stress of the corresponding depth of measurement of the 𝑞𝑡 value
𝑁𝑘𝑡 = an empirical factor typically between 10 and 20, an assumed 𝑁𝑘𝑡 of 15 was used for the analyses
Cohesive soil layers along the alignment were likely formed as over-bank flood plain deposits or colluvial
sediments derived from adjacent valley slopes. The deposits do not appear to have large-scale, spatially
continuous structure. To characterize the undrained shear strength of these deposits, representative CPT
profiles were reviewed and the undrained shear strength corresponding to the lowest quartile was used in
the analyses. The undrained shear strengths used in the stability analyses are summarized in Table 7-4.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 11
Table 7-4: Total Stress Strength Parameters for Cohesive Soils
Location Unit Name Representative CPT
Undrained Shear
Strength
25th Percentile
(kPa)
Sta. 1004+440 Clay (CL) CPT18-LX-007
CPT18-LX-008 77
Sta. 1005+260 Clay (CL)
(Upper and Lower)
CPT19-LX-202
CPT19-LX-204
CPT18-LX-011
77
Sta. 1005+600 Clay (CL) CPT19-LX-206
CPT19-LX-211 61
Sta. 1005+820 Clay (CL) CPT19-LX-214
CPT19-LX-215 72
Sta. 1005+940 Clay (CL) CPT19-LX-219 144
Sta. 1006+200 Clay (CL)
CPT19-LX-221
CPT19-LX-222
CPT19-LX-223
92
Sta. 1006+520 Clay (CL) CPT19-LX-227 58
Sta. 1007+000 Clay/Colluvium (CL) - 1001
Sta. 1007+060 Clay/Colluvium (CL) - 1001 Note: 1 Due to limited CPT data, an undrained shear strength of 100 kPa was assumed for the Clay/Colluvium.
Material Properties for Granular Soils and Bedrock
The material properties used for granular soil and bedrock are summarized in Table 7-5, below.
Table 7-5: Summary of Material Properties used in the Slope Stability Models
Unit Name Unit Weight
(kN/m3) Cohesion (kPa)
Effective Friction
Angle (Degrees)
Fill (Granular) 21 0 36
Road Fill (Granular) 21 0 28 – 36
Angular Rock Fill 24 0 40
Silty Sand (Loose to Compact) 20 0 29
Sand and Gravel (Loose to Compact) 20 0 31
Gravelly, Silty Sand (Compact) 20 0 30
Sand and Gravel (Dense) 21 0 35
Clay (CL) 19 See
Table 7-4
See
Table 7-3
Shale Bedrock 25 5901 44 1
Shale/Sandstone Bedrock 25 5601 49 1
Sandstone Bedrock 25 15301 60 1 Note: 1 Bedrock strength was estimated using a Mohr-Coulomb failure envelope that is equivalent to a Hoek-Brown failure
criterion using the Roclab computer program developed by Rocscience Inc. (Rocscience, 2007). Zero cohesion was used
+/- 10˚ from horizontal and +/- 20˚ from vertical.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 12
7.2.3 Groundwater Conditions
Groundwater conditions are based on drilling observations and CPTu data collected during the 2018 and
2019 investigations. The analyses were carried out using a Mean Normal Reservoir Level (MNRL) of
461.8 m elevation. During an emergency reservoir drawdown event the water level was assumed to be the
current normal water level of the Peace River or elevation 444 m, whichever is higher.
7.2.4 Geometry
The slope stability models were generated using a simplified geometry based on Binnie’s geometric
design. Areas of fill generally consisted of a 11 m wide embankment top with uniform fill slopes on either
side. Areas of cut generally consisted of a uniform cut slope extending up from a ditch invert located
300 mm below the underside of SGSB.
To achieve the target factors of safety noted in Table 7-1, cut and fill slopes were either steepened or
flattened during the stability analyses. Cut slopes were changed from the ditch invert, and fill slopes were
changed from the top edge of the embankment.
Optimization of cut and fill slopes was carried out by incrementally changing the cut and fill slopes until
the calculated factor of safety was at or slightly above the target factors of safety. Slope optimization was
carried out for the MNRL scenario.
Slope Stability Assessment
The results of the slope stability assessment are summarized in Table 7-6 to Table 7-20, below. Each
section contains a recommendation for maximum fill (or cut) slope angle for design purposes.
Slope stability models that include the in-stream Early Works platform (models at Sta. 1006+520,
1007+000 and 1007+060), are based on the assumption that the in-stream platform is constructed on
high shear strength material (e.g. bedrock or gravel and sand) and the platform itself has a relatively high
shear strength (effective friction angles of 36° and 38° were assumed in the analyses). The in-stream areas
below the platform have yet to be investigated. The in-stream areas and the condition of the platform will
be investigated after construction of the platform. The results from the above noted stability models,
specifically the RHS fill slope, are subject to confirmation following this investigation.
7.3.1 Sta. 1004+300 to Sta. 1004+660
Embankment Fill, 5 m high, left hand side (LHS) and right hand side (RHS).
Table 7-6: Sta. 1004+440, Results of Slope Optimization (Optimized Slopes Shown in Figure 6)
Location Scenario Target Factor of
Safety Fill Slope
Calculated Factor
of Safety
Sta. 1004+440 MNRL, LHS 1.54 3.25H:1.0V 1.63
Sta. 1004+440 MNRL, LHS 1.54 3.20H:1.0V 1.61
Sta. 1004+440 MNRL, LHS 1.54 3.10H:1.0V 1.58
Sta. 1004+440 MNRL, LHS 1.54 3.00H:1.0V 1.55
Sta. 1004+440 MNRL, LHS 1.54 2.95H:1.0V 1.53
Sta. 1004+440 MNRL, RHS 1.54 3.25H:1.0V 1.59
Sta. 1004+440 MNRL, RHS 1.54 3.20H:1.0V 1.58
Sta. 1004+440 MNRL, RHS 1.54 3.10H:1.0V 1.54
Sta. 1004+440 MNRL, RHS 1.54 3.05H:1.0V 1.53
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 13
Table 7-7: Sta. 1004+440, Results of Slope Stability Assessment (Figure 7)
Location Scenario
Target
Factor of
Safety
Fill Slope
Calculated
Factor of
Safety
Sta. 1004+440 Emergency Drawdown, LHS1 1.24 3.00H:1.0V 1.55
Sta. 1004+440 Emergency Drawdown, RHS1 1.24 3.10H:1.0V 1.54
Sta. 1004+440 Temporary Construction, LHS2 1.24 3.00H:1.0V 2.24
Sta. 1004+440 Temporary Construction, RHS2 1.24 3.10H:1.0V 2.34 Note: 1 Assumed piezometric surface above MNRL
2 Total stress analysis
Recommendation: LHS maximum fill slope 3.0H:1.0V, RHS maximum fill slope 3.1H:1.0V.
7.3.2 Sta. 1004+900 to Sta. 1005+460
Embankment Fill, 5 m high LHS, 9 m high RHS.
Table 7-8: Sta. 1005+260, Results of Slope Optimization (Optimized Slopes Shown in Figure 8)
Location Scenario Target Factor of
Safety Fills Slope
Calculated Factor
of Safety
Sta. 1005+260 MNRL, LHS 1.54 4.25H:1.0V 1.61
Sta. 1005+260 MNRL, LHS 1.54 4.00H:1.0V 1.55
Sta. 1005+260 MNRL, LHS 1.54 3.95H:1.0V 1.54
Sta. 1005+260 MNRL, LHS 1.54 3.90H:1.0V 1.53
Sta. 1005+260 MNRL, RHS 1.54 4.25H:1.0V 1.55
Sta. 1005+260 MNRL, RHS 1.54 4.20H:1.0V 1.54
Sta. 1005+260 MNRL, RHS 1.54 4.15H:1.0V 1.53
Table 7-9: Sta. 1005+260, Results of Slope Stability Assessment (Figures 9 and 10)
Location Scenario
Target
Factor of
Safety
Fill Slope
Calculated
Factor of
Safety
Sta. 1005+260 Emergency Drawdown, LHS 1.24 3.95H:1.0V 1.54
Sta. 1005+260 Emergency Drawdown, RHS 1.24 4.20H:1.0V 1.62
Sta. 1005+260 Temporary Construction, LHS1 1.24 3.95H:1.0V 3.19
Sta. 1005+260 Temporary Construction, RHS1 1.24 4.20H:1.0V 3.26 Note: 1 Total Stress Analysis
Recommendation: LHS maximum fill slope 3.95H:1.0V, RHS maximum fill slope 4.20H:1.0V.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 14
7.3.3 Sta. 1005+500 to Sta. 1005+690
Cut Slope, 8 m deep LHS.
Table 7-10: Sta. 1005+600, Results of Slope Optimization (Optimized Slope Shown in Figure 11)
Table 7-11: Sta. 1005+600, Results of Slope Stability Assessment (Figure 11)
Location Scenario Target Factor of
Safety Cut Slope
Calculated
Factor of Safety
Sta. 1005+600 Emergency
Drawdown, LHS1 1.24 3.10H:1.0V 1.54
Sta. 1005+600
Temporary
Construction,
LHS2
1.24 3.10H:1.0V 2.38
Note: 1 Assumed piezometric surface above MNRL 2 Total stress analysis
Recommendation: LHS maximum cut slope 3.10H:1.0V.
7.3.4 Sta. 1005+690 to Sta. 1005+910
Embankment Fill, 4 m high LHS, 13 m high RHS.
Table 7-12: Sta. 1005+820, Results of Slope Optimization (Optimized Slopes Shown in Figure 12)
Location Scenario Target Factor of
Safety Fill Slope
Calculated Factor
of Safety
Sta. 1005+820 MNRL, LHS 1.54 2.00H:1.0V1 1.83
Sta. 1005+820 MNRL, LHS 1.54 1.90H:1.0V 1.80
Sta. 1005+820 MNRL, LHS 1.54 1.80H:1.0V 1.75
Sta. 1005+820 MNRL, LHS 1.54 1.70H:1.0V 1.71
Sta. 1005+820 MNRL, LHS 1.54 1.50H:1.0V 1.61
Sta. 1005+820 MNRL, LHS 1.54 1.40H:1.0V 1.56
Sta. 1005+820 MNRL, LHS 1.54 1.35H:1.0V1 1.54
Sta. 1005+820 MNRL, LHS 1.54 1.30H:1.0V 1.51
Sta. 1005+820 MNRL, RHS 1.54 4.25H:1.0V 1.62
Sta. 1005+820 MNRL, RHS 1.54 4.15H:1.0V 1.59
Sta. 1005+820 MNRL, RHS 1.54 4.05H:1.0V 1.56
Sta. 1005+820 MNRL, RHS 1.54 4.00H:1.0V 1.54
Sta. 1005+820 MNRL, RHS 1.54 3.95H:1.0V 1.53 Note: 1 To maintain a FoS of 1.54 against shallow instability recommend using a maximum 2.00H:1.0V slope
Location Scenario Target Factor of
Safety Cut Slope
Calculated Factor
of Safety
Sta. 1005+600 MNRL, LHS 1.54 3.25H:1.0V 1.57
Sta. 1005+600 MNRL, LHS 1.54 3.20H:1.0V 1.56
Sta. 1005+600 MNRL, LHS 1.54 3.10H:1.0V 1.54
Sta. 1005+600 MNRL, LHS 1.54 3.00H:1.0V 1.50
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 15
Table 7-13: Sta. 1005+820, Results of Slope Stability Assessment (Figures 13 and 14)
Location Scenario
Target
Factor of
Safety
Fill Slope
Calculated
Factor of
Safety
Sta. 1005+820 Emergency Drawdown, LHS 1.24 1.35H:1.0V 1.83
Sta. 1005+820 Emergency Drawdown, RHS 1.24 1.35H:1.0V 1.37
Sta. 1005+820 Temporary Construction, LHS1 1.24 4.00H:1.0V 3.98
Sta. 1005+820 Temporary Construction, RHS1 1.24 4.00H:1.0V 2.46 Note: 1 Total stress analysis
Recommendation: LHS maximum fill slope 2.00H:1.0V, RHS maximum fill slope 4.00H:1.0V.
7.3.5 Sta. 1005+910 to Sta. 1005+970
Cut Slope, 5 m deep LHS.
Table 7-14: Sta. 1005+940, Results of Slope Stability Assessment (Figure 15 and 16)
Location Scenario
Target
Factor of
Safety
Cut Slope
Calculated
Factor of
Safety
Sta. 1005+940 Existing Conditions - Natural Slope 1.173
Sta. 1005+940 MNRL, LHS 1.54 2.0H:1.0V 0.943
Sta. 1005+940 MNRL, LHS 1.54 3.0H:1.0V 1.243
Sta. 1005+940 MNRL with Shear Key, LHS 1.54 2.5H:1.0V with Shear
Key
1.55 (below shear key)
1.54 (through shear key)
Sta. 1005+940 Emergency Drawdown with
Shear key, LHS1 1.24
2.5H:1.0V with Shear
Key
1.55 (below shear key)
1.54 (through shear key)
Sta. 1005+820 Temporary Construction,
LHS2 1.24
1.0H:1.0V temporary
cut slope 2.12
Note: 1 Assumed piezometric surface above MNRL
2 Total stress analysis
3 Model not shown on figures
Cut slopes flatter than 3.0H:1.0V unlikely feasible due to upslope ground geometry, replacement of toe of
excavation slope with stronger granular or rock shear key material is more effective.
Recommendation: 2.5H:1.0V slope with shear key as shown in Figure 5.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 16
7.3.6 Sta. 1006+120 to Sta. 1006+200
Embankment Fill, 8 m high LHS, 14 m high RHS.
Table 7-15: Sta. 1006+200, Results of Slope Optimization (Optimized Slopes Shown in Figure 17)
Location Scenario Target Factor of
Safety Fill Slope
Calculated Factor
of Safety
Sta. 1006+200 MNRL, LHS 1.54 2.75H:1.0V 1.55
Sta. 1006+200 MNRL, LHS 1.54 2.70H:1.0V 1.53
Sta. 1006+200 MNRL, RHS 1.54 3.25H:1.0V 1.54
Sta. 1006+200 MNRL, RHS 1.54 3.20H:1.0V 1.52
Table 7-16: Sta. 1006+200, Results of Slope Stability Assessment (Figures 18 and 19)
Location Scenario Target Factor of
Safety Fill Slope
Calculated
Factor of
Safety
Sta. 1006+200 Emergency Drawdown, LHS 1.24 2.75H:1.0V 1.71
Sta. 1006+200 Emergency Drawdown, RHS 1.24 3.25H:1.0V 1.53
Sta. 1006+200 Temporary Construction, LHS2 1.24 2.75H:1.0V 2.17
Sta. 1006+200 Temporary Construction, RHS2 1.24 3.25H:1.0V 2.51
Recommendation: maximum fill slope LHS 2.75H:1.0V, maximum fill slope RHS 3.25H:1.0V. LHS fill slope
can be steeper if waste soil is placed at toe of slope.
7.3.7 Sta. 1006+200 to Sta. 1006+780
Embankment Fill, 13 m high LHS, 26 m high RHS on in-river platform. Waste soil placed along LHS slope
up to elevation 465 m.
Table 7-17: Sta. 1006+520, Results of Slope Optimization LHS (Optimized Slope Shown in Figure 20)
Location Scenario Target Factor of
Safety Fill Slope
Calculated Factor
of Safety
Sta. 1006+520 MNRL, LHS 1.54 2.00H:1.0V 2.631,2
Sta. 1006+520 MNRL, LHS 1.54 1.50H:1.0V 2.241
Sta. 1006+520 MNRL, LHS 1.54 1.00H:1.0V 1.831 Notes: 1 Assumes fill (waste) placed against toe of LHS slope up to 465 m elevation
2 To maintain a FoS of 1.54 against shallow instability recommend using a maximum 2.00H:1.0V slope
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 17
Table 7-18: Sta. 1006+520, Results of Slope Stability Assessment (Figures 20 through 22)
Location Scenario
Target
Factor of
Safety
Fill Slope
Calculated
Factor of
Safety
Sta. 1006+520 MNRL, RHS 1.54 2.5H:1.0V 1.691
Sta. 1006+520 Emergency Drawdown, LHS 1.24 2.00H:1.0V 2.642
Sta. 1006+520 Emergency Drawdown, RHS 1.24 2.5H:1.0V 1.881
Sta. 1006+520 Temporary Construction, LHS3 1.24 2.00H:1.0V 1.33
Sta. 1006+520 Temporary Construction, RHS3 1.24 3.25H:1.0V 1.60 Notes: 1 RHS fill slope and factor of safety to be confirmed after in-river platform built and additional investigation carried out
2 Assumes fill (waste) placed against toe of LHS slope up to 465 m elevation 3 Total stress analysis
Recommendation: maximum fill slope LHS 2.0H:1.0V, RHS fill slope to be confirmed after additional
investigation carried out.
