+ All Categories
Home > Documents > gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper;...

gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper;...

Date post: 29-Aug-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
26
MINISTRY OF EDUCATION AND TRAINING VIETNAM ACADEMY OF SCIENCE AND TECHNOLOGY GRADUATE UNIVERSITY OF SCIENCE AND TECHNOLOGY ----------------------------- Duong Van Nam STUDY ON TREATMENT OF NATURAL RUBBER PROCESSING WASTEWATER USING INTEGRATED PHYSICOCHEMICAL AND BIOLOGICAL PROCESSES Major: Environmental Engineering Code: 9 52 03 20 SUMMARY OF ENVIRONMENTAL ENGINEERING DOCTORAL THESIS HA NOI, 2019
Transcript
Page 1: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

MINISTRY OF EDUCATION

AND TRAINING

VIETNAM ACADEMY OF

SCIENCE AND TECHNOLOGY

GRADUATE UNIVERSITY OF SCIENCE AND TECHNOLOGY

-----------------------------

Duong Van Nam

STUDY ON TREATMENT OF NATURAL RUBBER

PROCESSING WASTEWATER USING INTEGRATED

PHYSICOCHEMICAL AND BIOLOGICAL PROCESSES

Major: Environmental Engineering

Code: 9 52 03 20

SUMMARY OF ENVIRONMENTAL ENGINEERING

DOCTORAL THESIS

HA NOI, 2019

Page 2: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

The thesis was performed at Graduate University of Science and

Technology, Vietnam Academy Science and Technology

Supervisor 1: Dr. Phan Do Hung

Supervisor 2: Assoc. Prof. Dr. Nguyen Hoai Chau

Reviewer 1: Assoc. Prof. Dr. Vu Duc Toan

Reviewer 2: Assoc. Prof. Dr. Cao The Ha

Reviewer 3: Assoc. Prof. Dr. Tran Thi Viet Nga

The thesis will be defended at the doctoral thesis committee at the

Academy level, meeting at the Graduate University of Science

and Technology - Vietnam Academy of Science and Technology

at ………… on………, 20…….

The thesis can be found in:

- The library of Graduate University of Science and Technology

- National Library of Vietnam

Page 3: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

1

INTRODUCTION

1. Rationale of the thesis

Vietnam is one of the three leading countries in exploiting

and exporting natural rubber in the world. Annually, the natural

rubber processing (NRP) industry of Vietnam generates over 25

million cubic meters of wastewater. This is among the

wastewaters having a very high level of pollutants of organic

matter, nitrogen, phosphorus and total suspended solids (TSS).

Currently, wastewater treatment technologies being applied

in the natural rubber processing industry in Vietnam are mainly

the incorporation of a number of the following processes: rubber

latex decanting, flotation, UASB (Upflow Anaerobic Sludge

Blanket), oxidation ditches, aeration tanks, aerobic biological

filtration, algae ponds, and stationary ponds. These treatment

systems still exhibit many limitations such as inadequate

treatment efficiency, especially for organic matter, nitrogen and

phosphorous; large print foot and high energy requirement.

Although the NRP industry is one of five typical industries

(textile; NRP; pulp and paper; brewery; and leachate) generating

wastewater with high pollutant load, in Vietnam research on

treatment of NRP wastewater is still limited. So far, study on

appropriate technological processes for treating NRP wastewater

in Vietnam with approach to recover nutrients and energy using

integrated physicochemical and biological processes has not

been conducted.

Page 4: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

2

From the above reasons, this thesis was conducted to study

and propose an appropriate technological process for treating the

NRP wastewater with the aim to simultaneously solve the

following problems: (1) Energy recovery (biogas containing CH4

as fuel); (2) Simultaneous recovery of nitrogen and phosphorus as

fertilizer for agriculture; (3) Modifycation of reactors and

integration of physicochemical and biological processes to

improve the system performance in the simultaneous removal of

organic and nutrients substances in NRP wastewater.

2. Objectives of the thesis

The objective of this study is to develop an energy and

nutrients recovering wastewater treatment process combining

physicochemical and biological methods for NRP wastewater.

