+ All Categories
Home > Documents > Guidance Notes for Generation Licence applicants

Guidance Notes for Generation Licence applicants

Date post: 07-Dec-2021
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
17
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities 0 Information Paper Reference: Date Published: January 2018 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Guidance Notes for Applying for a Licence to Generate Electricity www.cru.ie
Transcript
Page 1: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

0

Information Paper

Reference: Date Published:

January 2018

An Coimisiún um Rialáil Fóntas

Commission for Regulation of Utilities

Guidance Notes for

Applying for a Licence to

Generate Electricity

www.cru.ie

Page 2: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

Table of Contents

Introduction .............................................................................................................................. 2

Application Validity – CRU Acceptance/Rejection Criteria ........................................................ 4

CRU Assessment and Applicant Updates ................................................................................ 4

Additional Information Requests .............................................................................................. 5

CRU Decision Making process................................................................................................. 6

Terms and Conditions of a Generation Licence ....................................................................... 6

When should I apply? .............................................................................................................. 6

How long will it take to consider my application? ...................................................................... 6

Format of Submission and application Fee .............................................................................. 7

Confidentiality of information submitted .................................................................................... 8

Further information on the Irish electricity market ..................................................................... 9

Page 3: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

2

Introduction These guidance notes are to assist applicants in applying for a Licence to Generate Electricity. They

should be read in conjunction with the Commission for Regulation of Utilities (CRU) application form that

is applicable to the project.

1.1 Legislative Background

1.1.1 Grant/Refuse Authorisations and Licences

The Electricity Regulation Act, 1999 as amended (the Act) gives CRU the necessary powers to licence

and regulate the generation, distribution, transmission and supply of electricity in Ireland. One of the

functions of CRU under the Act is to grant or refuse Licences to Generate Electricity (a Licence) following

assessment of an associated application.

All electricity generators must hold a Licence under the Act. It is an offence to generate electricity prior

to obtaining a Licence from CRU. On conviction, a person may be liable to a fine up to €1,904,

imprisonment for a term not exceeding 12 months, or both.

Authorisations to construct or reconstruct generating stations (Authorisations) are also issued by CRU

and separate Authorisation Guidance Notes are available at www.cru.ie.

Joint application forms are used for both Authorisations and Licences.

1.1.2 Environmental Assessment

The European Union (EU) (Birds and Natural Habitats) Regulations 2011 (S.I. 477 of 2011) (as amended)

implement the EU Habitats Directive (92/43/EEC) and EU Birds Directive (2009/147/EC). Under the

European Union (EU) (Birds and Natural Habitats) Regulations 2011 (as amended) the CRU is defined

as a “public authority”. Regulation 42 of the EU (Birds and Natural Habitats) Regulations 2011 (as

amended) outlines the obligations on public authorities in relation to Appropriate Assessment (AA). All

projects seeking an Authorisation to Construct or Reconstruct and/or a Licence to Generate in order to

generate electricity are required to undergo AA screening and/or AA.

Page 4: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

3

1.2 Exemption for <1MW Generating Stations

If a proposed generating station has an installed capacity of less than or equal to 1MW then applicants

are exempted from the need to apply to CRU for a Licence. Such generating stations stand licensed

pursuant to S.I 384 of 20081.

1 S.I. No. 384/2008 – Electricity Regulation Act 1999 (Section 14 (1A)) Order 2008

Page 5: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

4

Application Validity – CRU Acceptance/Rejection Criteria

CRU has developed application forms and guidance documents to assist applicants in developing a valid

application. The relevant application forms and guidance documents are available at www.cru.ie.

On receipt of an application, the CRU assessment team will carry out a Completeness Check to confirm

that the application is valid. Should CRU receive an invalid application i.e. missing documentation or an

incomplete application form, it will inform the applicant in writing that their application is incomplete and

will not be processed. A written list of the incomplete sections will be provided to support the applicant’s

development of a new and valid application.

To avoid the potential for submission of an invalid application, new applicants are encouraged to contact

CRU via [email protected] to request a pre submission meeting. At this pre submission meeting, CRU will

set out the application and assessment process and answer any questions the applicant may have.

Additionally, the CRU completeness check template is provided in Appendix 1 to assist applicants in

developing valid applications.Applicants should note that updating their application mid assessment will

delay the CRU assessment process and may necessitate a full reassessment. It may also invalidate the

original application and result in the requirement for a full new application. The decision to require a new

application or recommence an assessment will be made on a case by case basis and is fully at the

discretion of CRU.

