GOES-R Calibration Working Group (CWG)June 16, 2010
Presented By: Changyong Cao1 NOAA/NESDIS/STAR
CWG Progress Update
2
Outline
· Cal/Val Plans and CWG collaborations· NIST progress· Cal/Val data management· Discrepancy resolution· Cal/val interfaces· Aircraft flight campaigns· Tool development· Summary
5D-3
GOES-R Program Cal/Val Documents
Roles a
nd re
spon
sibilit
ies
Tech
nical
Details
Baselined on Feb 7, 2011
GOES-R Cal/Val Collaborators
5D-4
• Instrument and Ground Segments Vendors
All instruments• Flight Project
All instruments• Ground Project
All instruments• NOAA/NESDIS/STAR
All instruments
• MIT Lincoln Laboratory All instruments
• NIST Optical Technology Division
ABI Electron & Optical Physics Division
(SUVI, EXIS)
• Marshall Space Flight Center/UAH GLM SUVI
NGDC/SWPC (Space weather instruments)
Field Campaign (NASA, NOAA, JPL, etc.) ABI, GLM, SUVI
5
Calibration Coordination Team (CCT) Formed Under New PSE Leadership
AWG
PSE & Program Science
Flight
GSPInstr. Vendor
GS Vendor
MOST
DOST
GOES-R Calibration
Coordination Team
Scope – A coordinating body to ensure efficient implementation of calibration activities throughout the GOES-R Program during all mission phases.
GOES-R Calibration Coordination Team membership diagram
CCT members - Representatives of any group with responsibility to ensure L1b Product integrity, e.g.,• PSE & Program Science
(Cal/Val Working Group Reps) • Flight (Deputy Project Manager,
Instrument Managers) • Ground (Deputy Project
Manager)• Vendors (Instrument and
Ground)• AWG• MOST (MOM)• DOST (DOM)
Thanks to Mr. Ed Grigsby
Pre-Launch Resources - NIST
5D-6
NIST is a resource leveraged by PSE/Program Science (CWG) in order to provide:
• Review of vendor calibration plans and test setups• Links to primary SI standards• Development of plans for SI-traceable calibrations
NIST is currently involved in the following activities:• Deployment of the Traveling SIRCUS to the ABI Vendor testing
facility• Blackbody characterization using TXR• Characterization of ABI vendor’s integration sp• Validation of the ABI vendor’s FEL lamps• Determining the SRF of ABI filters• End-to-end calibrations of EXIS at SURF-III/Beamline 2• Review of the SUVI vendor
NIST SURF-III Facility
Tunable Laser
Wavemeter
IntegratingSphere
Exit Port
Spectrum Analyser
Optical fiber
Radiometerunder Test
Computer
ReferenceRadiometer
IntensityStabilizer
Monitor Detector (output to stabilizer)
Chopperor
Shutter
Speckle-removalSystem
Line
ar E
ncod
er
Tunable LaserTunable Laser
Wavemeter
IntegratingSphere
Exit Port
Spectrum Analyser
Optical fiber
Radiometerunder Test
Computer
ReferenceRadiometer
IntensityStabilizer
Monitor Detector (output to stabilizer)
Chopperor
Shutter
Speckle-removalSystem
Line
ar E
ncod
er
NIST SIRCUS
COMPLETED
COMPLETEDCOMPLETED
COMPLETED
COMPLETED
Major GOES-R Cal/Val-related Activities in Each Mission Phase
5D-7
• Pre-Launch Schedule determined by
Flight and Vendors Instrument and Test Design
and Review Instrument Testing and Test
Verification L1b Algorithm Development,
Implementation and Review
• Post-Launch Testing (PLT) Schedule determined by
MOST and DOST Science Test Design and
Review Science Tests Analysis and
Verification Cal Parameter Verification Long-Term Monitoring
Initialization Performance
Analysis/Anomaly Resolution L1b Product Validation
• Mission Operational Lifetime
Schedule determined by Ops
Long-Term Monitoring Vicarious Calibration Cal Parameter Update L1b Product Validation Anomaly Resolution
Pre-Launch Design & Development Review
Instrument/GS Vendor
Flight Instrument ManagerGOES-R Portal
Flight / Instrument Vendor Interface
Flight/CWGReview
Development Plans, Procedures, Reports, Draft CDRLs, RFA Responses, Requested Items
CDRLs, Reports
Reviews, TIMs, and
TRRsReports, Presentations
Feedback, Comments, RFAsC
DR
Ls, R
epor
ts
RFA Responses, Requested Items
RFAs
Feedback, Comments, Direction, RFAs
Feedback, Comments, RFAs
Participation
Pre-Launch Calibration Data Management
Addresses RFA #6
Instrument VendorCal Testing
Cal Analysis
Flight/Instrument Manager
GOES-R Portal
Flight / Instrument Vendor Interface
Flight/CWGValidation
Selected Cal Reports & Data for CDRLs
Cal Test Data, Results & ReportsVendor Archive
2030 expirationAll Instrument Test Data
Cal Test Data Requests,Test Anomaly Notification
Cal Test Data Requests,Test Anomaly Notification
Cal Test Data,Test Anomaly Resolution
Cal Test Data, Documentation, Results
Cal Test Validation Reports
Cal/Val Long-term Stewardship
CWG Discrepancy Reporting Process
5D-10
Instrument Data
CWGData analysis/
Document Review
Discrepancy Identification
Internal Review
PSE/Flight/Ground
Discrepancy Process
Discrepancy Report
