Date post: | 04-Apr-2018 |
Category: |
Documents |
Upload: | nguyenkhue |
View: | 218 times |
Download: | 2 times |
Proceedings of Indian Geotechnical Conference December 15-17,2011, Kochi (Invited Talk-2.)
GEOTECHNICAL CONSTRUCTION OF PILING FOUNDATIONS ON PROBLEMATICAL
SOIL GROUND OF KAZAKHSTAN
Zhussupbekov, A., Prof. of Geotechnical Institute, ENU of L.N.Gumilyov, Astana, Kazakhstan, [email protected]
Lukpanov, R., PhD of Geotechnical Institute, ENU of L.N.Gumilyov, Astana, Kazakhstan, [email protected]
Tulebekova, A., PhD student of Geotechnical Institute, ENU of L.N.Gumilyov, Astana, Kazakhstan, [email protected]
ABSTRACT: Nowadays many megaprojects are building up in new capital of Kazakhstan – Astana. Many foreign leading
companies are take part in construction that results to application of modern and advanced geotechnical technologies, in
particular pile technology. Therefore research of different modern pile technologies (Boring pile, Steel H-pile, CFA-continuous
flight auger, DDS-drilling displacement system) in inhomogeneous soil condition of Astana is presented in this pepper, as well
as technology, advantages and disadvantages. Many field load tests (static, dynamic) were performed, and by results of that
economical and technical efficiency was obtained. Significant differences between experimental (by SLT) and design (by
Standards) bearing capacity of these piles show us incomplete usage of technologies. Research of adjacent soil compaction due
to of high value of concrete pressure during CFA pile installation is also presents, as well as results of compression tests of
surrounding soil after DDS pile installation. Laboratory testing of soil after DDS pile installation allow understanding
relationship between elastic modulus, cohesion, angle of internal friction and DDS pile diameter.Authenticity and reliability of
each pile technology was given by results of more than 30 performed tests. Finally, final element method (FEM) analysis of
CFA and DDS piles was performed to analyze soil work condition around of these piles.
INTRODUCTION
Nowadays pile foundations become most popular during
construction of new capital of Kazakhstan. Very high rates of
construction and appearance of high-rise buildings which
extremely builds up by modern architectural and engineering
megaproject leads to mainly use pile foundations.
Nowadays many megaprojects are building up in Kazakhstan,
especially in new capital – Astana, such as Trade and
entertainment centre Khan Shatyry (See Fig. 1), House estate
- Severnoe Siyanie (See Fig. 2), Palace of Peace - Pyramid
(See Fig. 3) and many other.
Many unique megaprojects are realizing in Kazakhstan
Republic. For example New Aktau city with forecast
population 1.5 million people – the main goal of the project is
creation of the most beautiful city, place of the rest and
tourism not only for Kazakh people, but also for foreigners
(See Fig. 4). Many foreigner specialists from USA, Australia,
UAE and Europe will be attracted to this project. Another
megaproject is construction of the unique housing estate
Abu-Dabi Plaza designed by famous architecture Norman
Foster. This will be a most high building in Central Asia and
14th in the world. Abu-Dabi Plaza - a complex from several
tower, united around the main of the building by height 382
meters - 88 floors (See Fig. 5). Another one example of is
construction of long bridge going through Balkhash lake (See
Fig. 6). The length of the bridge will be 22 km and width is
34 m.
Modern megaprojects put forward modern requirements to
engineers. This led to refuse from traditional out-of-dates
technologies (traditional boring and driving diesel-hammer
piles) and use new more economical and reliable
technologies like CFA (continuous flight auger), DDS
(drilling displacement system), steel “H” piles.
Fig. 1 Trade and entertainment centre Khan Shatyry
Fig. 2 House estate - Severnoe Siyanie
7
Askar Zhussupbekov, Lukpanov R & Tulebekova, A
Fig. 3 Palace of Peace - Pyramid
Fig. 4 Megaproject of New Aktau City
Fig. 5 Housing estate Abu-Dabi Plaza
CFA and DDS technology both was established by German
company BAUER. The main distinction of this technology is
that soil compacted under the high value of concrete pressure
during CFA pile installation and due to of soil displacement
without excavation during DDS pile installation.
