Date post: | 07-Apr-2018 |
Category: |
Documents |
Upload: | kiran-duda |
View: | 226 times |
Download: | 0 times |
of 34
8/4/2019 Gurman Presentation
1/34
SIX MONTHS INDUSTRIAL TRAINING
AT
BHARTI REALTY COMMERCIAL COMPLEX
BY: GURMANPREET SINGH7140100014
8/4/2019 Gurman Presentation
2/34
VASCON ENGINEERS LIMITED has more then 25 years of experience inconceiving, developing, constructing and managing various projects. It is active
in multiple sectors including residential, industrial, IT parks, malls and
multiplexes, hospitality and community.
Right from its inception in 1986, vascon has remained committed to applying
the art or value based aesthetics into the science of construction through
efficient engineering. The vascon team is mainly made up of engineers who
are backed up by highly qualified specialists from various fields of
management.
8/4/2019 Gurman Presentation
3/34
NAME OF THE PROJECT: Bharti Realty Commercial Complex NAME OF THE CONTRACTOR: Vascon Engineers Limited CLIENT: Bharti Realty Limited SITE ADDRESS: Bharti Realty Commercial Complex, Opposite PU Extension
Library, Mall Road, Ludhiana.
ARCHITECHTURAL CONSULTANTS: Rajinder Kumar & Associates STRUCTURAL CONSULTANTS: Vintech Consultants
Estimated cost of project: ` 105 Crores
Cost of building work under vascon: ` 30 Crores
Total Area: 10009.598 sqm
The Project consists of 3 basements for parking, 11 floors in the
superstructure which will consist of Stores, Cinemas & Food Courts.
8/4/2019 Gurman Presentation
4/34
Site Clearance
Excavation Boring
Piling
Surveying
PCC
Marking Reinforcement
Concreting of Foundation
Assembling of Scaffolding
Column Casting
Slab & Beam Casting Disassembling of Scaffolding
Curing
8/4/2019 Gurman Presentation
5/34
EXCAVATION FOR PILING:- The depth of excavation was approx. 5mThe margin of 1m was provided from the boundary line for providing
the working space.
EXCAVATION FOR PCC & FOUNDATION :- Excavation for PCC &Foundation was done mechanically with the help of machines namely
JCB Digger, L&T Komatsu and Kobelco.The RL of the road in front of the
site is 99m. Excavation done was 18.045 m (Down) w.r.t to RL of road.
So, RL of bottom most point is 80.955m.
8/4/2019 Gurman Presentation
6/34
8/4/2019 Gurman Presentation
7/34
Piles are used in this building because of sandy soil. As sandy soil will not
sustain loads and is liable to landslide, therefore piles are used. Also
Building is at the edge of the main road so vibrations are created due to
moving loads (vehicles), this also forced the use of piles in this building.
The Reduced level of road in front of site is 99m. So, with respect to it a
permanent benchmark of 100m was marked on a particular location at
the site with help of auto level. As this permanent benchmark wasnt
visible from all the points on the site, therefore some temporary
benchmarks were also marked on the site and checked regularly. Reduced
level of top of casing of pile was found with respect to these permanent
and temporary benchmarks.
8/4/2019 Gurman Presentation
8/34
Layout of piles was done with the help of Posts (also called burjis) onReference line and theodolite.
Firstly, theodolite was set on one of the Post and then the horizontal anglewas measured equal to 0 along the reference line.
Taking angle equal to 0 along the reference line and then rotating theodoliteby 90, a point was dropped on the ground at a distance of 6.1m fromreference line and adjusted in such a way that this point should coincide withthe cross hair in theodolite.
Similarly another point is also taken at same distance from reference line onthe ground and these two points are tied with the help of thread, also calledline dori.
The two points are marked on the ground and tied with help of a thread.
Along the thread we get inner face of the pile, as diameter of pile is 600mm,therefore another two points at a distance 300 mm are marked from previous
two points and tied with a line dori so that line dori now is along the centreline of the pile.
