+ All Categories
Home > Documents > Greenfield standalone cement grinding unit

Greenfield standalone cement grinding unit

Date post: 02-Oct-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
27
. EXECUTIVE SUMMARY for Proposed Standalone Cement Grinding Unit [Project termed under Schedule (3b) Category b Cement Plants as per EIA Notification 2006 and its Amendments] Greenfield standalone cement grinding unit Survey No. 1015/8, 1016/11B, 1017/3B, 4B, 5, 6B, 1019/2A2, 2B1, 2B2, 2B3, 3A, 3B, 1018/1, 2,1022/1, Kailasapuram Village, Ottapidaram Taluk, Tuticorin District,Tamil Nadu By No.29, Thilak Street, T.Nagar, Chennai, Tamil Nadu – 600 017 1.6 M Report prepared by AmplEnviron Private Limited NABET Certificate: NABET/ EIA/ 2023/ IA0061, Valid till October 22, 2023 # 2-22-144/A, Navodaya Colony, Kukatpally, Hyderabad- 500 072, Ph.: 7720003413, Mail: [email protected] www.amplenviron.com
Transcript
Page 1: Greenfield standalone cement grinding unit

.

EXECUTIVE SUMMARY for

Proposed Standalone Cement Grinding Unit

[Project termed under Schedule (3b) Category b – Cement Plants as per EIA Notification 2006 and its Amendments]

Greenfield standalone cement grinding unit

Survey No. 1015/8, 1016/11B, 1017/3B, 4B, 5, 6B, 1019/2A2, 2B1,

2B2, 2B3, 3A, 3B, 1018/1, 2,1022/1, Kailasapuram Village,

Ottapidaram Taluk, Tuticorin District,Tamil Nadu

By

No.29, Thilak Street, T.Nagar, Chennai, Tamil Nadu – 600 017

1.6

M

Report prepared by

AmplEnviron Private Limited NABET Certificate: NABET/ EIA/ 2023/ IA0061, Valid till October 22, 2023

# 2-22-144/A, Navodaya Colony, Kukatpally, Hyderabad- 500 072, Ph.: 7720003413, Mail: [email protected]

www.amplenviron.com

Page 2: Greenfield standalone cement grinding unit

.

1. INTRODUCTION

M/s Jasan Infra Private Limited (JIPL) proposes to establish a Greenfield standalone

cement grinding unit at Survey No. 1015/8, 1016/11B, 1017/3B, 4B, 5, 6B, 1019/2A2, 2B1,

2B2, 2B3, 3A, 3B, 1018/1, 2,1022/1, Kailasapuram Village, Ottapidaram Taluk, Tuticorin

District ,Tamil Nadu in an area of 35 acres. 11.6 acres of land area is proposed for green belt.

The proposal is to put up a new Standalone Cement Grinding Unit with a capacity of 1.6 Million

tonnes per annum plant to manufacture Ordinary Portland Cement (OPC) / Portland Pozzolana

Cement (PPC) / `Portland Slag Cement (PSC). The main raw materials to be handled in this

project are Clinker, Slag, Gypsum, Fly Ash, etc.

The proposed activity falls under Category “B1” - Schedule S.No. 3(b) Cement grinding

Units- as per new EIA notification of Ministry of Environment Forest & Climate Change

(MoEF&CC) dated 14th September 2006 and subsequent amendments.Therefore, unit requires

obtaining Environmental Clearance (EC) from State Environment Impact Assessment

Authority (SEIAA), TamilNadu. As per MoEF&CC notification, it is mandatory for any new

or expansion and modernization projects or activities to obtain environmental clearance. This

is a newly proposed standalone cement grinding (OPC/PPC/PSC) unit of 1.6 million tonnes per

annum.

Under above circumstances, proponent has initiated action towards obtaining

environmental clearance. The proposal seeking ToR was placed in the 122nd SEAC meeting

held on 10.12.2018. The proposal was considered as recommended by SEAC in 336th SEIAA

meeting held on 11.01.2019 vide Letter No. SEIAA –TN/F.No.6576/SEAC- CXXII/3(b)/ToR-

600/2019 dated 11.01.2019 and after detailed discussion, the authority decided to issue ToR

with public consultation subject to standard ToR for preparation of EIA report along with

additional ToR .

