+ All Categories
Home > Documents > Green Campus Conference 4-19-2011 R. Gagne

Green Campus Conference 4-19-2011 R. Gagne

Date post: 12-Apr-2017
Category:
Upload: rob-gagne
View: 48 times
Download: 0 times
Share this document with a friend
29
GREEN CAMPUS CONFERENCE AT ECSU GREEN CAMPUS CONFERENCE AT ECSU APRIL 19, 2012 APRIL 19, 2012 The Latest & Greatest Energy Technology ! The Latest & Greatest Energy Technology ! Where we were, Where we were, Where we are, Where we are, Where we are headed…. Where we are headed…. Presented by Presented by Rob Gagne Rob Gagne CCSU Plant Facilities Engineer II CCSU Plant Facilities Engineer II [email protected] [email protected]
Transcript
Page 1: Green Campus Conference 4-19-2011 R. Gagne

GREEN CAMPUS CONFERENCE AT ECSUGREEN CAMPUS CONFERENCE AT ECSUAPRIL 19, 2012APRIL 19, 2012

The Latest & Greatest Energy Technology !The Latest & Greatest Energy Technology !Where we were, Where we were, Where we are, Where we are, Where we are headed….Where we are headed….

Presented byPresented byRob GagneRob GagneCCSU Plant Facilities Engineer IICCSU Plant Facilities Engineer [email protected]@ccsu.edu

Page 2: Green Campus Conference 4-19-2011 R. Gagne

CCSU’S ORIGINAL POWERHOUSECCSU’S ORIGINAL POWERHOUSE

Page 3: Green Campus Conference 4-19-2011 R. Gagne
Page 4: Green Campus Conference 4-19-2011 R. Gagne
Page 5: Green Campus Conference 4-19-2011 R. Gagne
Page 6: Green Campus Conference 4-19-2011 R. Gagne

POWERHOUSE 18,500 PPHBOILERS

Page 7: Green Campus Conference 4-19-2011 R. Gagne

• Planning for the Energy Center commenced in the early 1990s to respond to problems with the aging and undersized campus heating system

• Provides all heating, cooling, hot water and some electricity for the campus

• Staffed by CCSU on a 24/7 basis since the Fall of 2004

• Equipment in the Energy Center

o Three dual fuel Nebraska boilerso Two 1,250 kW Cummins natural gas

engineso One 1.5 ton electric centrifugal

chillero One 1.5 ton steam absorption chillero Two heat recovery steam generators

