GLOBAL CONSTRUCTION
CONSTRUCTION IN LATIN AMERICA: TACKLING THE EVER-INCREASING COMPLEXITY OF PROJECTS FROM A TO ZBy Francisco Matta, Managing Consultant, Joseph Vergara, Associate Director, and Julio Villa, Managing Consultant
INTRODUCTION
Latin America has experienced a marked increase in construction projects, from residential
and commercial developments to industrial and infrastructure facilities. Innovation in these
types of projects has also been increasing. Recent projects include the construction of the
new Mexico City International Airport, the planned development in Peru of San Lorenzo
Island into a satellite city, and the creation of an inter-oceanic corridor to facilitate trade
between Argentina and Chile.1 This increase in volume has resulted in a renewed interest
from both local and foreign developers, which has necessitated a more structured, complex,
and formal approach to the development of construction projects. Along with this increase
in volume, technology is driving the industry toward faster development, albeit with greater
risk.2 This article highlights common issues faced by local and regional owners, designers,
and builders in the Latin America construction market that result from the higher degree of
complexity as the region adjusts to this new paradigm.
THE OWNER
Owners control how risks are distributed, avoided, or minimized throughout the life of
a project — from inception through completion. In theory, they are masters of their own
destiny, as they can set and guide a project to a successful completion by managing
risks during its life, or they can fail to manage the project properly, assuring a long and
litigious path to an uncertain conclusion.
Despite the owner’s unique ability and advantageous position, many disputes and
controversies can be traced back to poor risk management practices, or lack of risk
management altogether, by a project’s owner. These issues are exacerbated where
multiple contractors and subcontractors with interdependent project deliverables
work on a project site. When project stakeholders are multicultural and bring different
management and interaction styles to the table, the chance of problems intensifies. Some
risk management suggestions that may be employed by owners to avoid, minimize, or
mitigate risks throughout the life of a project are discussed below.
1. Francisco Triviño, “A New Century of Latin American Progress,” XL Group Press Center, July 14, 2014. (http://xlcatlin.com/fast-fast-forward/articles/a-new-century-of-latin-american-progress)
2. Ibid
2
PROJECT SCOPING
Owners often employ a specialty-driven approach to scoping
projects — where multiple prime contracts are issued based on
the contractors’ specialties. A common reason for this approach,
as repeatedly explained by owners, is to avoid paying additional
markups by general contractors who would, in turn, subcontract
work beyond their expertise. However, this approach can create
risks that far offset its planned benefits. If not properly managed,
the interaction and transition among multiple main contractors
can result in a turbulent and costly project.
To avoid these problems, owners should follow a more holistic
approach when scoping a project. Consider, among other
factors: utilization of a project site, turnaround milestones among
contractors, and procurement of major equipment and materials.
Above all, owners should gauge the risks of potential scoping
scenarios through proper scheduling, because project scoping
issues often first manifest themselves as scheduling issues.
MASTER SCHEDULING
During a project’s initial stages, it is common for owners to rely
on macro-level schedules to guide key decisions, such as how to
partition scope and develop key contract documents. Yet, as the
project progresses, and work packages are sequentially (but not
necessarily logically) awarded, owners often abandon their initial
scheduling and rely on uncoordinated project schedules from
multiple contractors with different goals, positions, and agendas.
Thus, a coordinated project with many moving pieces becomes a
patchwork of poorly coordinated schedules and sequences.
To mitigate this risk, owners should prepare and maintain master
schedules that allow them to properly monitor the overall
project scheduling. This is not to say that owners should try
and impose schedules on contractors, which would impede
their means and methods, but to create, maintain, and monitor
schedules that hold all the pieces together. As a result, the
master schedule can serve to measure the status of the overall
project, as well as each individual part separately. Owners should
prepare, use, and enforce thorough specifications for scheduling,
claims, and change matters, and require the prime contractor’s
schedules to be maintained and coordinated with the owners’
master schedule.
STRICT ENFORCEMENT
It is common to experience a variation-prone attitude from
contractors in the Latin America market. This approach is
sometimes slow to take shape, but becomes pervasive under
excessive informality by owners and their representatives, and
lack of enforcement of contract provisions. It is common to
see contractors promoting camaraderie with owners and their
representatives in order to win concessions that push the limits of
the contract. These concessions seep in gradually through repeated
informal communications, which eventually set the stage for claims,
despite the failure to follow the contract provisions. Common
examples include: abuse of e-mail communications, improper use
of RFIs, casual abandonment of change mechanisms for cost and
delay, and other extra-contractual concessions between the parties.