The work of undertaking detailed studies and preparation of EIA report has been

assigned to NABET accredited EIA consultant for the cement plant sector by the project

proponent. Existing environmental data and the other data collection for the project has been

undertaken by NABL accredited lab- M/s. Femo Labs Pvt Ltd., for the study period May

2019 to July 2019.Draft EIA study report for the proposed standalone cement grinding

(OPC/PPC/PSC) unit of production capacity of 1.6 million tonnes per annum is prepared in

conformity with the conditions laid down in ToR.

Page 3: Greenfield standalone cement grinding unit

.

2. DESCRIPTION OF THE PROJECT

The general features of the proposed project and location are given below in table

Project activity description

Feature Details

Project or Activity Standalone Cement grinding(OPC/PPC/PSC) unit

Production capacity -1.6 Million Tonnes Per Annum

New /Greenfield Project

Category B1 Category project

Schedule No. 3(b) – Cement Plant

Location of project

site

1015/8, 1016/11B, 1017/3B, 4B, 5, 6B, 1019/2A2, 2B1, 2B2, 2B3,

3A,3B, 1018/1,2, 1022/1,Kailasapuram village ,

Ottapidaram Taluk ,

Tuticorin District,

TamilNadu.

Geo –

Coordinates/SOI

8°51'18.01"(N) latitude and 77°59'41.98"(E) longitude

The Plant area is a part of the Survey of India Toposheet No.

C43X13- 58H/13 & C44S1&5 -58L/1&5

It is Plain Land with an average altitude of 38 m above MSL.

Project size Production Capacity – 1.6 MmTPA - Standalone cement

(PSC/PPC/OPC) grinding unit in an area of 35 acres .

Project Cost Rs.120 Crores

Location of the Project

The proposed new project site falls in the Survey of India Topo-Sheet No. C43X13-

58H/13 and C44S1&5 – 58L/1&5. Proposed project site is located Survey No. 1015/8,

1016/11B, 1017/3B, 4B, 5, 6B, 1019/2A2, 2B1, 2B2, 2B3, 3A, 3B, 1018/1, 2,1022/1,

Kailasapuram Village, Ottapidaram Taluk, Tuticorin District, Tamil Nadu in an area of 35

acres. The general location map of project site is shown in Figure. The Geographical co-

ordinates of the site are given in Table. The project site is plain barren land with only a few

shrubs and the photos are given in Figure. The location of the project site in satellite mage

and the 5 km and 10 km zone is given in Figure.

Page 4: Greenfield standalone cement grinding unit

.

Figure – Location map of Proposed Project Site

Project Site

Page 5: Greenfield standalone cement grinding unit

.

The Survey of India Toposheet showing the project site and nearby features and 10

km is given in Figure.

Figure – Proposed Project site photos

Page 6: Greenfield standalone cement grinding unit

.

Figure – 5 Km & 10 Km from Project Site –Google Earth Satellite Image

Page 7: Greenfield standalone cement grinding unit

.

-

-

) Figure –SOI toposheet showing 10 km radius from project site (

Page 8: Greenfield standalone cement grinding unit

.

Figure - Geo coordinates superimposed on satellite image of project site

-

-

Page 9: Greenfield standalone cement grinding unit

.

-

W E

Figure 2.8 – The layout of site plan- Standalone Cement Grinding Unit

Page 10: Greenfield standalone cement grinding unit

.

Environmental setting of the proposed project

The salient features and environmental setting of nearby features is given in table

below.

Table -Salient Environmental Features

Feature Details

Village, Tehsil, District, State Kailasapuram (V), Ottapidaram (Taluk) Tuticorin (Dist),

TamilNadu.

District head quarters Thoothukudi – 14 km – East direction

IMD STATION Thoothukudi – 14 km – East direction

Max. Temp., oC 41.1

Min. Temp., oC 16.8

Relative Humidity,% 52-80

Annual rainfall, 625.8 mm

Topography Plain

Soil Type Sandy loam – SEA

Nearest Water Bodies

Bay of Bengal – 190 km – E:

Tirunelveli Canal – 4.1 km – S

Sellyanallur Canal – 8.7 km - NW

Nearest Highway National Highway (NH- 7) connecting Madurai – Tirunelveli

Nearest Railway station Kailasapuram RS - 0.80 km – W

Nearest Air port Tuticorin Airport – 14.0 km – s

Nearest port Tuticorin Port – 20KM South East

Nearest Industry Ind Bharath Power Plant – 7Km – North East

SIPCOT -9.5 km –South East

Nearest Forest Chalikulam RF – 7.2 km - North direction

Historical places None within 10 km radius

Page 11: Greenfield standalone cement grinding unit

.

