Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons...

Date post: 12-Jan-2017
Category:
Upload: informa-australia
View: 384 times
Download: 3 times
Share this document with a friend
33
REMOTE RENEWABLE ENERGY CONFERENCE GRAEME MARSHALL MELBOURNE ~ MARCH 2016
Transcript
Page 1: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

REMOTE RENEWABLE ENERGY CONFERENCE

GRAEME MARSHALL

MELBOURNE ~ MARCH 2016

Page 2: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

FOCUS

SETuP funding and construction models

Consequent behaviours

Land, procurement & contracts

Consequent behaviours

Expectations and reality

Photo gallery

Page 3: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

SETuP = Solar Energy Transformation Program 10 megawatts (MW) of solar power installed across 30

remote Indigenous NT communities over 3 years

Two main components:

• A medium penetration solar rollout:

– Reduce annual fuel use by 15% in over 30 communities

• Nauiyu (Daly River) high penetration solar site:

– 50% fuel savings

– Test integration of new technologies

– Enables diesel engines OFF

Page 4: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

SETuP Financing

ARENA

PWC

Grant Funding

($27.5m) $

$

Loan

($27.5m) Diesel Fuel

Savings ($)

SETuP

NTG/Tcorp

Page 5: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Financial model drives behaviours

High political interest in project viability

Focus on diesel prices & short-run inputs

Focus on how the loan payback works

NPV ‘doorstops’ – should certain communities be dropped?

Page 6: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

SETuP rollout timing:

2015/16 2016/17 2017/18

4 sites

16+ sites

10 + sites

Page 7: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Timetable drives behaviours

Aggressive timetable pressures learnings

but:

Focuses the mind

Aggressive timetable pressures land availability

but:

Alternative (‘fall-back’) communities are contentious

Page 8: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Construction & Ownership

DC AC

Solar panels PV Controller

Connection point

To community

Power Station

Control Room Communications

Page 9: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Technology drives behaviour

The 10 MW of SETuP is not insignificant in the NT

Interest & involvement

The $55m of SETuP is very significant in the NT

Great expectations

Diesel/gas generation - leave it to experts

PV? Everyone’s an expert!

Page 10: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

LAND

Allowed ~ 3 hectares/MW + shading (trees) - ample

Average lease cost is $5500/ha/pa

On average, we produce 560wp/$ of annual lease cost

Lowest is 100wp/$

Highest is 2100wp/$

Page 11: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

TECHNOLOGY

Inverters: SMA 25000 Tripower inverters

PV Controller: SMA Cluster Control

Panels: included Hanwha Q Cells, Canadian Solar, Jinko, Conergy and LG – 315 watt

Framing system: Clenergy Solar Terrace, Sigma XL, Conergy Linea

Page 12: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Prices per watt

Capital Cost Item Estimate Emerging Reality

Panel & inverters erected on frames

$3.10 $3.30

Balance of system $0.40 $0.45

Land costs $0.04 $0.037

Project management $0.50 $0.45

Page 13: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

PvSyst power production

Section Latitude Average Mwhpa produced

1 MWp solar produces Mwhpa

1 (1.625 MWp) 25 - 22 South 3292.5 2026.1

2 (0.4 Mwp) 22 South 799.1 1997.6

3 (1.3 MWp) 12 South 2470.1 1900.0

Page 14: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

ISSUES MANAGEMENT I

Balance: land availability with scheduled ARENA Milestones with climate (Wet)

Manage: Desire for large private pv penetration in SETuP communities

Massage: Solar-diesel hybrid won’t

negatively impact reliability

shorten diesel life

complicate day-to-day operation

drive up O&M

Page 15: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

ISSUES MANAGEMENT II

Keep the focus: on SETuP as a whole, try to avoid cherry-picking

Manage Expectations:

of communities for local employment (construction & longer-term)

of NT contractors & suppliers of big SETuP ‘paydays’

of parties that SETuP can be simultaneously a cash cow, a major employment generator and a technological showcase

of everyone that everything will work straight up

Page 16: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

FINAL OBSERVATIONS

Hofstadter's Law: It always takes longer than you expect, even when you take into account Hofstadter's Law.

Less elegantly - Dates in a calendar are closer than they appear to be.

Data: Is not the plural of anecdote

Page 17: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

SETuP

A Photo Journal…

Page 18: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Land & Leases

Areyonga

Page 19: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Land & Leases

Areyonga Power Station – new solar area

being fenced

Page 20: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Early days – complete clearing at Areyonga

Page 21: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Typical Central Australian site – ground cover to be

left & rubbish and shrubs to go

Page 22: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Nyirripi – Buffel grass and other rubbish

Page 23: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Typical satellite installation

Page 24: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Feral animal or culturally important animal?

Page 25: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Nyirripi – undulations on site

Page 26: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Kintore – Time lapse camera on roof of power

station

Page 27: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Time lapse camera

Page 28: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Typical satellite installation

Page 29: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP

Time lapse camera

Page 30: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP
Page 31: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP
Page 32: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP
Page 33: Graeme Marshall - NT Power & Water Corporation - Solar Transformation in the NT – Early lessons from SETuP