CRU Assessment and Applicant Updates

Once the application has passed the Completeness Check, the applicant will be notified that the

assessment has formally commenced. A CRU application reference number will be assigned for

assessment and this should be used in all correspondence with CRU.

The assessment will cover the following disciplines:

(a) Administrative;

(b) Technical;

(c) Environmental; and

(d) Financial.

Page 6: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

5

To keep applicants aware of assessment progress, fortnightly Assessment Progress Reports will be

issued by CRU for the duration of the assessment. An Assessment Progress Report template is provided

in Appendix 2.

Should an applicant require information that is not contained in the Assessment Progress Report, they

may submit a request for information to CRU by email via [email protected].

During the assessment, CRU may require Additional Information from the applicant to support their

application, or to clarify information already submitted. These requests will be issued within the

Assessment Progress Report.

Where matters arise that have the potential to result in a refusal of an application, the applicant will be

informed at the earliest opportunity to afford them the time to address the matter through the submission

of Additional Information.

Additional Information Requests

As outlined above, CRU may require Additional Information from the applicant to progress the application,

or to clarify information already submitted. Examples of Additional Information that may be requested

include:

Environmental

- Specific chapters of the Environmental Impact Assessment Report (EIAR), Environmental Impact

Statement (EIS) or Environmental Report (ER) that are relevant too and may help to inform the

Appropriate Assessment;

- Post-approval documentation that has been supplied to the planning authority that might include

but is not limited to habitat restoration plans/management plans, species protection plans or other

planning compliance documentation relating to ecology; and

- Copies of correspondence/consultation with relevant authorities such as NPWS, IFI or local

authority Biodiversity Officer.

Page 7: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

6

CRU Decision Making process

If CRU determines a Licence should be granted, the applicant will be issued with a soft and hard copy of

the signed Licence.

If CRU decides to refuse a Licence application, the applicant will be notified in writing of the reasons for

the refusal and will be informed of the appeals process as per Part IV, Sections 29 to 32 of the 1999 Act.

Please note that the appeals process is external to CRU procedure.

In granting a Licence, the CRU is not endorsing the plans of a generating station and it cannot be relied

upon as an indication of the likely commercial success or otherwise of its holder.

Terms and Conditions of a Generation Licence

A Licence is valid for a minimum of 30 years, subject to the Licence holder complying with the terms and

conditions of the Licence. This 30 year period includes a 15 year initial term and the potential for CRU to

issue a 15 year notice of termination of the Licence.

CRU may revoke a Licence if the holder fails to comply with the terms and conditions. The revocation

terms of the Licence are detailed in Schedule 2 of the Licence. Details of other terms and conditions of

a generation Licence can be found in the Licence.

When should I apply?

Applicants can apply as soon as they have all the CRU required information. Where a joint application

for and Authorisation and a Licence is not submitted, applicants must hold an Authorisation from CRU

prior to submitting their Licence application.

How long will it take to consider my application?

CRU aims to meet the following application assessment timelines:

Assessment steps Timeline

Acknowledge receipt of application Within 1 week of receiving application

Page 8: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

7

Completeness Check Within 2 weeks of receiving application

Assessment Up to 16 weeks*

CRU final decision making process 2 weeks following completion of assessment

*The assessment timelines are dependent on a number of factors, including:

1. Applicant response times to Additional Information requests; and

2. The location and ecological sensitivities2 in the vicinity of the proposed generating station.

Format of Submission and application Fee

A checklist of all documents applicants should enclose with the completed application form can be found

in Appendix 1. The application form also details these required documents.

All documentation should be submitted electronically to [email protected]. Files that are too large to be

submitted by email should be submitted by CD to:

Commission for Regulation of Utilities

Generation Licensing Section

The Grain House

The Exchange

Belgard Square North

Tallaght

Dublin 24

D24 PXW0

2 With reference to the Appropriate Assessment process

Page 9: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

8

The application fee must be paid at time of submission of the application. Payment will only be accepted

by Electronic Funds Transfer (EFT). The CRU bank details are:

IBAN: IE91AIBK93208677400043

BIC: AIBKIE2D

The application fees involved are banded according to the proposed installed capacity of the proposed

generating station. The fees are set out below.