Project site – Land Area Requirement

The total are of the site is 35 acres and lies adjoining to road which is connected NH-7. The

site area breakup is given in Table:

Table -Site area breakup details

S.No Usage of Land Area (Acres)

1 Plant structures / building Area 15.00

2 Roads and Parking Area 8.4

3 Plantation/ Greenbelt 11.6

Total 35.0

Process description

Cement manufacturing process technology is easily available and there are many

reputed cement plant equipment suppliers and turnkey executers are available for timely

implementation with high quality and safe construction.

All the raw material such as clinker, gypsum, fly-ash, slag etc., are used in a prefixed

formula and fed through a volumetric feeder in fixed proportion to a bucket elevator which in

turn feeds a hopper fitted with a volumetric table feeder, feeding the VRM/ball mill, the

VRM/ball mill grind the mix to a homogeneous mixture and this mixture is known as cement

in to 2 x 90 TPH Ball mill with 22 hours. This homogeneous mixture is then stored in the silos

and packed when needed. In between the mill and storing silos there is a dust collector, which

plays a crucial role in the prevention of pollution by sucking all the dust produced by the

grinding process. The process flow diagram is given in Figure

The Cement Grinding Plant comprises the following preparation, processing and

handling units:

Clinker unloading, handling, storing and retrieval system.

Gypsum unloading, handling, storing and retrieval system.

Clinker proportioning and feeding

Gypsum storage, proportioning and feeding.

Clinker and Gypsum Grinding.

Fly ash classification, pneumatic transportation and storing.

Fly-ash proportioning and feeding.

Page 12: Greenfield standalone cement grinding unit

.

Ground Cement Handling and storage

Ground Cement Extraction

Cement Packing

Packed Cement Loading in trucks for dispatch.

Complete ancillary system of water, power & pneumatic system.

Products: Production of Portland Slag Cement (PSC) and Portland Pozzolana Cement

(PPC) considering the market analysis of demand and supply, and in conjunction with

transportation logistics, the annual capacity will be 1.6 MTPA.

Unloading of Bag Filters

Clinker

Bag Filters

Fly Ash Silo Gypsum Slag

Clinker Bag Filters

Silo Cement

Bag Filters Mill

Bag Filters

Dispatch Packing

Plant Cement Silo

Note: OPC- Grinding of Clinker & Gypsum; PPC-Grinding of Clinker, Gypsum & Fly Ash; PSC-Grinding of Clinker, Gypsum & Slag

Figure 2.9 – Process flow diagram - Standalone Cement Grinding Unit

Page 13: Greenfield standalone cement grinding unit

.

The types of products made in the cement plant are listed in Table 2.4 & 2.4 (a).

Table 2.4 - Production details

Sr. Type of Cement Ingredient

1. PSC Clinker + Gypsum + Slag

2 PPC Clinker + Gypsum + Fly ash

3. OPC Clinker + Gypsum

Raw material required and transportation detail:

Clinker will be transported through Road/Rail from neighbouring states Viz., Andhra

Pradesh, Karnataka, Telangana etc., and the clinker will be un-loaded and stored in Covered

Shed.

Gypsum required will be sourced from SPIC, Tuticorin. Fly-Ash required will be

sourced from Tuticorin. Fly-ash is an Environmental Hazard in terms of its disposal and hence

utilizing fly-ash for the production of cement in environmental friendly manner saves the local

environment and establishing the plant will also be ushering the economic development of

Tamilnadu. GGBS (Ground Granulated Blast Furnace Slag) required will be sourced from

Salem/Vizag.

Plant Automation

The total plant operation will be done through computer based PLC / DCS system to

have micro level monitoring and controls.

Table 2.4 (a)- Production details (% by weight)

S.No Component Proportion, % by weight

PSC PPC OPC

1 Clinker 40-50 60 95

2 Gypsum 5 5 5

3 Fly Ash - 35 -

4 Slag 40-50 - -

Power

The maximum electrical power demand for the Plant is 7.5 MW. It shall be sourced

from TNEB. The unit has DG sets with the capacity of 3 x 500 KVA.

Page 14: Greenfield standalone cement grinding unit

.

Raw Material

The source of raw material and mode of transport is presented in the following table.

