Date post: | 09-May-2015 |
Category: |
Documents |
Upload: | global-ccs-institute |
View: | 241 times |
Download: | 1 times |
PANEL 1
INTERNATIONAL PROGRESS ON CCS PROJECTS Len Heckel – Shell Quest Laura Miller – Summit Power Hans Schoenmakers – ROAD
QUEST CCS PROJECT PROGRESSGlobal CSS Institute (GCCSI)
International Members Meeting
Calgary
October 10, 2012
Use this area for cover image(height 6.5cm, width 8cm)
Len Heckel – Quest Venture Manager
October 10, 2012 3 Quest Progress: GCCSI International Members Meeting
Alberta
Canada
Quest Fort Saskatchewan
Fort McMurray
Edmonton
Calgary
Quest Location
October 10, 2012 4 Quest Progress: GCCSI International Members Meeting
General Features
Quest CCS Project - fully integrated CCS (capture, transport & storage)
Project Approval – Sept 2012
JV among Shell (60%); Chevron (20%); and Marathon (20%)
Located at Scotford Upgrader Complex
35% reduction of Upgrader CO2
emissions
Uses existing technology
Capacity to capture over one million tonnesof CO2 per year for 25 years
Equiv to emissions from175,000 cars
Quest Progress: GCCSI International Members Meeting
October 10, 2012 5
Hardware
SALT SEALS
Cement
SHALE SEALS
TARGET FORMATION
Quest CCS Project CO2 capture plant located in Fort Saskatchewan, approx 50 km N.E. of Edmonton
Capture at the Scotford Upgrader from 3 Hydrogen Manufacturing Units
CO2 transported by 12 inch pipeline to storage, with 6 inch laterals
The pipeline will travel approx. 65 km north of the Scotford Upgrader to the chosen injection locations
Route selected to meet stakeholder requirements: 28 km follows existing ROW Drilled under North Saskatchewan River 30+ re-routes to accommodate landowner wishes
Base plan: 3 injection wells and associated monitoring
October 10, 2012 6 Quest Progress: GCCSI International Members Meeting
Project Approval Critical Features
Safe and secure storage complex
Capture technology fit to base facility
Degree of economic robustness
Clarity in regulatory environment
Extensive stakeholder engagement
October 10, 2012 7 Quest Progress: GCCSI International Members Meeting
Project Approval Critical Features
Safe and secure storage complex
Capture technology fit to base facility
Degree of economic robustness
Clarity in regulatory environment
Extensive stakeholder engagement
October 10, 2012 8 Quest Progress: GCCSI International Members Meeting
Storage
7
SALT SEALS
Intermediate Casing
Main Injection Casing
Cement
Surface Casing
Tubing
SHALE SEALS
TARGET FORMATION
PackerAssembly
Perforations allow CO2 to penetrate the formation
Saline aquifer storage
Basal Cambrian Sands (BCS) selected
Storage zone is a formation called Basal Cambrian Sands (BCS) 2,300 m, Prairies deepest sandstone
Multiple caprock and salt seal layers, no significant faulting visible from wells or seismic
The BCS is well below hydrocarbon bearing formations and potable water zones in the region
Relatively few wells drilled into the BCS, none within 10 km of the proposed storage site
Wells and Drilling
3 well plan, 5 more if required
Conventional drilling methods
Multiple steel casings for wells, 3 in freshwater zone, all cemented to surface
October 10, 2012 9 Quest Progress: GCCSI International Members Meeting
Geological Formation – BCS Complex
Basal Cambrian Sand (BCS)
Complex Location
October 10, 2012
10
Quest Progress: GCCSI International Members Meeting
Pore space area required to ensure no pressure front interference
Geological Formation Area of Interest (AOI)
DeltaPKpa
CO2 Saturation
October 10, 2012 11 Quest Progress: GCCSI International Members Meeting
CO2 Containment Loss Risk and Mitigation Diagram
Bulls-eye hazard assessment diagram – left: possible causes; centre: event; right: consequences
MMV Framework - Containment Risk Bowtie Analysis
October 10, 2012 12 Quest Progress: GCCSI International Members Meeting
Comprehensive plan developed – entire biosphere and lifecycle
Independently (DNV) certified MMV and storage plan
Measurement, Monitoring and Verification (MMV Plan)
October 10, 2012 13 Quest Progress: GCCSI International Members Meeting