Forensic claims analysts are often asked to examine projects
where no defined baseline schedule or updates were developed,
no time-impact analyses were produced (assuming they were
required by contract), and where parties carried over dozens
of lingering, schedule-affecting issues. Such poor management
practices by both owners and contractors make it extremely
difficult and time-consuming to later analyze and attribute
responsibility for any impacts to the project schedule, its critical
path, or any project milestones among project participants.
Similarly, it is common to see owners exposed to higher risks
because they gave up their greatest leverage in projects: the
ability to withhold payment for lack of contract compliance.
While it is not in their best interests to squeeze contractors
on payments during a project’s execution, owners must not
relinquish their leverage by approving and paying contractors
beyond the contractual requirements. Owners seldom enforce
delay-triggered provisions, such as their right to request
that contractors prepare, submit, and comply with recovery
schedules to receive payments. Likewise, owners tend not to
offset amounts due against accrued penalties, hence relegating
recovery of such penalties to the claims resolution process.
Where contractors are prone to informal dealings and protracted
claims resolution, the owner’s withholding payments whenever
allowable under the contract can discourage these tendencies
and promote timely resolution of issues to the benefit of the
project.
CHANGE MANAGEMENT
Managing change is part of every project. Changes should be
dealt with expeditiously, to prevent them affecting other areas
of the project. Proper change management starts at creating
and enforcing, through contract specifications, issues such
as determination of costs (direct, indirect, and markups) and
schedule impacts. Too often, analysts are faced with projects
where the sole focus of change management is on direct cost
issues, i.e., ensuring that the contractor gets paid for added
work. In this situation, the change orders only include the
approval of budgets for additional work, but omit consideration
of the impact on other work or schedules. Aligned with a strict
enforcement approach, owners should condition approval of
additional work on contractors fully complying with change
3
3. “Doing Business 2017 – Latin America and Caribbean (LAC),” Internationall Bank for Reconstruction and Development/The World Bank, New York, 2017, 44. http://www.doingbusiness.org/reports/~/media/WBG/DoingBusiness/Documents/Profiles/Regional/DB2017/LAC.pdf.
4. Ibid, 45.
5. bid, 46.
management specifications, including addressing all direct and indirect consequences
of additional work and all schedule impacts. In this regard, accord and satisfaction
provisions play a key role in change order management, as they permit having a clean
slate associated with every approved change order and prevent contractors from
reopening their case after the fact by seeking time extensions and impact damages on
agreed-upon changes.
THE DESIGNER
A designer’s responsibilities include the preparation of the construction documents,
including a project manual, and a set of technical specifications and construction drawings
that are compliant with all applicable codes, laws, and regulations. Other common
services for designers include review and approval of shop drawings and submissions, as
well as active participation in the permit application process. Additionally, construction
administration services, depending on the design contract, are often required. The
designer’s level of participation and knowledge of the local environment, during all phases
of construction, can minimize risks and help the project succeed.
PRECONSTRUCTION
The preconstruction phase is the most active and important for the designer. It is
during this phase that the design evolves from its initial conception to a detailed set
of construction drawings and specifications, and project sequencing is determined.
Code requirements and other legal requisites are also implemented at this phase, since
they affect the final design of a project. Permit requirements affect the final design, as
government requirements are incorporated into the owner’s initial program. This final
design, along with the owner’s financial and practical considerations, determine the
phasing or sequencing of a project and, at the same time, serves as the official approved
permit set to guide the construction of the project. Therefore, understanding the local
permit environment and anticipating potential obstacles is paramount for the designer
to assure an efficient and cost-effective design outcome.
In Latin America, the permit process can be significantly slower than in Europe and the
United States. According to the World Bank Group, there are, on average, about twice as
many procedures required to obtain a building permit in Latin America when compared to
the more expedited economies in the world. Some countries, like Uruguay and Argentina,
have three times as many procedures.3 Similarly, it takes an average of 181 days to obtain
permits in this region, with some countries, like Venezuela and Brazil, requiring over 425
days.4 In the European Union, the price of obtaining construction permits averages around 2
percent of a project’s cost. In countries like Puerto Rico, Honduras, Colombia, and Guatemala,
the permit price can be more than three times that amount, while in Mexico it can be almost
five times higher (9.8 percent).5
4
Understanding and implementing the appropriate building and land-use code
requirements is essential to avoid untimely and costly changes later. While many codes
in Latin American countries follow widely known codes such as the UBC or the IBC,
which in turn adopt international standards like AISC and ACI, other countries have
implemented local codes, like CIRSOC in Argentina.6 Understanding the interrelationship
between the applicable codes and regulations for each country is essential. Faulty code
applications by any team member can turn into project delays and cost overruns due to
the required time to find and correct the offending elements of the design.