Table - Raw Material Requirement

S. No Material Source

Category Source Locality

Quantity

(MmTPA)

Mode of Transport

to Site

1

Clinker

Purchased

Andhra Pradesh

Karnataka,

Telangana

0.525

Truck *

2 Gypsum Purchased SPIC,Tuticorin. 0.075 Truck*

3 Fly ash Purchased Tuticorin 0.46 Bulker

4 Slag Purchased Salem/Vizag 0.975 Truck/ wagon*

* All the trucks are covered by Tarpaulin.

a) Greenbelt

Greenbelt in an area of 11.6 acres will be developed inside the plant boundary as per

statutory norms.

b) Social infrastructure

The plant has well-defined Corporate Social Responsibility (CSR) policy to Carryout

social development and welfare measures in the surrounding villages.

c) Connectivity (Traffic and Transportation Road/ Rail/Metro/ Waterways Etc)

The proposed cement grinding unit has close proximity with Sea and good connection

with Indian Railway network. The plant is well connected by road/ High way.

d) Water requirement (source and supply of water)

The total water requirement is 100 KLD Ground water/ Storm water runoff. The

daily water consumption is presented in the water balance in the following Table 2.9.

Page 15: Greenfield standalone cement grinding unit

.

Table 2.9 - Water balance details

S. No Input (KLD) Total Source of water Out Put (KLD) Total

1 Greenbelt development 70 Stored rain water Evaporation Loss 70

2 Dust suppression 10 Stored rain water Evaporation Loss 10

3 Cooling 15 Ground water Evaporation Loss 15

4 Domestic use 5

Ground water Domestic

Effluent 4

Loss 1

Total (KLD) 100 Loss (KLD) 100

e) Air Emissions

The pollution expected from the cement grinding unit is PM. The fugitive emissions

are from truck unloading (Tipper), Clinker hopper, Clinker storage silo, weigh feeders for

clinker, gypsum and solid flow meter for fly ash storage silo, clinker grinding mill, cement

silos and packing machine. Bag filters will be provided to control SPM emissions <30

mg/Nm3.

Table 2.10- Air Emission details

S.

No

Stack

attached

to

Stack

height,

(m)

Temperature

of exhaust

gas, (°C)

Exit

velocity,

(m/s)

Pollutant Emission, (g/sec)

PM

SO2

NOX

1 2 x110

TPH ball

mill

40 80 14 1.5 - -

2 3X 500

KVA

15 160 12 1.1 1.2 1.6

f) Industrial waste management

No industrial waste water will be generated from the proposed Clinker

Grinding Unit.

Domestic waste water from plant will be treated in the STP & treated water

will be utilized for green belt development and dust suppression.

Rain water harvesting will be practiced at plant area.

Page 16: Greenfield standalone cement grinding unit

.

g) Solid waste management

No solid waste will be generated from the cement manufacturing process.

Dust collected from various air pollution control equipment will be recycled

completely in process

Used/Spent oil (Hazardous Waste) will be utilized for lubrication in machines,

chains, etc.; Remaining quantity will be sold to CPCB authorized recyclers.

Table 2.11 - Solid waste generation

Description Units Total Disposal

Waste bags, damaged bags TPA 12 Sold to manufacturer

Spent Oil KL/Year 2 Sent to authorized Recyclers

Used lead acid batteries Nos/ 2 Sent to authorized recyclers year

General Scrap (Rubber, Metal

& Electrical)

TPA 10 Sold to recyclers

h) Project schedule & cost estimates

Commencement of the Project : 3 months (after obtaining consent approval)

Completion of the Project : 12 months

i) Project cost

Project Cost: Rs.120 Crores

A break-up of the indicative estimate of the Project capital cost is provided below:

S. No Description Rs.in Lakhs

1 Land and development Expenses 250

2 Project management /Engineering fee 200

3 Plant Equipment including E&I 6,500

4 Miscellaneous Fixed Assets 350

5 Buildings (Plant structures) 3,500

6 Erection / Installation Charges 450

7 Pre-Operative Expenses 350

8 Contingencies 400

Grand Total in Rs lakhs 12,000

Page 17: Greenfield standalone cement grinding unit

Page 29 of 134

.

3. BASELINE ENVIRONMENT STUDY

Baseline data has been collected for the study of parameters- Ambient Air, Noise, Water &

Soil by NABL Accredited Laboratory M/s.Femo Labs Private Ltd . The study period is 1st May

2019 to 31st July 2019.

The environmental baseline data has been compiled for : Land Environment (Physiography,

Soils, Geology and Minerals); Water Environment (Water resources, and quality); Air

Environment (Meteorology and Ambient Air Quality); Noise Environment (Noise

level);Ecological Environment (Flora and Fauna);Socio-Economic environment (Demography

and occupation etc.) as per CPCB guidelines.

