GEOTECHNICAL ENGINEERING STUDY
Concord High School Athletic Field Improvements
4200 Concord Boulevard Concord, California 94521
Prepared for:
Mt. Diablo Unified School District 1936 Carlotta Drive
Concord, California 94519
Prepared by:
GEOSPHERE CONSULTANTS, INC. 2001 Crow Canyon Road, Suite 210
San Ramon, California 94583 Geosphere Project No. 91-03875-A
April 20, 2017 Mt. Diablo Unified School District 1936 Carlotta Drive Concord, California 94519 Attention: John Willford, Project Manager Subject: Geotechnical Engineering Study Concord High School – Athletic Field Improvements
4200 Concord Boulevard Concord, California 94521 Geosphere Project No. 91-03875-A
Dear Mr. Willford: Geosphere Consultants, Inc. has completed a Geotechnical Engineering Study for the proposed improvements at Concord High School in Concord, California. Transmitted herewith are the results of our findings, conclusions, and recommendations for foundations, exterior concrete slabs, site preparation, grading, drainage, and utility trench backfilling. In general, the proposed improvements at the site are considered to be geotechnically feasible provided the recommendations of this report are implemented in the design and construction of the project. This report is not intended to function as a geohazard report which was not included in our scope of work. We note that a geohazard report is not required to be submitted according to Division of State Architect (DSA) Interpretation of Regulations IR A-4.13 provided that new bleacher or other field structures, if any, are seismically separated into areas of 4,000 square feet or less in covered area (Paragraph 3.2.3). Should you have questions or need additional information, please contact the undersigned at (925) 314-7180. The opportunity to be of service to Mt. Diablo Unified School District and to be involved in the design of this project is appreciated. Sincerely, GEOSPHERE CONSULTANTS, INC. Raghubar Shrestha, Ph.D., P.E. Corey T. Dare, P.E., G.E. Senior Engineer Principal Geotechnical Engineer Distribution: PDF to Addressee ([email protected]) RS/CTD:pmf
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................................................................................. 1 1.1 Purpose and Scope ........................................................................................................................... 1 1.2 Site Description ................................................................................................................................ 1 1.3 Proposed Development .................................................................................................................... 2
2.0 PROCEDURES AND RESULTS ............................................................................................................................. 3 2.1 Literature Review ............................................................................................................................. 3 2.2 Drilling and Sampling ........................................................................................................................ 3 2.3 Laboratory Testing ............................................................................................................................ 4
3.0 GEOLOGIC AND SEISMIC OVERVIEW ................................................................................................................ 5 3.1 Geologic Setting................................................................................................................................ 5 3.2 Geologic Evolution of the Northern Coast Ranges ........................................................................... 5 3.3 Regional Faulting and Tectonics ....................................................................................................... 6
4.0 SUBSURFACE CONDITIONS ............................................................................................................................... 7 4.1 Subsurface Soil Conditions ............................................................................................................... 7 4.2 Groundwater .................................................................................................................................... 7 4.3 Field Infiltration Tests ....................................................................................................................... 7 4.4 Corrosion Testing ............................................................................................................................. 9
5.0 CONCLUSIONS AND RECOMMENDATIONS..................................................................................................... 12 5.1 Conclusions ..................................................................................................................................... 12 5.2 Seismic Design Parameters ............................................................................................................ 13 5.3 Site Grading .................................................................................................................................... 14 5.4 Utility Trench Construction ............................................................................................................ 17 5.5 Pier Foundations ............................................................................................................................ 19 5.6 Exterior Concrete Flatwork ............................................................................................................ 19 5.7 Athletic Track Asphalt Concrete Pavements .................................................................................. 20 5.8 Plan Review .................................................................................................................................... 20 5.9 Observation and Testing During Construction ............................................................................... 20
6.0 VALIDITY OF REPORT ...................................................................................................................................... 21 7.0 LIMITATIONS AND UNIFORMITY OF CONDITIONS .......................................................................................... 22 8.0 REFERENCES .................................................................................................................................................... 23
TABLE OF CONTENTS (continued) FIGURES
Figure 1 - Site Vicinity Map Figure 2 - Development Site Plan Figure 3 - Site Plan and Site Geology Map Figure 4 - Site Vicinity Geology Map Figure 5 – Regional Fault Map Figure 6a - Geological Cross Section A-A’ Figure 6b - Geological Cross Section B-B’
APPENDIX A
Key to Boring Log Symbols Boring Logs
APPENDIX B LABORATORY TEST RESULTS Liquid and Plastic Limits Test Report Sieve Analysis Results R-Value Test Result Corrosivity Test Summary
GEOTECHNICAL ENGINEERING STUDY
Project: Concord High School – Athletic Field Improvements Concord, California
Client: Mt. Diablo Unified School District Concord, California
1.0 INTRODUCTION
1.1 Purpose and Scope
The purposes of this study were to evaluate the subsurface conditions at the site and prepare geotechnical
recommendations for the proposed improvements. This study provides recommendations for foundations,
exterior concrete slabs, site preparation, grading, drainage, utility trench backfilling, and guideline specifications
for grading. This study was performed in accordance with the scope of work outlined in our proposal dated January
9, 2017.
The scope of this study included the review of pertinent published and unpublished documents related to the site,
the drilling of 13 subsurface borings, drilling and testing of three percolation holes, laboratory testing of selected
samples retrieved from the borings, engineering analysis of the accumulated data, and preparation of this report.
The conclusions and recommendations presented in this report are based on the data acquired and analyzed
during this study, and on prudent engineering judgment and experience. This study did not include an assessment
of potentially toxic or hazardous materials that may be present on or beneath the site.
1.2 Site Description
Concord High School is located at 4200 Concord Boulevard in Concord, California, as shown on Figure 1, Site
Vicinity Map. The proposed site improvements will be located at the northeast part of the campus. These
improvements are planned to replace existing infrastructure, namely the baseball, softball, and soccer/football
fields. The site is relatively flat, with the general site vicinity topography sloping very gently to the west past the
track and field area. The campus is bounded on the northeast by lands of the former Concord Naval Weapons
Station now part of the Concord Re-Use Area; on the southeast by a city park and residential development, on the
south by Concord Boulevard, and on the northwest by residential development. The site is located at
approximately 37.9776 north latitude and 121.9867 west longitude based on the Google Earth application, and
2
ground surface elevations range from approximately 166 to 177 feet above mean sea level based on the provided
Improvement Plan.
1.3 Proposed Development
It is our understanding that the proposed site improvements are to consist of new baseball, softball, and
football/soccer fields to replace the existing facilities, with an athletic track surrounding the latter improvement.
Basic plans of the proposed improvement areas were provided to us at the time of this report preparation.
However, no detailed plans were available. Other improvements may include new bleacher structures, utility
upgrades, exterior concrete flatwork, and landscaping. The proposed improvement locations are shown on the
attached Figure 2, Development Site Plan.
3
2.0 PROCEDURES AND RESULTS
2.1 Literature Review
Pertinent geologic and geotechnical literature pertaining to the site area were reviewed. These included various
publications and maps issued by the United States Geological Survey (USGS), California Geological Survey (CGS),
water agencies, and other government agencies, as listed in the References section.
2.2 Drilling and Sampling
A subsurface exploration program was undertaken to evaluate the soil conditions at the site. A total of 13 borings
were drilled on March 3rd, 2017. Of this total, three borings were drilled on each baseball and softball field, and
six borings on the football/soccer field. The locations of the borings in relation to the proposed improvements are
shown on the attached Figures 2 and Figure 3, Site Plan and Site Geology Map. The borings were drilled using a
Mobile B-53 drill rig equipped with 8” hollow-stem augers.