Then the marking of piles can easily be done with help of a measuring tapesuch that successive points along the thread are at a distance 750 mm c/caway from each other.
8/4/2019 Gurman Presentation
9/34
First of all chisel condition is examined.
Then a mark is made on the ground( with help of chisel) on which pile is to
be bored.
Then casing is placed on it.
Casing is then embedded into the ground by applying load over itsboundaries with the help of chisel.
Then after the bore of required depth is made then steel cages are put
into the bore and the steel cages are connected with each other by
providing lap.
Last step is to pour concrete with the help of pipes.
8/4/2019 Gurman Presentation
10/34
Total no of piles: 477
Concrete used in the piles: M30
Centre to Centre distance between two piles: 750mm
Diameter of an individual pile: 600mm
RL of concrete top: 95.055 m
8/4/2019 Gurman Presentation
11/34
REINFORCEMENT DETAIL-: The steel cage is divided into three parts Top Cage
Middle Cage
Bottom Cage
TOP CAGE
No of bars: 16
Diameter of bar: 16mm
No of Rings: 35@8mmMIDDLE CAGE
No of bars: 16
Diameter of bar: 25
No of Rings: 35@8mm
BOTTOM CAGE
No of Bars: 16 Diameter of bar: 25
No of Rings: 46@8mm
Lap length between two cages: 1m
8/4/2019 Gurman Presentation
12/34
VIEWS OF PILING WORK
8/4/2019 Gurman Presentation
13/34
Concrete used in the pilling work is of M30 grade. Concrete is brought
directly on the site in a mixer from ACC Ready Mix plant situated inSahnewal. Concrete mix is poured into the piles with the help of a cone
and pipe as shown in the figure.
8/4/2019 Gurman Presentation
14/34
First of all, excavation work was done at the required area.
Then, PCC bed was prepared by ramming the soil with the help of hand
rammers.
The RL of bottom most point was 80.955m. PCC of thickness 75 mm was
laid, therefore RL of top of PCC = 81.030m (80.955+0.075).
Grade of concrete used for PCC is M7.5 having ratio 1:4:8
8/4/2019 Gurman Presentation
15/34
Firstly, the posts (burjis) on X Grid (X1, X2, X3...) & Y Grid (Y1, Y2, Y3...)
were dropped and marked on the ground with the help of theodolite.
Now the column whose marking is to be provided is seen in the drawing
from which we get to know about the centre point of column.
For each column, two lines will be there, one each from a post (burji) on X
Grid & Y Grid, the intersection point of these lines is actually the centre
point of column.
Then by using the dimension given in the drawing, marking of the column
is done accordingly may it be circular or square.
8/4/2019 Gurman Presentation
16/34
MARKING OF SQUARE COLUMN
MARKING OF CIRCULAR COLUMN
8/4/2019 Gurman Presentation
17/34
Foundations are structural elements that transfer loads from to earth.
ISOLATED FOOTINGIsolated footings are provided under each column and may be square,
rectangular, or circular in plan. Footing may be flat or sloped. At our site
isolated square footings provided are sloped ones.
REINFORCEMENT DETAIL
Size of Isolated Footing: 6m 6m
Concrete Used: M20
Steel Used: Fe415
Diameter of bars: 20mm
Spacing: 200mm c/c
ISOLATED FOOTING
8/4/2019 Gurman Presentation
18/34
COMBINED FOOTING
Combined footings are provided to support two or more column loads. Thesemay be continuous with rectangular or trapezoidal in plan. Combined footings
become necessary under the following circumstances:
A) When the isolated footings overlap.
B) When the exterior column is close to the property line such that symmetricalisolated footing cannot be provided.
In combined footings, a slab was provided at the bottom, through which a strap
beam passes, columns were then erected from within the strap beam. The basic
purpose of providing strap beam is to distribute the pressure uniformly on
footing.
