www.ContechES.com Going With The Flow Open Bottom Structures for Fish Migration Tom Hennessey, Bridge Consultant MA,CT,RI
Transcript
Page 1: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Going With The Flow

Open Bottom Structures for Fish Migration

Tom Hennessey, Bridge Consultant MA,CT,RI

Page 2: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

• Contech Introduction

• Solution Overview

• Foundation Discussion

• Scour Discussion

• Applications

• Partnering With Contech

Solution Development

• Project Design Worksheet

• Structure Selection

• Siting & Layout

• DYOB

• Engineer Estimate

• Site Simulation

• Proposal Preparation

• Design Build Support

Design Support

• Specifications

• Contract Drawings

• Permitting

• Structural/Fabrication Drawings

• Approval Assistance

• Custom Shape Development

• Horizontal/Vertical Alignment

• Hydraulics & Scour Support

• Foundations

Installation Support

• Preconstruction Meeting

• On-Site Installation Assistance

• Logistics Coordination

Agenda

Options & Support Specific to Your Project Needs

Page 3: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Bridges & Structures, Stormwater Management, Pipe,

Erosion Control and Retaining Walls

Contech Engineered Site Solutions

Page 4: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

CROSSINGS. CULVERTS. BRIDGES. CONTECH.

Page 5: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

• Over 60 Engineers and CAD Specialists

• 200 Contech Specialists covering all 50 States

• Over 100 years experience in the Construction Industry

Contech. Your project partner.

Precast Plate Truss

50 years 80 years 60 years

8,000 installations 50,000 installations 20,000 installations

……………………. Comprehensive Engineering Support …………………..

…………………….Installations In Every State…………………..

Page 6: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

© 2017 Contech Engineered Solutions LLC, a QUIKRETE Company

LEGEND

Contech

Manufacturing

Partner

Manufacturing

Manufacturing Capabilities

Page 7: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Clear Span Bridges

Clear spans to 300’

Page 8: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Contech Structural Plate

Page 9: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Durability Benefits of Clear Span

BridgeCor

• Deep corrugated metal structures

Spans up to 80’

AASHTO approved

9X stiffer than MULTI-PLATE

Accelerated construction methods

Improves Long Term Durability• No Invert - Keep normal flows away from

structure

• Exposure to high flows for short duration

• Free draining backfill

• Clear span sensitive wetlands

Page 10: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Lightweight, Bolted Plate Construction

Freight economy Efficient assembly

Lift and set in place Handles highway loading

Page 11: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Precast – CON/SPAN and BEBO Concrete Arches

Page 12: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

PRECAST FOUNDATION PRECAST HEADWALLPRECAST ARCH UNIT

PRECAST WINGWALL CURVED ALIGNMENTTWIN LEAF CONSTRUCTION

Modular Components

Page 13: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Any Application, Many Solutions – You Optimize

Page 14: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Design Challenges

Page 15: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Structure Selection and Hydraulic Assistance

HEC-RAS Bridge Coordinates

Page 16: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

200 SF Waterway

0-300 Series

27’ Span

10

Page 17: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

CON/SPAN

Page 18: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

BEBO Arch Systems

Page 19: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 20: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Footing Reactions Minimize Stream Disturbance

Page 21: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

A precast foundation system that blends the speed of

precast with the economy of cast-in-place

Page 22: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 23: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Insert local appropriate applications –

no more than two slides

Insert local appropriate applications –

no more than two slides

CIP FILL PROCESS

Page 24: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Silver Hill Hospital

Page 25: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Silver Hill Hospital

Page 26: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Silver Hill Hospital

Page 27: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Copicut Reservoir Dam

Page 28: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Copicut Reservoir New Bedford, MA

Page 29: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Copicut Reservoir Dam

Page 30: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Copicut Reservoir Dam

Page 31: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Sale• TIMELINE

• PO- 7/31

• SHIPPED 8/30, ARRIVED 9/4

• FISH WINDOW CLOSED 9/15

Express Footers arrive with majority of steel reinforcement tied at manufacturing facility.

MONROE WOODLANDS – STEEL EXPRESS

Place on 4” minimum granular sub-footing

Page 32: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Steel Express Foundations

INSTALLATION

Secure footing with rebar anchors provided, and lap splice between units.

Assemble first ring of plate structure.

Page 33: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Steel Express Foundations

INSTALLATION

Place plate structure on footers and spread streambed material.

Page 34: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Structural Plate Shapes

Page 35: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Local Applications

Page 36: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 37: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Don’t Touch The Wetland

Page 38: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 39: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 40: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 41: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 42: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 43: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 44: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

ALBC Full Invert With Fish Baffles

Page 45: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 46: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 47: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 48: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 49: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 50: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 51: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 52: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 53: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 54: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 55: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 56: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 57: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 58: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 59: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 60: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 61: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 62: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Deep Creek Before

Page 63: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Deep Creek / New Arch

Page 64: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Trout Creek outlet before

restoration 2005

Page 65: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Trout Creek outlet after restoration 2005

Page 66: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Reline, Rehab, Liner Plate

PLATE TUNNEL LINER PLATEPRECAST

Page 67: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 68: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 69: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 70: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 71: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Reline before Fish Ladder

Page 72: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 73: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 74: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

CTDOT Marlborough CT 66” Elliptical Pipe

Page 75: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 76: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Apponaug River Relocation Warwick RI

Page 77: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

RI DOT Appanaug Circular Bridge Warwick, RI

Page 78: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

RI DOT Appanaug Circular Bridge Warwick, RI

Page 79: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

RI DOT Apponaug Circular Warwick, RI

Page 80: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

RI DOT Appanaug Circular Warwick, RI

Page 81: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

RI DOT Apponaug Circular Bridge Warwick, RI

2 Years after Installation

Page 82: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

RI DOT Aponaug Circular Bridge Warwick, RI

2 Years after installation

Page 83: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Bonny Rigg Road MA DOTBeckett, MA

Page 84: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Covered BridgeNewtown, CT

Page 85: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Working with Contech

Page 86: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Solution Development

Design Support Installation

Building Blocks to a successful Project

Page 87: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.comDYOB® at www.conteches.com

Page 88: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Page 89: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Contract Drawings

Page 90: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Solution Development

InstallationDesign Support

• Attending Pre-Bid Meetings

• Holding Preconstruction Meeting

• Field Consultants Attend all Installations

Building Blocks to a Successful Project

Page 91: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Solution Development

• Project Design Worksheet

• Structure Selection

• Siting & Layout

• DYOB

• Engineer Estimate

• Site Simulation

• Proposal Preparation

• Design Build Support

Design Support

• Specifications

• Contract Drawings

• Permitting

• Structural/Fabrication Drawings

• Approval Assistance

• Custom Shape Development

• Horizontal/Vertical Alignment

• Hydraulics & Scour Support

• Foundations

Installation Support

• Preconstruction Meeting

• On-Site Installation Assistance

• Logistics Coordination

Contech. Your project partner.

Options & Support Specific to Your Project Needs

• Comprehensive Site Solutions

• Over 60 Engineers and CAD Specialists

• 200 Contech Specialists covering all 50 States

• Over 100 years of experience

Page 92: Going With The Flow Open Bottom Structures for Fish Migration€œOpen...• Contech Introduction • Solution Overview • Foundation Discussion • Scour Discussion • Applications

www.ContechES.com

Questions?

CROSSINGS. CULVERTS. BRIDGES. CONTECH.