A Geosphere representative visually classified the materials encountered in the borings according to the Unified
Soil Classification System as the borings were advanced. Relatively undisturbed soil samples were recovered at
selected intervals using a three-inch outside diameter Modified California split spoon sampler containing six-inch
long brass liners, and a two-inch outside diameter Standard Penetration Test (SPT) sampler. The samplers were
driven by means of a 140-pound safety hammer with an approximate 30-inch fall. Resistance to penetration was
recorded as the number of hammer blows required to drive the sampler the final foot of an 18-inch drive. All of
the field blow counts recorded using Modified California (MC) split spoon sampler were converted in the final logs
to equivalent SPT blow counts using appropriate modification factors suggested by Burmister (1948), i.e., a factor
of 0.65 with inner diameter of 2.5 inches. Therefore, all blow counts shown on the final boring logs are either
directly measured (SPT sampler) or equivalent SPT (MC sampler) blow counts.
The boring logs with descriptions of the various materials encountered in each boring, a key to the boring symbols,
and select laboratory test results are included in Appendix A. Ground surface elevations indicated on the soil
boring logs were estimated to the nearest foot using Google Earth.
4
2.3 Laboratory Testing
Laboratory tests were performed on selected samples to determine some of the physical and engineering
properties of the subsurface soils. The results of the laboratory testing are either presented on the boring logs,
and/or are included in Appendix B. The following soil tests were performed for this study:
Dry Density and Moisture Content (ASTM D2216 and ASTM 2937) – In-situ dry density and/or moisture tests were
conducted on 15 samples to measure the in-place dry density and moisture content of the subsurface materials.
These properties provide information for evaluating the physical characteristics of the subsurface soils. Test
results are shown on the boring logs.
Atterberg Limits (ASTM D4318 and CT204) - Atterberg Limits tests were performed on two samples of cohesive
soils encountered at the site. Liquid Limit, Plastic Limit, and Plasticity Index are useful in the classification and
characterization of the engineering properties of soil, and help to evaluate the expansive characteristics of the soil
and determine the USCS soil classification. Test results are presented in Appendix B, and on the boring logs.
Particle Size Analysis (Wet and Dry Sieve) and Hydrometer (ASTM D422, D1140, and CT202) - Sieve analysis testing
was conducted on selected samples to determine the soil particle size distribution. This information is useful for
the evaluation of liquefaction potential and characterizing the soil type according to USCS.
R-Value Test (ASTM D2844 and CT301) – One R-value test was performed on a sample collected from the site to
evaluate the subgrade soil strength for pavement designs. The R-value test was conducted on bulk sample of near-
surface materials collected from cuttings generated from Boring B-8 at depth from about 2.5 feet. The R-value of
30 was determined from the laboratory test. The test result is presented in Appendix B, and on the pertinent
boring log.
Soil Corrosivity, Redox (ASTM D1498), pH (ASTM D4972), Resistivity (ASTM G57), Chloride (ASTM D4327), and
Sulfate (ASTM D4327) - Soil corrosivity testing was performed to determine the effects of constituents in the soil
on buried steel and concrete. Water-soluble sulfate testing is required by the California Building Code (CBC) and
International Building Code (IBC). Soil corrosivity test results are summarized in Appendix B and are discussed in
Section 4.4.
5
3.0 GEOLOGIC AND SEISMIC OVERVIEW
3.1 Geologic Setting
The site is located in the central portion of the northern Coast Ranges geomorphic province of California. The
Coast Ranges extend from the Transverse Ranges in southern California to the Oregon border and are comprised
of a northwest-trending series of mountain ranges and intervening valleys that reflect the overall structural grain
of the province. The ranges consist of a variably thick veneer of Cenozoic volcanic and sedimentary deposits
overlying a Mesozoic basement of sedimentary, metamorphic, and basic igneous Franciscan Formation and
primarily marine sedimentary rocks of the Great Valley Sequence. East-dipping sedimentary rocks of the Coast
Ranges are flanked on the east by sedimentary rocks of the Great Valley geomorphic province (Page, 1966).
Specifically, the project site is located east of San Francisco Bay and northwest of Mt. Diablo, which is the northern
peak of the Diablo Range. The site is situated near the northeastern margin of the northwest-trending Concord
Valley, and shown on the map by Graymer et al. (2006) as being underlain by Pleistocene-aged alluvium (Qpa)
consisting of sands, clays, and gravels. Dibblee (2006) shows the general site vicinity as underlain by Holocene-
age alluvial sediments of similar composition, with the hills to the northeast underlain by Eocene-age Markley
Sandstone on the northeast side of the Clayton – Marsh Creek Fault discussed in Section 3.3. According to the
Natural Resources Conservation Service, Web Soil Survey, the site soil is classified as the Clear Lake Clay unit and
partially Rincon Clay Loam, which generally have a medium to high plasticity and a moderate to high expansion
potential. The mapped geologic units in the site vicinity per Graymer et al. (2006) are shown on Figure 3 as well
as Figure 4, Site Vicinity Geologic Map.
3.2 Geologic Evolution of the Northern Coast Ranges
The subject site is located within the tectonically active and geologically complex northern Coast Ranges, which
have been shaped by continuous deformation resulting from tectonic plate convergence (subduction) beginning
in the Jurassic period (about 145 million years ago). Eastward thrusting of the oceanic plate beneath the
continental plate resulted in the accretion of materials onto the continental plate. These accreted materials now
largely comprise the Coast Ranges. The dominant tectonic structures formed during this time include generally
east-dipping thrust and reverse faults.
Beginning in the Cenozoic time period (about 25 to 30 million years ago), the tectonics along the California coast
changed to a transpressional regime and right-lateral strike-slip displacements as well as thrusting were
6
superimposed on the earlier structures resulting in the formation of northwest-trending, near-vertical faults
comprising the San Andreas Fault System. The northern Coast Ranges were segmented into a series of tectonic
blocks separated by major faults including the San Andreas, Hayward, and Calaveras. The project site is situated
between the active Concord and potentially active Clayton - Marsh Creek faults, but no known active faults with
Holocene movement (last 11,000 years) lie within the limits of the site.
3.3 Regional Faulting and Tectonics
Regional transpression has caused uplift and folding of the bedrock units within the Coast Ranges. This structural
deformation occurred during periods of tectonic activity that began in the Pliocene and continues today. The site
is located in a seismically active region that has experienced periodic, large magnitude earthquakes during historic
times. This seismic activity appears to be largely controlled by displacement between the Pacific and North
American crustal plates, separated by the San Andreas Fault zone located approximately 34 miles (54.4 km) west
of the site. This plate displacement produced regional strain that is concentrated along major faults of the San
Andreas Fault System including the San Andreas, Hayward, and Calaveras faults in this area, Figure 5 - Regional
Fault Map. The site is not mapped within an Alquist-Priolo Earthquake Fault Zone. The AP zone for the active
Concord Fault is located approximately 2.3 miles to the west of the site. The potentially active Clayton-Marsh
Creek Fault is situated within the low hills of the northern end of the Diablo Range between approximately 1 and
2.5 miles northeast of the site, where numerous strands of the fault have been mapped or inferred. Active faulting
can be found outside of the AP special studies zone; however, this is very rare.
7
4.0 SUBSURFACE CONDITIONS
4.1 Subsurface Soil Conditions
During our subsurface exploration program, we investigated the subsurface soils and evaluated soil conditions up
to a maximum depth of 10 feet in the borings performed for this study. From our collected data, we conclude that
where explored, the area of the proposed new development is generally underlain by a surficial layer of stiff to
very stiff, lean to medium plastic clays and sandy clays to the maximum depth explored.
Results of an Atterberg Limits laboratory test performed on samples of representative near-surface soil from
Borings B-2 and B-10 at depths from three to four feet indicated Liquid Limits of 38 and 45 and Plasticity Indices
of 18 and 25, respectively. Based on our visual observations and the laboratory test results, the surficial native
soils are judged to have a low to medium plasticity and a moderate expansion potential.
Our interpretations of the subsurface geologic and soil conditions are presented in Figures 6a & 6b, Cross-Sections
A-A’ and B-B’. Additional details of materials encountered in the exploratory borings, including laboratory test
results, are included in the boring logs in Appendix A, and laboratory test summaries are presented in Appendix
B.
4.2 Groundwater
Groundwater was not encountered in any of the borings drilled to a maximum depth of 10 feet below ground
surface for this study. Groundwater levels can vary in response to time of year, variations in seasonal rainfall, well
pumping, irrigation, and alterations to site drainage. A detailed investigation of local groundwater conditions was
not performed and is beyond the scope of this study.