8/4/2019 Gurman Presentation
19/34
Sizes of Combined Footing: 14m 5.5m
Beam Depth: 1725mm
Slab Depth: 900mm
Diameter of bars: 32mm, 25mm, 20mm (Main)
16mm (Distribution)
8/4/2019 Gurman Presentation
20/34
RAFT FOUNDATION
Raft foundation is provided when the soil is having very low bearing capacity
and or when columns loads are heavy, the required footing area becomes very
large and uneconomical.
RAFT FOUNDATION (PLAN)
In raft foundation, for each column individual pedestals were provided, columns
were then erected from within the pedestals.
8/4/2019 Gurman Presentation
21/34
Size of Raft Foundation: 24m 12m
Slab Depth: 1200mm
Diameter of bars: 20mm, 16mm, 32mm(extra steel b/w columns)
8/4/2019 Gurman Presentation
22/34
Shuttering should be cleaned of all dust and debris before laying of
concrete
In order to prevent the shuttering from absorbing water from concrete, acoat of crude oil or grease etc. is usually applied to the shuttering before
concreting.
While placing concrete, care should be taken that it should not be thrown
from height.
Concrete should be properly compacted before laying next one.
8/4/2019 Gurman Presentation
23/34
The term compaction of concrete means the compaction between
aggregate and aggregate, between aggregate and reinforcement, and
between aggregate and forms.
The main aim of compaction of concrete is done to eliminate air bubbles
and thus to give max density to the concrete. An intimate contact
between concrete and reinforcement is ensured by proper compaction.
Mechanical compaction was done at site as shown below.
8/4/2019 Gurman Presentation
24/34
Concrete achieves its strength through a hydraulic process known ashydration. With the addition of the correct amount of water, cement gels
into a paste that glues sand and aggregates together to form hardened
concrete. It has been established that the strength of concrete increases
with the age provided it is kept damp. During the process of curing the
concrete absorbs the water necessary for its complete chemical action to
reach its required strength. The strength of concrete increases more
rapidly in the first few days after setting and afterwards the rate of
increase in strength go on retarding. The period for which curing should
be continued depends upon the atmosphere conditions. Correct curing
also increases resistance of concrete to abrasion and reduces shrinkage.
8/4/2019 Gurman Presentation
25/34
POUNDING WITH WATER
It was done on horizontal surfaces. It is carried out by supplying water tothe surface of concrete in a way that ensures that it is kept continuously
moist.
CURING WITH JUTE BAGS
It is done on vertical surfaces. Fabrics are particularly useful in case ofvertical surfaces since they help distribute water evenly over the surface.
8/4/2019 Gurman Presentation
26/34
Firstly beam bottom and beam top(same as that of slab top) are markedon the column.
Assemblage of Scaffolding and Shuttering is then done accordingly.
The oil is applied to the shuttering plates so as to obtain the smooth
surface.
After this, the slab and beam are checked for steel as per drawing. Now the steel is lifted from bottom to maintain a cover with the help of a
cover block.
Concreting of slab and beam is done with mix 1:1.5:3 by pipes.
Compaction of concrete is done by vibrator.
8/4/2019 Gurman Presentation
27/34
8/4/2019 Gurman Presentation
28/34
Type: Two way slab.
Slab thickness: 150mm
Steel used: Fe 415
Concrete used: M20(1: 1.5 :3)
Diameter of bars used as main steel: 12mm @ 250mm c/c Diameter of bars used as distribution steel: 10mm @ 250 c/c
Effective cover provided: 25mm
8/4/2019 Gurman Presentation
29/34
SCAFFOLDING refers to a temporary platform built around the face of a
structure, allowing workers to perform construction or maintenancetasks that cannot be reached from the ground. In scaffolding work we
use lasers, cup locks, base plate, u head, vahler etc.
8/4/2019 Gurman Presentation
30/34
It is necessary to provide some temporary structure to confine and supportthe fresh concrete till it gains strength for self supporting. The temporarystructure provided for this purpose is known as FORMWORK OR
SHUTTERING.
8/4/2019 Gurman Presentation
31/34
8/4/2019 Gurman Presentation
32/34
8/4/2019 Gurman Presentation
33/34
8/4/2019 Gurman Presentation
34/34