In the study area, It is observed that all values are within the prescribed limits for ambient

air quality and stack emissions. The water quality of the area is found to be within the prescribed

limits for drinking water. The quality of the ground water samples are within prescribed limit. The

noise levels are found to be within limits. The soils are having good pH and have good water

holding capacity.

4. IDENTIFICATION OF IMPACTS

Land Use and Topography

There will not be any change in land use pattern. The proposed project activity will be carried

out on the land premises of industrial use. Hence, there is no major impact on land use pattern.

The drainage pattern will not be affected due the proposed project as the project is having no

natural drainage passing through the project site.

Air Environment

All the raw material will be stored either in closed chamber or in closed sheds and on lined

surfaces. Hence, there will be no possibility of leachate taking place.The dust collected in the air

pollution control equipment in the cement plant will be recycled back to the process. Hence, no

solid waste which will require disposal is generated from the plant.By AERMOD ,Base line study

indicates that the ambient level of various pollutants like PM2.5, PM10, SO2, NOx and CO is

within the limits stipulated by National Ambient Air Quality (NAAQ) Standards. The height of

the D. G Set stacks so provided will help in dispersing the pollutants emitted from the stacks

effectively into the atmosphere.

Hence, the operational phase activities are expected to have little impact on the air quality.

Hence, the concentration of general pollutants like Particulate matter (PM10 & PM2.5), Sulphur

Page 18: Greenfield standalone cement grinding unit

Page 30 of 134

.

Dioxide (SO2), CO and Nitrogen Oxides (NOX) are expected to be within the permissible limits.

Hence, minimal adverse impact is predicted

Noise Environment

a) During construction Phase, the following may occur :

The major activities which are likely to increase ambient noise levels during construction

phase are foundation work, fabrication of structures, operations of construction equipment,

movement of vehicles, loading & unloading of materials etc.

The study area is likely to experience increment in ambient noise level due to the above

mentioned activities which can be about 100 dB (A). The areas affected will be those which are

closer to the site. However, as there are no settlements and open land in the immediate vicinity of

the plant, the impact of noise will be negligible.

Mitigation Measures

Noise generating equipment will be used during day time only.

All the vehicles entering into the project site will be informed to maintain speed limits

and not to blow horns unless it is required.

The workers involved in operating major noise generating equipment will be provided

with personal protective equipment like ear plugs/ear muffs etc.

Plantation around boundary wall also reduces noise level.

b) During Operational phase , the following may occur

During operation phase, the sources of noise pollution are grinding unit and vehicular

movement. Any industrial complex in general consists of several source of noise in clusters or single.

This cluster/single source may be housed in building of different dimensions made of different

materials or installed in open or under sheds. The material of construction implies different

attenuation co-efficient.

Noise level outside plant boundary is about 56- 58 dB (A) which was measured during site

visit.In the operation area it will not be feasible to keep ambient noise levels below 85 dB

(A).Operating personnel will be provided with earplugs and earmuffs. As per Occupational Safety

and Health Administration (OSHA) Standards, the maximum allowable noise level for the workers

is 90dB (A) for 8 hours exposure a day. Therefore adequate protective measures in the form of ear

muffs / ear plugs will be provided to the workers, who will be working in high noise machinery

area during operation. In addition, reduction in noise levels in the high noise machinery area will

be achieved by adoption of preventive measures such as proper building layout in which the

equipment are to be located, adding sound barriers, use of acoustics enclosures with suitable

Page 19: Greenfield standalone cement grinding unit

Page 31 of 134

.

absorption material, etc.

Further, in addition to the plant noise control measures, all the open areas within premises

along the plant boundary will be provided with adequate green belt to diffuse the noise.

Water Environment

Nominal quantity of water will be used during construction period as it will be construction

of super structure (CCR & Laboratory, Admin Building, workshop,etc )as per proposed site layout.

There will be no stagnant pools of water which can promote breeding of mosquitoes and unsanitary

conditions. Tanker water will be used during construction, so that waters do not form

stagnant pools nor aggravate soil erosion.

Water consumption in the cement plant for domestic use, dust suppression, cooling and

plantation is 40 KLD. The agreement copy of groundwater withdrawal of 40 KLD is enclosed as

Annexure.

