FOCUS
SETuP funding and construction models
Consequent behaviours
Land, procurement & contracts
Consequent behaviours
Expectations and reality
Photo gallery
SETuP = Solar Energy Transformation Program 10 megawatts (MW) of solar power installed across 30
remote Indigenous NT communities over 3 years
Two main components:
• A medium penetration solar rollout:
– Reduce annual fuel use by 15% in over 30 communities
• Nauiyu (Daly River) high penetration solar site:
– 50% fuel savings
– Test integration of new technologies
– Enables diesel engines OFF
SETuP Financing
ARENA
PWC
Grant Funding
($27.5m) $
$
Loan
($27.5m) Diesel Fuel
Savings ($)
SETuP
NTG/Tcorp
Financial model drives behaviours
High political interest in project viability
Focus on diesel prices & short-run inputs
Focus on how the loan payback works
NPV ‘doorstops’ – should certain communities be dropped?
SETuP rollout timing:
2015/16 2016/17 2017/18
4 sites
16+ sites
10 + sites
Timetable drives behaviours
Aggressive timetable pressures learnings
but:
Focuses the mind
Aggressive timetable pressures land availability
but:
Alternative (‘fall-back’) communities are contentious
Construction & Ownership
DC AC
Solar panels PV Controller
Connection point
To community
Power Station
Control Room Communications
Technology drives behaviour
The 10 MW of SETuP is not insignificant in the NT
Interest & involvement
The $55m of SETuP is very significant in the NT
Great expectations
Diesel/gas generation - leave it to experts
PV? Everyone’s an expert!
LAND
Allowed ~ 3 hectares/MW + shading (trees) - ample
Average lease cost is $5500/ha/pa
On average, we produce 560wp/$ of annual lease cost
Lowest is 100wp/$
Highest is 2100wp/$
TECHNOLOGY
Inverters: SMA 25000 Tripower inverters
PV Controller: SMA Cluster Control
Panels: included Hanwha Q Cells, Canadian Solar, Jinko, Conergy and LG – 315 watt
Framing system: Clenergy Solar Terrace, Sigma XL, Conergy Linea
Prices per watt
Capital Cost Item Estimate Emerging Reality
Panel & inverters erected on frames
$3.10 $3.30
Balance of system $0.40 $0.45
Land costs $0.04 $0.037
Project management $0.50 $0.45
PvSyst power production
Section Latitude Average Mwhpa produced
1 MWp solar produces Mwhpa
1 (1.625 MWp) 25 - 22 South 3292.5 2026.1
2 (0.4 Mwp) 22 South 799.1 1997.6
3 (1.3 MWp) 12 South 2470.1 1900.0
ISSUES MANAGEMENT I
Balance: land availability with scheduled ARENA Milestones with climate (Wet)
Manage: Desire for large private pv penetration in SETuP communities
Massage: Solar-diesel hybrid won’t
negatively impact reliability
shorten diesel life
complicate day-to-day operation
drive up O&M
ISSUES MANAGEMENT II
Keep the focus: on SETuP as a whole, try to avoid cherry-picking
Manage Expectations:
of communities for local employment (construction & longer-term)
of NT contractors & suppliers of big SETuP ‘paydays’
of parties that SETuP can be simultaneously a cash cow, a major employment generator and a technological showcase
of everyone that everything will work straight up
FINAL OBSERVATIONS
Hofstadter's Law: It always takes longer than you expect, even when you take into account Hofstadter's Law.
Less elegantly - Dates in a calendar are closer than they appear to be.
Data: Is not the plural of anecdote
SETuP
A Photo Journal…
Land & Leases
Areyonga
Land & Leases
Areyonga Power Station – new solar area
being fenced
Early days – complete clearing at Areyonga
Typical Central Australian site – ground cover to be
left & rubbish and shrubs to go
Nyirripi – Buffel grass and other rubbish
Typical satellite installation
Feral animal or culturally important animal?
Nyirripi – undulations on site
Kintore – Time lapse camera on roof of power
station
Time lapse camera
Typical satellite installation
Time lapse camera
Thank You