Installed Capacity €

1MW to < 5MW 35

5MW to <15MW 55

15MW to < 40MW 100

40MW to < 50MW 200

50MW to < 100MW 400

100MW to < 200MW 1,330

200MW to < 500MW 3,320

500MW and greater 3,980

Installed capacity refers to the normal full load MW capacity of the generation unit (or the sum of the

normal full load MW capacities of all generation units associated with the application) as stated on the

generation unit nameplate(s). For the avoidance of doubt, the installed capacity is to include the MW

consumed by generation unit auxiliary plant directly supplied from the generation unit terminals and other

site load directly supplied by the generation unit(s) prior to connection with the transmission and/or

distribution systems.

Confidentiality of information submitted

Information provided in an application form and supporting documents will be covered by Section 13

(Prohibition on unauthorised disclosure of information) of the Act. However, CRU and the information we

hold is covered by the Freedom of Information Act, 1997 and legislation on the European Communities

(Access to Information on the Environment) Regulations 2007 to 2014 (AIE Regulations).

Details of the information we will publish can be seen on the CRU website.

Page 10: Guidance Notes for Generation Licence applicants

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

9

Further information on the Irish electricity market

There are a number of websites that can provide applicants with information about developments in the

Irish electricity market including:

CRU: Regulatory Information: www.cru.ie

SEMO: Market Information: www.sem-o.com

EirGrid: Connection Matters www.eirgrid.com

Gas Networks Ireland: Connection Matters https://www.gasnetworks.ie

SEAI: Sustainable Energy: www.seai.ie

DCCAE: REFIT – Renewable Subsidies: www.dccae.ie

Page 11: Guidance Notes for Generation Licence applicants

APPENDIX 1: APPLICATION CHECK LISTS

10

GENERATION LICENCE <40MW

CRU COMPLETENESS CHECKLIST

Date Received:

Date of Completeness Check:

1. Application Form

Signed and complete application form

2. Application Fee

Proof of payment of application fee. The application fee must be paid at the time of

submission of the application by EFT.

3. Financial Information

Evidence of finance. Where internally funded, proof of available funds from balance

sheets is acceptable. For third party finance, a letter of commitment from a financial

institution is acceptable, or where shareholders are providing finance the supporting

contract documents.

Copy of signed and dated letter of offer for REFIT for the proposed generating station.

4. Location of Generating Station

Map(s) or marine chart(s) sufficient to identify the location of the proposed generating

station.

5. Planning Permission

Final grant of planning permission or confirmation of planning exemption from the planning

authority.

6. Connection Agreement

Proof of connection agreement or proof of application for a connection agreement from

the transmission system operator or distribution system operator for the proposed

generating station. This must include a reference number and MEC.

7. Technical Information

C.V. or equivalent showing the qualifications and experience of the person or company

who will operate the proposed generating station.

8. Environmental Information

Page 12: Guidance Notes for Generation Licence applicants

APPENDIX 1: APPLICATION CHECK LISTS

11

All Appropriate Assessment (AA) related documentation provided in support of the

application. This includes:

Up-to-date information in support of AA Screening and/or AA for all elements

of the application to CRU that provides a robust scientific assessment of the

potential impacts of the proposed project, both alone and in-combination with

other plans, projects and land use changes. This might include an AA

Screening Report and Natura Impact Statement (NIS) and all associated

figures and appendices.

Where applicable, all information relevant to the AA process supplied to the

planning authority in response to any requests for further

information/clarifications at the planning and/or planning appeal stage

(including any addendums to AA Screening and NIS).

All of the above should be provided as a single pdf, inclusive of all figures and

appendices and should be clearly labelled.

Where the AA documentation has cross referenced to information outlined in

an Environmental Impact Assessment Report (EIAR)/Environmental Impact

Statement (EIS) or Environmental Report (ER) prepared for the proposed

project, a copy of this information must be provided, including all associated

figures and appendices. This usually includes but is not limited to the Flora &

Fauna (Biodiversity), Water/Hydrology and Soils chapters of EIARs/EISs/ERs.

All of the above should be provided as a single pdf, inclusive of all figures and

appendices and should be clearly labelled.

The submission of additional information may be requested by CRU at any stage of the assessment

process.

Page 13: Guidance Notes for Generation Licence applicants

APPENDIX 1: APPLICATION CHECK LISTS

12

GENERATION LICENCE >40MW DOCUMENT

CRU CHECKLIST COMPLETENESS CHECK

Date Received:

Date of Completeness Check:

1. Application Form

Signed and complete application form.

2. Application Fee

Proof of payment of application fee. The application fee must be paid at the time of

submission the application by EFT.

