February 5, 2015
Gov. Harry W. Nice Bridge
Replacement Delivery Method
Evaluation Process
William Pines, P.E.
PURPOSE OF PRESENTATION
MDTA Background and Capital Program
Discuss basic bridge facts
To highlight the progress that has been made in advancing the program to replace the Governor Nice Bridge
To discuss the “framework” for the selection of a project delivery method
2
Maryland Transportation
Authority (MDTA)
MDTA
Established in 1971
Purpose
Construct, manage, operate, and improve toll facilities
Funded by toll revenues, not tax dollars
Headquarters - Point Breeze Office Complex, Baltimore
9 Facilities
Bay Bridge
Baltimore Harbor Tunnel
Key Bridge
Fort McHenry Tunnel
Heavy Reliance on A/E Firms
Hatem Bridge
Intercounty Connector
John F. Kennedy Highway
Gov. Nice Bridge
Point Breeze
MDTA Facilities Toll facilities consist of high-volume signature bridges, tunnels and
highways that are major interstate and U.S. routes
*
Toll Plaza
Travel Plaza
MDTA Facility
I-95 ETLs
5
MDTA
6-Year Planned Budget ($Millions)
FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 TOTAL
$255.03 $74.5 $12.22 $0 $0 $0 $ 341.75
$139.27 $157.30 $63.18 $79.70 $60.20 $10.50 $510.15
$133.5 $190.00 $240.40
$284.50 $273.00 $249.20
$1,370.5
---------
---------
---------
---------
---------
---------
---------
$527.8 $421.8 $315.8 $364.1 $333.2 $259.7 $2,222.50
All Other Major Projects
Sys. Preservation and D&E
TOTAL
Mega Projects
6
Capital Planning Six-Year Program
Funding by Phase
($ Millions)
Project Planning, $0
Design, $179
Right-of-Way, $25
Construction, $2,019 Other, $204.9
Project Planning Design Right-of-Way Construction
Total Capital Program $2.2 Billion
7
I-95 Improvement Project
8
Hatem and Tydings Bridge Underwater Repairs
9
Bay Bridge Paint Projects
10
Bay Bridge Cable Rewrapping and
Dehumidification
11
Travel Plaza Redevelopment
12
Upcoming Significant Capital Projects
Rehabilitation Suspension Spans - Westbound Bay Bridge
Rehabilitate Decks of Eastbound Bay Bridge
Replace Canton Viaduct
Baltimore Harbor Tunnel - Replace Vent Fans
Replace Superstructure of Bridge over Patapsco Flats
Nice Bridge Replacement Subject of this presentation
13
Nice Bridge History
Construction Dates: March 1938 - December 1940
Opened December 15, 1940
Named in 1968 after Maryland Governor Harry W. Nice
14
FAST FACTS
15
Original Cost: $5 million
Toll Revenues (FY13): $13 million (collected SB only)
Length of facility (bridge & approaches): 2.2 miles
Bridge Length: 1.7 miles of two-lane bridge
Main span: vertical clearance is 135 feet and 800 feet long
Traffic Volume: 6.8 million vehicles (both directions)
16
Existing Bridge Facility
N VIRGINIA MARYLAND
Potomac River
Virginia Welcome
Center Barnesfield Park
Naval Surface Warfare Center
Dahlgren
Division
Morgantown
Generation
Station
Nice Bridge
Toll Plaza
Plan scale in feet
0 1,000 2,000 3,000 4,000 5,000
Steel truss arch bridge,
opened December 1940
EXISTING FACILITY MAINTENANCE BRIDGE
NB-2371R – Clean and Paint Structural Steel & Misc. Structural Repairs ($13.2M*)
NB-3001 - Rehabilitate Substructure and Superstructure of Nice Bridge ($3.2M*)
FACILITY COMPLEX
NB-2646R – Replace Underground Storage Tanks with Aboveground Storage Tanks ($614K*)
NB-2686 - Replace Roofs of Administration & Maintenance Buildings & Rehab Roof of Metal Storage Building ($452K*)
NB-2718 - Replace Generators at Administration and Maintenance Buildings ($683K*) *Total Projected Costs from CTP
17
PLANNING TASKS COMPLETED Environmental Assessment (EA) signed by FHWA (2009)
Finding of No Significant Impact (FONSI) signed by FHWA (2012)
In-depth Bridge Inspection and Fatigue Analysis completed (2013)
Life Cycle Cost Analysis completed (2013)
$56M in funding allocated for Preliminary Engineering & ROW
18
GUIDING PRINCIPLES
Complete the Harry W. Nice Bridge replacement project consistent with:
The context of MDTA’s statewide program and other future system priorities
Project Goals and Objectives (see next page)
Purpose & Need from Finding of No Significant Impact (FONSI)
19
PROJECT GOALS AND OBJECTIVES
Continue to maintain the existing 70+ year old bridge in Fair to Satisfactory Condition.