7.3.8 Sta. 1006+860 to Sta. 1007+030
Embankment Fill, 2 m high LHS, 28 m high RHS.
Table 7-19: Sta. 1007+000, Results of Slope Stability Assessment (Figures 23 and 24)
Location Scenario Target Factor
of Safety Fill Slope
Calculated
Factor of
Safety
Sta. 1007+000 MNRL, RHS 1.54 2.5H:1.0V1 1.561
Sta. 1007+000 Emergency Drawdown, RHS 1.24 2.5H:1.0V1 1.711
Sta. 1007+000 Temporary Construction, RHS2 1.24 2.5H:1.0V1 1.872 Note: 1 RHS fill slope and factor of safety to be confirmed after in-river platform built and additional investigation carried out
2 Total stress analysis
Recommendation: RHS fill slope to be confirmed after additional investigation carried out.
7.3.9 Sta. 1007+030 to Sta. 1007+070
Embankment Fill, 2 m high LHS, 28 m high RHS
Table 7-20: Sta. 1007+060, Results of Slope Stability Assessment (Figures 25 and 26)
Location Scenario Target Factor of
Safety Fill Slope
Calculated
Factor of
Safety
Sta. 1007+060 MNRL, RHS 1.54 2.5H:1.0V1 1.591
Sta. 1007+060 Emergency Drawdown, RHS 1.24 2.5H:1.0V1 1.581
Sta. 1007+060 Temporary Construction, RHS2 1.24 2.5H:1.0V1 1.562 Note: 1 RHS fill slope and factor of safety to be confirmed after in-river platform built and additional investigation carried out
2 Total stress analysis
Recommendation: RHS fill slope to be confirmed after additional investigation carried out.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 18
Impact of Long-Term Reservoir Erosion
In general, the Lynx Creek East segment is constructed on new embankment fill that will be protected
from long-term reservoir erosion through the use of riprap placed at or near the fill toe on the reservoir
side of the embankment. However, based on Binnie’s geometric plans there are three areas were reservoir
erosion was unmitigated and long-term reservoir erosion, as illustrated by BGC’s 2012 Erosion Impact
Lines (EIL), is anticipated to directly or indirectly threaten the global stability of the new highway
alignment.
The current geotechnical design criteria requires slope stability analyses to consider the effects of long-
term reservoir erosion (i.e. the new highway grade is shown to remain stable after 100 years of reservoir
erosion has occurred). For the purpose of the stability assessment it was assumed that from the reservoir
shoreline to the EIL the ground surface will be eroded down to approximately MNRL (481.6 m elevation).
In some locations, even if the long-term erosion (represented by the EIL) does not directly intercept the
new road grade, the erosion if unmitigated would result in loss of the existing ground adjacent to the new
highway alignment such that the global stability criteria is not maintained. The areas where long-term
reservoir erosion is anticipated to compromise stability of the highway alignment are described below.
West of Sta. 1005+100
The unmitigated EIL intersects the new highway alignment at a skew near Sta. 1005+100. The road grade
in this area is at about 471 m elevation and is in small cuts and fills. At the EIL an erosional slope
approximately 9 m high could develop which would compromise the stability of the roadway prism.
Nearby boreholes indicate the area is predominantly underlain by silt and clay; however, layers of sand
and gravel are also present. Slope stability analyses indicate that erosion up to the EIL is unlikely to impact
the new highway alignment west of approximately Sta. 1004+580; however, east of Sta. 1004+580 erosion
protection will be required to prevent the loss of ground that would compromise stability.
Recommendations for erosion mitigation include two options:
1) Excavate riprap into the ground along the reservoir side of road grade between approximately
Sta. 1004+580 and 1005+100. Note that the required excavation could be between 4 and 9 m
deep and the riprap would need to protect a 5H:1V slope geometry to maintain stability of the
road. Excavation and riprap placement would likely need to be carried out prior to construction of
the roadway prism, and the riprap may need to be buried depending on future land use. It is
considered that the volume of excavation for this option would be onerous.
2) Place riprap on the current ground surface close to the reservoir shoreline. To provide adequate
protection east of Sta. 1004+580 the riprap should protect the shoreline of the fan shaped
landform projecting out into the reservoir between Sta. 1004+580 and 1005+100. The
corresponding amount of earthworks should be greatly reduced in comparison to option 1.
Between Sta. 1005+400 and 1005+800
The unmitigated EIL is located on the far left (northwest) side of the new highway alignment. The road
grade in this area is at about 470 m elevation and is in small cuts and fills. If unmitigated an erosion slope
approximately 8 m high could develop which would compromise the global stability of the new highway
grade. Nearby boreholes indicate the area is underlain predominantly by silt and clay. Recommendations
for erosion mitigation include two options:
1) Excavate riprap into the ground near the toe of the embankment. The required excavation could
be between 4 and 8 m deep and the riprap would need to protect a 5H:1V slope geometry to
maintain stability of the road. Excavation and riprap placement would likely need to be carried out
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 19
prior to construction of the roadway prism, and the riprap may need to be buried depending on
future land use. It is considered that the volume of excavation for this option would be onerous.
2) Place riprap on the current ground surface close to the reservoir shoreline. The corresponding
amount of earthworks should be greatly reduced in comparison to option 1.
Between Sta. 1005+860 and 1006+000
The unmitigated EIL is located on the far left (northwest) side of the new highway alignment. The new
highway is in a small fill. The reservoir shoreline intersects the natural slope below the fill slope. Erosion of
the natural slope would undermine the fill slope. It is recommended that erosion mitigation is to extend
riprap down the natural slope.
Settlement Analyses
Settlement analyses were carried out for fills corresponding with culvert locations. Culvert locations,
culvert diameters, culvert lengths, approximate maximum embankment height and approximate
maximum depth to culvert invert from top of embankment are summarized in Table 9-1, below.
Table 9-1: Culvert Locations and Descriptions
Location Diameter (m) Length (m) Embankment
Height (m)
Depth to Culvert
Invert (m)
Sta. 1004+430 0.9 61.5 5 5
Sta. 1004+812 2.4 27.5 3 3
Sta. 1005+075 1.2 42.5 4 4
Sta. 1005+285 1.2 57.0 8 5
Sta. 1005+487 0.2 54.0 4 4
Sta. 1005+820 1.6 37.5 5 4
Sta. 1006+180 1.2 41.0 10 5
Sta. 1006+450 1.2 43.0 15 5
Sta. 1006+500 2.7 42.0 15 7
Sta. 1006+658 0.9 36.0 24 4
Sta. 1006+900 0.9 31.5 8 3
Sta. 1007+055 2.4 33.5 5 5
Settlement analyses considered:
1) Stress history of the soil;
2) Soil compressibility Parameters; and
3) Stress distribution below the embankment.
Settlement was calculated for granular soil layers using the stress-strain modulus method and for
cohesive soil layers using the consolidation method.
Soil Stress History
The valley bottom sediments below the new highway alignment likely consist of younger, post-glacial,
granular fluvial channel, terrace deposits, fine-grained (silt/clay) over-bank flood plain deposits, and
colluvial sediments derived from adjacent valley slopes. As determined by the CPT, the stress history of
these deposits is variable with measured over consolidation ratios (OCR) between 1 and greater than 10.
These deposits are interpreted to have been deposited after the last glacial advance and have therefore
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 20
not experienced loading from glacial ice. The observed pre-consolidation could be the result of
fluctuations of the water table, erosion of sediments, and ice and snow loads. Pre-consolidation can also
be produced by desiccation, freezing and thawing, and chemical changes caused by oxidation.
Based on the variability of the OCR measured by the CPT, and the potential mechanisms that caused the
pre-consolidation it is anticipated that the stress history of the soil is spatially variable. For the purpose of
the settlement analyses, the stress history of cohesive soil layers has been interpreted from nearby CPT
locations and granular soil layers are assumed to be normally consolidated.
Soil Compressibility Parameters
Granular Soil
Settlement of granular soils was calculated using a stress-strain modulus, Es. The stress strain modulus
was estimated using a correlation with the SPT ‘N’ value (Bowles, 1996).
𝐸𝑠 = 500 × (𝑁 + 15)
Where:
𝐸𝑠 = Stress strain modulus
𝑁 = determined from the Standard Penetration Test and based on a hammer energy level of 55%
Cohesive Soil
Settlement of cohesive soils was calculated using the results of a laboratory incremental load
consolidation test and a correlation using the Atterberg liquid limit. The results of the consolidation test
are summarized in Table 9-2, below.
Table 9-2: Results of Incremental Load Consolidation Test
A correlation by Terzaghi and Peck (1967), with a reported error of +/- 30%, was used to estimate the
compression index.
𝐶𝑐 = 0.009(𝑤𝑙 − 10)
Where:
𝐶𝑐 = Compression Index
𝑤𝑙= Atterberg liquid limit
Using the liquid limit noted in Table 9-2, the correlation predicts a compression index of 0.24 which is
comparable to the laboratory determined compression index of 0.23.
The recompression index (Cr) is estimated at 20% of the compression index.
The compression index was estimated using an average of liquid limits from samples in the vicinity of the
culverts. The number of test results used to determine the average, the minimum and maximum values,
and the estimated compression and recompression indices are summarized in Table 9-3.
Location Depth Soil Unit Liquid
Limit
Plastic
Limit
Plasticity
Index
Compression
Index
TH19-LX-218 1.8 m CL 37% 18% 19% 0.23
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 21
Table 9-3: Estimated Compression and Recompression Indices
Culvert
Location
Number of
Atterberg Tests
Liquid Limit (%) Estimated
Compression
Index (Cc)
Estimated
Recompression
Index (Cr) Min. Max. Ave.
Sta. 1004+430 10 33 51 41 0.28 0.06
Sta. 1004+812 5 30 39 32 0.20 0.04
Sta. 1005+075 2 30 41 36 0.23 0.05
Sta. 1005+285 9 36 57 46 0.32 0.06
Sta. 1005+487 6 35 44 39 0.26 0.05
Sta. 1005+820 14 20 44 29 0.17 0.03
Sta. 1006+180 7 25 44 33 0.21 0.04
Sta. 1006+450 2 27 40 34 0.22 0.04
Sta. 1006+500 5 20 55 38 0.25 0.05
Sta. 1006+658 2 33 36 35 0.23 0.05
Sta. 1006+900 4 28 38 35 0.23 0.05
Sta. 1007+055 1 22 22 22 0.11 0.02
Embankment Stress Distribution
The embankment will impose a stress increment in the underlying soil. The stress increment was
estimated by converting the cross-sectional area of the embankment into a rectangle with an
approximate equivalent area. The height of the equivalent rectangle is approximately the same height as
the embankment at road centerline. The top and bottom of the rectangle is horizontal. The rectangle is
assumed to infinitely long along the centerline of the highway alignment. The stress increment was
calculated below the rectangle by assuming a 2.0V:1.0H load distribution.
Settlement Estimates
Using the information noted above, settlement was estimated at culvert locations. The estimate
corresponds to settlement below the centerline of the new highway alignment. In most cases settlement
at the inlet and outlet of the culverts will be significantly less than settlement below the highway
centerline. The estimates include immediate settlement of granular soils as determined by the stress-
strain modulus method, and consolidation settlement of cohesive soils as determined by the
consolidation method. By the end of application of full static load (soon after the end of construction), the
majority of immediate settlement may have occurred; however, only a fraction of consolidation settlement
will have occurred. The results of the settlement estimates are summarized in Table 9-4.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 22
Table 9-4: Estimated Settlement at Culvert Location, below Road Centerline
Culvert
Location
Embankment
Height (m)
Effective
Embankment
Width (m)
Immediate
Settlement
(m)
Consolidation
Settlement
(m)
Total
Settlement
(m)
Sta. 1004+430 5 40 0.01 0.20 0.21
Sta. 1004+812 3 25 0.03 0.08 0.11
Sta. 1005+075 4 30 0.01 0.09 0.10
Sta. 1005+285 8 35 0.02 0.14 0.16
Sta. 1005+487 4 35 0.04 0.03 0.07
Sta. 1005+820 5 35 0.01 0.17 0.18
Sta. 1006+180 10 40 0.01 0.31 0.32
Sta. 1006+450 151 55 0.06 0.60 0.662
Sta. 1006+500 151 40 0.06 0.39 0.452
Sta. 1006+658 101 65 0 0.42 0.422
Sta. 1006+900 51 25 0.01 0.38 0.392
Sta. 1007+055 51 30 0.10 0 0.102 Note: 1 Average height relative to existing highway grade and RHS slope. Does not include height above in-stream platform which
is assumed to be relatively incompressible. 2 The presence of existing highway fill, disturbed slide debris and side cast fill below the new embankment fill in these areas
increases the error of the settlement estimates. Actual settlement could be greater than presented above.
Differential settlement was estimated assuming the ends of the culverts will not settle relative to highway
centerline (i.e. middle of the culvert). This assumption may be overly conservative for culverts located near
the top of high embankments. Estimated differential settlement is summarized in Table 9-5.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 23
Table 9-5: Estimated Differential Settlement along Culverts
Location
Distance
between Middle
and End of
Culvert, L (m)
Settlement
at Middle of
Culvert, δ
(m)
Differential
Settlement,
δ/L
Comments
Sta. 1004+430 31 0.21 0.007 Located at base of embankment on natural ground subgrade.
Sta. 1004+812 14 0.11 0.008 Located at base of embankment on uniform subgrade.
Sta. 1005+075 21 0.10 0.005 Located at base of embankment on natural ground subgrade.
Sta. 1005+285 29 0.16 0.006 Inlet located at base of embankment on natural ground, outlet on
embankment fill.
Sta. 1005+487 27 0.07 0.003 Located at base of embankment on natural ground subgrade.
Sta. 1005+820 19 0.18 0.009 Inlet located at base of embankment on natural ground, outlet on
embankment fill.
Sta. 1006+180 21 0.32 0.015 Located near mid-height of embankment. Differential settlement likely less
than estimate.
Sta. 1006+450 22 0.66 0.0301
Located near top of embankment. LHS located above existing fill of unknown
compressibility, RHS located above in-stream platform. Differential settlement
may exceed estimate.
Sta. 1006+500 21 0.45 0.0211
Located near mid-height of embankment. LHS located above existing fill of
unknown compressibility, RHS located above in-stream platform. Differential
settlement may exceed estimate.
Sta. 1006+658 18 0.42 0.0231
Located near top of embankment. Far LHS located above existing fill of
unknown compressibility, center and RHS located above in-stream platform.
Differential settlement may be a concern near inlet.
Sta. 1006+900 16 0.39 0.0241
Located near top of embankment. LHS and center located above existing fill
of unknown compressibility, far RHS located above in-stream platform.
Differential settlement may be a concern near outlet.
Sta. 1007+055 17 0.10 0.0061
Inlet located at base of embankment on natural ground, outlet on
embankment fill over existing fill of unknow compressibility. Differential
settlement may be a concern near outlet. Note: 1 The presence of existing highway fill, slide debris and side cast fill below the new embankment in these areas increases the error of the differential settlement estimates.
Actual differential settlement could be greater than presented above.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 24
Time Rate of Consolidation
The time rate of consolidation settlement is a function of the rate of dissipation of the excess pore
pressures (which in turn is a function of the length of the drainage path in the consolidating layers),
coefficient of consolidation, lateral extent of loading, presence and horizontal continuity of coarse-grained
interbedding layers (drainage layers), and other factors dependent on local conditions. Given the
asymptotic nature of the pore pressure dissipation process, the end of primary consolidation settlement is
generally considered to be the time it takes to complete 95% of the primary consolidation settlement.
The results from the laboratory incremental load consolidation test yielded a coefficient of consolidation
of approximately 6 m2/year, it is anticipated that the coefficient of consolidation will vary depending on
the soil unit. Coefficients of consolidation of 4 and 10 m2/year were also considered in estimating time
rate of consolidation. The estimated time rate of consolidation is summarized in Table 9-6, below.
Table 9-6: Time Rate of 95% Consolidation Considering Two-Way Drainage
Consolidating
Layer Thickness
(m)
Time Rate of 95% Consolidation1
Cv = 4 m2/year Cv = 6 m2/year Cv = 10m2/year
1 1 month 0.5 month 0.3 month
2 3 months 2 months 1 month
4 13 months 9 months 5 months
6 30 months 20 months 12 months Note: 1 Assumed two-way drainage
Based on the CPT profiles, it appears that consolidating layers are interbedded with drainage layers,
resulting in relatively short drainage paths and consequently relatively rapid drainage of excess pore
pressures. Considering a consolidating layer thickness of 1 m and a coefficient of consolidation of
6 m2/year, approximately 0.5 months may be required for 95% of consolidation settlement to occur;
however, the time could vary depending on the coefficient of consolidation layer thickness. In order to
mitigate settlement effects, embankment fills should be constructed as far in advance of settlement
sensitive structures (e.g. culverts and final pavement structure) as is feasible within the project schedule.