Cement will be manufactured by dry process technology. No wastewater will be generated

from cement plant process. Moreover, no streams are crossing through the project site. The domestic

sewage shall be treated in a septic tank followed by dispersion trench, as proposed to meet the

discharge norms. Thus no major adverse impact of waste-water is envisaged from the plant.

The waste water during construction will contain only suspended impurities. This water

would use in gardening and other non-consumption activities.

Ecological Environment

The site is neither an ecologically sensitive area nor a place of ecological importance. There

would be no requirement of tree felling for the construction of the project. There will be only an

addition of machinery.The construction work will be under temporarily made shed and it will be

addition of Ball mill only. Therefore, significant ecological impact is not envisaged during

construction phase of the proposed project.There is no forest land in the study area or project site.

The impact on the surrounding ecology during the operation of the project could mainly occur from

the deposition of air pollutants.The incremental emission level of air pollutants due to this project is

not likely to induce any significant changes in the ecology because the pollution dispersion will

remain confined within 50 meters from the plant (as per air quality modelling). However deposition

of small amount of pollutants may also affect the surrounding ecosystem. The project is therefore

planned with very efficient air pollution control systems.Most of the fugitive dust emission

generation points will be fitted with efficient air pollution control systems (bag filters and dust

collectors). Water sprinkling system will be done at material handling points to suppress the

generation of fugitive dust. These measures are adequate to minimize the adverse impact on nearby

Page 20: Greenfield standalone cement grinding unit

.

agricultural land.

Occupational Health

Exposure problems to noise, dust and heat are the major occupational hazards. Noise induced

hearing loss and dust related problems are the notified occupational hazard. The employees working

in dusty environment will be subjected to regular health check-up. The workers will be diagnosed

for respiratory functions at periodic intervals and during specific complaints for lung function test,

sputum test, X-ray test, etc.

It will be ensured that workers are not exposed above the threshold noise limits prescribed

by OSHA and Factories Act through suitable administrative controls. Personal Protective

Equipment like earplugs and muffs will be provided and administrative pressure applied for using

them. Auditory examination by qualified doctors upon the first employment and thereafter periodic

examination will be conducted.

5. ENVIRONMENTAL MONITORING PLAN

Environmental Quality Data Management

Environmental monitoring has been carried out by NABL accredited All the results will be available at

the project site and submitted to the TNPCB as per the requirements for Environmental Clearance.

Environment Management Cell

The environment management cell will be responsible for timely conduct of the monitoring activities.

The results of the analysis will be intimated to the project head. Any abnormality found in the test

results will be inspected and required corrective actions will be taken.

A complaint register will be maintained to note any complaint from the staff, visitors or any other

stakeholder. Corrective actions will be taken against the above complaints.

Environmental Management Budget Allocation

A capital cost provision of about Rs. 6.0 crores has been kept in the project cost towards the

environmental protection, control & mitigation measures and implementation of the EMP. The

budgetary cost estimate for the EMP is given in Table.

EMP Budget allocation

S.

No Item

Capital Cost

(Crores)

Recurring Cost

per annum

(Lac)

1 Air Pollution Control 3.00 6.0

Page 21: Greenfield standalone cement grinding unit

.

2 Water Pollution Control 0.50 1.0

3 Noise Pollution Control 0.50 0.25

4 Environment Monitoring and Management 0.20 10.0

5 Occupational Health 0.20 5.0

6 Green Belt 0.40 1.0

7 Salary of EMP staff 0 6.0

8 Safety Management 0.30 2.5

9 Rain water harvesting 0.90 4.0

Total 6.0 35.75

Environmental Monitoring Plan

Environment

Component

Project stage Parameter Location Duration /

Frequency

Ground Water

Quality

Construction Stage

Drinking water parameters Project site

Half yearly

Operation Phase

Drinking water parameters

Project site

Half yearly

Drinking water

Construction Stage

Drinking water parameters Supply

water

after

treatment

Half yearly

Operation Phase

Drinking water parameters Supply

water

after

treatment

Half yearly

Air

Construction Phase PM2.5,PM10, SO2, NO2,

CO,O3

a)Ambience(in & around plant) b)Fugitive emissions

Project Site

Half yearly

Operation Phase PM2.5,PM10, SO2, NO2,

CO, O3

a) Stack monitoring

b) Work zone

c) Ambience(in & around

plant)

d) Fugitive emissions

Project Site ( in and

around the

Half yearly

Noise

Construction Phase

Noise Level in dB (A) Project Site

Half yearly

Operation Phase Noise Level in dB (A) Project site Half yearly

Rainwater

harvesting

Operation Phase Inspection of storm water

drains and rainwater

harvesting pits

Project site

Prior to

monsoons

Page 22: Greenfield standalone cement grinding unit

.