4.3 Field Infiltration Tests
Geosphere performed a total of four percolation tests in the respective areas of the baseball field, softball field,
and football/soccer field. A hand auger was used to create a vertical boring six to eight-inches in diameter down
to a depth of about 18 inches below the existing surface. All loose soil material was removed from the bottom of
the test holes. A perforated pipe was installed into each hole. About two-inch thickness of drain rock was placed
at the bottom of each hole to prevent scouring when pouring water in. The bored hole was saturated with water
for an hour to allow soils to absorb the water so that steady flow can be achieved during the actual test. After the
initial saturation, percolation rates were monitored over several percolation cycles; once the rate had settled, the
8
average of the final three recorded rates were reported as the groundwater percolation rate for each location. In
addition, the data was adjusted according to the Porchet Method which corrects the method for side effects in
the boring in order to obtain an interpreted vertical infiltration rate. The results of the tests are presented below
in Tables 4.3.1 through 3.3.4.
Table 4.3.1: Percolation Test Results @ 18” Depth Test Location P-1: Football Field Area (See Figure 3)
Tested By: JG Test Date: 3/23/2017
Time Interval (min) Water Level Drop
(in) Percolation Rate
(min/in) Infiltration Rate
(in/hr)
10 0.8 12.5 0.49
30 2.4 12.5 0.51
10 0.8 12.5 0.49
30 2.2 13.6 0.47
Average Infiltration Rate (Inches/hour) 0.49
Table 4.3.2: Percolation Test Results @ 18” Depth Test Location P-2: Football Field Area (See Figure 3)
Tested By: JG Test Date: 3/23/2017
Time Interval (min) Water Level Drop
(in) Percolation Rate
(min/in) Infiltration Rate
(in/hr)
10 3.5 2.9 2.30
30 11.3 2.7 3.15
10 3.2 3.1 2.09
30 10.3 2.9 2.77
Average Infiltration Rate (Inches/hour) 2.58
Table 4.3.3: Percolation Test Results @ 4.5 Feet Depth Test Location P-3: Softball Field Area (See Figure 3)
Tested By: JG Test Date: 3/23/2017
Time Interval (min) Water Level Drop
(in) Percolation Rate
(min/in) Infiltration Rate
(in/hr)
10 1.0 10.0 0.22
30 3.1 9.7 0.23
10 0.7 14.3 0.15
30 1.0 30.0 0.07
10 0.6 16.7 0.13
30 0.8 37.5 0.06
Average Infiltration Rate (Inches/hour) 0.14
9
Table 4.3.4: Percolation Test Results @ 18” Depth Test Location P-4: Baseball Field Area (See Figure 3)
Tested By: JG Test Date: 3/23/2017
Time Interval (min) Water Level Drop
(in) Percolation Rate
(min/in) Infiltration Rate
(in/hr)
10 3.0 3.3 1.95
30 6.5 4.6 1.55
10 2.5 4.0 1.60
30 6.1 4.9 1.44
Average Infiltration Rate (Inches/hour) 1.63
Based on the observed data, the interpreted vertical infiltration rates ranged from 0.14 inches/hour to 2.58
inches/hour. For design of natural drainage systems a factor-of-safety of 2 is recommended. Due to the relatively
low interpreted infiltration rates within the proposed development areas, we do not anticipate using natural
drainage as a viable infiltration option. Therefore, a subsurface drainage system will have to be considered for this
project.
4.4 Corrosion Testing
A sample collected from the upper two to four feet of the soil profile at Boring B-10 was tested to measure sulfate
content, chloride content, redox potential, pH, resistivity, and presence of sulfides. Test results are included in
Appendix B and are summarized on the following table.
Table 4.4.1: Summary of Corrosion Test Results
Soil Description Sample Depth (feet)
Sulfate (mg/kg)
Chloride (mg/kg)
Redox (mV)
Resistivity (ohm-cm)
Sulfide
pH
Dark Gray Sandy CLAY 2 - 4 91 6 369 1,231 Negative 7.4
Water-soluble sulfate can affect the concrete mix design for concrete in contact with the ground, such as shallow
foundations, piles, piers, and concrete slabs. Section 19.3.1.1 in American Concrete Institute (ACI) 318-14, as
referenced by the CBC, provides the following evaluation criteria:
10
Table 4.4.2: Sulfate Evaluation Criteria
Sulfate Exposure
Class Water-Soluble Sulfate in Soil,
Percentage by Mass or (mg/kg)
(ASTM C1580)
Dissolved Sulfate in Water, ppm (ASTM D516 or
D4130)
Cement Type
Max. Water Cementitious
Ratio by Weight
Min. Unconfined
Compressive Strength, psi
Negligible S0 < 0.10 ( < 1,000)
< 150 NA NA NA
Moderate S1 0.10 to < 0.20 (1,000 to <2,000)
150 to < 1,500 II, IP (MS), IS
(MS)
0.50 4,000
Severe S2 0.20 to < 2.00 (2,000 to < 20,000)
1,500 to < 10,000 V 0.45 4,500
Very Severe
S3 Over 2.00 (20,000) Over 10,000 V plus Pozzolan
0.45 4,500
The water-soluble sulfate content was measured to be 91 mg/kg or 0.0091% by dry weight in the soil sample,
suggesting the site soil should have negligible impact on buried concrete structures at the site. However, it should
be pointed out that the water-soluble sulfate concentrations can vary due to the addition of fertilizer, irrigation,
and other possible development activities.
Table 19.3.2.1 in ACI 318-14 suggests use of mitigation measures to protect reinforcing steel from corrosion where
chloride ion contents are above 0.06% by dry weight (of cement). Based on the California Department of
Transportation (Caltrans), if chloride ion content in soil is equal or greater than 500 ppm (0.5% by weight) it is
considered as corrosive. The chloride content was measured to be 6 mg/kg or 0.0006% by dry weight in the soil
sample. Therefore, the test result for chloride content does not suggest a corrosion hazard for mortar-coated steel
and reinforced concrete structures due to high concentration of chloride.
In addition to sulfate and chloride contents described above, pH, oxidation reduction potential (Redox), and
resistivity values were measured in the soil sample. For cast and ductile iron pipes, an evaluation was based on
the 10-Point scaling method developed by the Cast Iron Pipe Research Association (CIPRA) and as detailed in
Appendix A of the American Water Works Association (AWWA) publication C-105, and shown on Table 4.3.3.
11
Table 4.4.3: Soil Test Evaluation Criteria (AWWA C-105)
Soil Characteristics Points Soil Characteristics Points
Resistivity, ohm-cm, based on single probe or water-saturated soil box.
Redox Potential, mV
<700 10 >+100 0
700-1,000 8 +50 to +100 3.5
1,000-1,200 5 0 to 50 4
1,200-1,500 2 Negative 5
1,500-2,000 1 Sulfides
>2,000 0 Positive 3.5
PH Trace 2
0-2 5 Negative 0
2-4 3 Moisture
4-6.5 0 Poor drainage, continuously wet 2
6.5-7.5 0 Fair drainage, generally moist 1
7.5-8.5 0 Good drainage, generally dry 0
>8.5 5
Assuming fair site drainage, the tested soil sample had a total score of 1 point, indicating a potential for low
corrosive rating. When total points on the AWWA corrosivity scale are at least 10, the soil is classified as corrosive
to cast and ductile iron pipe, and use of cathodic corrosion protection is often recommended.
These results are preliminary, and provide information only on the specific soil sampled and tested. Other soil at
the site may be more or less corrosive. Providing a complete assessment of the corrosion potential of the site soils
are not within our scope of work. For specific long-term corrosion control design recommendations, we
recommend that a California-registered professional corrosion engineer evaluate the corrosion potential of the
soil environment on buried concrete structures, steel pipe coated with cement-mortar, and ferrous metals.
12
5.0 CONCLUSIONS AND RECOMMENDATIONS
The following conclusions and recommendations are based upon the analysis of the information gathered during
the course of this study and our understanding of the proposed improvements.