This both technologies lead to reduction of settlement and
increase of bearing capacities of pile foundation. Steel “H”
piles for the first time are used in construction sites of
Kazakhstan and firstly applied at construction of “USA
Embassy”.
Fig. 6 Megaproject of Balkhash Bridge
Full classification of pile foundation used in constructions
sites of Kazakhstan is presented in Fig. 7.
Fig. 7 Pile foundations on construction sites of Kazakhstan
FETURES OF DDS AND CFA PILE TECHNOLOGIES
Installation of DDS pile consist of four steps, the steps of the
DDS technology are: placing the boring machine to the
boring place; boring the pile hole to the design level; filling
the concrete under the pressure of 300 kPa; installation of
steel anchor into the pile body. See Fig. 8.
Fig. 8 Pile foundations on construction sites of Kazakhstan
Installation of CFA pile consist of following steps: placing
the boring machine to the boring place; boring the pile hole to
the design level; removing the screw with simultaneous
8
Geotechnical construction of piling foundations on problematical soil ground of Kazakhstan
concrete filling under the high pressure and replace the
boring machine, installation of steel anchor into the pile body
with preparation of pile head. See Fig. 9.
Fig. 9 Steps of CFA pile installation
In modern CFA technology the systematic employment of
devices auto-recording the drilling data represent a real
breakthrough considering that in the past the CFA method
was not accurate, and relied on the operator’s ability: now
such devices guarantee the control and recording of the data
during the whole construction process. The recorded working
data are usually drilling/withdrawal speed, rotation speed,
depth, concrete pressure and delivery rate per increment of
auger lift during casting.
STATIC LOAD TEST OF DDS AND CFA PILES
Totally it was performed 14 static tests of DDS and 5 CFA
piles of different diameters and length. There are 7 tested
DDS piles of 410 mm diameter and 18 m length, 2 piles of
500 mm diameters and 2.5 m length1nd one pile of 600 mm
diameter and 12 m length. Field static load tests were carried
out for CFA and traditional piles with diameter of 600 mm
and 630 mm and length of 10, 20, 22 24 and 28 m. During DDS SLT loading was done in stages of 400kN and
200kN until 2800kN by three hydraulic jacks type of CMJ-
158A which were contact parallel. , the pressure in the jacks
was created by manual oil pump station MNSR-400, load
was controlled with monometer MTP-160, moving piles was
fixed by caving in-measurers of the type 6-PAO, which were
positioned in the both sides on unmovable bearings of
benchmark system. Reloading was conducted in stages
800kN and 400kN.
Loading of CFA piles was done in stages of 428 kN, 214 kN
and 140 kN by hydraulic jack DG200P150 with carrying
capacity of 2000 kN depending on the value of
settlement and speed of stabilization of deformation. The
pressure in the jack was created by manual oil pump station
NRG-8080, load was controlled with monometer
MA100VU63, Fig. 10.
1 –DDS tested pile; 2 – basic beam; 3 – auxiliary beam; 4– pipes
welded to anchor bar; 5 – jack SMJ-158A; 6 - caving in-measurer 6-
PAO; 7 - benchmark system; 8 – pump NSR-40 and, with
monometer MTP-160.
Fig. 10 Testing of CFA pile by static load
The first count out – right after putting the loading, then
consequently 4 counts out with the interval 15 minutes, 2
counts out with the interval 30 minutes and further in
every hour till the conditional stabilization of deformation.
For the criterion of conditional stabilization of deformation
was taken the speed of settlement of boring piles on the
given stage of loading that did not exceed 0.1mm during the
last 1 hour of observation.