6. PROJECT BENEFITS

The proposed project will provide various opportunities for economic and social

development of the villages surrounding S. Kailasapuram village.

8.1 Project Benefits

The industrial activity will help in improving the socio-economic benefits in areas like

employment, communication, educational etc.,

8.2 Employment Potential

Aound 500 people will be required for plant for direct and indirect employment. There is

indirect employment to many more people in the form of increase in contractual jobs, business

opportunities, service facilities etc in the nearby villages of Ottapidaram taluk.. This will

enhance the economic status.

Apart from the jobs, the company will medical and educational facilities to the employees

which can also be availed by the people around the plant.

8.3 CER and Social Welfare activities

The cement plant will be operated in socially and environmentally responsible manner, by

reducing the environmental impact of its operations and increasing its positive social impact.

It aims to achieve growth in a responsible way by encouraging staff to conserve natural

resources like water. The tree plantation around the pant site will add to the scenic beauty

and enhance environment. The cement plant will be in direct cooperation with Governments,

NGOs, and public fro implementation of CER activities The proposed cement grinding unit

of capacity 1.6 MTPA will enhance and uplift the socioeconomic conditions of surrounding

population.

S. No Activity Cost of CER

activity

Description Location

1. Solid waste Management facility for Savarimangalam and villages around 5 km from project site

50 lakhs

Installation of Dustbins with different waste will provide Gloves, Mask and other safety measure for rag pickers. Conduct awareness program for the people of village “how and why should segregate waste”.

All above mentioned 6 villages within 5 Km from project site

2. Skill Development and Training

30 lakhs

Sewing machines will be provided and trained to improve the skill of people around the project

All above mentioned 6 villages within 5 Km from project site

Page 23: Greenfield standalone cement grinding unit

.

S. No Activity Cost of CER

activity

Description Location

site

3. Technology Development in schools around 5 Km from the project site

30 lakhs

Improving the schools with smart Class system by providing Computers, projectors.

1. Kailasapuram

2. Umarikottai

3. Jambulingapuram

4. Pudiyamputhur

5. Keelathattaparai

6. Varthakareddipatti

4. Library 35 lakhs

Common Library will be established and maintained to improve the education quality of the Students and literates around the village.

All above mentioned 6 villages within 5 Km from project site

5. Health camps along with free medicine distribution

35 lakhs

Health camps will be conducted once in a year. Camps will be planned and carried out in association with reputed eye hospitals and specialists. This is for screening of diseases. Medicines will be provided free of cost.

All above mentioned 6 villages within 5 Km from project site

Total cost for CER 180khs

Page 24: Greenfield standalone cement grinding unit

.

7. ENVIRONMENTAL MANAGEMENT PLAN

Air Quality Management

During construction: The proposed activity may result in the increase of particulate concentration

generated due to the transportation of construction materials, land clearing and leveling of land,

operation of construction machinery/equipment, construction of foundations, buildings and other

requisite infrastructure etc.

close to the construction site.

The impacts shall be temporary in nature and However the following measures shall further reduce the

dust generation.

Construction materials will be fully covered during transportation

Land clearing for construction site will be kept at the absolute minimum practicable.

Construction site would be designed to minimize the removal of soil and vegetation.

Topsoil removed will be preserved by piling it along a boundary of the site and used later .

Dust suppression systems such as water sprinkling will be used as per requirement at the

construction site.

Vehicles will be properly maintained to comply with exhaust emission requirements

During operation:

The air emission from cement plant operation will be minimized by use dof Air Pollution

control measures such as Bag filters.

Fugitive emissions control during miming, loading, unloading and transportation

activities shall be practiced.

Water sprinkles shall be installed along the haul roads and operated to suppress the

dusts.

Over loading of trucks will be be avoided and raw materials shall fully be covered

with Tarpaulin on transportation.

Regular and preventive maintenance of transport vehicles shall be undertaken.

Transport vehicles shall be in compliance with emission norms.

Noise Level Management:

There will be marginal increase in noise levels during construction phase, which is temporary.

The noise shall be generated mainly due to operations of machinery/equipment used for

construction and transportation of materials to the site. The measures described below shall be able

mitigate the noise levels generated at site during construction and operation.