Discrepancy Found
Revision Requests(if applicable)
Validation Record
(No Discrepancy/Resolved)
Currently 8 discrepancies identified and some are being addressed through flight
5D-11
Postlaunch Instrument Calibration Data Flow
NOAA Satellite Operations Facility (NSOF)
L1b Data, GRB
CLASS
GAS
MM, PG, PD and
DE
CWG
Instrument Radiometric and Spectral Calibration Data Quality Assurance
for GOES-series R• Post Launch Verification• Long-term Monitoring• Vicarious Calibration• Deep-Dive Calibration Analysis
Wallops Command and Data Acquisition System (WCDAS)
Fairmount, WV (RBU)
Instrument Calibration Data• All Calibration Parameters and Algorithms
used in L0→L1b processing• Satellite Telemetry• Instrument Housekeeping & Engineering data• Instrument Calibration Data
Instrument Calibration DataVia
Terrestrial Data Link
L0Data
L1Data, GRB
Product Generation Operational Environment
L0 & Input Data
Ground Processing Algorithm
L1b CalibratedData
Product Generation Development Environment
L0 & Input Data
Experimental Ground
Processing Algorithm
ExperimentalL1b CalibratedData CLASS
Updated Calibration
Parameter Tables
Cal L0 and Processing Data
L1b, L2+ Products
MLS and 2-Day Store
Anomaly Resolution
Anomaly Resolution
L1b Product Performance Monitoring and Anomaly Resolution
5D-12
Instr. Telemetry
5-Day RDR CLASS
Mission Mgmt: Instr. Temps, etc.H & S Monitor
WCDAS/ NSOF
NSOFWCDAS-
WCDAS Cal Terminals
CALVAL WorkstationGov’t Tools
MLS2-day
MLS2-day
GAS
NSOF Cal Terminals
CLASS
STARAnomaly Resolution
STAR LS
STAR WorkstationsAutomated Cal Data Acquisition
GOES-R Integrated Cal/ValInstrument Performance Web Displays
CALVAL WorkstationGov’t Tools
STAR GOES-R Remote Access
Firewall
L0
GRB (L1b) TDL (CAL)
L1b, L2+, CAL
Remote Access
Product Generation: Product Performance
Monitor
Mission Management: GRB Monitor
Product Generation:GRB to L2+
Product Generation: Create
L0, L0 to L1b processing and
GRB generation.
L0
GOES-R ABI Post-Launch Test - leveraging operational experience from heritage instruments
Post-Launch Testing and Product Evaluation
Cal/Val Mission PDR Aug 2011
GEO-LEO
GEO-GEO
KPP Product Quality Evaluation Working with the Imagery Team
Post-launch Cal/Val using Lunar Observations
for MTF, band to band registration, RVS, and stability evaluation
Heritage
B3
Mission Lifetime Calibration Stray light Analysis and VNIR Lunar
Observations
B2
B4
B1
B5 B6
Stray Light Effect Analysis-Leveraging operational experience from heritage instruments
Simulated ABI Lunar Images using Hyperion Hyperspectral Observations
3.9 mm
GOES-R ABI will scan around the exclusion zone: a sophisticated KOZExclusion zone does not eliminate all of the stray light contamination.
Long-term Performance Monitoring
Heritage Activity
Sonoran Desert and White Sands Site Characterization
Heritage test site for GOES ImagersCharacterization of BRDF to remove
seasonal signal variation for vicarious calibration.
Mission Lifetime Calibration V&V Support and Instrument Performance
Monitoring
5D-15Cal/Val Mission PDR Aug 2011
Completed two flights: White Sands on May 23, and Sonoran Desert on June 10, 2011
GOES-R Instrument and L1b Product Analysis Tool
Development
Online/L0 Tools for All GOES-R Instruments Radiometric Calibration Tools
Instrument Noise Monitoring/Trending VNIR Lunar and Stellar Irradiance Trending/Analysis ABI
Instrument Telemetry Monitoring/Trending
GEO-GEO and GEO-LEO Inter-Comparison Trending/Analysis
ABI, SUVI, EXIS
Calibration Coefficients Monitoring/Trending
Vicarious Calibration Target Radiance Trending/Analysis – (DCC, Desert Site, Instrumented Sites, Rayleigh
Scattering, Sunglint) ABI, GLM
Raw Data Readers NWP Bias Monitoring ABI, GLM
L0 and L1b Product Assessment Aircraft Radiometer Underflights ABI
Spectral Calibration Tools Spatial Calibration ToolsSRF
Correction ABI, SUVI, EXIS Band-to-Band Registration ABI
SRF Analysis ABI, SUVI, EXIS MTF Analysis SUVI, ABI, GLM
Underflight ABI, EXIS LSF Analysis ABI
• CWG developing tools for: Long-term instrument performance monitoringL1b product radiometric, spatial and spectral calibration monitoring Instrument and L1b product anomaly resolution
• Tools to be deployed during GOES-R post-launch tests and mission operational life.
Field Campaigns
· Hardware Procurement for Cal/Val»Spectraoradiometer
– ASD 0.4-2.5um with 10nm resolution»Sunphotometer» Infrared camera
· Proposals
· Thanks to Dr. Steve Goodman17
Summary
· Developed a comprehensive GOES-R Cal/Val program to ensure product qualityCal/Val StrategyCal/Val PlanImplementation and execution
· GOES-R leveraging diverse complementary technical capabilities
· Provide life cycle support for a successful GOES-R program
· Realigned with the new PSE