9
Askar Zhussupbekov, Lukpanov R & Tulebekova, A
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000 3200 3400 3600 3800 4000 4200
Load, kN
Settle
ment, m
m
FEM Result of 20m CFA pile
CFA 5 (20m)
According to requirements of Kazakhstan Standard - SNiP
RK 5.01-03-2002 – ultimate value of settlement of the tested
pile is determined by Eq. 1:
mtuSS , (1)
where = coefficient for conversion factor of the limit value
of mean settlement of foundation of the building or structure
Su,mt into pile settlement obtained while static tests at
conventional settlement stabilization; mtSu, = is maximum
permissible value of foundation settlement of the designed
building or structure as stated either in the project statement
or Kazakhstan Standards requirements.
COMPARISON CFA AND CASING BORING
(TRADITIONAL) PILES
The comparison of CFA and traditional boring piles was
performed on construction sites: “Trade and entertainment
centre Khan Shatyry” and house estate of “Severnoe
Siyanie”. Field static load tests were carried out for CFA and
traditional piles with diameter of 600 mm and 630 mm.
A CFA pile is a type of drilled foundation in which the pile is
drilled to the final depth in one continuous process using a
continuous flight auger. The use of the continuous flight
auger rig avoids many of the problems of drilling and
concreting piles experienced when using conventional power
augers. The new CFA equipment can perform piles in most
type of soils (including sand, gravel, silt, clay, chalk and
weak weathered rock) with diameters up to 1200 mm and
lengths down to 35-40 meters. So, with proper planning and
design, performing equipment and skilled personnel, high
production rates and high quality product can be achieved
[Klosinski & Rychlewski].
In modern CFA technology the systematic employment of
devices auto-recording the drilling data represent a real
breakthrough considering that in the past the CFA method
was not accurate, and relied on the operator’s ability: now
such devices guarantee the control and recording of the data
during the whole construction process. The recorded working
data are usually drilling/withdrawal speed, rotation speed,
depth, concrete pressure and delivery rate per increment of
auger lift during casting. The numerical analyses are
important for understanding the interaction of CFA pile with
soil ground. The elasto-plastic analysis was provided by
FEM. It was used the mechanical properties of soil ground
for the numerical calculation of bearing capacity and
settlement. For analyzing bearing capacity of working as
friction CFA and Casing piles were modeled by numerical
computer program of FEM and compared with results of field
static load test. FEM mesh for calculation of single bored pile
is illustrated in Fig. 11.
Taking advantage of the axi-symmetric nature of the
problem, only a half domain of the model ground and pile
were analysed. The soil ground and pile were descretized into
four noded quadrilateral elements. Number of nodal points
are 675, number of finite elements are 606, number of
materials are 4 (1is sand with gravel, 2 is hard clay, 3 is clay,
4 is bored pile).
The results show that experimental and theoretical results are
not so different and presents in Figs 12-13.
Fig. 11 Mesh for finite element method
Fig. 12 Comparison “load-settlement” curves of field static
load test of piles and FEM, (Khan Shatyry)
10
Geotechnical construction of piling foundations on problematical soil ground of Kazakhstan
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
0 400 800 1200 1600 2000 2400 2800 3200 3600 4000 4400
Load, kN
Se
ttle
me
nt,
mm
Casing1 (10 m)
CFA1 (10 m)
CFA 2 (10m)
Casing2 (10m)
FEM Results
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000 3200 3400 3600 3800 4000 4200
Load, kN
Se
ttle
me
nt,
mm
FEM Result of 20m CFA pile
CFA 5 (20m)
0
0,5
1
1,5
2
2,5
3
3,5
4
4,5
5
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200
Load, kN
Sett
lem
ent,
mm
CFA3 (17m)
CFA4 (14m)
Casing4 (13m)
Casing3 (15m)
FEM result of 14 m CFA pile
Fig. 13 Comparison “load-settlement” curves of field static
load test of piles and FEM, (Severnoe Siyanie)
Through technology of CFA in construction sites “Grand
Astana” “Severnoe syanie” and “Khan Shatyry” before us
there was a question over-expenditure of concrete at the
installation of CFA pile. The actual volume of borehole was
about 1.3-1.4 times more than theoretical volume of borehole
[Zhusupbekov & Ashkey e.g.] After determination of
preliminary average radius (r+ r) increasing diameter of
CFA piles and remodeled numerical mesh of “Severnoe
Siyanie” and “Khan Shatyry” for FEM. It gives us increasing
bearing capacity of CFA piles respectively “load-settlement”
results of field static load test and stress and strain of soil
around of single CFA pile through FEM computer program.