5.1 Conclusions
The site is considered geotechnically suitable for the proposed improvements provided the recommendations of
this report are incorporated into the design and implemented during construction. The predominant geotechnical
issues that need to be addressed at this site are summarized below.
Drainage System – The percolation rates of the subsurface soils were measured to be relatively low, ranging from
0.14 to 2.58 inches/hour. Therefore, a designed subsurface drainage system should be installed beneath the fields
in order to facilitate proper drainage of collected surface water.
Seismic Ground Shaking – The site is located within a seismically active region. As a minimum, the building design,
if any, should consider the effects of seismic activity in accordance with the latest edition of the California Building
Code (CBC).
Expansive Soils –The near-surface soils at the site appear to have a moderate expansion potential. Therefore, no
special treatment is needed to stabilize underneath soils to prevent damage due to expansion and shrinking of
the subgrade soils other than proper moisture conditioning of the subgrade soils immediately prior to construction
of the improvements. However, for potentially sensitive installations such as an artificial turf football field and
track, rendering the field and surrounding track subgrade to a non-expansive condition by chemically treating with
quicklime should be considered. In addition, the recommendations provided in this report to minimize effects of
moderate expansion for all other improvements should be followed.
Winter Construction – If grading occurs in the winter rainy season, appropriate erosion control measures will be
required and weatherproofing of the excavations, athletic tracks, fields, and/or pavement areas should be
considered. Winter rains may also impact subgrade excavations and underground utilities.
Other potential geotechnical considerations, including those that should not significantly impact the project are
explained below.
13
Corrosive Soil – The preliminary corrosion evaluation indicated the test sample was non-corrosive to concrete,
buried cast, and ductile iron pipe.
Groundwater – Groundwater was not encountered at the site within 10 feet at the time of drilling. Therefore,
subsurface groundwater is not expected to significantly impact the proposed improvements.
5.2 Seismic Design Parameters
Structural buildings, if any, should be designed in accordance with local design practice to resist the lateral forces
generated by ground shaking associated with a major earthquake occurring within the greater San Francisco Bay
region. Based on the subsurface conditions encountered in our borings and our evaluation of the geology of the
site, we judge Site Class “D”, representative of stiff soils averaged over the uppermost 100 feet of the subsurface
profile to be appropriate for this site. For design of the proposed site structures in accordance with the seismic
provisions of the CBC 2016 and American Society of Civil Engineers (ASCE) 7-10, the following seismic ground
motion values should be used for design.
Table 5.2.1: Seismic Coefficients Based on 2016 CBC (per ASCE 7-10)
Item Value 2013 CBC SourceR1 ASCE 7-10
Table/FigureR2
Site Class D Table 1613A.3.2. Table 20.3-1
Mapped Spectral Response Accelerations Short Period, Ss 1-second Period, S1
1.747g 0.613g
Figure 22-1 Figure 22-2
Site Coefficient, Fa 1.0
Table 1613A.3.3(1)
Table 11.4-1
Site Coefficient, Fv 1.5
Table 1613A.3.3(2)
Table 11.4-2
MCE (SMS) 1.747g Equation 16A-37 Equation 11.4-1
MCE (SM1) 0.920g Equation 16A-38 Equation 11.4-2
Design Spectral Response Acceleration Short Period, SDS 1-second Period, SD1
1.165g 0.613g
Equation 16A-39 Equation 16A-40
Equation 11.4-3 Equation 11.4-4
Modified Peak Ground Acceleration (PGAM) 0.662g
R1 California Building Standards Commission (CBSC), “California Building Code,” 2013 Edition. R2 U.S. Seismic “Design Maps” Web Application, https://geohazards.usgs.gov/secure/designmaps/us/application.php
ASCE 7-15 § 11.6-1 and 11.6-2 indicate that the Seismic Design Category for all Occupancy Categories is “D”.
14
5.3 Site Grading
5.3.1 General Grading, Fill Material Requirements and Site Drainage
Site grading is generally anticipated to consist of minor cuts and fills required to construct the athletic track and
field as well as the baseball and softball fields to establish new site grades as required. Existing onsite soils
generated from cut areas following clearing and grubbing that is free of organic material (three percent or less by
weight) or debris is suitable for use as structural, non-select fill at the site, as approved by the Geotechnical
Engineer. Imported select fill, if any, should be non-expansive, having a Plasticity Index of 15 or less, an R-Value
greater than 40, and enough fines so the soil can bind together. Imported soils should be free of organic materials
and debris, and should not contain rocks or lumps greater than three inches in maximum size. The Geotechnical
Engineer should approve imported fill prior to delivery onsite.
Final grading should be designed to provide drainage away from athletic fields or provide adequate subsurface
drainage system. Adjacent concrete hardscape should slope a minimum two percent away from buildings or
structures, if any. Roof leaders and downspouts, if any, should not discharge into landscape areas adjacent to
buildings, and should discharge onto paved surfaces sloping away from the structure or into a closed pipe system
channeled away from the structure to an approved collector or outfall.
5.3.2 Site Preparation and Demolition
Site grading should be performed in accordance with these recommendations. A pre-construction conference
should be held at the jobsite with representatives from the owner, general contractor, grading contractor, and
Geosphere prior to starting the clearing and demolition operations at the site.
Prior to commencement of grading activities, areas to receive fill, structures, or pavements should be cleared of
existing surface vegetation, organic-laden soils, building materials including foundations if present, existing loose
soil, concrete, asphalt concrete (AC) and aggregate base (AB) pavement sections, debris and other deleterious
materials. Debris resulting from site stripping operations should be removed from the site, unless otherwise
permitted by the Geotechnical Engineer.
Excavations resulting from the removal of abandoned underground utilities, or deleterious materials should be
cleaned down to firm soil, processed as necessary, and backfilled with engineered fill in accordance with the
grading sections of this report. The Geotechnical Engineer’s representative should verify the adequacy of site
clearing operations during construction, prior to placement of engineered fill.
15
Existing underground utilities proposed to be abandoned, if present, should be properly grouted, closed, or
removed as needed. If the utilities are removed, the excavations should be backfilled with properly compacted fill
or other material approved by the Geotechnical Engineer. The extent of removal/abandonment depends on the
diameter of the pipe, depth of the pipe, and proximity to buildings and pavement.
5.3.3 Project Compaction Recommendations
The following table provides the recommended compaction requirements for this project. Not all soils, aggregates
and scenarios listed below may be applicable for this project. Specific grading recommendations are discussed
individually within applicable sections of this report.
Table 5.3.3.1: Project Compaction Requirements
Description Min. Percent Relative Compaction
(per ASTM D1557)
Relative to Optimum
Moisture Content
Fill Areas, Engineered Fill, Onsite Soil 90 + 3
Fill Areas, Engineered Fill, Select Fill 90 ± 3
Athletic Fields, Onsite Soil – scarified subgrade or used as Fill 90 + 3
Athletic Fields, Aggregate Base or Select (non-expansive) Engineered Fill
90 + 3
Athletic Fields – Treated Soil 90 ± 3
Concrete Flatwork, Subgrade Soil 90 + 3
Concrete Flatwork, Aggregate Base 90 ± 3
Underground Utility Backfill 90 + 3
AC Pavement – Onsite Subgrades (upper 12 inches) 95 + 3
AC Pavement – Non-Expansive Subgrades in Non-Traffic (e.g., Field) Areas (upper 12 inches)
90 ± 3
Pavement – Class 2 Aggregate Base Section 95 ± 3
5.3.4 Athletic Fields (Football, Softball & Baseball) Grading
After demolition, site preparation, and grading to the required subgrade level, all of the field subgrade soil should
be scarified to a depth of at least eight inches, moisture conditioned to at least three percent over optimum
moisture, and compacted to the project compaction requirements listed on the above table as determined by
ASTM D1557 (Modified Proctor). If loose or soft soil is encountered, these soils should be removed to expose firm
soil and backfilled with engineered fill. Engineered fill should be placed in maximum eight-inch thick, pre-
16
compacted lifts. The fill should be moisture conditioned and thoroughly mixed during placement to provide
uniformity in each layer. After the final compacted soil subgrade has been reached, a minimum six-inch thick layer
of Aggregate Base (AB) should be placed immediately after grading to protect the subgrade soil from drying.
