Net Metering Guidelines
for LebanonIng. José Daniel Lara
Net Metering: a working definition
A system in which renewable energy generators (mostly solar panels) are connected to a public-utility power grid and surplus power is transferred onto the grid, allowing customers to offset the cost of power drawn from the utility.
The objective of electricity generation has no commercial purposes.
In the case of Lebanon the user may have interests in order to enhance local reliability.
A classical residential net metering
installation
1. Solar Panels
2. Inverter/Converter
3. Main Panel
4. Load
5. 2-way meter
6. Grid
Why do technical standards matter?
Guarantee safety for the users and
installations where the power
generation units are installed.
Protect the network (shared asset)
from undesired voltage or current
injections.
Protect the distribution system and
other users from undesired
operations. For example, islanding
or reconnect after electric fault.
Impacts of PV systems to the grid - 1
Inadequate inverters can cause power quality issues such as:
Harmonic distortion
Flicker
DC injection
Electromagnetic interference
Reverse Power (when installed in parallel with diesel generators)
Most of this issues are covered by manufacturing standards. The majority of suppliers comply with minimum power quality standards.
Two main standards groups depending on
the standardization organizations.
American UL: Safety standards from the
equipment perspective
UL 1741 Covers Power Conversion and Protection Equipment
IEEE: Interconnection standards, grid compatibility and many others
IEEE 1547 Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems
NFPA: Safety standards from the installation perspective (mostly to avoid fires)
European (IEC)
IEC 61727:2004 Photovoltaic (PV) systems – Characteristics of the utility interface
IEC 62116:2008 Test procedure of islanding prevention measures for utility-interconnected photovoltaic inverters
IEC 60364-7-712: Electrical Installations of Buildings: Requirements for Special Installations or Locations – Solar Photovoltaic power supply systems
IEC 61683 (Power conditioners – Procedure for measuring efficiency
Some European countries have local version of ICE norms like GER and UK.
Impacts of PV systems to the grid - 2
Normally the timing between load
and solar power generation is not
coordinated.
This reality causes the distributed
units to inject power into the grid
during some hours of the day.
Even though the net daily energy
demand can be positive.
In order to manage this is
important for the utility to gather
data from the installation.
Components of a Distributed Generation
Installation
The Utility should gather information about all the devices in
the schematic and guarantee access to the Utility Disconnect
when performing maintenance on the grid.
Components of a Distributed Generation
Installation with storage
This installation
scheme is similar
to the previous
one.
The only
addition is the
battery system
installed right
before the
inverter.
Standards on utility disconnect to avoid
islanding.
This is a very important standard to take into account considering the
conditions in Lebanon.
On one hand, the system needs to disconnect when the grid shuts down and
avoid islanding. However, the system also needs to be resilient to voltage and
frequency variations typical in Lebanon's distribution grid.
Example of the American IEEE 1547 (60 Hz based):
Example of application to Lebanese system:
under voltage limit (level 1): 200 V
under voltage limit (level 2): 115 V
over voltage limit (level 1): 240 V
overvoltage limit (level 2): 310 V
lower frequency limit: 49 Hz
upper frequency limit: 51 Hz
loss of main detection limit: 300 ms
Any inverter compliant with IEC 62116 should be able to be configured with
these parameters.
Standards on utility disconnect to avoid
islanding.
Minimum required information for a Net
Metering project.
Energy source information
Main energy source: [Wind, Solar, Biomass]
Expected daily and annual energy output [kWh]
List of assets [Inverters, Batteries, Diesel Gen Sets]
Load information
Expected peak load (peak load when DG is not online) [kW]
Expected net peak load (peak load most of the time) [kW]
Expected daily and annual energy consumption [kWh]
Feasibility study performed (if available)
Using this information the decision process can be expedited. If the expected
daily energy produced is below 20% of the total daily energy consumed the
grid impacts will be minimal.
Minimum required information for a Net
Metering project.
If the total daily energy produced exceeds 50% of the total daily energy
demanded, it is likely that the system will require a deep interconnection
study that should include:
Power Flow analysis
Max and Min expected voltages
Short Circuit current analysis
Protection coordination with the utility.
Extremely important! GPS coordinates of the plant location [Lat, Long]
Required inverter information
Obtain pictures of the nameplate and datasheets to
corroborate that the inverter complies with
international standards.
All the certificates for the standards can be
obtained from the manufacturer. (See example)
IMPORTANT: If the inverter was custom
configured with regards to anti-islanding those
parameters need to be recorded.
Plant drawings as built displaying
protections and circuit breakers.
Example, Tahrir square.
General guidelines:
Make sure that the utility has access to the main circuit breaker to disconnect the
power plant if necessary.
The installation must contain ground fault protection in the schemes.
The opportunities of Net Metering with
PV panels.
Old System
GG G G
Tensión de generación
Tensión de Transmisión
Tensión de distribución
Carga GD GD GD
GG G G
Tensión de generación
Tensión de Transmisión
Tensión de distribución
Carga
New System