Undertake all pre-construction activities and eventual construction for the replacement structure and removal of the existing structure in an environmentally sensitive manner and consistent with the approved NEPA documents and applicable permits
20
PROJECT GOALS & OBJECTIVES (CONT’D.)
Design, construct, operate and maintain a cost-effective replacement structure that provides a safe, durable and efficient new Nice Bridge for at least 100 years, under the most financially advantageous toll structure that provides best-value for MDTA and our customers.
21
Learning from Others
22
David Capobianco Tappan Zee Bridge, NY
Roger Prince Goethals Bridge, NY
Doug Robb & Ken Butler Indian River Inlet Bridge, DE
Suzanne Plezia Gerald Desmond Bridge, CA
Audubon Bridge, LA
Tim Conway Kosciuszko Bridge, NY
Huey Long Bridge, LA Steve Spohrer
Learning from Others (Cont’d.)
23
“Lessons Learned” Workshops (Cont’d.)
24
Value Adding Examples:
Procurement
• All panelists used a fixed price contract. Suggested to
advise the proposers of the project budget, so that the
award is based on the scope for the price in best value
procurement
Cost Estimates
• Risk assessments should be used to determine appropriate
contingencies. Contingencies should be reported in the
Financial Plan, and it is appropriate to include a
reasonable allowance item in the contract.
“Lessons Learned” Workshops (Cont’d.)
25
Value Adding Examples:
General Design & Construction
• Tie the materials acceptance criteria to the corrosion plan,
so that the project service life Design assumptions are tied
to actual Construction performance.
Bridge Types and Aesthetics
• Cable stay commonly used today for projects with main
span lengths 650' to 1,500'(+). The panel believed that
cable stay/extradose bridges are most economical type
for spans ≥ 500‘.
“Lessons Learned” Workshops (Cont’d.)
26
Value Adding Examples:
Construction
• Be careful with the provisions for weather delays. The risk
allocation needs to be clearly spelled out to prevent
claims.
Design-Build Quality
• Require Developer to include an independent road
safety inspection with punchlist corrections prior to
acceptance.
“Lessons Learned” Workshops (Cont’d.)
27
Value Adding Examples:
P3 Projects
• P3’s are not only used as a funding mechanism, but more
importantly to get fixed long-term costs, transfer risk, gain
innovation and efficiencies, and provide a multi-year
“warranty” through the concession period. Delivery
technique most focused on life-cycle costs and prevents
deferring maintenance.
Milestone Payments
• The panel recommended to use milestone payments for
mega-projects, while holding a significant final payment
to push for project completion.
“Lessons Learned” Workshops (Cont’d.)
28
Value Adding Examples:
Operations and Maintenance
• Handback requirements in O&M concessions are often
overly focused on pavement and bridges, while not
appropriately addressing barriers, ancillary structures, etc.
Project Delivery Selection
• Value for Money analysis is only one tool to assist with
selecting project delivery. The key factors that influence
the delivery decision should be: Finance, Risk, Public
Value, & Schedule.