ENERGY ENERGY CENTERCENTER

Page 8: Green Campus Conference 4-19-2011 R. Gagne

Energy Center Control Room Energy Center Space

ENERGY CENTER EQUIPMENTENERGY CENTER EQUIPMENT

Page 9: Green Campus Conference 4-19-2011 R. Gagne

65,000 PPH ENERGY CENTER BOILER

Page 10: Green Campus Conference 4-19-2011 R. Gagne

1,500 TONELECTRIC CHILLER

Page 11: Green Campus Conference 4-19-2011 R. Gagne

1,500 TONSTEAM ABSORPTION CHILLER

Page 12: Green Campus Conference 4-19-2011 R. Gagne

CUMMINS QSV 18 CYLINDER 1,250 KW GENERATORS

Page 13: Green Campus Conference 4-19-2011 R. Gagne

HEAT RECOVERY STEAM GENERATORS 2,000 PPH

Page 14: Green Campus Conference 4-19-2011 R. Gagne

300 HPCOOLING WATER PUMPS

Page 15: Green Campus Conference 4-19-2011 R. Gagne

500 HPSECONDARY CHILLED WATER PUMPS

Page 16: Green Campus Conference 4-19-2011 R. Gagne

UTILITY TUNNEL CONSTRUCTIONUTILITY TUNNEL CONSTRUCTION

Page 17: Green Campus Conference 4-19-2011 R. Gagne

UTILITY TUNNEL CONSTRUCTIONUTILITY TUNNEL CONSTRUCTION

Page 18: Green Campus Conference 4-19-2011 R. Gagne

UTILITY TUNNEL COMPLETIONUTILITY TUNNEL COMPLETION

Page 19: Green Campus Conference 4-19-2011 R. Gagne

UTILITY TUNNELINTERIOR

Page 20: Green Campus Conference 4-19-2011 R. Gagne

ENERGY CENTER SWITCHGEAR ROOM

Page 21: Green Campus Conference 4-19-2011 R. Gagne

ELECTRICAL PROFILEELECTRICAL PROFILE

Page 22: Green Campus Conference 4-19-2011 R. Gagne

FUEL CELLFUEL CELL

Page 23: Green Campus Conference 4-19-2011 R. Gagne

• 1,400 kW Direct Fuel Cell power plant was installed in the Fall 2011 and delivering power by January 1, 2012

• Minimum electrical capacity 1,303 kW . Minimal steam capacity 1,600 lb/hr with three modes of operation.

• Grid Connected Mode (with or without existing E.C. generators)

• Grid Independent Mode (without the utility grid) MICRO GRID

• Island Hot Standby Mode (powering its own parasitic loads)

FUEL CELLFUEL CELL

Page 24: Green Campus Conference 4-19-2011 R. Gagne

FUEL CELL FUEL CELL

Page 25: Green Campus Conference 4-19-2011 R. Gagne

FUEL CELL FUEL CELL

Page 26: Green Campus Conference 4-19-2011 R. Gagne

• Phase 1 (completed October 2011): Consisted of energy efficient improvement measures to Copernicus Hall, and Vance Academic Center. Implementation cost $164,166.00. Total energy savings $111,592.00 with a 1.5 year payback. Additional incentive through CEEF, $3,753.50 when project was closed out.

• Phase 2 (funding request submitted): Energy efficient improvement measures to the Energy Center. Implementation cost $270,671.00. Total energy savings $192,332.00 with a 1.4 year payback. Additional incentive through CEEF, $54,026.27 when project is closed out.

RETRO-COMMISSIONING RETRO-COMMISSIONING

Page 27: Green Campus Conference 4-19-2011 R. Gagne

• Retrofitting of 500 lamps across the CCSU campus with energy saving Sylvania DG LED retrofit kits

• Lessen electrical usage without compromising safety and security

• Bulb life approximately 5 times a traditional lamp

• Annual reduction of 240,900 kWh with an approximate 41k cost savings

• Reduction of criteria pollutants such as sulfur oxide, nitrogen and carbon compounds

• Reduction of light pollution in accordance with the Dark Sky Initiative

LED REPLACEMENT PROJECTLED REPLACEMENT PROJECT

Page 28: Green Campus Conference 4-19-2011 R. Gagne

• Copernicus Garage lighting: 700 (150watt HPS)fixtures were replaced with 100 watt MH

• Welte Garage lighting: 216 (150 watt HPS) fixtures were replaced with 8 foot 4 lamp fluorescents, approximately 112 watts per fixture

• Combined average savings for two garages is approximately 4,000 kWh per month

• Square D Monitoring: provides the ability to monitor each buildings electrical load

• Infrared motion sensor lighting controls: Installed in various portions of campus to include hallways, classrooms, etc.

OTHER CAMPUS WIDE ENERGY OTHER CAMPUS WIDE ENERGY EFFICIENCY PROJECTSEFFICIENCY PROJECTS

Page 29: Green Campus Conference 4-19-2011 R. Gagne

We will continue to:– Investigate any and all incentive programs

available– Research additional retro-commissioning and

continue with persistent strategies on existing retro-commissioning projects

– Educate and involve the campus community in energy conservation and sustainability efforts

– Stay committed to meeting the goals and efforts in the University’s Climate Action Plan

WHERE ARE WE HEADED?WHERE ARE WE HEADED?

(IN THE RIGHT DIRECTION!)(IN THE RIGHT DIRECTION!)


Recommended