The results of “load-settlement” through FEM illustrated in
Figs. 14-15.
Fig. 14 Comparison static load test and FEM results after
increasing of diameter of CFA pile, (Khan Shatyry)
Fig. 15 Comparison static load test and FEM results after
increasing of diameter of CFA pile, (Severnoe Siyanie)
COMPARISON DDS (FDP) AND CASING BORING
(TRADITIONAL) PILES
The principal feature of DDS technology is special boring
element, presented in Fig. 16. The pile hole forming via two
stages: during the moving of boring element down the bullet
teeth loose the soil and stabilizer displaces surrounding soil.
During the moving of boring element up the secondary
compaction of hole has a place.
Fig. 16 Cone-shape tool for a boring and displacement of
soils
In order to research DDS pile the static load tests (SLT) of
DDS and Casing boring piles were performed. The main
purpose of SLT performance is comparison of bearing
capacity of DDS and Casing pile. Totally it was performed 14
static tests of DDS piles of different diameters and length on
two construction sites [Sultanov & Zhussupbekov e.g.]
First construction site is “Trade and entertainment centre
Khan Shatyry”. Totally 11 piles were tested on this site, there
11
Askar Zhussupbekov, Lukpanov R & Tulebekova, A
are 8 tested piles of 410 mm diameter and 18 m length, 2
piles of 500 mm diameters and 10 m length, and one pile of
600 mm diameter and 18 m length. Construction sites No 2 is
“Industrial Base” where were tested 3 DDS piles 500 mm of
diameter and 2.5 m length.
Comparison of DDS and Casing boring piles bearing
capacities are presented in Fig. 17. As you see there is big
difference between DDS and Casing boring piles bearing
capacities.
Fig. 17 Comparison of DDS and Casing boring piles bearing
capacities
Significant differences between bearing capacities of DDS
and Casing boring piles show us incomplete usage of DDS
technology resources. Classically differ two stages of pile
works under the vertical load: during the first stage is
developing the ultimate state of stress-stain condition of soil,
during the second stage the slippage of pile through the soil
has a place. DDS pile works identically, but in case of DDS
pile surrounding soil subject to compaction, this lead to
increase of bearing capacity. As you know classically bearing
capacity subdivides into two constituent there are: shaft and
tip resistance. In Kazakhstan`s standard - Soil basement and
foundations classical equation was modified, and presented
by following equation:
(2)
where yc = safety factor; ycR and ycf = coefficients of soil work
condition under the pile tip and surround of pile respectively.
In this case we interested by coefficient of soil work
condition. In case of traditional bored pile no compaction is
occurred therefore coefficient of shaft work of pile equal 0,7,
in case of DDS piles due to of surrounding compaction of soil
this coefficient must be increased. Moreover in case of DDS
pile surrounding soil only undergoes to compaction, under
the pile no compaction. By results of static load tests of DDS
and Case piles the inverse problem was performed to
definition of interested us coefficients. Obtained coefficients
of DDS piles shaft work for different EGE (engineering
geological elements) were presented in Table 1.
Table 1 Coefficients of DDS piles shaft work
Depth, m Ycf Ycf(average)
EGE2
5 1,23 6 1,18 7 1,15 5 1,45 6 1,37 7 1,32 5 1,67 6 1,56 7 1,23
1,38
EGE3
5 1,31 6 1,25 7 1,21 5 1,33 6 1,26 7 1,21 5 1,32 6 1,25 7 1,21
1,26
EGE4
5 1,12 6 1,08 7 1,05 5 1,21 6 1,16 7 1,12 5 1,43 6 1,34 7 1,28
1,20
After reprocessing of obtained data by statistic analysis
several results of elastic modulus were rejected from
following analysis. It is necessary take account elastic
modulus, angle of internal friction and cohesion increase due
to compaction during design DDS pile. With that view the
nomograms were developed, Fig. 18-20. By these
nomograms designers may easily correct elastic modulus,
angle of internal friction and cohesion of different
engineering element of Astana, to accurate design DDS piles.
