+ All Categories
Home > Documents > Green Building & Measurement Challenges

Green Building & Measurement Challenges

Date post: 02-Oct-2021
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
55
Green Building & Measurement Challenges (Instrumentation for Monitoring Central Chiller Plant Efficiency) Francis Tay Principal Manager Green Mark Department Building and Construction Authority Singapore
Transcript
Page 1: Green Building & Measurement Challenges

Green Building & Measurement Challenges (Instrumentation for Monitoring Central Chiller Plant Efficiency)

Francis Tay Principal Manager

Green Mark Department Building and Construction Authority

Singapore

Page 2: Green Building & Measurement Challenges

Agenda • Singapore’s Green Building Master Plan • Hallmark of Green Mark: Chiller Efficiency • Measurement & Verification

– Standards and Requirements – Instrumentations – Pitfalls and Lessons Learnt

• Smart Chiller Efficiency Portal

Page 3: Green Building & Measurement Challenges

The BCA Green Mark Programme – A cornerstone of our green polices and

initiatives

Climate Resources

Wellbeing Ecology

4 Sustainability Outcomes

5 Focus Areas

Climate Responsive

Design

Building Energy

Performance

Resource Stewardship

Smart and Healthy Building

Advanced Green Efforts

Singapore’s Green

Building Journey

Page 4: Green Building & Measurement Challenges

BCA-NParks Green Mark for Existing Parks BCA-NParks Green Mark for New Parks

BCA Green Mark for Infrastructure BCA Green Mark for Districts

BCA-LTA Green Mark for Rapid Transit System

A Suite of BCA Green Mark Schemes

BCA Green Mark for Non-Residential Buildings BCA Green Mark for Residential Buildings

BCA Green Mark for Landed Houses BCA Green Mark for Healthcare Facilities

BCA Green Mark for New Data Centres Version 1.1

BCA Green Mark for Non-Residential Buildings

BCA Green Mark for Residential Buildings BCA Green Mark for Existing Schools

BCA Green Mark for Office Interior BCA Green Mark for Restaurants

BCA Green Mark for Supermarkets BCA Green Mark for Retail

BCA-IDA Green Mark for Data Centre

New Buildings Existing Buildings

Beyond Buildings

Within Buildings

Singapore’s Green

Building Journey

Page 5: Green Building & Measurement Challenges

2005 2010 2018 2020 2030

>34% Green Buildings

> 13% Green Buildings

>50% Green Buildings

>80% Green Buildings

< 0.1% Green Buildings

~3200 building projects have met Green Building Standard

~ 94 million m2 green GFA

Green Building Achievements and Accolades

Ranked 2nd in Top 10 Global Cities for

Green Building 2016

International Star of Energy Efficiency

Award 2013 1st country outside America & Europe to win

WGBC Chairman’s Award 2015

Singapore’s Green

Building Journey

Aspen Institute Energy & Environment Awards 2010

Page 6: Green Building & Measurement Challenges

Focus New Buildings

Focus Existing Buildings

Focus Occupants and Tenants

Launched BCA

Green Mark Scheme

2005

2008 2006

Legislation on Environmental

Sustainability for New Buildings

2011

Established the Singapore Green Building Council

Launched BCA Centre for

Sustainable Buildings

Legislation on Environmental

Sustainability for Existing Buildings

2012 2013

Launched BCA Building Energy

Submission System

2014 2015

2009

Developing the Green Building Eco-system through Comprehensive Plans

& Policies

Singapore’s Green

Building Journey

80% of all buildings (by gross floor area) to meet Green Building Standard by 2030

Page 7: Green Building & Measurement Challenges

Approach to Green Buildings 1. Passive strategies (Climate positive) – to implement as a first priority!

• Natural Ventilation

• Behavioural changes

• Daylight

• Operation and regular maintenance

2. Active Systems – with high efficiency to support or supplement the passive measures. E.g. Energy efficient AC, lighting and low flow water fittings

3. Renewable Systems

Page 8: Green Building & Measurement Challenges

Air-conditioning with Chiller Plant

Page 9: Green Building & Measurement Challenges

Green Mark Rating

Peak Building Cooling Load (RT)

< 500 ≥ 500 Efficiency (kW/RT)

Certified 0.85 0.75 Gold 0.80 0.70

GoldPlus 0.75 0.68 Platinum 0.70 0.65

Existing Building New Building

Minimum System Efficiency of Water-Cooled Chilled Water Plant

Green Mark Rating

Peak Building Cooling Load (RT)

< 500 ≥ 500 Efficiency (kW/RT)

Certified 0.80 0.70 Gold 0.80 0.70

GoldPlus 0.70 0.65 Platinum 0.70 0.65

Page 10: Green Building & Measurement Challenges
Page 11: Green Building & Measurement Challenges

Business Case of Retrofitted Existing Buildings

Page 12: Green Building & Measurement Challenges

Measured m²/RT Range Average

Office Buildings (58 projects)

35 – 65 48

Hotels (32 projects) 36 – 88 58 Retail Buildings (28 projects)

18 – 38 27

Benchmark Cooling Load of Office Building

Page 13: Green Building & Measurement Challenges

Why Accurate Measurements of Chilled Water Plant Efficiency?

• Chiller plant system accounts for the highest electrical consumption in all commercial buildings

• Small temperature difference between supply and return chilled water temperature

• Making the most out of the Building Automation System • Used as an accountability tool to gauge the performance of

the supplied equipment post installation • You can only improve what you can measure

Page 14: Green Building & Measurement Challenges

14

CHWS Temp CHWR Temp DT Temp CHW FlowCooling capacity

Elect power input Efficiency

C C C L/S tons Kwi Kwi/tonActual performance 7.00 12.00 5.00 168.2 1000 780 0.780Error in temp -0.50 0.50Claimed performance 6.50 12.50 6.00 168.2 1200 780 0.650

0.130% error 16.7%

Error in efficiency

Ave Cooling capacityAnnual

operating Hrs Cooling loadError in

efficiencyError in energy

savings Tarrif rateError in energy

savingstons Hr ton-hr kwi/ton KWH $/KWH $

1,000 8760 8,760,000 0.130 1,138,800 0.20 227,760

14

50% of a chiller

+/- 0.5C temp error results in +/- $228K saving error!

Impact of Poor M&V

Page 15: Green Building & Measurement Challenges

Permanent Instrumentations of Central Chilled Water Plant

Provision of permanent measuring instruments for monitoring water-cooled central chilled-water plant efficiency. The installed instrumentation shall have the capability to calculate resultant plant efficiency (i.e. kW/RT) within 5% of its true value and in accordance with SS591 – Code of Practice for Long Term Measurement and Verification for Water-cooled Chilled Water Plant Systems.

Page 16: Green Building & Measurement Challenges

The individual uncertainty of each measurement system - mass flow rate (by flow meter), electrical power input (by power meter) and the temperature difference (by temperature sensors) are as follows :

Error Budget

Item Measurement System (includes sensor and data

acquisition system)

End-to-End Measurement Uncertainty

(% of reading)

01 Flow 1% see note (1) + 1% (i.e. 2%)

02 Power 2%

03 Temperature sensors with accuracy of ± 0.05°C @ 0°C

1.3% see note (2) Temperature difference (ΔT)

Page 17: Green Building & Measurement Challenges

Note: (1) An additional 1% to be included in the computation of measurement errors for flow meter. (2) The measurement error (%) for temperature sensors is calculated based on the Root Sum Square error for the 2 temperature

sensors for the design or actual delta T (i.e. ΔT). In this case, Temperature sensors with accuracy @ 0°C = ± 0.05°C Design/ Actual ΔT = 5.5 °C Measurement errors for ΔT = √(0.052 + 0.052)/ 5.5 °C x 100% = 1.3%

Error Budget (Cont’)

Page 18: Green Building & Measurement Challenges

Based on the above information, the overall uncertainty of measurement is as shown in the following :

where UN = individual uncertainty of variable N (%) N = mass flow rate, electrical power input or delta T Errorrms = √ (∑ (UN)2) = √ (22 + 22 + 1.32) = 3.1%

Therefore, the total uncertainty for the calculated chilled-water plant efficiency (kW/RT) is 3.1% which falls within the 5% of the true value.

Error Budget (Cont’)

Page 19: Green Building & Measurement Challenges

Permanent Instrumentations of Central Chilled Water Plant (GM2015 for New Development)

• Location and installation of the measuring devices to meet the manufacturer’s recommendation • All data logging with capability to trend at 1 minute sampling time interval, and recorded to the 3rd

decimal digit • Flow meters are to be provided for chilled-water and condenser water loop and shall be full bore

ultrasonic / full bore electromagnetic type of 1% uncertainty or equivalent. Electromagnetic flowmeter shall be capable of electronic in-situ verification to within ±2 % of its original factory calibration

• Temperature sensors are to be provided for chilled water and condenser water loop and shall have an end-to-end measurement uncertainly not exceeding ±0.05°C over the entire measurement or calibration range. All thermo-wells shall be installed in a manner that ensures the sensors can be in direct contact with fluid flow. Provisions shall be made for each temperature measurement location to have two spare thermo-wells located at both sides of the temperature sensor for verification of measurement accuracy

• Dedicated power meters (of IEC Class 1 or equivalent) and associated current transformers (of class 0.5 or equivalent) are to be provided for each of the following groups of equipment: chillers, chilled water pumps, condenser water pumps, cooling towers, condensing units, AHUs and PAHUs

Class 1 in GM2017 for Existing Buildings

Page 20: Green Building & Measurement Challenges

Thermistor RTD A mixture of metals and metal oxide

materials. Ceramic Wire Wound & Thin Film

10 K Ohms at 25° C, … 100 Ohms @ 0° C, …

Steinhart and Hart Equation Callendar-Van Dusen equation

Page 21: Green Building & Measurement Challenges

Example of Temperature Sensor Installation

Page 22: Green Building & Measurement Challenges

Example of Temperature Sensor Installation

Page 23: Green Building & Measurement Challenges

Heat Balance Substantiating Test Verification of central chilled water plant efficiency: Heat balance – substantiating test for water-cooled central chilled water plant to be computed in accordance with AHRI-550/590

Page 24: Green Building & Measurement Challenges

The heat balance is represented by the following equation:

qcondenser = qevaporator + Winput where,

qcondenser = heat rejected qevaporator = cooling load Winput = measured electrical power input to compressor

Heat Balance Substantiating Test

Condenser

Evaporator Motor

Gear

KWinput

Energy in = Energy out

Oil heater

Cooling Load

Heat rejected

Page 25: Green Building & Measurement Challenges

The computation of the percent heat balance (see formula below) that is the total heat gain and total heat rejected must be within ± 5% for 80% of the sampled points over the normal building operation hours.

Percent Heat Balance =

Note: For open drive chillers, the Winput shall take into account the motor efficiency provided by the manufacturer.

An example is provided as follows: Input power (measured) = 100kW Motor rated efficiency (η) = 90% Adjusted Winput = 100kW x 90% = 90kW

Adjusting for Open Drive Chillers

(qevaporator + Winput) - qcondenser qcondenser

x 100% ≤ 5%

Page 26: Green Building & Measurement Challenges

In the event where hydraulic losses of pumps constitute a substantial heat gain, these losses have to be properly accounted for. The value shall be determined from pump efficiency values provided by the manufacturer. An example is illustrated as follows:

Motor input power (measured) = 30kW (A) Motor rated efficiency (η) = 90% (B) Pump rated efficiency (η) = 80% (C) Hydraulic losses = (A) x (B) x [(100% – (C)] = 30kW x 90% x (100% - 80%) = 5.4kW Adjusted Winput = kWi (chillers) + 5.4kW

Heat Balance Substantiating Test

Page 27: Green Building & Measurement Challenges

Worked Example (Variable Primary Flow)

A: qevaporator = FM1 x Cp x (CHWR - CHWS) B: qcondenser = FM2 x Cp x (CWR - CWS) C: Winput = kWi-1 + kWi-2 + kWi-3 where Cp = 4.19 kJ/kg.°C and density of chilled water is assumed to be 1kg/l Percent heat balance = [(A + C) – B] / B x 100% Note: In the event where heat balance exceeds ±5%, hydraulic losses of pumps constituting substantial heat gain can be included on the right hand side of the heat balance equation. The value of which shall be determined from certified gear losses and pump efficiency values provided by the manufacturer.

Page 28: Green Building & Measurement Challenges

Temperature Sensor Flow Meter Power Meter + CT Data Acquisition

Installation Location & installation of measuring devices to meet manufactures’ recommendation

Direct contact with fluid flow

Measurement Uncertainty

1.3% 2% 2%

Location - Chilled water supply header(s) - Chilled water return header(s) - Condenser water supply header(s) - Condenser water return header(s)

-Chilled water supply/return header(s) - Condenser water supply/return header(s)

-Chiller(s) electrical panel(s) - Chilled water pump(s) electrical panel(s) - Condenser water pump(s) electrical panel(s) - Cooling tower(s) electrical panel

Type -Thermistors - RTDs

- Full bore magnetic - Ultrasonic (conditional)

- Digital power meter - Datalogger + Gateway - DDC(s) - BTU meters

Others 2 spare thermo-wells at each measurement location

Electronic In-situ verification 1 minute sampling interval

Summary

Page 29: Green Building & Measurement Challenges

Desktop M&V Setup

Page 30: Green Building & Measurement Challenges

COMMON MISTAKES Site Installation

Page 31: Green Building & Measurement Challenges

Location of Permanent Instrumentation

Small Chillers Big

Chillers

Page 32: Green Building & Measurement Challenges
Page 33: Green Building & Measurement Challenges

< 5D

Situation Problem Location of flowmeter less than 5D recommended distance from bend

Might not accurately measure flow readout

Location of temperature sensor too near mixing point

High fluctuation in temperature readout

Location of Permanent Instrumentation

Page 34: Green Building & Measurement Challenges

Situation Problem Location of thermowell with opening facing a pipe.

Not enough space “straight length” to insert thermistor probe into the thermowell

Location of Thermowell

Page 35: Green Building & Measurement Challenges

Situation Problem Location of flowmeter and temperature sensor before and after bypass pipe

Might not accurately measure building cooling load

Location of Permanent Instrumentation

Page 36: Green Building & Measurement Challenges

< 5D

Situation Problem Location of flowmeter less than 5D recommended distance from bend/reducer/expansion

Might not accurately measure flow readout

reducer

Location of Permanent Instrumentation

Page 37: Green Building & Measurement Challenges

Vertical Position Easily accessible for maintenance, but there is water impact (NOT a good choice)

Page 38: Green Building & Measurement Challenges

Installation at 135° & 225° Position It might collect condensation water If there is leakage from the test plug, there will be water pool

Page 39: Green Building & Measurement Challenges

Too near to the chiller

Avoid installation near to a chiller

Page 40: Green Building & Measurement Challenges

Heat Balance is Off • Low flow + Long Pipe • Sensor Location

Page 41: Green Building & Measurement Challenges

Heat Balance is Off

e.g. fluctuating flow due to on-off valve

Page 42: Green Building & Measurement Challenges

Continuous Commissioning

Continuous or monitoring-based commissioning is required for persistent high performance

Page 43: Green Building & Measurement Challenges

Chiller Efficiency Smart Portal • Continuous monitoring • Trend Analytics to spot performance variance • Autonomous alarm

Periodic Energy Audit Continuous Monitoring

Efficient Effective Empower

Page 44: Green Building & Measurement Challenges

What it isn’t

Page 45: Green Building & Measurement Challenges

Data Collection • Light-touch, Risk-free, Universal

– Will not disrupt operations – Does not exert control nor command

• Chiller Sensor Data – To compute efficiency (kW/RT) – Leverage existing instruments

• 4 means – Export from BMS , then upload – Via a BACnet gateway – Via a Modbus gateway – Via a software interface to BMS

Page 46: Green Building & Measurement Challenges

BCA Portal

Internet

Feed-in Feed-in

Direct from Building

Remote Service Provider

Owners’ Ops Centre

Smaller, MCST Buildings

BCA Smart Chiller Portal

Page 47: Green Building & Measurement Challenges

• Light-touch, Light-weight and Universal • BCA

− Publish the interface and installation examples

• Building Owners − Direct feed, or − Feed in from their Integrated BMS or Command Centre

• Portal Service Provider − Feed in for their subscribers

Chiller Portal

1. File Export 4. iBMS / Portal Service Provider HTTPS

HTTPS HTTPS

HTTPS

2. BACnet Gateway 3. Modbus Gateway

REST API

BCA Smart Chiller Portal Standardised Data Interface

Page 48: Green Building & Measurement Challenges

Title REST API to insert chiller plant raw data (Draft)

URL http://bca_cesp.portal.com/api/ImportRawData

Method The request type - POST

URL Params Not Required

Data Params [ { "BuildingId": "buildinga", "ObjectId": "chiller", "ObjectNo": "1", "DataFieldId": "power", "Value": "110", "Timestamp": "2016-01-16 02:15:01", "Key": "secretkey" },

{ "BuildingId": "uwctamp", "ObjectId": "chiller", "ObjectNo": "1", "DataFieldId": "SupplyTemparatue", "Value": "110", "Timestamp": "2016-01-16 02:15:01", "Key": "secretkey "}, ]

Success Response Code: 200

Error Response Code: 400, if buildingId not valid Code: 402, if building object datafield mapping not valid Code: 403, if secrectkey for that building is not correct Code: 404, Other problem

Notes

BCA Smart Chiller Portal Standardised Data Interface (in Green Mark 2017 Appx A)

Page 49: Green Building & Measurement Challenges

BCA Smart Chiller Portal User friendly & Intuitive Dashboard

Page 50: Green Building & Measurement Challenges

BCA Smart Chiller Portal Efficiency Breakdown

Page 51: Green Building & Measurement Challenges

BCA Smart Chiller Portal Generate Energy Audit Report

Page 52: Green Building & Measurement Challenges

BCA Smart Chiller Portal Analysis for Trouble-shooting

Page 53: Green Building & Measurement Challenges

BCA Smart Chiller Portal Baseline & Alert Rules

Page 54: Green Building & Measurement Challenges

Dashboard Event List

BCA Smart Chiller Portal Mobile App

Page 55: Green Building & Measurement Challenges

Walking the talk for Smart FM – Performance-based for Existing Buildings

Higher value proposition – Continuous commissioning to sustain performance

– Data-driven Productivity tool − Manage by exception

– Simplify Re-certification & Legislation − Facilitate GM Re-Certification & 3 Yearly Energy Audit

− Less bureaucratic and paperwork

− Lower cost of compliance

Re-inventing Green Mark with Smart Chiller Portal


Recommended