Grossmont-Cuyamaca Community College DistrictFacilities Construction Update
April 17, 2018
Presented by
Fred ParkerProgram Manager
Gafcon, Inc.
Agenda
2
• Grossmont College Update
• Cuyamaca College Update
• Energy Conservation Measures
• Analysis of Construction Costs
• Cost Savings Update
Grossmont College
3
Performing and Visual Arts Center
• Project Estimate : $42.7 M
• Scope:
• Removal of Buildings 22 A-C
• Construction of a new 38,680 square foot (SF), 390-seat teaching and performance theater
• The theater will include the new Hyde Gallery
• Status:
• Footing layout and chilled water re-route work are ongoing
• First concrete pour of deep Orchestra pit poured on 4/9/18.
• Construction Duration: December 2017-October 2019
Grossmont College
4
Science, Math and Career Tech Complex – Building 31 Renovation
• Project Estimate: $14.3 M
• Scope:
• Remodel of Bldg. 31 including classrooms, labs, and offices
• Outdoor gathering area
• Status:
• All tenants relocated to swing space over winter break
• Bids received and under review
• Construction start May 2018
Grossmont College
5
Interim Swing Space-Phase 1-3
• Project Estimate: $3.4 M
• Scope:
• Phase 1 provides Building 31 swing space in Parking Lot 5 South
• For phases two and three of this project, the interim space will house programs affected by construction from Buildings 21, 24, 27 & 36
• Status:
• Construction complete. Buildings occupied and functional.
Grossmont College
6
Science, Math and Career Tech Complex – Building 36
• Project Estimate: $33.5 M
• Scope:
• Removal of Building 36 and construction of a new two (2) story 46,850 GSF building & Includes Veteran’s Center
• Removal of buildings 32B, 37, 30B, 38C, 95 at the end of the project
• Status:
• Schematic Design Underway
• DSA submission fall 2018
• Construction start fall 2019
Cuyamaca College
7
• Project Estimate: $1.4 M
• Scope:
• Remodel existing building to accommodate Water/Waste Water Technology program
• 2 classrooms, 2 labs and office space
• Status:
• Renovation underway
• Construction duration: March 2018-July 2018
Building L Remodel
Cuyamaca College
8
• Project Estimate: $4.2 M
• Scope:
– Expansion of Veteran Center
– Reconfiguration of space includes:
• Bookstore
• Food Services
• Student Affairs
• Status:
• In design
• Construction duration: winter-summer 2019
Student Center & Veterans Services
Cuyamaca College
9
• Project Estimate: $12.5 M
• Scope:
• New offices and retail building
• Remodel existing
• New greenhouses
• New storage
• Status:
• Design Development Complete
• Construction Documents underway
• Submission to the Division of the State Architect anticipated May 2018
• Construction duration: spring 2019-summer 2020
Ornamental Horticulture Complex
Cuyamaca College
10
Student Services & Administration Building
• Project Estimate: $31 M
• Scope:
• New Student Services and Administration facility
• Veteran Support Center
• Status:
• Schematic Design
• Bidding/Award: 2019
• Construction start: 2020
Cuyamaca College
11
Landscape Improvements-Central Park
• Project Estimate: $2 M
• Scope:
• Scope is being defined
• Designed in coordination with the upcoming Student Services and Administration Building
• Status:
• Schematic Design
• Bidding/Award: Fall 2019
• Construction start: 2020
Year 4: Energy Conservation Measures
Energy Conservation Measures
12
Project Budget: $685,327
• State funding received
• Grossmont College
• Prop 39- Main Chiller Addition
• Cuyamaca College
• Building D Main Chiller water loop
• Monitor Based Commissioning
• Status:
• Out to bid
• Anticipated construction start June 2018
Building D Main Chiller Water Loop
(Prop V & Prop 39)
Energy Conservation Measures
13
• Project Estimate: $9 M
• Scope:
• Expansion of central plant
• Modernization of aging chiller equipment and infrastructure
• Status:
• In design
• Anticipated construction start fall 2019
Chiller Expansion & Year 5 Energy Conservation Measures
Grossmont College Main Chiller Addition
Cuyamaca College Central Plant
14
Construction Trends & Escalation Outlook
Analysis of Construction Costs
• Typical escalation factor used in the construction industry has ranged from 3% to 4.5% through 2016
• National total construction spending in 2017 was forecasted to finish at $1.263 billion, an increase of 6% over 2016
• Escalation has shot up to an average of 22% in the greater San Diego market.
• Factors include:
• A rebounding economy
• Mega projects in Nevada and Arizona
• Construction start is up by 6%
• Contractors are busy and resources (labor pool) is at an all-time low
• Commodities are trending higher than normal
• Extensive amount of local school bonds passed in 2016
• Materials: substantial increases in the costs of cement, copper pipe and lumber.
15
Escalation Impacts in 2017
Analysis of Construction Costs
PROJECT BUDGET BID DAY
RESULTS
PERCENTAGE
OVER
1 Performing Arts Center –
Sage Creek High School,
Carlsbad, Ca.
$11.5M $14.8M 30%
2 Orange Coast Community
College Planetarium
$14.1M $16.39M 16.24%
3 Sacramento Municipal
Utilities District HQ
$66M $97M 46%
4 Pinole Valley High School $97M $130M 56%
5 Anatolia Elementary School $20M $24.76M 23.8%
Cost Savings Update
16
Cost Savings UpdateCampus Project Cost Savings Reason
GrossmontCollege
Performing and Visual Arts Center $93,000 Change ordernegotiations:• CM at Risk Contract• Sound blankets• Wayfinding
signage
GrossmontCollege
Performing and Visual Arts Center $852,000 Value engineering efforts:• Reduced sun
shades and increased mullion spacing
• Soil screening• Site utilities
reallocated
Total $945,000
17
Questions?
Bond Program Update