Fig. 18 Elastic modulus correction nomogram
iicfcRcd hfuRAF
12
Geotechnical construction of piling foundations on problematical soil ground of Kazakhstan
Fig. 19 Cohesion correction nomogram
Fig. 20 Internal friction angle correction nomogram
DRIVING STEEL “H” SECTION PILES
Driving steel “H” piles were installed on “USA Embassy”
construction site. The site is situated on the Southeast side of
Astana city on the right side of the Esil river, and so ground
soil presented by soft loam and clay soil with a rare lenses of
gravel sand. Steel piles “H” section of type HP12x74
(HP305x110) was made from high-strength low alloy
colombia-vanadium of class 50 (345) according to ASTM
A572. The maintenance of chemical elements in structure of
steel of pile are: carbon (C) – min 0.08%; Iron (Fe) – 98%;
Manganese (Mn) – 1.35%; Fluorine (P) – max 0.04%;
Sulphur (S) – max 0.04%; Silicon (Si) – max 0.04% [Bazilov
R.K]. On an edge of pile shoe from the strong steel tips HP-
7780-B made Associated Pile and Fitting Corp (Clifton, satae
of New Jersey) weld.
First static load test was performed for 7 m length of pile.
The bearing capacity of this pile had been 500 kN. It was
chosen to increase the bearing capacity to designed level by
jointing pile sections. The length of pile was increased step
by step and SLTs were repeated to attain allowable value of
bearing capacity. Finally designed bearing capacity was
achieved for 10 m length of steel pile. Results of static load
tests for different length of steel piles presented in Fig. 21.
The advantages steel piles is possibility of joint the sections
to increase of pile length, therefore depth of steel pile is
unconfined. Steel piles has one significant disadvantage is
impossibility to use in aggressive soil condition even in
unaggressive soil condition steel piles is very expansive due
to of anticorrosive actions.
Fig. 21 Increscent bearing capacity by results of extension of
pile length
COMPARISON SLT RESULTS OF DIFFERENT
TYPES OF PILE
SLT of different types of pile was performed with a view to
compare bearing capacity of traditional (namely, boring
casing pile and driving pile).
Unfortunately, most part of tested piles is not achieved
ultimate settlements prescribed by Kazakhstan Standard -
24mm, and so, for bearing capacity comparison it was
chosen to use 3mm settlement criteria, as long as all the
piles achieved this settlement.
All the piles were designed to the criteria of 2200kN bearing
capacity. Designed parameters of piles (length and cross
section) by Kazakhstan Standards are presented in Table 2. Table 2 Designed pile characteristic
Type of
pile
Required
quantity, e.a.
Length of
pile, m
Diameter or
cross section,
m
CFA 1 10 0.5
DDS 1 10 0.5
Casing 1 10 0.5
Driving 2 12 0.3 x 0.3
Results of comparison are presenting in Fig. 22
and Table 3.
All of these coefficients show incapacity of accurate design
of modern pile technology by out-of date Standards,
otherwise this coefficients tending to 1. The results of SLT
showed entirely expected regularity. CFA piles showed
highest bearing capacity as long as during CFA pile
installation it was expended much more concrete (in 2 times)
than during Casing pile installation. This factor was not
considered during design, the coefficient therefore equal
1.43. DDS pile approved effluence of compacted soil and
coefficient therefore equal 1.22 (DDS versus Casing).
Differences between Driving and Casing pile neglected
13
Askar Zhussupbekov, Lukpanov R & Tulebekova, A
small, the reason of differences might be empirical
coefficients required by Standards.
Table 3 Comparison of different piles
Description Coefficient of reserve
FCFA/FDDS 1.17
FCFA/FCasing 1.43
FCFA/FDriving 1.55
FDDS/FCasing 1.22
FDDS/FDriving 1.33
FCasing/FDriving 1.08
Fig. 22 Comparison of different piles
CONCLUSIONS
The results of field static load tests of CFA piles showed high
value bearing capacity higher than traditional casing pile.
For designing CFA technology for pile foundations of
buildings and structures need consider volume changing
of borehole by appearance in borehole additional pressure
respectively over-expenditure of the concrete depending
soil conditions and length of piles. CFA pile more
productivity than traditional casing pile. It is possible to
install 6 CFA piles per working day versus 3 casing
piles.
Significant differences between bearing capacities of DDS
and Casing boring piles show us incomplete usage of DDS
technology resources. Kazakhstan standards have not any
recommendations to DDS pile design, prescribed in standards
recommendation applicable for traditional pile design and
give not accurate results for DDS pile design. The coefficient
of shaft work of DDS pile was defined and equal from 1.2 to
1.38 depending on soil condition. Application of DDS
technology allows reducing total expanse per 35 to 40%.
The reason of big difference between DDS experimental and
designed bearing capacity is strengthening of surround soil
due to of technological compaction. This lead to increase of
soil parameters such as angle of internal friction, cohesion,
Young modulus and so on. By the results of laboratory
testing the nomograms to correct angle of internal friction,
cohesion, and Young modulus were developed. It is possible
to use these nomograms during design DDS pile of 400, 500
and 600mm of diameter in similar soil condition.
Steel “H” piles for the first time are used in construction sites
of Kazakhstan and firstly applied at construction of “USA
Embassy”. Application of steel piles more expansive then
prefabricated concrete driving piles due to of expansive
anticorrosive actions. Nevertheless it is possible to increase
bearing capacity of steel pile by expansion pile length by
jointing the steel sections.
REFRENCES
1. B. Klosinski & P.Rychlewski. Analysis of bearing
capacity and settlement of CFA piles. Deep
foundations on bored and auger piles, Van Impe (ed.),
Rotterdam, 2003. – pp. 153-156.
2. A. Zh. Zhusupbekov and Y. Ashkey, V.N. Popov, A.J.
Belovitch and G.A. Sultanov, Analyzing the static test of
boring piles through CFA technology. Proceedings 4th
International Conference on Soft Soil Engineering, 2006,
(Canada, Vancouver), 213-215 .
3. Ashkey, E. (2008). “Interaction of CFA bored piles with
soil condition in Astana.” A dissertation submitted for the Ph.D. degree. Astana, Kazakhstan. 50-52.
4. G.A. Sultanov, R.E. Lukpanov, S.B. Enkebaev. Research
of Interaction between Displacement Pile and Soil
Basement. Proceedings of Kazakhstan-Korean joint
geotechnical seminar. 2010, Astana, Kazakhstan, 84-91
pp.
5. Sultanov, G., Zhusupbekov, A., Lukpanov, R, Enkebaev,
S., (2010). Laboratory testing of elastic modulus of soil
around of displacement pile. Proc. L.N.Gumilyev
Eurasian National University. Astana, Kazakhstan, 214-
219.
6. Sultanov, G., Zhusupbekov, A., Lukpanov, R, Enkebaev,
S., (2010). Definition of dependence between
experimental and designed values of bearing capacities of
displacement pile. .” Proc. L.N.Gumilyev Eurasian
National University. Astana, Kazakhstan, 226-232.
7. Sultanov, G., Zhusupbekov, A., Lukpanov, R, Enkebaev,
S., (2010). Comparison analysis of DDS and traditional
boring pile works by FEM analysis results. Proc.
L.N.Gumilyev Eurasian National University. Astana,
Kazakhstan, 219-226.
8. R.K. Bazilov. Research of steel “H” section piles in soil condition of Astana. A dissertation submitted in partial
fulfillment of the requirements for the degree of doctor of
philosophy, 2008, 58-63 pp.
9. SNiP RK 5.01-03-2002 “Pile foundation”. 10. SNiP RK 5.01-01-2002 “Soil basement and foundations”.
14