At some culvert locations a staged construction methodology or a preload is required to mitigate
settlement, as described in Section 10.0. Instrumentation (in the form of settlement plates and
piezometers as described in Section 0) will be used to monitor settlement rates and inform timing of
completion settlement sensitive structures.
Secondary Compression Settlements
Secondary compression may occur after initial consolidation of the cohesive soil layers. Due to the
variable stress history of the soil deposit it is difficult to estimate the magnitude of secondary
compression. It is anticipated that secondary compression will be relatively small for soils that remain in
recompression and somewhat larger for soils in virgin compression. Differential settlement from
secondary compression is not anticipated to be a concern.
Settlement of Existing Fill
New embankment fill will be located above existing highway fill between approximately Sta. 1006+020
and the end of the segment (Sta. 1007+280), the embankment will also cover existing slides and slide
debris, and side cast fill on the RHS slope down to the river. The top of the new embankment is up 15 m
above the existing highway surface, and up to 20 m above the RHS slope down to the river. Although
settlement has been estimated in this area (see Table 9-4), the variability of the existing fill, slide debris
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 25
and side cast fill will increases the error of the settlement estimates, and actual settlement could be
greater than presented in Section 9.6.
However, some settlement could occur during construction of the embankment and prior to the
embankment height achieving the invert elevation of the culverts. Any settlement that occurs during
construction of the embankment and before construction of the culverts would offset the total theoretical
amount of settlement experienced by the culverts.
Although significant zones of organic soil or organic debris were not encountered during the site
investigation these zones may be present between the boreholes, or on the slope down to the river. Long-
term settlement can occur when the organic soil or debris decomposes and consolidates. If zones of
organic soil or organic debris are encountered during construction, the organic soil and debris should be
excavated and removed from below the embankment.
Sub-excavation of existing highway fills and existing slide debris can be considered if it is desirable to
reduce settlement; however, it may be onerous and impractical to remove significant volumes of existing
fill. Other mitigations could include:
1) Partial excavation of the fill and slide debris;
2) Use geogrid to bridge or distribute settlement over a larger area;
3) Construct as much of the grade as soon as possible, monitor the grade for settlement, and
compensate for any settlement prior to installing culverts and the final highway surface.
Note that in general excavation of existing highway fill and slide debris is not required for slope stability
objectives.
Settlement Mitigation
It is understood the criteria for differential settlement along a corrugated steel pipe culvert is limited to
the lesser of 1% of the culvert length or 0.15 m. As all culvert lengths are greater than 15 m, the limiting
factor is the settlement criterion of 0.15 m. Based on this criterion nine culvert locations require mitigation
to reduce the amount of anticipated differential settlement; these locations are summarized in Table 10-1.
Table 10-1: Estimated Differential Settlement and Settlement Criterion
Location Settlement at Middle of Culvert,
δ (m)
Exceeds Differential Settlement
Criterion of 0.15 m
Sta. 1004+430 0.21 Yes
Sta. 1004+812 0.11 No
Sta. 1005+075 0.10 No
Sta. 1005+285 0.16 Yes
Sta. 1005+487 0.07 No
Sta. 1005+820 0.18 Yes
Sta. 1006+180 0.32 Yes
Sta. 1006+450 0.66 Yes
Sta. 1006+500 0.45 Yes
Sta. 1006+658 0.42 Yes
Sta. 1006+900 0.39 Yes
Sta. 1007+055 0.10 Yes1 Note: 1 The presence of existing highway fill, potentially decomposable slide debris, and side cast fill below the new
embankment in this area results in unreliable estimates of differential settlement using conventional consolidation
settlement analysis methods. Actual differential settlement could be greater than presented above. For design purposes it
is assumed differential settlement could exceed 0.15 m.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 26
Where the differential settlement criterion is exceeded, settlement can be mitigated by using a staged
construction methodology or by preload. A staged construction methodology would involve constructing
the embankment up to the culvert invert elevation for a distance of 30 m on either side of the culvert axes
and monitoring for settlement. Once sufficient settlement has occurred such that the anticipated residual
settlement is less than 0.15 m the culvert can be installed, and the remaining embankment constructed. A
preload would involve initial placement of the embankment fill (using temporary culverts as needed) to
the final highway design grade for a distance of 30 m on either side of the culvert axes and monitoring for
settlement. Once sufficient settlement has occurred such that the anticipated residual settlement is
estimated to be less than 0.15 m the preload can be removed and the permanent culvert installed. Note
that preload fill that will be left in place after culvert installation must meet the gradation and compaction
requirements for the design location it is left in. The recommended mitigation for each culvert location
that exceeds the differential settlement criterion is summarized in Table 10-2. The estimated potential
minimum time for settlement abatement to occur (i.e. when residual settlement is estimated to be less
than 0.15 m) is also included in Table 10-2.
Table 10-2: Settlement Mitigation
Location Settlement Mitigation Potential Minimum Time Required for
Settlement Abatement
Sta. 1004+430 Preload 6 Weeks
Sta. 1005+285 Staged Construction 4 Weeks
Sta. 1005+820 Staged Construction 4 Weeks
Sta. 1006+180 Staged Construction 4 Weeks
Sta. 1006+450 Preload 6 Weeks
Sta. 1006+500 Preload 6 Weeks
Sta. 1006+658 Preload 6 Weeks
Sta. 1006+900 Preload 6 Weeks
Sta. 1007+055 Staged Construction 4 Weeks
East of Station 1006+000 Binnie provided a suggested three stage embankment construction approach to
accommodate traffic during construction (Binnie, 2020). For the culvert at Sta. 1006+180 the staged
culvert construction can occur during Binnie’s suggested Stage 2 Construction and using the Stage 2
Construction cross section. For the culvert at Station 1007+055 the staged culvert construction approach
can occur during Binnie’s suggested Stage 1 Construction. For the culverts at Stations 1006+450,
1006+500, 1006+658, and 1005+900 the preload can occur during Binnie’s suggested Stage 2
Construction and using the Stage 2 Construction cross section.
Instrumentation
During construction of the embankments it is recommended that monitoring of ground movements,
settlement and groundwater pressures be carried out.
Slope Inclinometer Casing
Slope inclinometer casings are proposed at the toe of high embankment slopes that are underlain by
cohesive soils. The slope inclinometer casings will be monitored during construction to check for lateral
deformation within the cohesive soil. The bottom portion of the slope inclinometer casings will be
installed in bedrock. Slope inclinometer casings are proposed at the locations noted in Table 11-1.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 27
Table 11-1: Slope Inclinometer Casings
Location Offset Target Elevation at Bottom of Casing
Sta. 1004+380 30 m Right 454 m
Sta. 1005+280 47 m Right 451 m
Sta. 1005+280 30 m Left 451 m
Sta. 1005+840 62 m Right 444 m
Settlement Plates
Settlement plates are proposed for culvert crossing embankments where settlement monitoring for
staged construction or preload is recommended. Each settlement plate will consist of a horizontal plate
located at the base of the embankment and a vertical riser pipe that extends up through the
embankment. Settlement plates are proposed at the locations noted in Table 11-2.
Table 11-2: Settlement Plates
Location Offset
Sta. 1004+420 7 m Right1
Sta. 1004+430 7 m Left
Sta. 1005+280 5 m Right1
Sta. 1005+280 25 m Right
Sta. 1005+815 10 m Right1
Sta. 1005+815 25 m Right
Sta. 1006+185 5 m Left
Sta. 1006+185 5 m Right1
Sta. 1006+455 5 m Left
Sta. 1006+455 5 m Right1
Sta. 1006+505 5 m Left1
Sta. 1006+505 5 m Right
Sta. 1006+653 15 m Left
Sta. 1006+653 5 m Right
Sta. 1006+895 5 m Left
Sta. 1006+895 5 m Right
Sta. 1006+895 15 m Right
Sta. 1007+050 20 m Right
Note: 1 Settlement plate co-located with a vibrating wire piezometer
Vibrating Wire Piezometers
Vibrating wire piezometers are proposed to be paired with settlement plates at culvert crossing
embankments where either staged construction or preload is recommended. The vibrating wire
piezometers will be used to measure pore pressures in cohesive soil layers during construction of the
embankments. Vibrating wire piezometers are proposed at the locations noted in Table 11-3. Note that all
vibrating wire piezometers are co-located with a settlement plate.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 28
Table 11-3: Vibrating Wire Piezometers
Location Offset Piezometer Tip Target Elevation
Sta. 1004+420 7 m Right 460 m
Sta. 1005+280 5 m Right 455 m
Sta. 1005+815 10 m Right 457 m
Sta. 1006+185 5 m Right 456 m
Sta. 1006+455 5 m Right 450 m
Sta. 1006+505 5 m Left 455 m
Large Diameter Culvert Headwalls
Custom designed cast-in-place reinforced concrete headwalls are required at five locations and a custom
designed reinforced concrete outlet collar is required at one location. The locations of the custom
designed headwalls and outlet collar are provided in Table 12-1. At other locations standard BCMoTI pre-
cast concrete headwall designs will be used.
Table 12-1: Headwall and Collar Locations, and Pipe Diameter
Location Pipe Diameter (m) Structure
Sta. 1002+4651 2.0 Headwall
Sta. 1004+812 2.4 Headwall
Sta. 1005+285 1.2 Collar
Sta. 1005+487 2.0 Headwall
Sta. 1006+500 2.7 Headwall
Sta. 1007+055 2.4 Headwall Note: 1 Located in the Lynx West Segment
Subgrade Conditions
A summary of anticipated subsurface conditions at each structure location is provided in Table 12-2.
Table 12-2: Summary of Subsurface Conditions at Headwall and Collar Locations
Location
Subgrade Conditions Fill Height
above
Culvert
Embankment Slope
Comment Inlet Outlet Inlet Outlet
Sta. 1002+4651 Silt Silt 4 m 2H:1V 2H:1V In cut
Sta. 1004+812 Silt and silty
sand
Silt and silty
sand 2 m 3H:1V 3H:1V
Scratch
grade
Sta. 1005+285 Clay
3 m
embankment
fill
4 m 4H:1V 4.25H:1V
Scratch
grade / in
fill
Sta. 1005+487 Clay Clay 2 m 3H:1V 3H:1V Scratch
grade
Sta. 1006+500
7 m
embankment
fill
20 m
embankment
fill
4 m 2H:1V 3H:1V2 In fill
Sta. 1007+055
Silty gravel
and silty
sand
5 m
embankment
fill
2 m 2H:1V 3H:1V2
Scratch
grade / in
fill Note: 1 Located in the Lynx West Segment
2 Right-hand side fill slope to be confirmed after in-river platform built and additional investigation and analyses carried out
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 29
Note that the right-hand side (outlet) fill slope at Sta. 1006+500 and 1007+055 will not be finalized until
an investigation and additional slope stability analyses are carried out upon completion of the in-river
early works platform for the fill.
Soil Bearing Capacity
To calculate the soil bearing capacity it was assumed the headwalls and apron slabs are approximately 4
by 6 m in plan and embedded a minimum of 0.3 m into the surrounding soil. The culvert collar at Sta.
1005+820 is assumed to be 1.8 by 0.3 m in plan and embedded a minimum of 0.9 m into the surrounding
soil. Note that soil bearing capacity will increase for larger plan areas and embedment depths. Based on
the assumed foundation configurations noted above, factored ultimate geotechnical bearing capacities
were calculated and summarized in Table 12-3. The factored ultimate bearing capacity includes a
geotechnical resistance factor, Φ = 0.55. Note that a minimum 0.5 m thick pad of compacted Clean
Granular Fill (as defined in Section 13.3) is required below the headwalls. Where the subgrade surface
below the pad of Clean Granular Fill is fine-grained (e.g. clay, silt, silty sand), the subgrade is to be lined
with a Class 2 non-woven geotextile as defined in Section 13.7. Fine-grained subgrades are anticipated at
Sta. 1004+465, 1004+812, 1005+487, 1007+055 (inlet only).
Table 12-3: Factored Ultimate Bearing Capacities
Location
Factored Ultimate Bearing
Capacity (kPa) Assumed Subgrade Conditions
Inlet Outlet
Sta. 1002+4651 70 kPa 70 kPa Minimum 0.5 m pad of compacted Clean Granular
Fill, over silt
Sta. 1004+812 70 kPa 70 kPa Minimum 0.5 m pad of compacted Clean Granular
Fill, over silt and silty sand
Sta. 1005+285 N/A 160 kPa ~3 m embankment thickness of compacted Clean
Granular Fill, over clay
Sta. 1005+487 70 kPa 70 kPa Minimum 0.5 m pad of compacted Clean Granular
Fill, over clay
Sta. 1006+500 160 kPa 160 kPa
>3 m embankment thickness of Clean Granular Fill
at inlet and outlet; assumed embankment slope of
2H:1V
Sta. 1007+055 160 kPa 160 kPa
Minimum 0.5 m pad of compacted Clean Granular
Fill at inlet, over silty gravel; >3 m embankment
thickness of Clean Granular Fill at outlet; assumed
embankment slope of 2H:1V Note: 1 Located in the Lynx West Segment
It is anticipated that differential settlement between the headwall and the culvert will not exceed 25 mm
unless the factored ultimate limit states bearing capacity is exceeded. Note that staged construction and
preloading will occur at some culvert locations which will further reduce the potential for differential
settlement between the headwall and culvert.
Frost Design Considerations
Based on past experience in the area, Wood anticipates that frost could penetrate approximately 3 m
below ground surface. Because the headwalls and culverts will be exposed to freezing temperatures the
depth of frost penetration should be measured from the underside of the headwall and culvert invert.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 30
The natural clay, silt and silty sand soils below the headwalls and culverts are susceptible to frost heave.
To reduce the potential for differential frost heave between the headwall and the culvert, Wood
recommends using a consistent subgrade surface below both the headwall and culvert.
However, if it is desirable to reduce frost heave altogether, Wood recommends replacing the soil below
the headwall and culvert with Clean Granular Fill extending at least 3 m below the underside of the
headwall and culvert invert. An alternative to fully replacing the soil below the headwall and culvert with
Clean Granular Fill is to protect the underlying soil from freezing by using rigid board insulation. The rigid
board insulation would be placed below the headwall and culvert and extend laterally out by
approximately 3 m. If required, a detail for using rigid board insulation (including thickness and strength
of rigid board insulation) can be developed by Wood.
Lateral Earth Pressures
Earth pressures against the headwalls can be calculated using the earth pressure coefficient specified in
Table 12-4. Active earth pressure coefficients apply to flexible retaining structures capable of displacing at
least 1% of the net retained height. For all other structures, use the at-rest case. Retaining structures are
assumed to be backfill with Clean Granular Fill with a friction angle of 38°.
Table 12-4: Earth Pressure Coefficients under Static Condition for Various Sloping Conditions
Earth Pressure
Case
Static Condition
Flat 4.25H:1V1 4H:1V1 3H:1V1 2H:1V1
Active 0.24 0.27 0.27 0.29 0.33
At-rest 0.38 0.47 0.48 0.51 0.56
Passive 4.20 7.00 7.24 8.85 13.80 Note: 1Slope is measured from horizontal and upward and away from structure
For calculating lateral earth pressure use a bulk unit weight of 21 kN/m3 for Clean Granular Fill backfill.
Backfill behind the structure should not be placed before the structure concrete has adequate strength.
Compaction of backfill within 2 m of the wall should be in maximum 0.10 m thick lifts using a walk behind
plate compactor. To take into account the increase lateral earth pressure due to compaction, increase the
calculated lateral earth pressure by at least 12 kPa.
Sliding Friction Coefficient
Resistance of shallow foundations to horizontal loads may be determined using a concrete-soil interface
friction angle of 25° for cast in-place or precast concrete founded on Clean Granular Fill. Sliding resistance
determined based on this interface friction angle is an unfactored resistance, which can be calculated by
multiplying the sum of the vertical forces that are exerted on the footing by the tangent of the concrete-
soil interface friction angle provided above. The factored resistance against sliding may be determined by
applying a resistance factor.
General Recommendations
The following section provides geotechnical recommendations that are generally applicable for the design
and construction of the new highway alignment.
Stripping
Stripping will be required below all foundation subgrades. Approximate stripping depth by project station
are summarized in Table 13-1.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 31
Table 13-1: Stripping Depths by Station
Location Stripping
Depth (m) Comments
1004+330 to 1004+660 0.2 -
1004+660 to 1004+780 0.1 -
1004+780 to 1004+840 0.2 -
1004+840 to 1004+900 0.1 -
1004+900 to 1005+460 0.2 -
1005+460 to 1005+500 0.2
Potential to encounter existing site disturbance (e.g. disturbed soil, fill, buried debris) from previous
land use. Sub-excavation may be required if site disturbance is encountered during subgrade
review.
1005+500 to 1005+690 0.2 -
1005+690 to 1005+910 0.6
RHS, potential to encounter existing site disturbance (e.g. disturbed soil, fill, buried debris) from
previous land use. Sub-excavation may be required if site disturbance is encountered during
subgrade review.
