Gujarat Solar Park World’s first Multi developer, Multi facility, Multi
Technology and Multi beneficiary solar park At Charanka Village, Dist Patan - Gujarat
First of its kind in the world
Fastest Implementation
Multi Developer, Multi Facility, Multi Technology and Multi
Beneficiary Solar Park
Integrated hub of Solar power generation
Unique Integration of Environment benefit , Infrastructure
development and Social upgradation
Benchmark project for other states.
Hybridization of Wind and Solar
Upgradation in the standard of living in the rural area
GUJARAT SOLAR PARK: Redefining the concept
Project Location Charanka Village, Santalpur Taluka,
Patan District, Gujarat
The
Site
Radhanpur
Santalpur
Kutch Branch Canal
Little Runn of
Kutch
Charanka
Village
Nearest Urban
Area: Palanpur
Nearest NH: NH
15 @ 20 km
Nearest Rly
Station: Santalpur
• Total Identified Land by
GPCL: ~ 2,500 Ha
• Land Selected for the
Proposed Park: ~ 2000 Ha
• Ownership: ~ 60% Govt.
Land (mostly wasteland)
Details of infrastructure facilities provided in solar park
4
Roads
Raw Water Pipeline
Rehabilitation of existing nala
Rehabilitation of existing reservoir
Water Treatment Plant
Water Distribution Network
Water Tank (GLSR/OHT)
Sewage Treatment Plant
400/220/66 KV & 66 KV Auxiliary SS
Auxiliary Power Distribution Network
Telecom Network
Fencing (Boundary)
Compound wall
Entrance
Security Towers
Training Institute
Common facilities
Helipad
Green belt / buffer
Water to meet the irrigation demand
Landscaping
Surya Teertha
Internal (plot)fencing
Land levelling / Grading
Fire Station
Master Plan
5
Patrolling road
Internal roads
Nala
Reservoir
Water Pipe Line
Power generation capacity : 500MW
Present Installed Capacity: 214 MW
No. of Developers : 21
Well defined Plot Allotment Policy
and timely allocation of plots to
developers
Benefits over “Conventionally defined
Solar Park”
Tangible Benefits:
Basic infrastructure development benefits
shared with local villages
Communication network
Provision of Irrigation water
Developer investment of Rs. 3600 Cr
(Till date)
Employment generation of about 1500
labours
Economic upliftment of rural area
Intangible Benefits:
Increase in Water conservation
Increase in Vegetation cover
Reduction in desertification process
Carbon Emission reduction
Increase in aesthetic value of area
Social upliftment
Fastest Commissioning
Foundation Laying Ceremony – 30 Dec, 2010
Dedication Ceremony to the nation – 19 Apr, 2012
214 MW Solar Project s Commissioned
Gujarat Solar Park at a glance
Aerial View of Solar Project
Development
Aerial View of Observatory Deck
constructed within Gujarat Solar
Park for 360 Degree View of
overall Solar Park
Ocean of Solar PV Panels spread across the Solar Park
Panoramic View of Gujarat Solar Park
12