+ All Categories
Home > Documents > Government Office Center Mid-Atlantic U.S.

Government Office Center Mid-Atlantic U.S.

Date post: 01-Jan-2016
Category:
Upload: quinlan-rutledge
View: 17 times
Download: 0 times
Share this document with a friend
Description:
Government Office Center Mid-Atlantic U.S. Penn State AE Senior Thesis Project Alexander Ward | Construction Management James Faust | CM Advisor. Government Office Center Mid-Atlantic U.S. Presentation Outline: Project Background Analysis #3: Integrated Processes Engaged Owner - PowerPoint PPT Presentation
Popular Tags:
23
Government Office Center Mid-Atlantic U.S. Penn State AE Senior Thesis Project Alexander Ward | Construction Management James Faust | CM Advisor
Transcript
Page 1: Government Office Center Mid-Atlantic U.S.

Government Office Center

Mid-Atlantic U.S.

Penn State AE Senior Thesis ProjectAlexander Ward | Construction Management

James Faust | CM Advisor

Page 2: Government Office Center Mid-Atlantic U.S.

Government Office Center

Mid-Atlantic U.S.

Penn State AE Senior Thesis ProjectAlexander Ward | Construction Management

James Faust | CM Advisor

Presentation Outline:

I.Project BackgroundII.Analysis #3: Integrated Processes

A. Engaged OwnerIII.Analysis #2: SIPS Study for Curtain Wall Activities

A. Renewable Energy/Electrical BreadthIV.Analysis #1: Implementation of Building Information Modeling

A. Facilities ManagementV.Analysis #4: Progressive Collapse

A. Structural BreadthVI.Summary of Conclusions & Acknowledgements

Page 3: Government Office Center Mid-Atlantic U.S.

Project Background

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

$42 Million Renovation 14 Story Federal Office &

Courthouse 316,000 SF August 1, 2011 – January 31, 2014 Major upgrades to Envelope and

HVAC systems LEED Gold (LEED 2009 EBO&M) Occupied throughout construction

Slide 3

Page 4: Government Office Center Mid-Atlantic U.S.

Integrated Processes

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Problem Identification:Industry trending toward integrated solutionsEngaged owners extremely important in processNeed to educate owners on importance of role

Research Goal:Evaluate key benefits of engaged owner

Slide 4

Page 5: Government Office Center Mid-Atlantic U.S.

Integrated Processes

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

An Engaged Owner is:Actively involved in the design and design review processAware of the unique challenges of the projectWilling to use uncommon project delivery and construction strategies when feasible

…improved delivery through schedule acceleration…

Slide 5

Page 6: Government Office Center Mid-Atlantic U.S.

Integrated Processes

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

An Engaged Owner is:More informed of design options being considered by the project teamMore educated on the consequences of these design optionsActively involved in design reviewsSupportive and responsive during construction phase

…improved delivery through schedule acceleration…

…faster and more refined decision making…

Slide 6

Page 7: Government Office Center Mid-Atlantic U.S.

Integrated Processes

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

An Engaged Owner is:Helpful in defining project needs early in the development processEducated and understands how design teams meet the previously defined program requirementsClear in explaining why a design change is needed and what it will accomplish

…improved delivery through schedule acceleration…

…faster and more refined decision making…

…reduced frequency and degree of changes…

Slide 7

Page 8: Government Office Center Mid-Atlantic U.S.

SIPS Study for Curtain Wall Activities

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Problem Identification:Highly repetitive curtain wall replacement activitiesOpportunity to implement BIPV system

Research Goal:Evaluate the benefits of SIPS and BIPV

Slide 8

Page 9: Government Office Center Mid-Atlantic U.S.

SIPS Study for Curtain Wall Activities

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Activities:Installation of weather wallDemolition of existing curtain wallInstallation of new structural steelInstallation of new curtain wallDemolition of weather wallFrame and rough-inRestoration of finishes

Slide 9

North Area in Red – South Area in Blue

Page 10: Government Office Center Mid-Atlantic U.S.

SIPS Study for Curtain Wall Activities

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Existing Schedule:Oct. 11, 2011 – Sept. 16, 2013 (101 weeks)8 week schedule gap between North and SouthLongest activity requires 100 days (North finishes)

Slide 10

Page 11: Government Office Center Mid-Atlantic U.S.

SIPS Study for Curtain Wall Activities

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

$1.65M Total Value

25 Weeks Saved

$425K

$1.225M

Slide 11

Page 12: Government Office Center Mid-Atlantic U.S.

BIPV Curtain Wall

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Slide 12

Page 13: Government Office Center Mid-Atlantic U.S.

BIPV Curtain Wall

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Slide 13

Feasibility:+$404,200 for PV marginal cost–$382,500 for sunshades deduction=$21,700 net marginal cost

~$13,000 per year in energy savings

Payback < 2 years

Need to consider heat gain, constructability, etc.

Page 14: Government Office Center Mid-Atlantic U.S.

Implementation of BIM

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Problem Identification:Minimal push of information downstream for future needs

Research Goal:Evaluate the benefits of implementing BIM for facilities management uses

Slide 14

Page 15: Government Office Center Mid-Atlantic U.S.

Implementation of BIM

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Slide 15

Page 16: Government Office Center Mid-Atlantic U.S.

Implementation of BIM

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Slide 16

Page 17: Government Office Center Mid-Atlantic U.S.

Progressive Collapse

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Problem Identification:Original construction decades prior to recent federal requirements

Research Goal:Compare the cost and schedule impacts of adding this scope of work in three scenarios

Slide 17

Page 18: Government Office Center Mid-Atlantic U.S.

Progressive Collapse

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Freyrom Anchor Section Slide 18

Page 19: Government Office Center Mid-Atlantic U.S.

Summary of Conclusions

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

The Balfour Beatty Construction Team

Industry Professionals

Penn State AE Department

My Family and Friends

Slide 19

Acknowledgements

Questions or Comments?

Page 20: Government Office Center Mid-Atlantic U.S.

Appendix Slides

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of ConclusionsVII.Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Page 21: Government Office Center Mid-Atlantic U.S.

Project Background

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Owner | U.S. General Services Administration

CM | Balfour Beatty Construction Architect | TranSystems Corporation Structural Engineer | Thornton

Tomasetti MEP Engineer | Greenman-Pedersen,

Inc. Sustainability / Design Consultant |

William McDonough + Partners

Page 22: Government Office Center Mid-Atlantic U.S.

SIPS Study for Curtain Wall Activities

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.

Traditional SIPS:

Non-Traditional SIPS:

Page 23: Government Office Center Mid-Atlantic U.S.

Implementation of BIM

Presentation Outline:I.Project BackgroundII.Integrated ProcessesIII.SIPS Study for Curtain Wall ActivitiesIV.Implementation of BIMV.Progressive CollapseVI.Summary of Conclusions & Acknowledgements

Government Office Center | Mid-Atlantic U.S.


Recommended