1005+910 to 1005+970 0.6 -
1005+970 to 1006+120 0.8 -
1006+120 to 1006+210 0.6 -
1006+210 to 1006+780 RHS 0.1
LHS 0.3
RHS, if organic soil or organic debris is identified during construction review, sub-excavation of
organic soil or organic debris will be required.
RHS, existing slide between Sta. 1006+380 and 1006+460, optional sub-excavation to reduce
settlement to overlying embankment fill, sub-excavation not required for stability objectives.
1006+780 to 1006+860 0.3 RHS, if organic soil or organic debris is identified during construction review, sub-excavation of
organic soil or organic debris will be required.
1006+860 to 1007+030 0.3
RHS, if organic soil or organic debris is identified during construction review, sub-excavation of
organic soil or organic debris will be required.
RHS, existing historically remediated slide between Sta. 1006+780 and 1006+900, optional sub-
excavation to reduce settlement to overlying embankment fill, sub-excavation not required for
stability objectives.
RHS, existing not remediated, recently active slide between Sta. 1006+900 and 1007+030, optional
sub-excavation to reduce settlement to overlying embankment fill, sub-excavation not required for
stability objectives.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 32
Location Stripping
Depth (m) Comments
1007+030 to 1007+070 0.3 RHS, if organic soil or organic debris is identified during construction review, sub-excavation of
organic soil or organic debris will be required.
1007+070 to 1007+280 0.3 RHS, if organic soil or organic debris is identified during construction review, sub-excavation of
organic soil or organic debris will be required.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 33
In addition to the stripping depths noted above, deeper stripping and/or sub-excavation will be required
if deleterious soils (e.g. soft, wet, weakened, and organic soils or loose fill) are encountered. All stripped
foundation subgrades should be reviewed by a geotechnical engineer or their representative to confirm
that deleterious soils have been removed prior to fill placement.
It is recommended that the existing asphalt surface be removed below the footprint of new embankments
and that the underlying gravel surface be scarified prior to placement of embankment fill. Approximate
asphalt thicknesses are noted in Section 6.0.
Subgrade Preparation
The following subgrade preparation procedure is recommended for general highway construction.
1) Remove all deleterious soils (e.g. soft, wet, weakened, and organic soils or loose fill) from the
subgrade surface. A geotechnical engineer or their representative should review subgrade
surfaces to confirm that deleterious soils have been removed.
2) As soon as possible following exposure of a fine-grained subgrade crown the subgrade surface
with a minimum cross fall of 2% to promote drainage. This will help minimize softening of the
subgrade surface due to ponding and infiltration of surface water. Note that the subgrade surface
must have a 2% cross fall prior to placement of SGSB.
3) For fine-grained subgrades, minimize disturbance of the subgrade surface by limiting vehicle and
construction traffic over the prepared subgrade surface. If the subgrade surface becomes
disturbed and softened, removal of the softened soil and replacement will fill similar the
surrounding subgrade will be required.
4) Areas of unsuitable subgrade soils that are determined to be too deep to be practically removed
will require additional subgrade improvements as directed by a geotechnical engineer at the time
of construction. Subgrade improvements may consist of (but are not limited to) use of a
geotextile separator, biaxial geogrid layers(s), granular backfills and/or other methods.
Embankment Fill Construction
The following general recommendations are provided for embankment fill construction.
1) All fill foundation preparation, fill placement and fill compaction operations should be observed
by qualified geotechnical engineering field personnel to confirm that that construction is in
accordance with the recommendation in this report and BCMoTI Standard Specifications (2016).
2) Existing deleterious soils (e.g. soft, wet, weakened, and organic soils or loose fill) should be
removed from under the footprint of the embankment and from the outside face of existing
highway fill slopes prior to placing new fill.
3) Fill material should consist of inorganic granular soil with moisture content near (+/- 1%) of the
optimum moisture content for compaction, as determined by laboratory moisture-density testing.
In general, the following two granular fill types are recommended.
a) Clean Granular Fill (CGF) – to be used for all embankment and/or berm fills located below an
elevation of 466 m, and the lower and back 1 m of fills placed on or against groundwater
seepage zones.
- CGF is to be free of organics and other detritus.
- CGF is to have less than 5% particles passing the 0.075 mm sieve.
-CGF can have particle sizes up to 300 mm, provided adequate lift thickness and compaction
is achieved before placement of the next lift. The construction contractor must demonstrate
via test strips and test excavations that they have the equipment and methodology to achieve
a compaction nominally equivalent to 95% Standard Proctor Maximum Dry Density (ASTM
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 34
D698), with no observable segregation or deflection and no rutting greater than 10 mm
under construction traffic loading.
b) Type D Granular Fill (Type D) – to be used for all other fill locations, except along the lower
and back 1 m of fills placed on or against groundwater seepage zones.
- Type D is to be free of organics and other detritus.
- Type D material gradation shall meet BCMoTI Standard Specification (2016), Section 201.44
and consist of predominately granular material that contains a maximum of 20% particles
passing the 0.075 mm sieve.
- Type D can have particle sizes up to 300 mm, provided adequate lift thickness and
compaction is achieved before placement of the next lift. The construction contractor must
demonstrate via test strips and test excavations that they have the equipment and
methodology to achieve a compaction nominally equivalent to 95% Standard Proctor
Maximum Dry Density (ASTM D698), with no observable segregation or deflection and no
rutting greater than 10 mm under construction traffic loading.
4) Fill that will overlie groundwater seepage zones (from either natural or existing fill slopes) will
require field review by a geotechnical engineer. These areas should be treated on a case by case
basis. A conceptual treatment could be placement of a granular drainage blanket from the base
of the excavation to a minimum 2 m above the seepage area. The granular drainage blanket
would need to be separated from adjacent material using a non-woven geotextile (as defined in
Section 13.7).
5) Fills underlain by groundwater seepage zones should be covered by a minimum 1 m thick layer of
CGF, the top of the CGF layer should extend at least 0.5 m above the high-water mark of any
standing water, or at least 0.5 m above the adjacent original ground surface. A non-woven
geotextile should be placed on the prepared subgrade before placement of the CGF. A layer of
non-woven geotextile should be placed over the CGF layer where Type D will be placed over the
CGF.
6) Drainage from under an embankment area should be directed to an exposed face of a ditch or a
sub-drain system but should not be directed over the face of potentially unstable or erodible
slopes without additional armoring and/or riprap.
7) At the transition sections between the new highway embankment and existing embankment
(approximately between Sta. 1007+100 and 1007+280), positive subsurface drainage away from
the existing highway embankment is to be maintained. New fills places near granular fills below
the existing highway should be constructed with CGF and extend a minimum 0.1 m below the
underside of the existing granular fill so as not to block internal drainage.
Cut Slope Construction
The following general recommendations are provided for cut slope construction.
1) Cut slopes that encounter seepage must be reviewed by a geotechnical engineer and may need
to be protected from piping erosion by the placement of a granular drainage blanket on the face
of the slope from the base of the ditch to a minimum 2 m above the seepage zone.
2) Fine-grained cut materials are unsuitable for re-use and should be considered waste.
3) Cut areas should be hydroseeded with an appropriate vegetation seed mix as soon as possible
after soil disturbed is finished.
Temporary Excavations
Temporary excavations greater than 1.2 m in depth, where worker entry is required, should be constructed
in accordance with the current Part 20.78 through 20.95 of the Occupational Health and Safety Regulation
as per WorkSafeBC. The construction contractor is ultimately responsible for the safety of temporary
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 35
excavation slopes. Should excavations encounter groundwater, flatter slopes than those recommended by
WorkSafeBC could be required. Excavations greater than 1.2 m in depth with steeper slopes and those
subject to seepage or sloughing should not be entered unless they are shored, braced or sloped as
approved by the contractor’s geotechnical engineer.
Temporary excavations and construction work will be required below steep and unstable slopes,
particularly along the in-stream stability berm (L2 alignment). The construction contractor is responsible
for developing safe work procedures to carry out work below all slopes.
Culverts and Headwalls
The following general recommendations are provided for installing culverts.
1) Excavated and remove all deleterious soils (e.g. soft, wet, weakened, and organic soils or loose fill)
from below the proposed culvert bedding subgrade.
2) If the culvert bedding subgrade surface is fine-grained, a non-woven geotextile separator (as
defined in Section 13.7) will be required between the bedding material and the fine-grained
subgrade.
3) Use culvert bedding material that meets BCMoTI Standard Specifications, Section 303.
Where culverts have headwalls, the headwall foundation should be founded on a minimum 0.5 m thick
layer of compacted CGF that extends down from the outside edge of the foundation at 1H:1V to a
subgrade bearing surface that is approved by a geotechnical engineer. Where the subgrade surface is
fine-grained, a non-woven geotextile separator will be required between the compacted CGF and the
fine-grained subgrade.
Geotextile and Biaxial Geogrid Specifications
Where non-woven geotextiles are required, the recommended specifications are provided in Table 13-2.
Table 13-2: Non-Woven Geotextile Specifications
Note: 1 Elongation > 50%, as per ASTM D4632 2 Based on minimum average roll values (as per ASTM C 4759) in the weaker principal direction 3 Based on maximum average roll values
Property Test Method Class 1 Class 2
Material Type Non-Woven1 Non-Woven1
Grab Tensile Strength2 ASTM D 4632 ≥ 900 N ≥ 700 N
Sewn Seam Strength2 ASTM D 4632 ≥ 810 N ≥ 630 N
Tear Strength2 ASTM D 4533 ≥ 350 N ≥ 250 N
Puncture Strength2 ASTM D 6241 ≥ 1925 N ≥ 1375 N
Permittivity ASTM D4491 ≥ 0.2 sec-1 ≥ 0.1 sec-1
Apparent Opening Size3 ASTM D 4751 < 0.43 mm < 0.22 mm
Recommended Application > 50 kg class riprap
Drainage layers
Subgrade separation
< 50 kg class riprap
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 36
Where geogrid is required for local subgrade improvement during construction, the recommended
specification for a biaxial polypropylene geogrid are provided in Table 13-3.
Table 13-3: Biaxial Polypropylene Geogrid Specifications
Property Test Method Value
Tensile Strength @ 5% Strain, Machine Direction1 ASTM D 6637 ≥ 11.8 kN/m
Tensile Strength @ 5% Strain, Cross Machine
Direction1 ASTM D 6637 ≥ 18.8 kN/m
Maximum Aperture Size 50 mm
Minimum Aperture Size 15 mm
Flexural Stiffness1 ASTM D 7748 ≥ 700 g-cm
Roll Width +/- 0.1 m
Note: 1 Based on minimum average roll values (as per ASTM C4759).
Pavement Structure
The recommended pavement structure is dependent on the nature of the soil subgrade that will be
encountered (in cuts) or constructed (fills). Table 13-4 provides recommended pavement structures for the
new highway alignment for two different subgrade conditions: Type A for well-drained granular
subgrades, and Type B for poorly drained and/or fine-grained subgrades.
Table 13-4: Recommended Minimum Pavement Structure Thickness
Subgrade Type Pavement
Structure Asphalt (AP)
Crushed Base
Course (CBC)
Select
Granular
Subbase
(SGSB)
Well Drained Granular Soils (Sand
and Gravel <10% Fines) A 125 mm 300 mm 300 mm
Poorly Drained or Fine-Grained
Soils (>10% Fines) B 125 mm 300 mm 600 mm1
Note: 1 A non-woven geotextile separator will be required between SGSB and fine-grained subgrades
It is currently anticipated that both Type A and B structures would be used in the highway segment.
Where subgrade fill (embankments) meet the gradation for SGSB the thinner Type A structure would be
used. Where the subgrade is a fine-grained soil the thicker Type B structure would be used. For the Type B
pavement structure, a non-woven geotextile separator will be required below the SGSB. Likely locations
where non-woven geotextile separators will be required are included in Table 13-5.
Table 13-5: Likely Locations for Non-Woven Geotextile Separator below SGSB
Location Anticipated Subgrade
Sta. 1004+660 to 1004+9801 Clayey sand / silt
Sta. 1005+500 to 1005+690 Clay
Sta. 1005+910 to 1005+970 Clay Note: 1 Non-woven geotextile not required on fill around culvert at Sta. 1004+812
Where the new pavement structure abuts the existing structure at the east end of the segment, the new
SGSB thickness should match or exceed that of the existing structure to not hinder drainage.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 37
Soil Waste Disposal
The following procedures are recommended for general siting and placing waste from unsuitable or
surplus soil materials generated by the project. Specific disposal scenarios different from below should be
assessed on a case by case basis by a geotechnical engineer.
1) Waste material should only be placed on slopes with a gradient of 10° (approximately 5.7H:1V) or
less and should not be placed in the vicinity of the crests of other slopes where they could have a
destabilizing influence.
2) Do no site waste areas within or near environmentally sensitive locations such as riparian zones,
seepage zones, or where the waste will cause ponding of water or redirection of drainage
patterns (including ditches).
3) Waste materials should be placed with a maximum slope of 3H:1V and to a maximum height of
3 m. Place the waste in maximum 1 m thick lifts and level with tracked equipment, as required.
4) Where practicable, do not site waste piles adjacent to existing and proposed road fills except for
the designated B8 and B9 disposal sites located between Sta. 1006+060 and 1006+940, described
further in Section 14.0, below. Waste piles placed adjacent to road fills are often encountered
during future road widening and upgrading projects, frequently leading to costly removal during
construction.
5) Waste sites placed adjacent to road fills should not block drainage from existing fills and should
be kept at least 1 m below the proposed road pavement structure subgrade and/or any other
granular fills that are likely to transmit drainage.
6) Contour the waste material to promote surface drainage. To maintain positive drainage from the
fill surface while allow for long-term settlement of the loosely placed fill, use a minimum 10%
cross fall slopes to crown the waste material.
7) Use appropriate short-term measures to control off-site transport of fines in runoff (such as silt
fencing). Maintain the short-term controls until effective long-term measures (such as vegetation
cover) are established.
Subject to relevant environmental and land use requirements, disposal of surplus excavation material
(waste) is not anticipated to be a geotechnical concern, especially if deposited on fluvial terrace areas
and/or below the reservoir inundation level. Surplus material should not be disposed along slope crests or
on slopes steeper than 10°. Waste material should not be disposed of against the toes or sides of granular
(e.g. CGF) fill slopes where internal drainage under static and rapid drawdown conditions is required.
Designated Soil Waste Disposal Sites
Binnie has selected areas for waste deposal. Two large volume areas are located on the LHS of the
alignment between Sta. 1006+060 and 1006+940 and are shown in Figure 2. The large volume area west
of the L15 highway access road is identified as B8 and the large volume area east of the access road is
identified as B9. The areas are generally bound to the south by the new highway embankment and to the
north, east and west by the bottom slopes of the Peace River Valley. Areas B8 and B9 are discussed
further below.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 38
Site B8
Site B8 is located on the LHS of the alignment between Sta. 1006+060 and the L15 highway access road at
Sta. 1006+225. The waste disposal site is bordered to the south by the new highway embankment, to the
east by the L15 highway access road embankment and to the north and west by the existing ground
surface that slopes up from the toe of the highway embankment. The site is approximately 165 m long,
50 m wide and triangular in plan area. The waste soil will extend from approximately 461 m elevation up
to approximately 465 m elevation.
The top surface of the waste material is planar and slopes towards the new embankment at 2%. The top
surface is drained by a 1.2 m diameter culvert located at Sta. 1006+180. It is anticipated that long-term
settlement of the top surface will be greater above the buried toe of the embankment where the waste
soil will be thickest. Long-term settlement may result in the waste surface becoming lower than the
culvert inlet, resulting in areas of standing water.
The slope stability model at Sta. 1006+200 does not consider the effect of the B8 waste disposal area, see
Section 0 and Figures 17 through 19. Steeper LHS embankment fill slopes may be possible once the B8
waste disposal area is considered. Additional stability analyses will be carried out for 100% design.
Site B9
Site B9 is located on the LHS of the alignment between the L15 highway access road at Sta. 1006+225 and
1006+940. The waste disposal site is bordered to the south by the new highway embankment, to the west
by the L15 highway access road embankment and to the north and east by the existing ground surface
that slopes up from the toe of the highway embankment. The site is approximately 715 m long with a
width that generally varies between 30 and 100 m. The waste soil will extend from approximately 453 m
elevation up to approximately 465 m elevation.
The top surface of the waste material is planar and slope towards the new embankment at 2%. The waste
site is located below three separate but coalesced/overlapping alluvial fans that drain onto the waste
surface. Flow from the fans will be drained by three culverts located at Sta. 1006+450, 1006+500 and
1006+658. In general, it is anticipated that long-term settlement of the top of the waste surface will be
greater above the buried toe of the embankment where the waste soil will be thickest. Long-term
settlement may result in the waste surface becoming lower than the culvert inlets, resulting in areas of
standing water.