It is essential to know the local permitting environment (contacts, time, procedures,
costs, etc.) or hire a local expeditor who does. Blindly working with unfamiliar permitting
procedures will almost certainly result in wasted time and efforts, especially considering
the bureaucratic obstacles in the permit processes of Latin American countries.
Furthermore, becoming knowledgeable about applicable codes and understanding how
to integrate them to avoid excessive implementation of unnecessary requisites or, worse,
insufficient application of requirements and safeguards, is key. Not only do codes vary
by country, they can vary by zones within each country. Experience shows that some
local and regional designers fail to grasp these concepts, especially considering the
increasing formalization of processes.
CONSTRUCTION AND CLOSEOUT
During the construction and closeout phases of the project, the role of the designer becomes
less intense, although by no means unimportant. Depending on the obligations assumed by
the designer for these two phases, supervisory, managerial, and inspection duties may be
required. Typical duties for the designer during the construction phase of a project include:
review of submissions, shop drawings, and other material; review of payment applications;
periodic visits to the project to observe and document the progress, and often keep the
owner informed; quick and resolute investigation of differing existing conditions and their
corresponding revisions to the design; coordination of any other revisions required that may
affect the proposed design; and the response to RFIs and issuance of additional sketches
and other clarifications during the execution of the project. Most of these duties are time-
sensitive and require the designer to evaluate and respond quickly. Finally, during the closeout
phase the designer reviews punch lists, helps in formalizing change orders, and, if required by
contract, issues the final payment application, among other duties.
Unfortunately, in Latin America these requirements have often been treated by designers
as secondary and less important than their design and preconstruction duties. This practice
exacerbates problems, as the necessary decision-making skills and professionalism are
reduced. It is important to clearly understand the contractual duties of a designer, including
the required response time to review items (submissions, shop drawings, RFIs, etc.), since
failure to comply with those requirements could lead to problems, in light of the more
integrated, stricter, and highly formalized contract configurations becoming commonplace in
Latin America.
6. J. Chavez et al., “Building Codes and Relative Seismic Vulnerability in Latin American Countries,” 15th World Conference on Earthquake Engineering, Lisbon, 2012, 1 and 8. http://www.iitk.ac.in/nicee/wcee/article/WCEE2012_4534.pdf.
5
THE BUILDER
The increasing complexity of construction projects in Latin
America, coupled with the generally weak historical contract
management in the region, poses increased risks for contractors.
Local contractors must deal with subcontractor coordination,
scheduling control, cost control, labor and union relations,
procurement and expediting of materials and equipment, and
many other functions related to the project — all the normal risks
associated with construction contracting, plus the increased
risks due to changes in the traditional owner/contractor relation.
Onsite, construction phase management may include the
coordination of several subcontractors, implementation of
phased or fast-track construction, monitoring progress of
work, adjustment of the work due to changed conditions or
unanticipated interferences, determination of materials, equipment
and workmanship conformance with the contract documents,
management of inspection and testing where required, change
order management, review of payments, and other issues. These
considerations become especially challenging considering regional
and cultural aspects of the projects in Latin America.
The opening of international investment in infrastructure in
some Latin American nations, and globalization in general, have
resulted in increased participation by international players in the
local construction market. In response to contract requirements,
these new players have brought more complex and formal
construction management practices to a local environment that
may not have adapted correspondingly. Some examples of this
increased formality include, but may not be limited to:
• Robust quality assurance systems
• Enhanced safety plans enforced on the job sites
• Maintaining auditable project files
• Extensive prequalification procedures for subcontractors and
vendors
• Background checks of construction company principals
• Anti-corruption and compliance policies and procedures
• Evidence of fulfilment with environmental rules and regulations
• Step-by-step dispute resolution procedures at international
forums
• Detailed reporting requirements on a daily/weekly/monthly basis
Based on the previous description of the current construction
environment and the above-mentioned considerations, the
following suggestions could contribute to the effective execution
of a project while mitigating certain risks for the contractor and
promoting effective project coordination among contractors.
COMMUNICATION
“Speaking the same language” is an important issue for the
contractor, both literally and figuratively. While it is obvious
that foreign parties must be able to communicate with the local
parties and subcontractors in their spoken language, it is also
important to speak the same “contractual language.” Effective,
clear, and direct communication is paramount for the successful
coordination of a project. It is essential in delineating and
clarifying the scope of work, the roles and responsibilities of each
party, and the resolution of disputes or disagreements on a wide
variety of issues related to the project. A well-established strategy
to comply with the agreed-upon contract language, as well as
in-place procedures for management and storage of project
correspondence and electronic communications, is imperative.
