SW Gibbs St. Pedestrian Bridge Over I-5
Project Update: August 13, 2009
SW Gibbs St. Pedestrian Bridge
! Status! Bid Opening - September 24, 2009
! Construction Estimate - $6.5M
! Anticipated Construction Notice to Proceed –Mid-November
! Anticipated Construction Activity – January 2010
! Completion – January 15, 2011