Alternatively, the soil subgrade should be kept moist by watering until aggregate base or other field surface
material is placed. After the field soil subgrade is prepared, the artificial turf section with an AB layer as applicable
and with proper designed drainage system should be installed.
As an additional measure of protection against surface volume change effects on artificial turf and track sections,
consideration should be given to chemically treating the graded turf and track subgrade to a non-expansive
condition using quicklime. For design purposes, a three percent by dry weight mixture of quicklime added to the
upper 12 inches of turf/track subgrade may be considered. Quicklime treatment of the field/track subgrades may
also double as winterizing stabilization of the subgrade should construction take place during the wet season
(Section 5.3.6). Note: If the subgrade is lime treated, the six-inch thick AB section may be eliminated.
We should be given an opportunity to review the final proposed artificial turf section for this project. Re-evaluation
of the subgrade preparation recommendations may be required depending upon the specifically proposed design
section for the artificial turf.
5.3.5 Grading Flatwork Areas and Athletic Tracks
Areas to receive flatwork or asphalt concrete (AC) pavements below track surfaces should be scarified to a depth
of eight inches below existing grade or final subgrade, whichever is lower. Scarified areas should be moisture
conditioned and compacted. Where required, engineered fill should be placed and compacted to reach design
subgrade elevation. Once the compacted pavement subgrade has been reached, it is recommended that a
minimum of six inches of AB in paved (i.e., athletic tracks) and four inches of AB on-grade concrete slab areas be
placed immediately after grading to protect the subgrade soil from drying. Alternatively, the subgrade should be
kept moist by watering until AB is placed, or the artificial track surface pavement subgrade may be lime treated
as described in Section 5.3.4. If the track subgrade is lime treated, the AB section underlying AC may be omitted.
If an AB section is placed under the track AC course, the AB section should be vertically cut off along the pavement
boundaries using a deepened concrete curb or header to reduce the potential for moisture to migrate under the
pavement section. Cutoffs should extend a minimum two inches below the bottom of the AB layer.
17
Rubber-tired heavy equipment, such as a full water truck, should be used to proofload exposed subgrade areas
where pumping is suspected. Proof loading will determine if the subgrade soil is capable of supporting
construction equipment without excessive pumping or rutting.
5.3.6 Site Winterization and Unstable Subgrade Conditions
If grading occurs in the winter rainy season, unstable and unworkable subgrade conditions may be present and
compaction of onsite soils may not be feasible. These conditions may be remedied using soil admixtures, such as
lime. A four percent mixture of lime based on a soil unit weight of 125 pcf is recommended for planning purposes.
Treatment should vary between 8 to 12 inches, depending on the anticipated construction equipment loads and
degree of observed subgrade instability. More detailed and final recommendations can be provided during
construction. Stabilizing subgrade in small, isolated areas can be accomplished with the approval of the
Geotechnical Engineer by over-excavating one foot, placing Tensar TriAx TX-140, BX1100, or equivalent geogrid
on the soil, and then placing at least 12 inches of Class 2 aggregate base on the geogrid. The upper six inches of
the aggregate base should be compacted to at least 90 percent relative compaction.
5.4 Utility Trench Construction
5.4.1 Trench Backfilling
Utility trenches may be backfilled with onsite soil above the utility bedding and shading materials. If rocks or
concrete larger than four inches in maximum size are encountered, they should be removed from the fill material
prior to placement in the utility trenches. Utility bedding and shading compaction requirements should be in
conformance with the requirements of the local agencies having jurisdiction and as recommended by the pipe
manufacturers. Jetting of trench backfill is not recommended. Compaction recommendations are presented in
Table 5.3.3.1.
If rain is expected and the trench will remain open, the bottom of the trench may be lined with one to two inches
of gravel. This would provide a working surface in the trench bottom. The trench bottom may have to be sloped
to a low point to pump the water out of the trench.
5.4.3 Pipe Bedding and Shading
Pipe bedding material is placed in the utility trench bottom to provide a uniform surface, a cushion, and protection
for the utility pipe. Shading material is placed around the utility pipe after installation and testing to protect the
pipe. Bedding and shading material and placement are typically specified by the pipe manufacturer, agency, or
18
project designer. Agency and pipe manufacturer recommendations may supersede our suggestions. These
suggestions are intended as guidelines and our opinions based on our experience to provide the most cost-
effective method for protecting the utility pipe and surrounding structures. Other geotechnical engineers, agency
personnel, contractors, and civil engineers may have different opinions regarding this matter.
Bedding and Shading Material - The bedding and shading material should be the same material to simplify
construction. The material should be clean, uniformly graded, fine to medium grained sand. It is suggested that
bedding and shading material contain less than three percent fines with 100 percent passing the No. 8 sieve.
Coarse sand, angular gravel or aggregate base should be avoided since this type of shading material may bridge
when backfilling around the pipe, possibly creating voids, and may be too stiff as bedding material. Open graded
gravel should be avoided for shading since this material contains voids, and the surrounding soil could wash into
the voids, potentially causing future ground settlement. However, open graded gravel may be required for
bedding material when water is entering the trench. This would provide a stable working surface and a drainage
path to a sump pit in the trench for water in the trench. The maximum size for bedding material should be limited
to about ¾ -inch.
Bedding Material Placement - The thickness of the bedding material should be minimized to reduce the amount
of trench excavation, soil export, and imported bedding material. Two to three inches for pipes less than eight-
inches in diameter and about four to six inches for larger pipes are suggested. Bedding for very large diameter
pipes are typically controlled by the pipe manufacturer. Compaction is not required for thin layers of bedding
material. The pipe needs to be able to set into the bedding, and walking on a thin layer of bedding material should
sufficiently compact the sand. Rounded gravel may be unstable during construction, but once the pipe and shading
material is in place, the rounded gravel will be confined and stable.
Shading Material Placement – Jetting is not typically recommended since the type of shading material is unknown
when preparing the geotechnical report and agencies typically do not permit jetting. If the sand contains fines or
if the sand is well graded, jetting will not work. Additionally, if too much water is used during jetting, this could
create a wet and unstable condition. However, clean, uniformly graded and fine to medium sand can be placed
by jetting. The shading material should be able to flow around and under the utility pipe during placement. Some
compactive effort along the sides of the pipe should be made by the contractor to consolidate the shading material
around the pipe. A minimum thickness of about six-inches of shading material should be placed over the pipe to
protect the pipe from compaction of the soil above the shading material. The contractor should provide some
19
compactive effort to densify the shading material above the pipe. Relative compaction testing is not usually
performed on the shading material. However, the contractor is ultimately responsible for the integrity of the utility
pipe.
5.5 Pier Foundations
Foundations for bleacher structures, light towers, poles, and other athletic field features such as scoreboards and
goal post poles, if any, may consist of drilled pier foundations deriving their vertical supporting capacity through
skin friction between the side surfaces of the foundations and the adjacent soil. For design purposes, the allowable
skin friction for gravity loads may be assumed to be 400 psf for the portion of pier embedded in competent native
soils or engineered fills. These values assume a safety factor of 2, and may be increased by one-third for seismic
or transient loads. Uplift loads should be limited to two-thirds of these values. For piers situated adjacent to or on
slopes, the portion of pier with horizontal cover less than 10 feet, measured from outside perimeter of the pier to
the slope surface should be neglected in computing vertical capacity.
Lateral resistance for drilled pier foundations may be determined for onsite soils using an allowable passive
resistance equal to an equivalent fluid weighing 350 pounds per cubic foot (pcf) acting against the foundation for
lateral load resistance against the sides of foundations perpendicular to the direction of loading where the
foundation is poured neat against undisturbed material (i.e., native soils, engineered fills or existing fills). The top
foot of passive resistance at foundations not adjacent to and confined by pavement, interior floor slab, or
hardscape should be neglected. For pier foundations, passive pressure can be assumed to act across two times
the pier diameter. For piers situated adjacent to or on slopes, the portion of pier with horizontal cover less than
10 feet, measured from outside perimeter of the pier to the slope surface should be neglected in computing lateral
capacity.