Page 25: Greenfield standalone cement grinding unit

.

Provision of rubber padding for eqipments.

Use of protective devices like ear muff/plugs by the workers.

As far as possible no construction activities will be planned during day time,

Sound proof operators cabin of equipment shall be provided.

Ear muffs/plugs shall be provided to the workers in higher noise zones.

Green belt with thick foliage shall be developed around site, to act as acoustic barriers.

Water Quality Management:

During construction of the project, provision for infra structural services including water

supply, sewage ,drainage facilities and electrification will be made. The existing toilet facilities for

workers shall also extend to the construction labor. These facilities would be connected to a septic tank

and maintained to ensure minimum impact on the environment. The drainage system of construction

area will be connected to the existing drainage system at an early stage. Salient features of water quality

management comprise the following.

All the domestic waste water shall be sent to septic followed by soak pit.

Wash down area for cleaning of vehicles wheels shall be provided and wheel wash waste

shall be drained properly.

To prevent contamination from accidental spillage, the storage areas will be bunded and will

be inspected and cleaned at regular intervals.

As far as possible local labourers will employed so as to reduce the burden on the resource

Soil Quality Management

The following measures shall be adopted to prevent the soil contamination:

The removed earth/soil during foundations will be utilized for making roads, fill the available

depressions within the plant area. It shall not dumped outside the plant premises.

Land clearing for construction site will be kept at the absolute minimum practicable.

Construction site would be designed to minimize the removal of soil and vegetation

Topsoil will be cleared and stored for later reinstatement purposes by piling it along a

boundry of the site.

Dust bins shall be placed at requisite locations

With a view to attenuate noise propagation and mitigate fugitive air pollution impacts, it is

planned to develop a greenbelt all along the periphery of project site. Compatible species

will be identified for greenbelt. Saplings will be suitably nurtured. Regular watering will

be undertaken. Soil conditioning and fertiliser application will be undertaken. If required,

suitable soil treatment will be provided to ensure good growth of tree cover.

Page 26: Greenfield standalone cement grinding unit

.

Socio-Economic Environment

The proposed cement plant and the construction activity will benefit the local population in a

number of ways.

The plant will provide benefits to local people through both direct and indirect employment.

Solid Waste Management

Non hazardous solid waste generated from the cement plant is cement dust collected from

various pollution control devices.

The dust collected in the air pollution control equipment in the cement plant will be recycled

back to the process. Hence no solid waste that requires disposal is generated from the plant.

Hazardous Waste The hazardous waste of spent oil is used as secondary fuel and batteries

will be sold to authorized recyclers.

Safety and Health of employees

Adequate space will be provided for construction of temporary sheds for construction

workers The contractors will supply potable water for the construction workers.

The safety staff will supervise the safe working of the contractor and their employees.

Work spots will be maintained clean, provided with optimum lighting and enough

ventilation to eliminate dust.

Implementation and responsibility for EMP

The cement plant officials and environmental cell will take responbility of implementing

EMP. The annual plan will bedevised and followed under the heads of

Air Pollution Control

Stack Emission Management

Fugitive emission Management

Noise Mitigation

Wastewater Management

Solid waste Management

Energy Conservation

Green belt development

Occupational safety and health

The cost has been worked out and the implementation will be taken up meticulously.

Page 27: Greenfield standalone cement grinding unit

.

8. CONCLUSION

The cement project is proposed to meet the growing demand for cement to meet the

needs of the construction sector.

The baseline environmental condition of the project area in terms of Air Quality, Noise

Levels Water Quality, Soil and biological Environmental attributes are well within the

limit.

For air quality impact predictions ISCST3 model software was used to identify the

GLC during operation phase. The resultant concentration of air quality parameters

are within the Ambient Air Quality standards.

Since the cement production operation is a dry process, waste water is not generated.

Domestic use and dust suppression only utilize water. The impact on water environment

is practically minimal.

The plant machinery design and acoustic measures ensure that no significant impact on

the noise environment.

CER activities will be carried out by the proponent as per the guidelines of the MoEFCC

Safety precautions for employess and fire safety will be carried out as per legal

requirements.

Greenery development and rainwater harvesting are planned to enhance environmental

benefits.

The effective implementation and supervision of EMP to mitigate the environmental

impacts could be achieved through a suitable training to employees and by use of

profession help of environmental experts.

The proposed cement grinding unit of capacity 1.6 MTPA will enhance and uplift the

socioeconomic conditions of surrounding population.


Recommended