3. Financial Information

Statements of the accounts for the last two years kept by the applicant in respect of

relevant undertakings carried on by the applicant, showing the financial state of affairs

of that undertaking and its profit or loss, together with copies of the latest audited

accounts

If more than three months have elapsed since the end of the accounting year covered

by the accounts submitted, a certificate from the applicant stating no material adverse

change has occurred.

Where the applicant is a special purpose vehicle, a statement or relevant parent

company accounts and guarantees.

Copy of signed and dated offer of REFIT for the proposed generating station.

An outline statement of the proposals for the business of the applicant to which the

application relate, for the next five years, including;

Annual forecasts of costs, sales and revenues and project financing, stating

the assumptions underlying the figures provided.

Details of any expected subsequent substantial capital outflows, including

major decommissioning costs

Estimates of net annual cash flows for subsequent periods sufficient to

demonstrate the financial security and feasibility of the project(s) to which the

application relates

Information on the intended source of finance and (were relevant) confirmation

from the relevant lender(s).

Page 14: Guidance Notes for Generation Licence applicants

APPENDIX 1: APPLICATION CHECK LISTS

13

4. Location of generating station(s)

Map(s) or marine chart(s) sufficient to identify the location of all generating stations to

which the application relates.

5. Planning Permission

Final grant of planning permission or confirmation of planning exemption from planning

authority.

6. Connection agreement offer

Proof of connection agreement or application for a connection agreement from the

transmission system operator or distribution system operator for the proposed

generating station. This must include a reference number and MEC.

7. Environmental Information

All Appropriate Assessment (AA) related documentation provided in support of the

application. This includes:

Up-to-date information in support of AA Screening and/or AA for all elements

of the application to CRU that provides a robust scientific assessment of the

potential impacts of the proposed project, both alone and in-combination with

other plans, projects and land use changes. This might include an AA

Screening Report and Natura Impact Statement (NIS) and all associated

figures and appendices.

Where applicable, all information relevant to the AA process supplied to the

planning authority in response to any requests for further

information/clarifications at the planning and/or planning appeal stage

(including any addendums to AA Screening and NIS).

All of the above should be provided as a single pdf, inclusive of all figures and

appendices and should be clearly labelled.

Where the AA documentation has cross referenced to information outlined in

an Environmental Impact Assessment Report (EIAR)/Environmental Impact

Statement (EIS) or Environmental Report (ER) prepared for the proposed

project, a copy of this information must be provided, including all associated

figures and appendices. This usually includes but is not limited to the Flora &

Fauna (Biodiversity), Water/Hydrology and Soils chapters of EIARs/EISs/ERs.

All of the above should be provided as a single pdf, inclusive of all figures and

appendices and should be clearly labelled.

Page 15: Guidance Notes for Generation Licence applicants

APPENDIX 1: APPLICATION CHECK LISTS

14

8. Technical Information

C.V. or company profile showing the qualifications and experience of the person or

company who will operate the proposed generating station

9. Construction Timeline

Construction and commissioning programme, identifying the major milestones in the

project development, from authorisation to completion.

The submission of additional documents may be requested by CRU at any stage of the assessment

process.

Note

All applicants are advised that in order to trade in the market, in addition to holding the necessary

Licences from the CRU, accession to the Trading and Settlement Code is required. Applications for

market accession are to be made to the Single Electricity Market Operator (SEM-O) once the relevant

Licences from the CRU have issued. To facilitate timely accession to the market, applications should

be made as early as possible. Please contact the SEM-O Market Registration team at

[email protected] or by telephone at 1800 778111 for information on this process.

Page 16: Guidance Notes for Generation Licence applicants

APPENDIX 2: ASSESSMENT PROGRESS REPORTS

15

GENERATION LICENCE ASSESSMENT PROGRESS REPORT

CRU APPLICATION REFERENCE:

GENERATING STATION NAME:

DATE RECEIVED:

ASSESSMENT AREA PROGRESS REPORTS

Assessment Area Progress Report Additional Information request

Administrative e.g. in process

e.g.

Technical e.g. complete

Environmental e.g. in process e.g. please provide an updated cumulative

impact assessment that assesses the

impact of the proposed project other land

use types and plans/projects.

Financial e.g. in process

Response to all Additional Information requests must be made electronically to

[email protected]. Please note that a delay in responding to Additional Information requests

may result in a delay to the overall assessment timeline.

Applicants must insert the CRU application reference number into the subject line on all

email correspondence.

Page 17: Guidance Notes for Generation Licence applicants

16


Recommended