CHANGE MANAGEMENT
Changes within a construction project are one of the most frequent
causes of cost escalation and schedule overruns. When (not if)
changes arise, the contractor must be aware of all the contractual
obligations and their consequences. If the scope or budget of the
project is affected due to changes, the contractor must know the
causes and effects, determine who is responsible, and must assure
those alterations in the scope or budget are properly documented
and transmitted to the other project stakeholders.
SCHEDULING CONTROL
Identifying strategic activities and potential delays, as well as
ensuring the timeliness of all work carried out, is paramount, but
documenting those activities that affect critical tasks in revised
versions of the project´s construction schedule is key to leaving
a sound contemporaneous project scheduling record. This is the
main area that, in our experience, more growth is needed from
the local players.
DOCUMENT CONTROL
Maintaining records of all engineering drawings, specifications,
information, directives, verbal instructions, and documents
received from other project participants is critical to achieve
effective coordination both within and among the various
project stakeholders. The records generated, from the
conception through the final acceptance of the proposed
change, are very valuable in any type of analysis during the
project’s execution, but they are often more critical during
post-completion evaluations. In complex projects, cloud-based
document management platforms have proven to be valuable
tools. They allow everyone involved in the project access to the
latest revisions of documents, regardless of their location.
©2018 Navigant Consulting, Inc. All rights reserved. W33843
Navigant Consulting, Inc. (“Navigant”) is not a certified public accounting or audit firm. Navigant does not provide audit, attest, or public accounting services. See navigant.com/about/legal for a complete listing of private investigator licenses.
This publication is provided by Navigant for informational purposes only and does not constitute consulting services or tax or legal advice. This publication may be used only as expressly permitted by license from Navigant and may not otherwise be reproduced, recorded, photocopied, distributed, displayed, modified, extracted, accessed, or used without the express written permission of Navigant.
linkedin.com/showcase/NavigantGlobalConstruction
twitter.com/navigant
QUALITY ASSURANCE/QUALITY CONTROL
QA/QC teams in construction projects must be vigilant about performing
their duties: analyzing the project’s performance, detecting deviations from
the issued documents and their impacts, managing the quality of all work
carried out, documenting nonconforming work, implementing corrective
actions, and getting written approval of any repaired/reworked jobs.
Some government clients in Latin America include among their contract
requirements the establishment of a fully documented quality control
system, often linking contractual responsibilities to results of quality control
audits regularly performed throughout the execution of the project.
INTERINSTITUTIONAL RELATIONSHIP MANAGEMENT
Relationships are crucial in all business endeavors. The large number
of different stakeholders make this especially true in the construction
industry. In Latin American countries, maintaining good relationships with
government entities is crucial. However, there is always a risk of politically
influenced hurdles. Officials may base decisions on external considerations
like unnecessary media exposure, preference to local or familiar companies
both for job creation objectives as well as campaigning purposes. This
is yet another reason to become familiar with the local regulating and
contracting entities, or hire a representative who knows the ins and outs of
the local political and business environment.
Issues of bribery and corruption are rampant in this region, and regional
players need to understand that the influx of international players may
require compliance with stricter anti-corruption and anti-bribery policies
and procedures. Furthermore, knowledge of local companies would be an
added advantage, as being able to confidently hire local entities will go a
long way in facilitating a smooth project execution.
CONCLUSION
This article is based on our experience in the Latin American construction
industry. As such, we have aimed to illustrate the most common
hurdles encountered by local and regional parties commonly involved
in construction projects. Owners, designers, and contractors looking to
participate in this more formalized construction market will certainly
benefit from anticipating potential obstacles that could arise during the
project. Undoubtedly, the increased sophistication of the Latin American
construction industry requires no less than the most attentive, efficient, and
diligent execution of contracted obligations and standard of care duties.
CONTACTS
FRANCISCO MATTAManaging Consultant [email protected]
JOSEPH VERGARAAssociate Director [email protected]
JULIO VILLAManaging Consultant [email protected]
navigant.com
About Navigant
Navigant Consulting, Inc. (NYSE: NCI) is a
specialized, global professional services firm
that helps clients take control of their future.
Navigant’s professionals apply deep industry
knowledge, substantive technical expertise,
and an enterprising approach to help clients
build, manage, and/or protect their business
interests. With a focus on markets and
clients facing transformational change and
significant regulatory or legal pressures, the
firm primarily serves clients in the healthcare,
energy, and financial services industries.
Across a range of advisory, consulting,
outsourcing, and technology/analytics
services, Navigant’s practitioners bring sharp
insight that pinpoints opportunities and
delivers powerful results. More information
about Navigant can be found at navigant.com.