5.6 Exterior Concrete Flatwork
Exterior concrete flatwork with pedestrian traffic should be at least four-inches thick. If an underlying aggregate
base layer is used, the AB layer should be at least four inches thick and should be cut off from direct moisture
transmission from directly adjacent landscape areas by use of a concrete cutoff or a deep header board extending
at least two inches below the base of the aggregate base layer. In any case, due to the moderately expansive
conditions, we recommend that the upper eight-inches of flatwork subgrade be moisture conditioned to a
minimum of three to five percent over optimum moisture. This moisture should be verified within 24 hours of
placing aggregate base over the subgrade and again prior to concrete pouring.
20
5.7 Athletic Track Asphalt Concrete Pavements
R-value testing was conducted on a representative soil sample of potential subgrade material. Laboratory test
results indicated a measured R-Value of 30. Based on the test result and anticipated loading, we recommend using
a minimum three-inch thickness of ½” nominal maximum size asphalt concrete (AC) mix underlain by a six-inch
thick layer of Class 2 aggregate base (AB) on the compacted subgrade. However if the subgrade is lime treated, as
discussed in Section 5.3.4, we recommend a minimum four-inch thickness of ½” nominal maximum size AC mix
placed directly over the lime treated subgrade (i.e., AB layer not required).
5.8 Plan Review
We recommend that Geosphere be provided the opportunity to review the final project plans prior to
construction. The purpose of this review is to assess the general compliance of the plans with the
recommendations provided in this report and confirm the incorporation of these recommendations into the
project plans and specifications.
5.9 Observation and Testing During Construction
We recommend that Geosphere be retained to provide observation and testing services during site preparation,
mass grading, underground utility construction, foundation excavation, and to observe final site drainage. This is
to observe compliance with the design concepts, specifications and recommendations, and to allow for possible
changes in the event that subsurface conditions differ from those anticipated prior to the start of construction.
21
6.0 VALIDITY OF REPORT
This report is valid for three years after publication. If construction begins after this time period, Geosphere should
be contacted to confirm that the site conditions have not changed significantly. If the proposed development
differs considerably from that described above, Geosphere should be notified to determine if additional
recommendations are required. Additionally, if Geosphere is not involved during the geotechnical aspects of
construction, this report may become wholly or in part invalid; Geosphere’s geotechnical personnel should be
retained to verify that the subsurface conditions anticipated when preparing this report are similar to the
subsurface conditions revealed during construction. Geosphere’s involvement should include grading and
foundation plan review, grading observation and testing, foundation excavation observation, and utility trench
backfill testing.
22
7.0 LIMITATIONS AND UNIFORMITY OF CONDITIONS
The recommendations of this report are based upon the soil and conditions encountered in the borings. If
variations or undesirable conditions are encountered during construction, Geosphere should be contacted so that
supplemental recommendations may be provided.
This report is issued with the understanding that it is the responsibility of the owner or his representatives to see
that the information and recommendations contained herein are called to the attention of the other members of
the design team and incorporated into the plans and specifications, and that the necessary steps are taken to see
that the recommendations are implemented during construction.
The findings and recommendations presented in this report are valid as of the present time for the development
as currently proposed. However, changes in the conditions of the property or adjacent properties may occur with
the passage of time, whether by natural processes or the acts of other persons. In addition, changes in applicable
or appropriate standards may occur through legislation or the broadening of knowledge. Accordingly the findings
and recommendations presented in this report may be invalidated, wholly or in part, by changes outside our
control. Therefore, this report is subject to review by Geosphere after a period of three (3) years has elapsed from
the date of issuance of this report. In addition, if the currently proposed design scheme as noted in this report is
altered Geosphere should be provided the opportunity to review the changed design and provide supplemental
recommendations as needed.
Recommendations are presented in this report which specifically request that Geosphere be provided the
opportunity to review the project plans prior to construction and that we be retained to provide observation and
testing services during construction. The validity of the recommendations of this report assumes that Geosphere
will be retained to provide these services.
This report was prepared upon your request for our services, and in accordance with currently accepted
geotechnical engineering practice. No warranty based on the contents of this report is intended, and none shall
be inferred from the statements or opinions expressed herein.
The scope of our services for this report did not include an environmental assessment or investigation for the
presence or absence of wetlands or hazardous or toxic materials in the soil, surface water, groundwater or air, on,
below or around this site. Any statements within this report or on the attached figures, logs or records regarding
odors noted or other items or conditions observed are for the information of our client only.
23
8.0 REFERENCES
American Society for Testing and Materials, West Conshohocken, Pennsylvania. American Society of Civil Engineers (ASCE), third printing 2013, Minimum Design Loads for Buildings and Other Structures; Standard 7-10.
California Building Code, 2016, Title 24, Part 2. California Department of Transportation (Caltrans); California Standard Specifications, 2015. California Geological Survey, 2008, Guidelines for evaluating and mitigating seismic hazards in California: California Geological Survey Special Publication 117A, 98 p.
Dibblee, T.W. Jr., 2006, Geologic Map of the Clayton Quadrangle, Contra Costa County, California: Santa Barbara Museum of Natural History, Dibblee Geology Center Map #DF-192, edited by Minch, J.A., scale 1:24,000. Graymer, R.W., Moring, B.C., Saucedo, G.J., Wentworth, C.M., Brabb, E.E., and Knudsen, K.L., 2006, Geologic Map of the San Francisco Bay Region, California: U.S. Geological Survey Scientific Investigations Map 2918, Scale 1:275,000. Jennings, C.W., and Bryant, W.A., compilers, 2010: 2010 Fault activity map of California: California Geological Survey, Geologic Data Map No. 6, scale 1:750,000, with 94-page Explanatory Text booklet. Page, B.M., 1966, Geology of the Coast Ranges of California: in Bailey, E.H., Jr., editor, Geology of Northern California: California Geological Survey Bulletin 190, p. 255-276. 2007 Working Group on California Earthquake Probabilities (WGCEP), 2008, The Uniform California Earthquake Rupture Forecast, Version 2 (UCERF 2): U.S. Geological Survey Open-File Report 2007-1437. U. S. Geological Survey Earthquake Information Center, 2012, website, earthquake.usgs.gov Publications may have been used as general reference and not specifically cited in the report text.
FIGURES
Figure 1 - Site Vicinity Map Figure 2 - Development Site Plan
Figure 3 - Site Plan and Site Geology Map Figure 4 - Site Vicinity Geology Map
Figure 5 – Regional Fault Map Figure 6a - Geological Cross Section A-A’ Figure 6b - Geological Cross Section B-B’
158
160
162
164
166
168
170
172
174
176
0 50 100 150 200 250 300 350 400158
160
162
164
166
168
170
172
174
176
0 50 100 150 200 250 300 350 400
Schematic Geologic Cross-Section A-A'Distance Along Baseline (ft)
SUBSURFACE DIAGRAM
A
Ele
va
tio
n (
ft)
CL - Unified Soil Classification System (USCS)14 - Blows Per Six Inches, Standard Penetration Test(21) - N Value
A'
CLIENT Mount Diablo Unified School District
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
4-4-5(9)
3-4-8(12)
2-4-3(7)
CL
CL
5-10-12(22)
5-5-11(16)
2-3-3(6)
CL
CL
4-5-8(13)
4-5-10(15)
12-13-17(30)
CL
CL
CL
3-4-6(10)
3-5-6(11)
4-5-10(15)
CL
CL
5-6-6(12)
3-3-6(9)
4-4-5(9)
CL
CL
4-5-7(12)
6-7-13(20)
3-3-4(7)
CL
5-6-8(14)
3-3-5(8)
9-16-30(46)
CL
CL
GS
Figure a
B- 1 B- 2
B- 4
B- 6
B- 9
B-10
B-11
164
165
166
167
168
169
170
171
172
173
174
175
0 20 40 60 80 100 120 140164
165
166
167
168
169
170
171
172
173
174
175
0 20 40 60 80 100 120 140
Distance Along Baseline (ft)
SUBSURFACE DIAGRAME
leva
tio
n (
ft)
CL - Unified Soil Classification System (USCS)14 - Blows Per Six Inches, Standard Penetration Test(21) - N Value
CLIENT Mount Diablo Unified School District
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
3-4-5(9)
5-8-10(18)
5-9-16(25)
CL
GC
5-6-6(12)
3-3-6(9)
4-4-5(9)
CL
CL
3-6-11(17)
5-6-9(15)
6-10-23(33)
GS
CL
GC
Figure bSchematic Geologic Cross-Section B-B'
B B'
B- 7B- 9B-12
APPENDIX A
Key to Boring Log Symbols Boring Logs
KEY TO EXPLORATORY BORING LOGS
110
PLASTICITY CHART
LIQUID LIMITS (%)
PLA
ST
ICIT
Y IN
DE
X (
%)
"A" L
INE
CL-ML
CL-OL
CH-OH
OL-M
L
OH-MH
0-30(Low)
30-50(Medium)
>50(High)
50
60
40
30
20
10
050 60403020100 100908070
Grab Bulk Sample Initial Water Level Reading
Shelby Tube
Standard Penetration Test
2.5 Inch Modified California
Final Water Level Reading
No Recovery
Blow Count
The number of blows of the sampling hammer required to drive the sampler through each of three 6-inch increments. Less than three increments may be reportedif more than 50 blows are counted for any increment.The notation 50/5” indicates 50 blows recorded for 5 inches of penetration.