A riprap channel with ten check dams is located upstream of the culvert at Sta. 1006+500. The stream
channel and check dams will be founded on waste soil between 0 and 4 m thick. Long-term settlement
from the waste soil could result in settlement of various magnitudes along the stream channel. If long-
term settlement along the stream channel is undesirable, the waste soil below the stream channel should
be placed with a higher level of compaction.
The slope stability model at Sta. 1006+520 considers the effect of the B8 waste disposal area, see Section
7.3.7 and Figures 20 through 22. The LHS embankment fill slope is recommended based on the
assumption that waste soil will be placed up to 465 m elevation. If there is a possibility that waste soil will
not be placed up to 465 m elevation, or not placed in this area at all, then additional slope stability
modelling is required and a flatter LHS embankment fill slope will be recommended.
Geotechnical Recommendations by Station
Using the results of the geotechnical investigation and slope stability assessment, a summary of station-
specific preliminary recommendations are provided below.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 39
Station Range Reference Geometric
Design
Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations
From To
1004+330 1004+660
Cut up to 5 m
Fill up to 7 m
2H:1V to 4H:1V: Fill Slopes
TP18-LX-032
(Lynx West),
TP18-LX-033
(Lynx West),
TP18-LX-034,
TP18-LX-035,
TP18-LX-036,
TP18-LX-037,
TP18-LX-038,
CPT18-LX-007,
CPT18-LX-008.
Upper 0.1 to 0.2 m: Topsoil.
Below Topsoil Upper Terrace: Gravel, silty, sandy to 1.8 m depth, over
bedrock, or bedrock near surface
Below Topsoil Lower Terrace: 3.6 m to >5.0 m of clay. Test pits TP18-LX-035
and TP18-LX-036 encountered sand and silt (>1.2 m thick) below the clay.
Shale Bedrock: encountered in two test holes as follows:
- TP18-LX-032 (1.8 m – 473.1 m); and
- TP18-LX-033 (0.1 m – 470.1 m).
Groundwater: inferred at 6.2 m depth in CPT18-LX-008.
Stripping 0.2 m
Max Cut Slope 3H:1V (may encounter bedrock; bedrock slope can be cut steeper,
bedrock should be considered PAG)
Estimated Waste: 10%
Max Fill Slope LHS 3.00H:1.0V
Max Fill Slope RHS 3.10H:1.0V
Granular Fill
1004+660 1004+780
Scratch Grade
Shallow fills (<2 m) and
ditch cuts up to 1 m.
2H:1V Cut Slopes
2H:1V to 4H:1V Fill Slopes
TP18-LX-039.
Upper 0.1 m: Topsoil.
Below Topsoil: 2.3 m clayey sand with 0.3 m gravel with some clay below.
Below Gravel: >2.3 m of silt present.
Shale Bedrock: not encountered.
Groundwater: not encountered.
Stripping 0.1 m
Max Cut Slope 2H:1V
Estimated Waste: 100%
Max Fill Slope 3.00H:1V
Granular Fill
Non-woven geotextile separator likely required below SGSB.
1004+780 1004+840 Fill and Culvert Crossing
Fill up to ~4 m
TH18-LX-018,
TH18-LX-017,
TP18-LX-040,
TP18-LX-056,
CPT18-LX-009.
Upper 0.1 to 0.2 m: Topsoil
Below Topsoil: generally, sand and gravel interbedded with silt and clay over
shale bedrock.
Shale Bedrock: encountered in two test holes as follows:
- TH18-LX-018 (7.6 m – 459.4 m); and
- TH18-LX-017 (7.9 m – 459.7 m).
Groundwater: not encountered.
Stripping 0.2 m
Max Fill Slope 3.00H:1V
Granular Fill
Hwy 29 alignment crosses an entrenched seasonal stream channel and located near
the distal edge of an alluvial fan. Indications of recent small debris flow/flood events
in channel (observed summer 2019). A 2.4 m diameter culvert with upstream check
dams is proposed.
Riprap along shoreline between Sta. 1004+580 and 1005+100 to provide long-term
reservoir shoreline erosion protection.
Non-woven geotextile separator likely required below SGSB, but not above fill around
the culvert.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 40
Station Range Reference Geometric
Design
Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations
From To
1004+840 1004+900
Scratch Grade
Shallow fills (<2 m) and
ditch cuts up to 1 m.
2H:1V Cut Slopes.
2H:1V to 4H:1V Fill Slopes.
TP18-LX-041.
Upper 0.1 m: Topsoil
Below Topsoil: 1.4 m sand and gravel over >3.4 m of silt.
Shale Bedrock: not encountered.
Groundwater: not encountered.
Stripping 0.1 m
Max Cut Slope 2H:1V
Estimated Waste: 100%
Max Fill Slope 3.00H:1V
Granular Fill
Riprap along shoreline between Sta. 1004+580 and 1005+100 to provide long-term
reservoir shoreline erosion protection.
Non-woven geotextile separator likely required below SGSB.
1004+900 1005+460 Fill up to 9 m in height.
5H:1V Fill Slopes
TH19-LX-201,
TH19-LX-203,
TH18-LX-019,
TH18-LX-020,
TH18-LX-021,
TP18-LX-042,
TP18-LX-043,
CPT19-LX-202,
CPT19-LX-204,
CPT18-LX-010,
CPT18-LX-011,
CPT18-LX-012,
CPT18-LX-013.
Upper 0.1 to 0.2 m: Topsoil.
Below Topsoil: a mixture of silt and clay, interbedded with sand and gravel
over shale bedrock.
Shale Bedrock: encountered in four test holes as follows:
- TH18-LX-019 (7.6 m – 458.3 m);
- TH19-LX-201 (5.5 m – 456.9 m);
- TH18-LX-020 (4.6 m – 454.5 m); and
- TH19-LX-203 (3.1 m – 457.7 m).
Groundwater: inferred at 2.4 m depth in CPT19-LX-202, and 2.7 m depth in
CPT19-LX-204.
Stripping 0.2 m
Max Fill Slope LHS 3.95H:1V
Max Fill Slope RHS 4.20H:1V
Granular Fill
Riprap along shoreline between Sta. 1004+580 and 1005+100 to provide long-term
reservoir shoreline erosion protection.
Riprap along shoreline between Sta. 1005+400 and 1005+800 to provide long-term
reservoir shoreline erosion protection.
1005+460 1005+500 Culvert Crossing
Fill up to ~3 m
TH19-LX-205,
TH19-LX-207,
CPT19-LX-206,
CPT18-LX-014.
Upper 0.1 to 0.2 m: Topsoil.
Below Topsoil: a mixture of silt and clay over shale bedrock. Test hole TH19-
LX-207 encountered a gravel layer at 6.6 m to 7.3 m and a sand layer at 11.6
m to 12.5 m.
Shale Bedrock: encountered in two test holes as follows:
- TH19-LX-205 (7.0 m – 457.6 m); and
- TH19-LX-207 (13.7 m – 456.7 m).
Groundwater: encountered at 9.4 m in test hole TH19-LX-207, inferred at
6.1 m depth in CPT19-LX-206.
Stripping 0.2 m
Max Fill Slope 3.00H:1.0V
Granular Fill
Hwy 29 alignment crosses an entrenched stream channel and along distal edge of an
alluvial fan. Alignment is closer to alluvial fan than current highway crossing so risk
from debris flow/flood events higher than exists for the current highway crossing. A
2.0 m diameter culvert with upstream check dams is proposed.
Potential to encountered existing site disturbance (e.g. disturbed soil, fill, buried
debris) from previous land use. Sub-excavation may be required if site disturbance is
encountered during construction.
Riprap along shoreline between Sta. 1005+400 and 1005+800 to provide long-term
reservoir shoreline erosion protection.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 41
Station Range Reference Geometric
Design
Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations
From To
1005+500 1005+690
Cut (up to 10m) left into
alluvial fan.
5H:1V Cut Slopes.
TH19-LX-208,
TH19-LX-209,
TH19-LX-210,
TH18-LX-022,
CPT19-LX-211,
CPT18-LX-015,
CPT18-LX-016,
CPT18-LX-017,
CPT18-LX-018,
CPT18-LX-019.
Upper 0.2 m: Topsoil.
Below Topsoil: a mixture of silt and clay, interbedded with sand and gravel
over shale bedrock.
Shale Bedrock: encountered in three test holes as follows:
- TH19-LX-208 (16.8 m – 457.2 m);
- TH19-LX-209 (18.7 m – 457.9 m); and
- TH19-LX-210 (12.3 m – 457.4 m).
Groundwater: encountered at 9.1 m in test hole TH19-LX-210, inferred at 6.1
m depth in CPT19-LX-211.
Stripping 0.2 m
Max Cut Slope 3.10H:1V
Estimated Waste: 100%
Max Fill Slope 3.00H:1.0V
If seepage observed during construction a gravel blanket may be required on face of
slope.
Riprap along shoreline between Sta. 1005+400 and 1005+800 to provide long-term
reservoir shoreline erosion protection.
Non-woven geotextile separator likely required below SGSB.
1005+690 1005+910 Fill up to 13 m.
5H:1V Fill Slopes.
TH19-LX-212,
TH19-LX-213,
TH18-LX-023,
TH18-LX-024,
TH18-LX-025,
TP18-LX-044,
CPT19-LX-214,
CPT19-LX-215,
CPT18-LX-020,
CPT18-LX-021,
CPT18-LX-022,
CPT18-LX-023,
CPT18-LX-024.
Upper 0.1 m to 0.6 m: Topsoil
Below topsoil: 7.8 m to 13.7 m of clay. Test hole TH19-LX-213 encountered
sand at 13.7 m to 14.6 m.
Shale Bedrock: encountered in two test holes as follows:
- TH19-LX-212 (7.8 m – 456.1 m); and
- TH19-LX-213 (14.6 m – 453.0 m).
Groundwater: encountered at 3.7 m in test hole TP18-LX-044, inferred at 8.5
m depth in CPT19-LX-215.
Stripping 0.6 m
Max Fill Slope LHS 2.0H:1.0V
Max Fill Slope RHS 4.00H:1.0V
Granular Fill
RHS, potential to encounter existing site disturbance (e.g. buried foundations,
disturbed soil, fill) from previous land use. Sub-excavation may be required if site
disturbance is encountered during construction. Gas bubbles observed in pond near
Sta. 1005+880.
Riprap along shoreline between Sta. 1005+400 and 1005+800 to provide long-term
reservoir shoreline erosion protection.
Riprap along shoreline between Sta. 1005+860 and 1006+000 to provide long-term
reservoir shoreline erosion protection.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 42
Station Range Reference Geometric
Design
Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations
From To
1005+910 1005+970
Cut left up to 7 m into
alluvial fan.
Cut slope 2H:1V.
TH19-LX-216,
TH19-LX-217,
TH19-LX-218,
TH18-LX-026,
TPH18-LX-045.
Upper 0.6 m: Topsoil
Below topsoil: a mixture of silt and clay, interbedded with sand over
bedrock.
Shale Bedrock: encountered in all test holes as follow:
- TH19-LX-218 (12.8 m – Elev. 451.0 m);
- TH19-LX-217 (13.9 m – Elev. 455.2 m); and
- TH19-LX-216 (23.3 m – Elev. 457.7 m).
Groundwater: not encountered.
Stripping 0.6 m
Max Cut Slope 2.5H:1.0V (with angular rock shear key)
Estimated Waste 100%.
Max Fill Slope 3.00H:1.0V
Granular Fill
Riprap along shoreline between Sta. 1005+860 and 1006+000 to provide long-term
reservoir shoreline erosion protection.
Non-woven geotextile separator likely required below SGSB.
1005+970 1006+120 Fill up to 15 m.
2H:1V to 4H:1V Fill Slopes.
TH18-LX-027,
TH18-LX-028,
TH18-LX-029,
PV18-LX-033,
TPH18-LX-046,
TPH18-LX-047,
CPT19-LX-219.
Upper 0.1 m to 0.8 m: Topsoil
Below topsoil: In test holes TPH18-LX-046 and TH18-LX-027 clay was
encountered (2.3 m to 3.1 m thick). Test hole TH18-LX-029 encountered
gravel (1.8 m thick) below the topsoil.
Shale Bedrock: encountered in three test holes as follows:
- TPH18-LX-046 (2.4 m – Elev. 455.5 m);
- TH18-LX-029 (2.6 m – Elev. 443.8 m); and
- TH18-LX-027 (3.8 m – Elev. 453.3 m).
Groundwater: encountered at 1.5 m in test hole TH18-LX-029, inferred at 5.6
m depth in CPT19-LX-219.
Stripping 0.8 m
Max Fill Slope LHS 2.75H:1.0V
Max Fill Slope RHS 3.25H:1.0V
Granular Fill
Riprap along shoreline between Sta. 1005+860 and 1006+000 to provide long-term
reservoir shoreline erosion protection.
Soil waste disposal site B8 on LHS.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 43
Station Range Reference Geometric
Design
Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations
From To
1006+120 1006+210
Fill up to 15 m over existing
highway 29.
Left Slope - 2H:1V to 4H:1V
Right Slope – 3H:1V
TH19-LX-220,
TPH18-LX-049,
CPT19-LX-221.
Upper 0.1 m to 0.6 m: Topsoil
Below topsoil: 2.5 m to 8.5 m of clay over 0.6 m of sand and gravel.
Shale Bedrock: encountered in TH19-LX-220 at 9.5 m (Elev. 453.4 m).
Groundwater: not encountered.
Stripping 0.6 m
Max Fill Slope LHS 2.75H:1.0V
Max Fill Slope RHS 3.25H:1.0V
Granular Fill
Soil waste disposal site B8 on LHS.
1006+210 1006+780
Fill up to 25 m on right side
of highway.
Fill up to 15 m on left side
of highway
Left Slope - 2H:1V to 4H:1V
Right Slope – 3H:1V
Part of Early Works
Left of Highway
TH19-LX-224,
TH19-LX-225,
TH19-LX-228,
TH18-LX-033,
CPT19-LX-222,
CPT19-LX-223,
CPT19-LX-227.
Upper 0.1 m to 0.3 m: Topsoil
Below topsoil: 3.6 m to 12.8 clay over bedrock. Test hole TH19-LX-224
encountered sand below the clay. Test hole TH18-LX-033 encountered 1.5 m
of silty sand at ground surface.
Shale Bedrock: encountered in all test holes at depths ranging from 3.8 m
to 15.2 m.
Bedrock depths were as follows:
- TH19-LX-224 (15.2 m – Elev. 450.4 m);
- TH19-LX-225 (13.1 m – Elev. 451.4 m);
- TH18-LX-033 (11.6 m – Elev. 446.5 m); and
- TH19-LX-228 (3.8 m – Elev. 449.4 m).
Groundwater: not encountered.
Stripping RHS 0.1 m (If organic soil or organic debris is identified during construction
review, sub-excavation of organic soil or organic debris will be required).
Stripping LHS 0.3 m
Max Fill Slope LHS 2.0H:1.0V (LHS fill slope assumes fill (waste) placed against toe of
slope up to 465 m elevation. Soil waste disposal site B9).
Max Fill Slope RHS to be confirmed after in-river platform built and additional
investigation carried out
Granular Fill
Existing slide (not remediated) between Sta. 1006+380 and 1006+460 on RHS slope.
Potential sub-excavation for settlement objectives; however, sub-excavation not
required for stability objective.
Left of Hwy 29 alignment there are three separate but coalesced/overlapping alluvial
fans. The alignment is shifted away from the fans and is higher than the current
highway. Qualitatively, the risk from debris flow/flood events appears to be less for
the alignment that the existing highway. Three culverts are proposed, one culvert is
2.7 m in diameter with 10 upstream check dams.
Under Existing
Highway 29
TH19-LX-226,
TH18-LX-037,
PV18-LX-034.
Upper 0.1 m: Asphalt pavement.
Below Asphalt: 1.3 m to 1.5 m gravel fill.
Below Fill: Generally, silt and clay, with a gravel layer at 8.3 m to 12.4 m in
TH19-LX-226, and a sand layer at 10.5 m to 13.4 m in TH18-LX-037.
Shale Bedrock: was encountered in two test holes as follows:
- TH19-LX-226 (12.4 m – Elev. 445.4 m); and
- TH18-LX-037 (13.4 m – Elev. 444.8 m).
Groundwater: not encountered.
Existing fill below highway is anticipated to be variable in composition and
density.
Slope to the
Right of Existing
Highway 29
TH18-LX-030,
TH18-LX-034,
TPH18-LX-050.
Upper 0.1 m: Topsoil
Below Topsoil: 0.6 m to 3.8 m of silt and clay.
Below Silt and Clay: 0.9 m to 4.7 m of sand and gravel, with varying silt
content over shale bedrock.
Shale Bedrock: was encountered in three test holes as follows:
- TH18-LX-030 (4.0 m – Elev. 452.0 m);
- TH18-LX-034 (8.5 m – Elev. 444.2 m); and
- TPH18-LX-050 (2.0 m – Elev. 443.7 m).
Groundwater: encountered at 0.6 m in test hole TPH18-LX-050.