Project Approval Critical Features
Safe and secure storage complex
Capture technology fit to base facility
Degree of economic robustness
Clarity in regulatory environment
Extensive stakeholder engagement
October 10, 2012 14 Quest Progress: GCCSI International Members Meeting
Capture Design
Shell ADIP-X Amine process (99%+ pure CO2),1.2 MTPa capacity Mutlistage centrifugal compressor to 8.5 Mpa (supercritical state) TEG dehydration unit
Capture 3D Model – HMU 1&2
October 15, 2012 10Quest: PTAC Clean Energy Production Forum 2012
Amine Absorbers (HMU 1 & 2)
Amine Stripper
Compressor & Dehydration System
October 10, 2012 15 Quest Progress: GCCSI International Members Meeting
October 10, 2012 16 Quest Progress: GCCSI International Members Meeting
Project Approval Critical Features
Safe and secure storage complex
Capture technology fit to base facility
Degree of economic robustness
Clarity in regulatory environment
Extensive stakeholder engagement
Quest Progress: GCCSI International Members Meeting
October 10, 2012 17
Costs/ Revenues and Funding Agreements
SALT SEALS
Cement
SHALE SEALS
TARGET FORMATION
Total cost of Quest – Approx. Cdn$1.4 billion Includes Pre FID, capital and 10 years opex Capital Ratio: 80% Capture, 10% pipeline, 10% wells
Revenues – GHG offsets (credits) Net amount – stored CO2, less direct and indirect emissions Credits to be used first by Shell’s Alberta assets for regulatory compliance Additional credits as early developer
Government Funding Support – Cdn$865 million Cdn$120 million Canadian Federal Government (Pre FID) Cdn$745 million Alberta Province (Construction, Startup and 10 years operation) Extensive knowledge sharing Stringent monitoring (MMV) plan NPV Zero commitment
October 10, 2012 18 Quest Progress: GCCSI International Members Meeting
Project Approval Critical Features
Safe and secure storage complex
Capture technology fit to base facility
Degree of economic robustness
Clarity in regulatory environment
Extensive stakeholder engagement
October 10, 2012 19 Quest Progress: GCCSI International Members Meeting
Provincial GHG framework established November 2010 – CCS Act passed, establishing overall structure
May 2011 – Pore space regulations set – Quest acquires required area
March 2012 – ERCB Public Hearing
July 2012 – ERCB Decision Report Issued – conditional approval
August 2012 – Quest License granted with Ministers Approval
September 2012 – Well License approvals granted
December 2012 – Expected completion of Regulatory Framework Assessment work
Regulatory Framework and Timeframe
October 10, 2012 20 Quest Progress: GCCSI International Members Meeting
Project Approval Critical Features
Safe and secure storage complex
Capture technology fit to base facility
Degree of economic robustness
Clarity in regulatory environment
Extensive stakeholder engagement
October 10, 2012 21 Quest Progress: GCCSI International Members Meeting
Extensive and continuous public engagement 1st public project disclosure: Oct 2008 (booklet, news release and open house)
Stakeholder consultation program initiated Jan 2010
All landowners within 450 of either side of pipeline right of way
All landowners in storage AOI
All Landowners within 5 km of Scotford
Municipal districts/ local authorities
Industry stakeholders
Provincial / Federal regulators
Aboriginal communities
Open Houses: March, November 2010, September 2011 and planned November 2012
Quest Café’s: June, October 2011
Bi-annual County and Town Council updates
Quest phone line, e-mail address and web site available for project questions
Stakeholder Engagement
October 10, 2012 22 Quest Progress: GCCSI International Members Meeting
Community Open Houses Q4, 2012
Well Program Q4 2012 2 additional injection wells
Associated deep monitoring and groundwater wells
Capture & Pipeline in Execute phase Capture at 90% model review stage
Capture construction underway with foundation work Q4 2012
Pipeline construction begins Q3 2013
Operations Handover Q2 2015
Full production Q3 2015
Timeline and Upcoming Activities
Thank You