N-Value
Number of blows 140 LB hammer falling 30 inchesto drive a 2 inch outside diameter (1-3/8 inch I.D)split barrel sampler the last 12 inches of an 18inch drive (ASTM-1586 Standard Penetration Test)
CU -DS - Results of Direct Shear test in terms of total cohesion (C, KSF) or effective cohesion and friction angles (C’, KSF and degrees)LL - Liquid LimitPI - Plasticity IndexPP - Pocket Penetrometer testTV - Torvane Shear Test results in terms of undrained shear strength (KSF)UC - Unconfined Compression test results in terms of undrained shear strength (KSF)#200 - Percent passing number 200 sieveCu - Coefficient of UniformityCc - Coefficient of Concavity
Consolidated Undrained triaxial test completed. Refer to laboratory results
General Notes
1. The boring locations were determined by pacing, sighting and/or measuring from site features. Locations are approximate. Elevations of borings (if included) were determined by interpolation between plan contours or from another source that will be identified in the report or on the project site plan. The location and elevation of borings should be consideredaccurate only to the degree implied by the method used.
2. The stratification lines represent the approximate boundary between soil types. The transition may be gradual.
3. Water level readings in the drill holes were recorded at time and under conditions stated on the boring logs. This data has been reviewed and interpretations have been made in the text of this report. However, it must be noted that fluctuations in the level of the groundwater may occur due to variations in rainfall, tides, temperature and other factors at the time measurements were made.
4. The boring logs and attached data should only be used in accordance with the report.
COMPONENTS
PARTICLES SIZES
SIZE OR SIEVE NUMBER
Cu<4 and or [ 1 or Cc 3]Cc< >
Cu<6 and or [Cc<1 or Cc>3]
>
MC1-1
MC1-2
MC1-3
106 17
3" TOPSOIL : (CL) CLAY : Dark brown, moist, stiff, w/ organics.
(CL) CLAY : Brown, moist, stiff, w/ gravels.
Gravelly Sand Lense.
becomes medium stiff.
Bottom of borehole at 10.0 feet.
4-4-5(9)
3-4-8(12)
2-4-3(7)
3.3
3.8
1.5
NOTES
GROUND ELEVATION 166 ft
LOGGED BY JG
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B- 1
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC2-1
MC2-2
MC2-3
112 18 38 20 18 6518
3" TOPSOIL : (CL) CLAY : Dark brown, moist, very stiff, w/ some gravelsand organics.
(CL) SANDY CLAY : Brown, moist, very stiff, w/ fine sand andgravels.
Clayey Sand Lense.
becomes moist to very moist, medium stiff.
Bottom of borehole at 10.0 feet.
5-10-12(22)
5-5-11(16)
2-3-3(6)
3.3
4.5
1.5
NOTES
GROUND ELEVATION 167 ft
LOGGED BY JG
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B- 2
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC3-1
MC3-2
MC3-3
106 20
3" TOPSOIL : (CL) CLAY : Dark brown, moist, stiff, w/ some gravels andorganics.
(CL) CLAY : Brown, moist, stiff, w/ gravels.
becomes moist to very moist, medium stiff.
Bottom of borehole at 10.0 feet.
4-5-6(11)
4-5-7(12)
2-3-2(5)
2.5
4.0
1.3
NOTES
GROUND ELEVATION 168 ft
LOGGED BY JG
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B- 3
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC4-1
MC4-2
MC4-3
3" TOPSOIL : (CL) CLAY : Dark brown, moist, stiff, w/ some gravels andorganics.
(CL) CLAY : Brown, moist, very stiff, w/ gravels.
(CL) GRAVELLY CLAY : Brown, moist, hard, w/ sand.
Bottom of borehole at 10.0 feet.
4-5-8(13)
4-5-10(15)
12-13-17(30)
2.8
>4.5
>4.5
NOTES
GROUND ELEVATION 169 ft
LOGGED BY JG
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B- 4
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC5-1
MC5-2
MC5-3
110 18
3" TOPSOIL : (CL) CLAY : Dark brown, moist, very stiff.
(CL) CLAY : Brown, moist, stiff, w/ gravels.
(GS) SANDY CLAYEY GRAVEL : Brown, moist, mediumdense.
Bottom of borehole at 10.0 feet.
8-12-12(24)
3-3-6(9)
6-8-11(19)
3.5
3.8
2.0
NOTES
GROUND ELEVATION 170 ft
LOGGED BY JG
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B- 5
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC6-1
MC6-2
MC6-3
102 22 69
3" TOPSOIL : (CL) SANDY CLAY : Dark brown, moist, stiff, fine.
(CL) CLAY : Brown, moist, stiff.
becomes very stiff, w/ gravels.
Bottom of borehole at 10.0 feet.
3-4-6(10)
3-5-6(11)
4-5-10(15)
3.8
4.0
3.5
NOTES
GROUND ELEVATION 174 ft
LOGGED BY JG
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B- 6
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC7-1
MC7-2
MC7-3
104 24
1" AGGREGATE BASE : Gray
(CL) CLAY : Dark brown, moist, stiff, w/ some gravels.
becomes very stiff.
(GC) SANDY CLAYEY GRAVEL : Mottled brown, olive, red,and orange, damp, medium dense.
Bottom of borehole at 10.0 feet.
3-4-5(9)
5-8-10(18)
5-9-16(25)
3.5
NOTES
GROUND ELEVATION 175 ft
LOGGED BY NA
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B- 7
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC8-1
MC8-2
MC8-3
107
114
21
16
9" GRAVELLY SAND : Gray, w/ fine gravels
(GS) GRAVEL w/ SAND : Gray, damp, medium dense.
(CL) CLAY : Dark brown, moist, very stiff.
becomes stiff, w/ traces of fine gravels.
(GC) SANDY CLAYEY GRAVEL : Mottled brown, olive, red,and orange, moist, very dense.
Bottom of borehole at 10.0 feet.
4-5-10(15)
4-4-8(12)
25-33
2.8
3.3
NOTES
GROUND ELEVATION 175 ft
LOGGED BY NA
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B- 8
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC9-1
MC9-2
MC9-3
100 24 76
3" TOPSOIL : (CL) CLAY w/ SAND : Dark brown, moist, stiff, fine.
(CL) CLAY : Brown, moist.
becomes stiff.
Bottom of borehole at 10.0 feet.
5-6-6(12)
3-3-6(9)
4-4-5(9)
1.5
3.0
2.5
NOTES
GROUND ELEVATION 175 ft
LOGGED BY JG
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B- 9
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC10-1
MC10-2
MC10-3
105
105
21
19
45 20 25 8325
3" TOPSOIL : (CL) CLAY w/ SAND : Dark brown, moist, stiff, w/ fine sandand traces of gravel.
becomes very stiff.
becomes dark brown to brown, medium stiff.