PROJECT DELIVERY OPTIONS
DBB: Design-Bid-Build
CM/GC: Construction Manager/General Contractor
DB: Design-Build
DBOM: Design-Build Operate Maintain
P3/ Public-Private Partnership / DBFOM: Design-Build-Finance-Operate-and-Maintain
29
CONCEPTUAL WORKFLOW CHART
30
Evaluation of Delivery/Procurement Options
Develop Risk Register • identify • assess • assign
T&R Projections • toll policy decision (timing) • existing conditions • economics, demographics • traffic models • T&R projections • strengths/risks of projections Risk Workshop(s)
(includes Market Soundings)
Financial Analysis • Public Options • Private Options
Value for Money Analysis
Select Project Delivery Method (includes additional risk and delivery method workshops)
Prepare Financial and Project Management Plans
Federal Funding Analysis
Cost Estimates • construction • O&M • capital expenditures • timing escalation
Engineering/Bridge Concepts • toll policy decision (cash) • channel clearances • profile, typical section • safety, levels of service
RISK BASED PROJECT APPROACH Project Delivery method decision driven by evaluating the
party/parties in the best position to manage risks.
Typically the assuming party has a level of control over factors that affect risks and are positioned to:
minimize the adverse impacts of the risk on themselves, and
minimize the adverse impacts of the risk on others
31
PRELIMINARY ENGINEERING
TASKS UNDERWAY Comprehensive “due diligence” activities
Engineering Concepts and Cost Estimates
Traffic/Revenue Study
Advance Coordination with Stakeholders
Risk Evaluation
Financial & Value for Money” Analysis
Assessment of Project Delivery Options
Financial & Project Management Plan
32
33
Main Span Horizontal Clearance Reduction:
Existing Clearance = 700 feet Existing Clearance w/ sufficient Vert. Clearance = 480 feet
USCG Bridge Guide Clearance (Potomac River) = 250 feet Upstream bridges = 175 feet (max.) Downstream buoys = 450 feet
* Objective: Proposed bridge safely meets the needs of all stakeholders.
“Due Diligence” Examples
34
Existing typical section
Alternate 7 Modified typical section
* “Right Sizing” bridge
“Due Diligence” Examples (Cont’d.)
“Due Diligence” Examples (Cont’d.)
35
Geophysical investigation complete. Over 1,000+ anomalies detected.
Approximately 50 anomalies dive inspected; none indicated UXO.
Finding construction, fishing, & vessel debris.
Further diving planned for Spring 2015 to investigate another 100-125 anomalies.
Navy to complete more sophisticated Geophysical investigation Spring 2015.
Munitions & Explosives of Concern (MEC):
“Due Diligence” Examples (Cont’d.)
36
Geotechnical Data Collection: Permits received for boring program.
Contract NB2849 for subsurface exploration
and laboratory testing is scheduled to Advertise Spring 2015.
JPA and NFMS coordination ongoing for foundation testing program. Working with Tappan Zee team for NFMS coordination
Contract NB2856 for foundation system testing is planned to Advertise Spring 2016, following receipt of boring data.
RIGHT-OF-WAY TASKS UNDERWAY 1. Developing ROW Mosaics and plats
2. Acquiring properties on the Maryland side within the NEPA limits of disturbance
3. Working with Virginia to clear ROW on the VA side
37
FINANCIAL QUESTIONS TO BE ADDRESSED
A Range of public and private Funding Options:
Operational options will include MDTA Staff vs. Private sector operation and/or maintenance
38
FINANCIAL QUESTIONS TO BE ADDRESSED CONT’D.
Two basic Toll Collection System options [affects T&R, O&M, Capital Expenditures, and Cost Estimates]:
Toll Schedule Structure/Sensitivity Analyses and other factors
39
AET (All Electronic Tolls) ORT (Open Road Tolling + Cash)
MD 200 FMT
ENGINEERING QUESTIONS
TO BE ADDRESSED
Prescriptive vs. Performance Design Criteria
Forecast long-term traffic needs and available capacity
Use Lessons Learned, Market Soundings, and Industry meetings to help inform sizing of construction packages and quality management plan.
40
NEXT STEPS
Continue Preliminary Engineering and ROW activities
Continue Financial and Funding analysis
Determine Project Delivery Decision (Est. End of CY 2015)
Develop the Financial and Project Management Plans
Although exact timing remains TBD, and will be driven by the final decision on the funding and delivery method, the assumed time frame for the start of construction is between 2020 and 2025
41