Slide between 1006+380 and 1006+460 (not remediated).
Fill may have been side cast over the RHS.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 44
Station Range Reference Geometric
Design
Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations
From To
Near Peace River
TH18-LX-031,
TPH18-LX-048,
TH18-LX-035,
TH18-LX-038.
Upper 0.1 m: Topsoil
Below Topsoil: 1.1 m to 2.3 m of sand and gravel, with varying silt content
over shale bedrock.
Shale Bedrock: encountered in all test holes at depths ranging from 1.1 m
to 2.6 m.
Bedrock depths were as follows:
- TH18-LX-031 (1.1 m – Elev. 445.1 m);
- TPH18-LX-048 (2.6 m – Elev. 444.3 m);
- TH18-LX-035 (2.3 m – Elev. 443.5 m); and
- TH18-LX-038 (1.3 m – Elev. 445.5 m).
Groundwater: encountered in all test holes at depths ranging between 0.6 m
and 0.8 m.
1006+780 1006+860
Fill up to 8 m on left side of
highway.
Fill up to 25 m on right side
of highway.
Left Slope – 2H:1V to 4H:1V
Right Slope – 3H:1V
Part of Early Works
Under existing
Highway 29
TH18-LX-039.
Upper 0.1 m: Asphalt pavement.
Below Asphalt: 2.1 m gravel fill.
Below Fill: 2.0 m of gravel over silt and clay.
Shale Bedrock: encountered at 13 m (Elev. 448.0 m) in test hole TH18-LX-
039.
Groundwater not encountered.
Existing fill below highway is anticipated to be variable in composition and
density.
Stripping 0.3 m (If organic soil or organic debris is identified during construction
review, sub-excavation of organic soil or organic debris will be required).
Max Fill Slope LHS 2.0H:1.0V (LHS fill slope assumes fill (waste) placed against toe of
slope up to 465 m elevation. Soil waste disposal site B9). Max Fill Slope RHS to be
confirmed after in-river platform built and additional investigation carried out.
Granular Fill
Existing slide (historically remediated) between Sta. 1006+780 and 1006+900 on RHS
slope. Potential sub-excavation for settlement objectives; however, sub-excavation
not required for stability objective.
Slope to the
Right of Existing
Highway 29
TH18-LX-101,
TH18-LX-102.
Upper 0.03 m: Topsoil
Below Topsoil: generally sand and gravel interbedded with silt and clay over
bedrock.
Shale Bedrock: was encountered in two test holes as follows:
- TH18-LX-101 (9.8 m – Elev. 444.6 m); and
- TH18-LX-102 (8.5 m – Elev. 444.6 m).
Groundwater: not encountered.
Fill may have been side cast over the RHS.
Fill above Peace
River
TH18-LX-103
Upper 6.2 m: gravel over shale bedrock.
Shale Bedrock: was encountered at 6.2 m (Elev. 444.4) in test hole TH18-LX-
103.
Groundwater: not encountered.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 45
Station Range Reference Geometric
Design
Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations
From To
1006+860 1007+030
Fill on right side of highway.
Left Slope – 2H:1V to 4H:1V
Right Slope – 3H:1V
Part of Early Works
Under existing
Highway 29
TH18-LX-041,
TH18-LX-105.
Upper 0.1 m: Asphalt pavement.
Below Asphalt: 1.1 m to 1.4 m sand and gravel fill.
Below Fill: generally, silt and clay interbedded with sand and gravel over
bedrock.
Shale Bedrock: was encountered in two test holes as follows:
- TH18-LX-041 (12.8 m – Elev. 452.5 m); and
- TH18-LX-105 (9.9 m – Elev. 458.1 m).
Groundwater: not encountered.
Existing fill below highway is anticipated to be variable in composition and
density.
Stripping 0.3 m (If organic soil or organic debris is identified during construction
review, sub-excavation of organic soil or organic debris will be required).
Max Fill Slope LHS 2.0H:1.0V
Max Fill Slope RHS fill slope to be confirmed after in-river platform built and
additional investigation carried out.
Granular Fill
Existing slide (historically remediated) between Sta. 1006+780 and 1006+900 on RHS
slope. Potential sub-excavation for settlement objectives; however, sub-excavation
not required for stability objective.
Existing slide (not remediated and recently active) between Sta. 1006+900 and
1007+030 on RHS slope. Potential sub-excavation for settlement objectives; however,
sub-excavation not required for stability objective.
Slope to the
Right of Existing
Highway 29
TH18-LX-104.
Upper 0.03 m: Topsoil
Below Topsoil: 5.8 m of clay over 0.9 m of gravel.
Shale Bedrock: was encountered at 6.7 m (Elev. 445.5 m) in test hole TH18-
LX-104.
Groundwater: not encountered.
Fill may have been side cast over the RHS.
Existing slide (historically remediated) between Sta. 1006+780 and
1006+900
Existing slide (not remediated and recently active) between Sta. 1006+900
and 1007+030
Near Peace River
TH18-LX-042.
Upper 0.2 m: clay.
Below Clay: 1.4 of gravel over shale bedrock.
Shale Bedrock: was encountered at 1.6 m (Elev. 443.9 m) in test hole TH18-
LX-042.
Groundwater: not encountered.
1007+030 1007+070
Culvert crossing and debris
fan. Large Fill up to 28 m
into the river.
3H1:1V Fill Slopes.
Part of Early Works
Under existing
Highway 29
TH18-LX-044.
Upper 0.1 m: Asphalt pavement.
Below Asphalt: 10.7 m sand and gravel fill.
Below fill: 7.6 m of silty sand and, sand and gravel over shale bedrock.
Shale Bedrock: was encountered at 18.3 m (Elev. 453.7 m) in test hole TH18-
LX-044.
Groundwater: not encountered.
Existing fill below highway is anticipated to be variable in composition and
density.
Stripping 0.3 m (If organic soil or organic debris is identified during construction
review, sub-excavation of organic soil or organic debris will be required).
Max Fill Slope LHS 2.0H:1.0V
Max Fill Slope RHS to be confirmed after in-river platform built and additional
investigation carried out.
Granular Fill
Highway 29 alignment crosses a well-known debris flow and flood area near Sta.
1007+060. Events that plug/damage existing culvert and/or overtop current highway
occur approximately every 5 years. A 2.4 m diameter culvert with upstream check
dams is proposed.
Fill above Peace
River
TP19-LX-229,
TPH18-LX-052.
Upper 5.2 m: gravel and sand over shale bedrock.
Shale Bedrock: was encountered at 5.2 m (Elev. 441.1 m) in test hole TPH18-
LX-052.
Groundwater: not encountered.
Fill may have been side cast over the RHS. Variable colluvium deposit from
various debris flow events.
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 12 June 2020 Page 46
Station Range Reference Geometric
Design
Configuration
Representative
Geotechnical
Investigation
Anticipated Subsurface Conditions Geotechnical Recommendations
From To
1007+070 1007+280
Large Fill up to 28 m into
the river, transitions to
reservoir shoreline
protection berm.
3H1:1V Fill Slopes.
Part of Early Works
TH18-LX-045
Upper 0.1 m: sand fill.
Below Fill: silty sand interbedded with clay over shale bedrock.
Shale Bedrock: was encountered at 4.0 m (Elev. 441.5 m) in test hole TH18-
LX-045.
Groundwater: not encountered.
Stripping 0.3 m (If organic soil or organic debris is identified during construction
review, sub-excavation of organic soil or organic debris will be required).
Max Fill Slope LHS 2.0H:1.0V
Max Fill Slope RHS to be confirmed after in-river platform built and additional
investigation carried out.
Granular Fill
Geotechnical Assessment and Design
Lynx Creek East Segment
Project # KX052807.11 | 20 May 2020 Page 48
References
AMEC Environment & Infrastructure (05 March 2012). Report. Preliminary Geotechnical Assessment,
Proposed Lynx Creek Segment, Highway 29 Definition Design, Site C Clean Energy Project.
Submitted to R.F. Binnie & Associates Ltd.
BCMoTI (2016) 2016 Standard Specifications for Highway Construction. Adopted July 1, 2016
BGC Engineering Inc. (30 November 2012). Report. Site C Clean Energy Project, Preliminary Reservoir
Impact Lines. Submitted to BC Hydro.
Bidwell, A.K. (May 1999).The Engineering Geology of the Fort St. John Area. Master of Engineering Report,
University of Alberta.
Binnie & Associates Ltd. (June 2020). Highway No. 29, Lynx Creek, Suggested Construction Staging,
Drawings R3-336-1200 to -1206.
Bowles, J.E. (1996). Foundation Analysis and Design, Fifth Edition. McGraw-Hill International Editions
GEO-SLOPE International Ltd., Computer Program, GeoStudio 2016, version 8.16.5.15361.
Hartman, G.M.D. and Clague, J.J. (25 June 2008). Quaternary Stratigraphy and Glacial History of the Peace
River Valley, Northeast British Columbia. Canadian Journal of Earth Science, Volume 45, pages
549-564.
Lunne, T., Robertson, P.K., Powell, J.J.M (1997) Cone Penetration Testing in Geotechnical Practice. Spon
Press.
Stott, D.F. (1982). Lower Cretaceous Fort St. John Group and Upper Cretaceous Dunvegan Formation of the
Foothills and Plains of Alberta, British Columbia, District of Mackenzie and Yukon Territory.
Geological Survey of Canada, Bulletin 328.
Stark, T.D., Eid, H.T. (1994). Drained Residual Strength of Cohesive Soils. Journal of Geotechnical
Engineering, Vol. 120, No. 5.
Wood Environment & Infrastructure Solutions (04 November 2019a). Memorandum. Highway 29 – Lynx
Creek East – Relative Debris Flow Risk. Submitted to R.F. Binnie & Associates Ltd.
Wood Environment & Infrastructure Solutions (06 November 2019b). Memorandum. Highway No. 29, Lynx
Creek East, Preliminary Stability Assessment of Farrell Creek Road Slide and In-Stream Reservoir
Shoreline Stability Berm. Submitted to R.F. Binnie & Associates Ltd.
Wood Environment & Infrastructure Solutions (6 November 2019c). Geotechnical Data Report, Lynx Creek
East Segment. Submitted to R.F. Binnie & Associates Ltd.
Wood Environment & Infrastructure Solutions (16 March 2020). Geotechnical Data Report, Lynx Creek West
Segment. Submitted to R.F. Binnie & Associates Ltd.
Appendix A
Figures 1 to 4
Geotechnical Investigation
Figure 5
Shear Key Sta. 1005+940
L1000-LINEDesign
Alignment
Hwy 29
P e a c eR i v e r
L y n x
C r e e k
D r yC r e e k
F a r r e l l
Cre
ek
LynxCreekWest
LynxCreekEast
Notes:1. L1000-LINE centreline alignment provided by R.F. Binnie & Associates Ltd. CAD file '20200417 - Lynx Creek 100DD - UTM.dwg', received 17 April 2020.2. Image provided by Bing Maps Road - © 2019 Microsoft Corporation © 2018 HERE
LegendL1000-LINE Centreline Alignment
Borrow Investigation Area
!(
!(
!(
!(
!(
_̂
VancouverKamloops
ChetwyndFort St John
PrinceGeorge
ProjectLocation
This drawing was originally produced in colour.
CLIENT:
S:\Internal\KX052807-GIS\1-LynxCreek\LCE-AlignGeotechInv-DetDes-Fig1-SiteLocPlan.mxd
SCALE:
PROJECTION:
DATUM:
CHK'D BY:
DWN BY: TITLE:
PROJECT:REV NO.:
PROJECT NO.:
DATE:
HIGHWAY NO. 29LYNX CREEK EASTUTM Zone 10
NAD 83
EM
BB SITE LOCATION PLANGEOTECHNICAL INVESTIGATION
A
FIGURE 1
KX052807.11
JUNE 2020
$
1:150,000
0 2 4 6 81km
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
WoodEnvironment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
BC HYDRO c/o R.F. BINNIE &ASSOCIATES LTD.
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
a Division of Wood Canada Limited (Wood)Wood Environment & Infrastructure Solutions
1004+4001004+600
1004+8001005+000
1005+200 1005+400 1005+600 1005+800 1006+000 1006+200 1006+400 1006+600
1004+330.000
!A
!A
!A !A
")
")
#*
#*
#*
#*#* #*
#*
#* #* #*
#*
#*
#*
#*#* #*
#* #*
")
")
")
")
")
")")
")
")
")
")")
!A
!A
!A!A
!A
!A
!A
!A
!A!A
!A
!A
!A
!A!A
!A
!A
!A
!A
!A
!A
!A
!A
!A !A!A
!A
")
")
")
")
")
")
")
")")
")
")
")!A
!A
!A
!A!A
!A
!A
#*
#*
#*
#*
#*
#*
#* #*
#*
#*
#*
!A !A!A
!A !A
!A
!A!A
!A
!A
!A
!A
!A!A !A
!A
!ALynxCreekEast
LynxCreekWest
Highway 29
P e a c eR i v e r
TH19-LX-201TH19-LX-203
TH19-LX-205
TH19-LX-207 TH19-LX-208
TH19-LX-209
TH19-LX-210TH19-LX-212
TH19-LX-213TH19-LX-216
TH19-LX-217
TH19-LX-218
TH19-LX-220CPT19-LX-202
CPT19-LX-204CPT19-LX-206 CPT19-LX-211
CPT19-LX-214
CPT19-LX-215
CPT19-LX-219
CPT19-LX-221
CPT19-LX-222
CPT19-LX-223
TH19-LX-224 TH19-LX-225
TH19-LX-226
TH19-LX-228CPT19-LX-227
TH18-LX-017
TH18-LX-018
TH18-LX-019TH18-LX-020
TH18-LX-021
TH18-LX-022
TH18-LX-023 TH18-LX-024
TH18-LX-025
TH18-LX-026
TH18-LX-027
TH18-LX-028TH18-LX-029
TPH18-LX-045
TPH18-LX-046
TPH18-LX-047
TPH18-LX-049
CPT18-LX-018CPT18-LX-007CPT18-LX-008
CPT18-LX-009
CPT18-LX-010
CPT18-LX-011CPT18-LX-012
CPT18-LX-013
CPT18-LX-014
CPT18-LX-015
CPT18-LX-016
CPT18-LX-017
CPT18-LX-019
CPT18-LX-020CPT18-LX-021 CPT18-LX-022
CPT18-LX-023CPT18-LX-024
TP18-LX-056TP18-LX-034
TP18-LX-035
TP18-LX-036
TP18-LX-037
TP18-LX-038TP18-LX-039
TP18-LX-040
TP18-LX-041 TP18-LX-042
TP18-LX-043
TP18-LX-044
PV18-LX-025
PV18-LX-026
PV18-LX-027
PV18-LX-028
PV18-LX-029
PV18-LX-030 PV18-LX-031
PV18-LX-032
PV18-LX-033
PV18-LX-034 TH18-LX-030TH18-LX-031
TH18-LX-033
TH18-LX-034
TH18-LX-035 TH18-LX-038TPH18-LX-048TPH18-LX-050
PV18-LX-035 PV18-LX-036
TH81-18
PDH78-1
TH81-17
TP18-LX-032
TP18-LX-033
PROJECTION:
DATUM:
CHK'D BY:
DWN BY:
This drawing was originally produced in colour.
CLIENT: DATE:
KX052807.11
JUNE 2020
A
SITE PLAN WITH ORTHOPHOTOGEOTECHNICAL INVESTIGATION
HIGHWAY NO. 29LYNX CREEK EAST FIGURE 2
TITLE:
PROJECT:
UTM Zone 10
NAD 83
EM
BBPROJECT NO.:
REV NO.:
1 of 2SHEET NO.1:5,000S:\Internal\KX052807-GIS\1-LynxCreek\LCE-AlignGeotechInv-DetDes-Fig2-SitePlan-Ortho.mxd
MAIN VIEW SCALE:
0 100 200 300 40050m
Notes:1. L1000-LINE centreline alignment, slope stake lines, disposal sites, approximate extent of early works and supporting linework provided by R.F. Binnie & Associates Ltd. CAD file '20200417 - Lynx Creek 100DD - UTM.dwg', received 17 April 2020.2. Maximum Normal Reservoir Level (461.8 m) downloaded from BC Hydro SharePoint 11 April 2018.3. Orthophoto imagery (foreground) provided by BC Hydro 9 January 2018.4. Orthophoto imagery (background; 2009) provided by R.F. Binnie & Associates Ltd., received 1 June 2011.
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.Legend
!A 2019 Alignment Test Hole Location
") 2019 Alignment Test Pit Location
#* 2019 Alignment CPT Location
!A 2018 Alignment Test Hole Location") 2018 Alignment Test Pit Location#* 2018 CPT Location
") 2018 Pavement Core Location!A Historical Drillhole Location
Maximum Normal Reservoir Level(461.8 m)
L1000-LINE Centreline AlignmentL2-LINE Centreline AlignmentSlope Stake LineCulvertDisposal SiteApproximate Extent of Early Works
$
21
1:75,000
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
a Division of Wood Canada Limited (Wood)Wood Environment & Infrastructure Solutions
1006+000 1006+200 1006+400 1006+600 1006+800 1007+0001007+200
LIMIT
OFCO
NSTR
UCTIO
N10
07+2
80.00
0
!A
!A
!A
!A!A!A
!A
!A!A
!A
!A
!A
!A
!A
!A
!A
!A
#*#* #*
#* #*
")
")
")
")")
!A
!A
!A!A
!A
!A
!A
!A!A
!A
!A
!A
!A
!A
!A
!A
!A!A
!A
!A !A!A
!A
!A
")
!A
!A
!A
!A!A
!A
!A
#*
#*
#* #*
#*
#*
#*
!A
!A
!A
!A
!A
!A!A !A
!A
!A
")
TP05-01BH06-01A
Highway 29P e a c e R i v e r
TH19-LX-212
TH19-LX-213TH19-LX-216
TH19-LX-217
TH19-LX-218
TH19-LX-220
CPT19-LX-214
CPT19-LX-215
CPT19-LX-219
CPT19-LX-221
CPT19-LX-222
CPT19-LX-223
TH19-LX-224 TH19-LX-225
TH19-LX-226
TH19-LX-228
TP19-LX-229
CPT19-LX-227
TH18-LX-024
TH18-LX-025
TH18-LX-026
TH18-LX-027
TH18-LX-028TH18-LX-029
TPH18-LX-045
TPH18-LX-046
TPH18-LX-047
TPH18-LX-049CPT18-LX-023
CPT18-LX-024TP18-LX-044
PV18-LX-033
PV18-LX-034 TH18-LX-030TH18-LX-031
TH18-LX-033
TH18-LX-034
TH18-LX-035
TH18-LX-037
TH18-LX-038
TH18-LX-039 TH18-LX-041
TH18-LX-042TH18-LX-044
TH18-LX-045
TH18-LX-101TH18-LX-102
TH18-LX-103 TH18-LX-104 TH18-LX-105TPH18-LX-048TPH18-LX-050
TPH18-LX-052
PV18-LX-035 PV18-LX-036
TH81-18
PDH78-1
TP05-02
BH06-01BH06-02
PV05-01
TH96-01
TH96-02TP96-01
TP96-03
TH81-17
TH80-02
TH79-1
TH79-2DH11-41
PROJECTION:
DATUM:
CHK'D BY:
DWN BY:
This drawing was originally produced in colour.
CLIENT: DATE:
KX052807.11
JUNE 2020
A
SITE PLAN WITH ORTHOPHOTOGEOTECHNICAL INVESTIGATION
HIGHWAY NO. 29LYNX CREEK EAST FIGURE 2
TITLE:
PROJECT:
UTM Zone 10
NAD 83
EM
BBPROJECT NO.:
REV NO.:
2 of 2SHEET NO.1:5,000S:\Internal\KX052807-GIS\1-LynxCreek\LCE-AlignGeotechInv-DetDes-Fig2-SitePlan-Ortho.mxd
MAIN VIEW SCALE:
0 100 200 300 40050m
Notes:1. L1000-LINE centreline alignment, slope stake lines, disposal sites, approximate extent of early works and supporting linework provided by R.F. Binnie & Associates Ltd. CAD file '20200417 - Lynx Creek 100DD - UTM.dwg', received 17 April 2020.2. Maximum Normal Reservoir Level (461.8 m) downloaded from BC Hydro SharePoint 11 April 2018.3. Orthophoto imagery (foreground) provided by BC Hydro 9 January 2018.4. Orthophoto imagery (background; 2009) provided by R.F. Binnie & Associates Ltd., received 1 June 2011.
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.Legend
!A 2019 Alignment Test Hole Location
") 2019 Alignment Test Pit Location
#* 2019 Alignment CPT Location
!A 2018 Alignment Test Hole Location") 2018 Alignment Test Pit Location#* 2018 CPT Location
") 2018 Pavement Core Location!A Historical Drillhole Location
Maximum Normal Reservoir Level(461.8 m)
L1000-LINE Centreline AlignmentL2-LINE Centreline AlignmentSlope Stake LineCulvertDisposal SiteApproximate Extent of Early Works
$
21
1:75,000
1004+300
470 470
Elevation (m
)
Station (m)
Elevation (m
)
460 460
1004+400 1004+500 1004+600 1004+700 1004+800 1004+900
480 480
490 490
ST
A 1004+
330.000
61.5
m -
900
mm
Ø C
SP
2.0
WT
@ 1
.37%
25.0
m -
240
0mm
Ø C
SP
3.5
WT
@ 3
.33%
LYNX
CREEK
WEST
LYNX
CREEK
EAST
TS
GP-GCML
END
0.1
2.42.7
5
m
TP18-LX-039TS
ML
END
0.11.5
4.9
914
23
18
m
TP18-LX-041WW
SC3
GM2
9177
28
18
21
26
40
WW PL LL
2000010000 250125
qt(kPa) fs
(kPa)
CPT18-LX-009
Refusal
5
TS
CL
END
0.2
4.45
28
3130
3124
m
TP18-LX-034WW
TS
CL
ENDWater Level6/23/2018
0.2
3.85
28
32
3024
24
22 44
m
TP18-LX-035WW PL LL TS
CL
CHENDWater Level
6/24/2018
0.2
4.25
26
31
32
3030
23
22
22
39
45
51
m
TP18-LX-036WW PL LL
TS
CL
END
0.1
5.2
22
29
30
2928
22
20
23
40
34
47
m
TP18-LX-037WW PL LL
TS
CL
END
0.1
5
151714242323292529
21
21
21
33
41
34
m
TP18-LX-038WW PL LL
SM4 SM4
MH
SPBR
2.33.1
6.1
7.67.99.2
448
13447
7
65
R
1214137
292930
23
87
12
m
TH18-LX-017N WW
SM4
GM2
SM3
END
BR0.1
1.82 END
84
m
TP18-LX-032WW
GM3
TS
N/A
PROJECTION:
N/A
DATUM:
PROFILE – L1000-LINE ALIGNMENT
STATION 1004+300 TO 104+950
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
AS NOTED
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 1 of 5
Notes:
1. Hole elevation taken from LIDAR provided by BC Hydro 9 January 2018.
2. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
3. L1000-LINE centreline alignment profile and existing ground profile at centreline provided by R.F. Binnie
& Associates Ltd. CAD file '20200608 ACAD-200PR_LYNX.dwg', received 8 June 2020.
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Legend
L1000-LINE Centreline Alignment Profile
Existing Ground Profile at Centreline
Maximum Normal Reservoir Level (461.8 m)
470
Elevation (m
)
Station (m)
460
1005+000 1005+100 1005+200 1005+300
480
470
Elevation (m
)
460
1005+400 1005+500 1005+600
450
480
450
42.5m
- 1200m
m Ø
C
SP
2.8 W
T @
2.65%
60.5
m -
120
0mm
Ø C
SP
2.8
WT
@ 0
.80% 35
.0m
- 2
000m
m Ø
CS
P2.
8 W
T @
4.7
7%
MNRL
Cross Section
Station 1005+340
See Figure 4 Sheet 1
qt(kPa) fs
(kPa)
CPT18-LX-010
Refusal
5
qt(kPa) fs
(kPa)
CPT18-LX-011
Refusal
5
qt(kPa) fs
(kPa)
CPT18-LX-012
Refusal
2
4
2000010000 250125
2000010000 250125
2000010000 250125CL
ML
0.2
5.36.17.6
10.6END
6558
12182311
R
442530282635282723
10
1921
3041
0.83 / 3.03
0.54 / 1.6
m
TH18-LX-019N WW PL LL Is50
Dia/Axial
qt(kPa) fs
(kPa)
CPT19-LX-206
Refusal
5
2000010000 250125
(MPa)
BR
SM2
TS
TS
CL
BR
0.2
3.84.65.56.7 END
1043123622R
R
303730293232199
229
10
2424
26
4040
50
m
TH19-LX-201N WW PL LL
TS
CL
BR
0.1
3.14.3 END
46556RR
26212526253011
24
2629
45
4955
m
TH19-LX-203N WW PL LL
TS
CL
BR
0.6
16.817.8 END
334875
6
7
7
7
9
5
6
R
R
2114141615
23
1827
17
21
25
30
23
20
17
18
30
33
27
m
TH19-LX-208N WW PL LL
SM3SM2
N/A
PROJECTION:
N/A
DATUM:
PROFILE – L1000-LINE ALIGNMENT
STATION 104+950 TO 105+600
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
AS NOTED
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 2 of 5
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Legend
L1000-LINE Centreline Alignment Profile
Existing Ground Profile at Centreline
Maximum Normal Reservoir Level (461.8 m)
Notes:
1. Hole elevation taken from LIDAR provided by BC Hydro 9 January 2018.
2. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
3. L1000-LINE centreline alignment profile and existing ground profile at centreline provided by R.F. Binnie
& Associates Ltd. CAD file '20200608 ACAD-200PR_LYNX.dwg', received 8 June 2020.
470
Elevation (m
)
460
1005+600 1005+700 1005+800 1005+900 1006+000
450
480
470
Station (m)
Elevation (m
)
460
1006+000 1006+100 1006+200
450
480
40.5
m -
160
0mm
Ø C
SP
2.8
WT
@ 2
.00%
44.5
m -
120
0mm
Ø C
SP
2.8
WT
@ 1
.51%
Cross Section
Station 1005+660
See Figure 4 Sheet 2
Cross Section
Station 1005+840
See Figure 4 Sheet 3
MNRL
Cross Section
Station 1005+940
See Figure 4 Sheet 4
TSML
CL
BR
0.21.42.1
12.313.2
Water Level4/29/2019
461161078
8
5
6
5
RR
30
7119715
12
27
30
32
211917
16
18
26
33
m
TH19-LX-210N WW PL LL
TS
CL
BR
0.6
7.88.6
534111087
8
RR
1822181013122522
26
2621
16
17
17
28
32
31
m
TH19-LX-212N WW PL LL
TS
CL
SM4
CL
BR
0.6
4.9
6.7
13.914.9
5812
71814
32
14
12
12
4
R
R
232421
23182114
13
25
17
9
20
25
18
15
15
33
29
18
m
TH19-LX-217N WW PL LL
Refusal
qt(kPa) fs
(kPa)
CPT19-LX-214
5
10
2000010000 250125
qt(kPa) fs
(kPa)
CPT19-LX-219
Refusal
5
qt(kPa) fs
(kPa)
CPT19-LX-221
Refusal
5
qt(kPa) fs
(kPa)
CPT19-LX-223
Refusal
5
2000010000 250125
2000010000 250125
2000010000 250125
SM2
ENDEND
END
N/A
PROJECTION:
N/A
DATUM:
PROFILE – L1000-LINE ALIGNMENT
STATION 1005+600 TO 1006+250
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
AS NOTED
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 3 of 5
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Legend
L1000-LINE Centreline Alignment Profile
Existing Ground Profile at Centreline
Maximum Normal Reservoir Level (461.8 m)
Notes:
1. Hole elevation taken from LIDAR provided by BC Hydro 9 January 2018.
2. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
3. L1000-LINE centreline alignment profile and existing ground profile at centreline provided by R.F. Binnie
& Associates Ltd. CAD file '20200608 ACAD-200PR_LYNX.dwg', received 8 June 2020.
470
Elevation (m
)
Station (m)
460
1006+300 1006+400 1006+500 1006+600
450
440
430
470
Elevation (m
)
460
1006+700 1006+800 1006+900
450
430
440
41.5
m -
120
0mm
ØC
SP
2.8
WT
@2.
53%
39.0
m -
900
mm
Ø C
SP
2.0
WT
@ 2
.00%
35.0
m -
900m
m Ø
CS
P 2
.0W
T @
2.00
%
30.0
m -
270
0mm
Ø C
SP
3.5
WT
@ 2
.00%
Highway 29
MNRL
Cross Section
Station 1006+420
See Figure 4 Sheet 5
Cross Section
Station 1006+900
See Figure 4 Sheet 6
ASPHGP-GM
CH
CL
GP-GC
0.11.6
8.3
18.5 END
2057105128
11
15
3
26292227272728182214
24
17
55
42
N/A / N/A
N/A / N/A
N/A / N/A
1.01 / 2.74
0.87 / 2.83
1.98 / 2.07
5.61 / 4.43
m
TH19-LX-226N WW PL LL Is50Is50
Dia/AxialTS
CH
SP
BR
0.1
3.14
19.7 END
56831535R
2016202119245
m
TH18-LX-030N WW
CLCHML
BR
1.22.3
3.8
7.28.5
21.1 END
816171764613
14
R
232026301826302012
28914
25
22
49
55
m
TH18-LX-034N WW PL LL
SM1
GM1TS
BR
0.61.3
12.4END
Water Level8/13/2018
m
TH18-LX-038
TS
CL
ML
BR
00.62.3
8.59.8
19.9
7796
16
7
16
2239
57RR
89
121714
14
17
1069
17 28
m
TH18-LX-101N WW PL LL
GP-GM
BR
3.8
6.2
10.8 END
1431
23RR121316
R
433
71210
15
m
TH18-LX-103
N WW
GM2
SM4
GM2GM2
END
VWP
(4/3/2019)
VWP
(4/3/2019)
1.14 / 2.420.66 / 2.77
4.97 / 5.11
5.15 / 5.24
4.55 / 4.14
5.14 / 6.60
0.67 / 2.19
0.15 / 3.74
1.35 / 2.04
1.92 / 3.72
Is50Is50Dia/Axial
(MPa)
0.10 / 2.28
4.76 / 3.87
1.47 / 3.89
4.19 / 5.85
4.58 / 4.09
5.85 / 5.05
5.92 / 4.73
1.09 / 1.09
Is50Dia/Axial
(MPa)
(MPa)
6.7
189R
92RR
91399
2.68 / 5.133.81 / 5.54
1.67 / 5.18
0.51 / 2.95
0.16 / 1.06
4.41 / 5.62
8.57 / 6.67
N WW Is50Is50Dia/Axial
(MPa)
4.26 / 2.834.83 / 6.80
3.85 / 3.88
2.43 / 4.20
1.67 / 3.43
1.56 / 5.05
2.54 / 2.01
Is50Is50Dia/Axial
(MPa)
0.93 / 5.61
2.10 / 6.92
6.88 / 6.58
Is50Is50Dia/Axial
(MPa)
12.4
BR
N/A
PROJECTION:
N/A
DATUM:
PROFILE – L1000-LINE ALIGNMENT
STATION 1006+250 TO 1006+900
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
AS NOTED
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 4 of 5
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Legend
L1000-LINE Centreline Alignment Profile
Existing Ground Profile at Centreline
Maximum Normal Reservoir Level (461.8 m)
Notes:
1. Hole elevation taken from LIDAR provided by BC Hydro 9 January 2018.
2. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
3. Not all instrumentation, groundwater levels, and slope inclinometer movement levels shown.
4. L1000-LINE centreline alignment profile and existing ground profile at centreline provided by R.F. Binnie
& Associates Ltd. CAD file '20200608 ACAD-200PR_LYNX.dwg', received 8 June 2020.
470
480
Elevation (m
)
Station (m)
460
1006+900 1007+000 1007+100 1007+200 1007+300
450
440
430
490
470
480
Elevation (m
)
460
450
430
490
1007+400 1007+500
500
440
500
30.0
m -
240
0mm
Ø C
SP
3.5
WT
@ 4
.00%
35.0
m -
900m
m Ø
CS
P 2
.0W
T @
2.00
%
LIM
IT O
F C
ON
ST
RU
CT
ION
ST
A 1
007+
280.
000
Cross Section
Station 1006+900
See Figure 4 Sheet 6
Highway 29
13
ASPHGP
CL
CL
BR
0.10.81.2
5.8
8.8
11.912.8
26.2 END
73634
1010
11
8
14
48R
R
31612211718
2214
15
19
14
15
15
19
38
37
28
m
TH18-LX-041N WW PL LL
ASPH
BR
0.1
3.8
7.6
10.7
15.8
18.3
24.4 END
24714979261312
10
11
R
12
14
16
15
37
R
R
225471211
6
9
11
12
12
12
13
14
8
7
m
TH18-LX-044N WW
1189
161821
19
15
7211311
m
TH18-LX-105N WW
FILLSP-SM
ML
ML
BR
0.11.52.3
5.6
9.9
30.9 END
536378656
9
20
213
GC4
SM4
GM1
SM2
GM1
SM4
SM2
SM2FILL
ASPH
N/A / N/A0.26 / 1.07
0.82 / 3.46N/A / N/A
3.84 / 5.39
3.36 / 5.99
5.48 / 3.80
1.81 / 3.88
3.28 / 5.29
6.67 / 6.45
Is50Dia/Axial
(MPa)
0.68 / 1.08
N/A / N/A
3.24 / 4.59
3.78 / 3.63
1.91 / 3.69
1.83 / 2.84
1.58 / 2.24
4.76 / 5.82
1.71 / 4.66
7.52 / 5.45
2.68 / 3.13
2.23 / 6.13
1.70 / 2.75
Is50Dia/Axial
(MPa)
2.48 / 4.68
2.47 / 3.66
1.17 / 3.74
Is50Is50Dia/Axial
(MPa)
N/A
PROJECTION:
N/A
DATUM:
PROFILE – L1000-LINE ALIGNMENT
STATION 1006+900 TO 1007+550
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
AS NOTED
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 3
SHEET NO. 5 of 5
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
0m 25 50 75 100
H 1 : 2000
V 1 : 400
0m 5 10 15 20
Legend
L1000-LINE Centreline Alignment Profile
Existing Ground Profile at Centreline
Notes:
1. Hole elevation taken from LIDAR provided by BC Hydro 9 January 2018.
2. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
3. L1000-LINE centreline alignment profile and existing ground profile at centreline provided by R.F. Binnie
& Associates Ltd. CAD file '20200608 ACAD-200PR_LYNX.dwg', received 8 June 2020.
4. Additional existing ground surface provided by R.F. Binnie & Associates Ltd. CAD file
'EXSURF-COG-17-0472.dwg', received 30 October 2019.
Maximum Normal Reservoir Level
(461.8 m)
-40 -20 0 20 40
Elevation (m
)
480
Offset (m)
460
60
440
Elevation (m
)
480
440
80
460
MNRL
℄L1000-LINE
TSCLBR
0.1
3.14.3 END
46556RR
26212526253011
242629
454955
m
TH19-LX-203N WW PL LL
qt(kPa)
R
fs(kPa)20000
CPT19-LX-204
10000 1000500
R
CPT19-LX-202
qt(kPa) fs
(kPa)1000
20000
2
50010000
24
4 R
qt(kPa)
CPT18-LX-013
fs(kPa)
2
25020000
10000 500
N/A
PROJECTION:
N/A
DATUM:
CROSS SECTION
1005+340
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
1:600
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 4
SHEET NO. 1 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. Typical cross section based on L1000-LINE centreline alignment and existing ground surface provided
by R.F. Binnie & Associates Ltd. CAD file 'ACAD-R3-336-L1000-1004+330 to 1006+000.dwg', received
3 June 2020.
Legend
Typical Cross Section Based on L1000-LINE Centreline Alignment
Existing Ground Surface
Maximum Normal Reservoir Level (461.8 m)
24181260m
1 : 600
-40 -20 0 20
Elevation (m
)
480
Offset (m)
460
440
Elevation (m
)
480
460
440
-60
℄L1000-LINE
TS
CL
GP-GM
CL
BR
0.6
3.84.5
18.719.9 END
45
2269
257
5
7
7
10
16
10
15
35141611203
13
15
20
26
23
20
20
19171613
17
18
28
41
m
TH19-LX-209N WW PL LL
TS ML
CL
BR
0.21.42.1
12.313.2
Water Level4/29/2019
46
116
107885
6
5RR
30
71197
1512
27
30
32211917
16
18
26
33
m
TH19-LX-210N WW PL LL
R
qt(kPa) fs
(kPa)
CPT19-LX-211
5
10
2000010000 1000500SM2
END
N/A
PROJECTION:
N/A
DATUM:
CROSS SECTION
1005+660
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
1:600
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 4
SHEET NO. 2 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. Typical cross section based on L1000-LINE centreline alignment and existing ground surface provided
by R.F. Binnie & Associates Ltd. CAD file 'ACAD-R3-336-L1000-1004+330 to 1006+000.dwg', received
3 June 2020.
Legend
Typical Cross Section Based on L1000-LINE Centreline Alignment
Existing Ground Surface
Maximum Normal Reservoir Level (461.8 m)
24181260m
1 : 600
-20 0 20 40
Elevation (m
)
480
Offset (m)
460
60
440
Elevation (m
)
480
460
440
-40 80
℄L1000-LINE
MNRL
TS
CL
SP-SMBR
0.6
13.714.616.3
73028111517222212
4
4
8
6RR
22131112131691012
19
19
18
16
19
15
14
13
42
24
20
23
m
TH19-LX-213N WW PL LL
R
qt(kPa) fs
(kPa)
CPT19-LX-214
5
20000
10
10000 250125
R
qt(kPa) fs
(kPa)
CPT18-LX-023
2000010000 500250
2
4
TS
CL0.1
4 END Water Level6/7/2018
1717
1020
16
2014
13
3526
m
25
TP18-LX-044WW PL LL
END
N/A
PROJECTION:
N/A
DATUM:
CROSS SECTION
1005+840
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
1:600
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 4
SHEET NO. 3 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. Typical cross section based on L1000-LINE centreline alignment and existing ground surface provided
by R.F. Binnie & Associates Ltd. CAD file 'ACAD-R3-336-L1000-1004+330 to 1006+000.dwg', received
3 June 2020.
Legend
Typical Cross Section Based on L1000-LINE Centreline Alignment
Existing Ground Surface
Maximum Normal Reservoir Level (461.8 m)
24181260m
1 : 600
-20 0 20 40
Elevation (m
)
480
Offset (m)
460
440
Elevation (m
)
480
460
440
-40
℄L1000-LINE
0.6
11.3
14.115.7
21.822.6
25.323.3
512
212418
14
18
18
23
19
10
20
22
27
1717
171515
16
10
20
14
19111313
14
1110
88
16
15
17
17 41
37
m
TH19-LX-216WW LL
TS
CL
CL
BR
TS
CL
SP-SM
SP-SMML
CLBR
17.1
18
18
11
15
13
18
22
23
14
16
36
N PL
0.6
6.74.9
13.914.9
581271814
14
32
12
12
4R
23
R
24
2321
182114
2513
17
9
2025
18
15
15
33
29
18
m
TH19-LX-217N WW LLPL
TS
CL
SP-SMMLBR
0.6
12.814.9
17
14
1014
10
7
R
26
1213
13
148
27
25
19
m N
END
SM3
SM4
11
5
9.8
9
20
21
9
R
1610
17
13
23
7
W
TH19-LX-218W
END
END
SM3
N/A
PROJECTION:
N/A
DATUM:
CROSS SECTION
1005+940
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
1:600
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 4
SHEET NO. 4 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. Typical cross section based on L1000-LINE centreline alignment and existing ground surface provided
by R.F. Binnie & Associates Ltd. CAD file 'ACAD-R3-336-L1000-1004+330 to 1006+000.dwg, received
3 June 2020.
Legend
Typical Cross Section Based on L1000-LINE Centreline Alignment
Existing Ground Surface
Maximum Normal Reservoir Level (461.8 m)
24181260m
1 : 600
-40 -20 0 20 40
Elevation (m
)
480
Offset (m)
460
60 80
440
Elevation (m
)
480
460
440
-60 100
P e a c e
R i v e r
Highway
29
L1000-LINE
MNRL
℄
TS
BR
13.1
END
CL
0.3
26.1
4810181115201215
18
18
3R
27261841251723211921232827242212
2223
2119
19
3640
3746
49
1.59 / 1.520.67 / 1.281.52 / 5.101.94 / 5.27
1.06 / 4.33
0.55 / 2.67
0.92 / 3.51
4.53 / 5.88
m
TH19-LX-225N WW PL LL Is50Is50
Dia/Axial
(MPa)
CH
CL
GP-GC
0.11.6
8.3
18.5
12.4
END
2057
105
128
1115
3
26292227272728182214
24
17
55
42
N/A / N/AN/A / N/AN/A / N/A
1.01 / 2.740.87 / 2.831.98 / 2.07
5.61 / 4.43
m
TH19-LX-226N WW PL LL Is50Is50
Dia/Axial
(MPa)
ASPH GP-GM
6.7
BR
N/A
PROJECTION:
N/A
DATUM:
CROSS SECTION
1006+420
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
1:600
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 4
SHEET NO. 5 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. Typical cross section based on L1000-LINE centreline alignment and existing ground surface provided
by R.F. Binnie & Associates Ltd. CAD file 'ACAD-R3-336-L1000-141-Model.dwg', received 20 May 2020.
Legend
Typical Cross Section Based on L1000-LINE Centreline Alignment
Existing Ground Surface
Maximum Normal Reservoir Level (461.8 m)
24181260m
1 : 600
-20 0 20 40
Elevation (m
)
480
Offset (m)
460
60 80
440
Elevation (m
)
480
460
440
-40
P e a c e
R i v e r
MNRL
Highway
29
℄L1000-LINE
TS
CL
GP-GC
BR
0
5.86.7
12.4END
1315242010122347R
11105
11129857
19 35
m
TH18-LX-104N WW PL LL
ASPHGP
CL
CL
BR
0.10.81.2
5.8
8.8
11.912.8
26.2END
73634101011
8
1448RR
316122117182214
15
1914
15
15
19
38
37
28
m
TH18-LX-041N WW PL LL
CH
BR
0.21.6
14 END
Water Level8/9/2018
8RRR
414
1012
m
TH18-LX-042N WW PL LL
GC4
SM4
GM1VWP (4/3/2019)
N/A / N/A0.26 / 1.070.82 / 3.46N/A / N/A3.84 / 5.393.36 / 5.995.48 / 3.801.81 / 3.88
3.28 / 5.29
6.67 / 6.45
Is50Is50Dia/Axial
(MPa)
N/A / N/AN/A / N/AN/A / N/AN/A / N/A2.39 / 5.854.5 / 4.84
Is50Is50Dia/Axial
(MPa)
2.42 / 3.626.15 / 5.711.19 / 1.740.10 / 3.40
1.29 / 3.26
1.38 / 4.43
0.94 / 2.48
9.30 / 6.40
Is50Is50Dia/Axial
(MPa)
N/A
PROJECTION:
N/A
DATUM:
CROSS SECTION
1006+900
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
1:600
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 4
SHEET NO. 6 of 6
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
Notes:
1. SPT N values and associated laboratory testing data provided with the Sticklogs may not be presented
at representative elevations. Please refer to Appendix B – Investigation Logs for additional details.
2. Not all instrumentation, groundwater levels, and slope inclinometer movement levels shown.
3. Typical cross section based on L1000-LINE centreline alignment and existing ground surface provided
by R.F. Binnie & Associates Ltd. CAD file 'ACAD-R3-336-L1000-176-Model.dwg', received 20 May 2020.
Legend
Typical Cross Section Based on L1000-LINE Centreline Alignment
Existing Ground Surface
Maximum Normal Reservoir Level (461.8 m)
24181260m
1 : 600
-20 0 20 40
Ele
va
tio
n (m
)
480
Offset (m)
460
440
Ele
va
tio
n (m
)
480
460
440
-40
℄L1000-LINE
2.5 m
1
1
1
1
1.0
2.5
Or To Suit
1.0
2.5
5.0 m
12.5 m
10°
25 Kg Riprap
Non-Woven Geotextile
N/A
PROJECTION:
N/A
DATUM:
SHEAR KEY - CONCEPT ONLY
1005+940
GEOTECHNICAL INVESTIGATION
PROJECT:
TITLE:
REV. NO.:
PROJECT NO.:
KX052807.11
A
CLIENT:
DWN BY:
CHK'D BY:
JUNE 2020
DATE:
SCALE:
EM
1:500
BB
HIGHWAY NO. 29
LYNX CREEK EAST
This drawing was originally produced in colour.
FIGURE 5
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited (Wood)
3456 Opie CrescentPrince George, BC, CANADA V2N 2P9Tel. (250) 564-3243 Fax (250) 562-7045
BC HYDRO c/o R.F. BINNIE & ASSOCIATES LTD.
Notes:
1. Typical cross section based on L1000-LINE centreline alignment and existing ground surface provided
by R.F. Binnie & Associates Ltd. CAD file 'ACAD-R3-336-L1000-1004+330 to 1006+000.dwg, received
3 June 2020.
Legend
Typical Cross Section Based on L1000-LINE Centreline Alignment
Existing Ground Surface
Maximum Normal Reservoir Level (461.8 m)
100m 5
1 : 500
2015
Appendix B
Figures 6 to 26
Slope Stability Analyses
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1004+440
LHS & RHS AT MNRL AND RAPID DRAWDOWN
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 6
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1004+440
LHS & RHS USING UNDRAINED STRENGTH
PARAMETERS
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 7
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1005+260
LHS & RHS AT MNRL
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 8
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1005+260
LHS & RHS AT RAPID DRAWDOWN
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 9
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1005+260
LHS & RHS AT USING UNDRAINED STRENGTH
PARAMETERS
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 10
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1005+600
LHS AT MNRL AND RAPID DRAWDOWN (UPPER) USING
UNDRAINED STRENGTH PARAMETERS (LOWER)
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 11
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1005+820
LHS & RHS AT MNRL
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 12
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1005+820
LHS & RHS AT RAPID DRAWDOWN
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 13
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1005+820
LHS & RHS USING UNDRAINED STRENGTH
PARAMETERS
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 14
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1005+940
LHS AT MNRL AND RAPID DRAWDOWN
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 15
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1005+940
LHS AT MNRL USING UNDRAINED STRENGTH
PARAMETERS
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 16
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1006+200
LHS & RHS AT MNRL
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 17
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1006+200
LHS & RHS AT RAPID DRAWDOWN
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 18
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1006+200
LHS & RHS USING UNDRAINED STRENGTH
PARAMETERS
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 19
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1006+520
LHS & RHS AT MNRL
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 20
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1006+520
LHS & RHS AT RAPID DRAWDOWN
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 21
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1006+520
LHS & RHS USING UNDRAINED STRENGTH
PARAMETERS
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 22
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1007+000
RHS AT MNRL AND RAPID DRAWDOWN
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 23
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1007+000
RHS AT MNRL USING UNDRAINED STRENGTH
PARAMETERS
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 24
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1007+060
RHS AT MNRL AND RAPID DRAWDOWN
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 25
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
EM/LD JUNE 2020
NP KX052807.11
N/A A
N/A
AS SHOWN
SLOPE STABILITY ANALYSES
STA. 1007+060
RHS USING UNDRAINED STRENGTH PARAMETERS
HIGHWAY 29, BC
LYNX CREEK EAST SEGMENT
GEOTECHNICAL ASSESSMENT AND DESIGN FIGURE 26
R.F. BINNIE & ASSOCIATES LTD.
Wood Environment & Infrastructure Solutionsa Division of Wood Canada Limited (Wood)
3456 Opie Crescent
Prince George, BC, Canada V2N 2P9
Tel. (250) 564-3243 Fax (250) 562-7045
CLIENT DWN BY:
CHK'D BY:
PROJECTION:
DATUM:
SCALE:
PROJECT
DATE:
PROJECT NO:
REV. NO.:
FIGURE NO:
CHK'D BY:
TITLE
Limitations
Project # KX052807.11 | 12 June 2020 Limitations
Limitations
1. The work performed in the preparation of this report and the conclusions presented are subject
to the following:
a. The Standard Terms and Conditions which form a part of our Professional Services
Contract;
b. The Scope of Services;
c. Time and Budgetary limitations as described in our Contract; and
d. The Limitations stated herein.
2. No other warranties or representations, either expressed or implied, are made as to the
professional services provided under the terms of our Contract, or the conclusions presented.
3. The conclusions presented in this report were based, in part, on visual observations of the Site
and attendant structures. Our conclusions cannot and are not extended to include those portions
of the Site or structures, which are not reasonably available, in Wood’s opinion, for direct
observation.
4. Where testing was performed, it was carried out in accordance with the terms of our contract
providing for testing. Other substances, or different quantities of substances testing for, may be
present on-site and may be revealed by different or other testing not provided for in our contract.
5. The utilization of Wood’s services during the implementation of any remedial measures will allow
Wood to observe compliance with the conclusions and recommendations contained in the report.
Wood’s involvement will also allow for changes to be made as necessary to suit field conditions as
they are encountered.
6. This report is for the sole use of the party to whom it is addressed unless expressly stated
otherwise in the report or contract. Any use which any third party makes of the report, in whole or
the part, or any reliance thereon or decisions made based on any information or conclusions in
the report is the sole responsibility of such third party. Wood accepts no responsibility whatsoever
for damages or loss of any nature or kind suffered by any such third party as a result of actions
taken or not taken or decisions made in reliance on the report or anything set out therein.
7. This report is not to be given over to any third party for any purpose whatsoever without the
written permission of Wood.
8. Provided that the report is still reliable, and less than 12 months old, Wood will issue a third-party
reliance letter to parties that the client identifies in writing, upon payment of the then current fee
for such letters. All third parties relying on Wood’s report, by such reliance agree to be bound by
our proposal and Wood’s standard reliance letter. Wood’s standard reliance letter indicates that in
no event shall Wood be liable for any damages, howsoever arising, relating to third-party reliance
on Wood’s report. No reliance by any party is permitted without such agreement.