Bottom of borehole at 10.0 feet.
4-5-7(12)
6-7-13(20)
3-3-4(7)
2.3
4.3
2.6
NOTES
GROUND ELEVATION 176 ft
LOGGED BY NA
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B-10
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC11-1
MC11-2
MC11-3
109 17
3" TOPSOIL : (CL) CLAY : Dark brown, moist, stiff, w/ traces of gravels.
(CL) CLAY : Brown, moist, stiff, w/ some gravels.
(GS) SANDY CLAYEY GRAVEL : Mottled brown, olive, red,and orange, damp, dense.
Bottom of borehole at 10.0 feet.
5-6-8(14)
3-3-5(8)
9-16-30(46)
3.8
NOTES
GROUND ELEVATION 176 ft
LOGGED BY NA
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B-11
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC12-1
MC12-2
MC12-3
97
110
24
17
9" SAND : Gray, w/ fine gravel
(GS) GRAVEL w/ SAND : Gray, damp, medium dense.
(CL) CLAY : Dark brown, moist, very stiff, w/ traces of gravels.
(GC) SANDY CLAYEY GRAVEL : Mottled brown, olive, red,and orange, moist, dense.
Bottom of borehole at 10.0 feet.
3-6-11(17)
5-6-9(15)
6-10-23(33)
0.50
3.3
NOTES
GROUND ELEVATION 175 ft
LOGGED BY NA
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B-12
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
MC13-1
MC13-2
MC13-3
100 24
3" TOPSOIL : (CL) CLAY : Brown, moist, stiff, w/ traces of organics.
w/ traces of gravels.
becomes lighter brown, medium stiff.
Bottom of borehole at 10.0 feet.
3-4-8(12)
4-4-10(14)
2-3-3(6)
1.3
3.3
1.6
NOTES
GROUND ELEVATION 172 ft
LOGGED BY NA
DRILLING METHOD Hollow Stem Auger 8"
HOLE SIZE 8 inches
DRILLING CONTRACTOR Exploration Geoservices Inc. GROUND WATER LEVELS:
CHECKED BY CTD
DATE STARTED 3/3/17 COMPLETED 3/3/17
AT TIME OF DRILLING ---
AT END OF DRILLING ---
AFTER DRILLING ---
SA
MP
LE
TY
PE
NU
MB
ER
RE
CO
VE
RY
%(R
QD
)
DR
Y U
NIT
WT
.(p
cf)
MO
IST
UR
EC
ON
TE
NT
(%
)
LIQ
UID
LIM
IT
PL
AS
TIC
LIM
IT
PL
AS
TIC
ITY
IND
EX
FIN
ES
CO
NT
EN
T(%
)
ATTERBERGLIMITS
PL
AS
TIC
ITY
IND
EX
GR
AP
HIC
LO
G
DE
PT
H(f
t)
0
5
10
MATERIAL DESCRIPTION
SP
T B
LO
WC
OU
NT
S(N
VA
LU
E)
PO
CK
ET
PE
N.
(tsf)
PAGE 1 OF 1
BORING NUMBER B-13
PROJECT NUMBER 91-03875-A
PROJECT NAME Concord High School - Athletic Fields
PROJECT LOCATION 4200 Concord Boulevard, Concord, California 94521
CLIENT Mount Diablo Unified School District
2001 Crow Canyon Road, Suite 210San Ramon, CA 94583Telephone: (925) 314-7100Fax: (925) 855-7140
APPENDIX B LABORATORY TEST RESULTS
Liquid and Plastic Limits Test Report
Sieve Analysis Results R-Value Test Result
Corrosivity Test Summary
Tested By: MA Checked By:
Dark brown sandy CLAY. 38 20 18 85.6 65.3 CL
Brownish black lean CLAY with sand. 45 20 25 95.0 82.9 CL
91-03875-A Geosphere Consultants,Inc.
MATERIAL DESCRIPTION LL PL PI %<#40 %<#200 USCS
Project No. Client: Remarks:
Project:
Soil Mechanics Lab
Oakland, California Plate
Depth: 4.5' Sample Number: B-2 2-2
Depth: 4.5' Sample Number: B-10 10-2
PLA
ST
ICIT
Y I
ND
EX
0
10
20
30
40
50
60
LIQUID LIMIT0 10 20 30 40 50 60 70 80 90 100 110
CL-ML
CL o
r OL
CH o
r OH
ML or OL MH or OH
Dashed line indicates the approximateupper limit boundary for natural soils
4
7
LIQUID AND PLASTIC LIMITS TEST REPORT
Concord HS-Athletic Fields
Tested By: MA Checked By:
Soil Mechanics Lab
Oakland, California
Client:
Project:
Project No.: Plate
Geosphere Consultants,Inc.
Concord HS-Athletic Fields
91-03875-A
SYMBOL SOURCESAMPLE DEPTH
Material Description USCSNO. (ft.)
SOIL DATA
PE
RC
EN
T F
INE
R
0
10
20
30
40
50
60
70
80
90
100
GRAIN SIZE - mm.
0.0010.010.1110100
% +3"Coarse
% Gravel
Fine Coarse Medium
% Sand
Fine Silt
% Fines
Clay
0.0 0.0 4.7 4.3 5.4 20.3 65.3
0.0 0.0 5.8 1.4 3.7 20.2 68.9
0.0 0.0 4.1 3.3 3.2 13.3 76.1
0.0 0.0 0.7 1.5 2.8 12.1 82.9
6 in.
3 in.
2 in.
1½
in.
1 in.
¾ in.
½ in.
3/8
in.
#4
#10
#20
#30
#40
#60
#100
#140
#200
Particle Size Distribution Report
B-2 2-2 4.5' Dark brown sandy CLAY. CL
B-6 6-1 2' Dark brown sandy CLAY. CL
B-9 9-1 2' Brownish black lean CLAY with sand. CL
B-10 10-2 4.5' Brownish black lean CLAY with sand. CL
R-VALUE TEST REPORT
CONSOLIDATED ENGINEERING LABORATORIES -- SAN RAMON, CA
R-VALUE TEST REPORT
Date: 4/5/2017
Project No.: 9103875A
Project:Concord High School-Athletic Improvements
Location: B-8 Depth @ 2.5"
Sample Number: 10S170405-1
Remarks:
Checked by: WY
Tested by: JLA
Brown Fat Clay with Gravel
Sampled on 3/3/17 by N. Anastasio
10S170405-1
Material DescriptionTest Results
No.
Compact.
Pressure
psi
Density
pcf
Moist.
%
Expansion
Pressure
psi
Horizontal
Press. psi
@ 160 psi
Sample
Height
in.
Exud.
Pressure
psi
R
Value
R
Value
Corr.
Resistance R-Value and Expansion Pressure - ASTM D 2844
R-value at 300 psi exudation pressure = 30
1 160 116.5 17.0 0.00 104 2.50 316 32 32
2 130 116.9 17.1 0.00 114 2.50 239 27 27
3 180 117.5 16.1 0.00 94 2.50 427 41 41
Exudation Pressure - psi
R
-valu
e
100 200 300 400 500 600 700 8000
20
40
60
80
100
CTL # Date: PJ
Client: Project:Remarks:
Chloride pH Sulfide MoistureAs Rec. Min Sat. mg/kg mg/kg % Qualitative At Test
Dry Wt. Dry Wt. Dry Wt. EH (mv) At Test by Lead %Boring Sample, No. Depth, ft. ASTM G57 Cal 643 ASTM G57 ASTM D4327 ASTM D4327 ASTM D4327 ASTM G51 ASTM G200 Temp °C Acetate Paper ASTM D2216
B-10 - 2-4 - - 1,231 6 91 0.0091 7.4 369 20 Negative 23.3 Dark Gray Sandy CLAY
Corrosivity Tests Summary
(Redox)
PJ
91-03875-A
Resistivity @ 15.5 °C (Ohm-cm)
Proj. No:Checked:3/10/2017
Geosphere Consultants
Soil Visual Description
724-155
Concord HS Athletic Field
Sample Location or ID Sulfate ORP
Tested By: