GREEN CAMPUS CONFERENCE AT ECSUGREEN CAMPUS CONFERENCE AT ECSUAPRIL 19, 2012APRIL 19, 2012
The Latest & Greatest Energy Technology !The Latest & Greatest Energy Technology !Where we were, Where we were, Where we are, Where we are, Where we are headed….Where we are headed….
Presented byPresented byRob GagneRob GagneCCSU Plant Facilities Engineer IICCSU Plant Facilities Engineer [email protected]@ccsu.edu
CCSU’S ORIGINAL POWERHOUSECCSU’S ORIGINAL POWERHOUSE
POWERHOUSE 18,500 PPHBOILERS
• Planning for the Energy Center commenced in the early 1990s to respond to problems with the aging and undersized campus heating system
• Provides all heating, cooling, hot water and some electricity for the campus
• Staffed by CCSU on a 24/7 basis since the Fall of 2004
• Equipment in the Energy Center
o Three dual fuel Nebraska boilerso Two 1,250 kW Cummins natural gas
engineso One 1.5 ton electric centrifugal
chillero One 1.5 ton steam absorption chillero Two heat recovery steam generators
ENERGY ENERGY CENTERCENTER
Energy Center Control Room Energy Center Space
ENERGY CENTER EQUIPMENTENERGY CENTER EQUIPMENT
65,000 PPH ENERGY CENTER BOILER
1,500 TONELECTRIC CHILLER
1,500 TONSTEAM ABSORPTION CHILLER
CUMMINS QSV 18 CYLINDER 1,250 KW GENERATORS
HEAT RECOVERY STEAM GENERATORS 2,000 PPH
300 HPCOOLING WATER PUMPS
500 HPSECONDARY CHILLED WATER PUMPS
UTILITY TUNNEL CONSTRUCTIONUTILITY TUNNEL CONSTRUCTION
UTILITY TUNNEL CONSTRUCTIONUTILITY TUNNEL CONSTRUCTION
UTILITY TUNNEL COMPLETIONUTILITY TUNNEL COMPLETION
UTILITY TUNNELINTERIOR
ENERGY CENTER SWITCHGEAR ROOM
ELECTRICAL PROFILEELECTRICAL PROFILE
FUEL CELLFUEL CELL
• 1,400 kW Direct Fuel Cell power plant was installed in the Fall 2011 and delivering power by January 1, 2012
• Minimum electrical capacity 1,303 kW . Minimal steam capacity 1,600 lb/hr with three modes of operation.
• Grid Connected Mode (with or without existing E.C. generators)
• Grid Independent Mode (without the utility grid) MICRO GRID
• Island Hot Standby Mode (powering its own parasitic loads)
FUEL CELLFUEL CELL
FUEL CELL FUEL CELL
FUEL CELL FUEL CELL
• Phase 1 (completed October 2011): Consisted of energy efficient improvement measures to Copernicus Hall, and Vance Academic Center. Implementation cost $164,166.00. Total energy savings $111,592.00 with a 1.5 year payback. Additional incentive through CEEF, $3,753.50 when project was closed out.
• Phase 2 (funding request submitted): Energy efficient improvement measures to the Energy Center. Implementation cost $270,671.00. Total energy savings $192,332.00 with a 1.4 year payback. Additional incentive through CEEF, $54,026.27 when project is closed out.
RETRO-COMMISSIONING RETRO-COMMISSIONING
• Retrofitting of 500 lamps across the CCSU campus with energy saving Sylvania DG LED retrofit kits
• Lessen electrical usage without compromising safety and security
• Bulb life approximately 5 times a traditional lamp
• Annual reduction of 240,900 kWh with an approximate 41k cost savings
• Reduction of criteria pollutants such as sulfur oxide, nitrogen and carbon compounds
• Reduction of light pollution in accordance with the Dark Sky Initiative
LED REPLACEMENT PROJECTLED REPLACEMENT PROJECT
• Copernicus Garage lighting: 700 (150watt HPS)fixtures were replaced with 100 watt MH
• Welte Garage lighting: 216 (150 watt HPS) fixtures were replaced with 8 foot 4 lamp fluorescents, approximately 112 watts per fixture
• Combined average savings for two garages is approximately 4,000 kWh per month
• Square D Monitoring: provides the ability to monitor each buildings electrical load
• Infrared motion sensor lighting controls: Installed in various portions of campus to include hallways, classrooms, etc.
OTHER CAMPUS WIDE ENERGY OTHER CAMPUS WIDE ENERGY EFFICIENCY PROJECTSEFFICIENCY PROJECTS
We will continue to:– Investigate any and all incentive programs
available– Research additional retro-commissioning and
continue with persistent strategies on existing retro-commissioning projects
– Educate and involve the campus community in energy conservation and sustainability efforts
– Stay committed to meeting the goals and efforts in the University’s Climate Action Plan
WHERE ARE WE HEADED?WHERE ARE WE HEADED?
(IN THE RIGHT DIRECTION!)(IN THE RIGHT DIRECTION!)