3. Main research contents of the thesis

1) Overview of current technologies for treatment of NRP

wastewater;

2) Study on removal of organic substances and energy

recover from NRP wastewater by Expanded Granular Sludge

Bed (EGSB) reactor;

3) Study on simultaneous recovery of nitrogen and

phosphorus from NRP wastewater by Magnesium Ammonium

Phosphate (MAP) precipitation method;

4) Study on simultaneous removal of organic and nitrogen

substances from anaerobically treated NRP wastewater in

modified Sequencing Batch Reactors (SBRs);

5) Proposal of an energy and nutrients recovering wastewater

treatment process for NRP wastewater.

Page 5: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

3

CHAPTER 1. LITERATURE REVIEW

This chapter presented the following contents: Overview of the

natural rubber processing industry; Characteristics of NRP

wastewater; The situation of study and treatment of NRP

wastewater in domestic and oversea; Wastewater treatment methods

related to the thesis; Existing problems in NRP wastewater

treatment in Vietnam; and Study orientation of the thesis.

The review showed that the study and treatment of NRP

wastewater have attracted great attention in past decades in the

world and Vietnam as well, and achieved relatively good results.

However, previous studies have mainly focused on the treatment of

organic matter in wastewater without paying attention to the

treatment of nitrogen substances, as well as the recovery of energy

and nutrients.

CHAPTER 2. REMOVAL OF ORGANIC MATTER AND

RECOVERY OF ENERGY BY EGSB REACTOR

2.1. Materials and research methodology

1) Materials, chemicals, and equipment

Wastewater: Simulated wastewater (wastewater prepared from

coagulation process of natural rubber latex in the laboratory) was

used for the start-up period of EGSB reactor. Real NRP

wastewater was used for further studies.

Seed sludge: Anaerobic sludge from an UASB of Sai Gon - Me

Linh Brewery was used as seed sludge.

Page 6: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

4

Experimental equipment: An EGSB reactor with a reaction

volume of 13.5 L and a height of 155 cm, divided into reaction

zone (I) and settling zone (II) as shown in Figure 2.3.

1. Control box

2. Wastewater tank

3. Wastewater supply pump

4. Scum breaking pump

5. Circulating pump

6. EGSB reactor

7. Treated wastewater tank

8. Gas measuring device

I. Reaction zone

II. Setting zone

Figure 2.3. Experimental EGSB system

2) Research methodology

Experimental procedure

Wastewater from the wastewater tank (2) was pumped into

the bottom of the EGSB reactor (6), flowed up through the sludge

bed in the reaction zone (I), entered the settling zone (II), then

flowed into the treated water tank (7). Volume of generated

biogas from the reactor was measured by the gas meter (8).

Experimental conditions

The EGSB reactor was started up with simulated wastewater

(27 days) and real NRP wastewater (60 days) by a gradual

increase in organic loading rate (OLR). After the steady state

reached, effects of OLR in the range of 7 – 20 kg CODm-3d-1 on

COD removal, biogas generation and the system stability were

investigated using the real NRP wastewater.

1

2 7 8

6

I …

….… ….. ..

… ….. ..

… ….. .. … ….. .. … ….. .. … ….. ..

… ….. ..

… ….. ..

… … ….. ..

II

3

4

5

Page 7: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

5

2.2. Results and discussion

1) Development of anaerobic granular sludge

On day 27 On day 87

Figure 2.5. Anaerobic granules of EGSB reactor during start-up

period

The EGSB reactor start-up was performed for 87 days to

form anaerobic granules. After 27 days of starting, anaerobic

granules appeared, and particles with size of 0.5 - 1.0 mm

accounted for 38.5% of activated sludge in the EGSB reactor.

After 87 days, the amount and size of anaerobic granules in

EGSB reactor has increased significantly: at the lower part of the

sludge layer, the particles with dimensions of 0.5 - 1.0 mm and

1.0 - 2.0 mm accounted for 45.5% and 35.4%, respectively; in

the upper part of the sludge layer, these percentages were 62.6%

and 18%, respectively. The image of anaerobic granules on days

27 and 87 was shown in Figure 2.5.

2) COD removal

COD removal efficiency of the EGSB reactor after start-up

period was shown in Figure 2.8. The results showed that COD

treatment efficiency was quite stable in the experimental modes

and tended to decrease in the first days after an increase of OLR,

but quickly stabilized in each experimental mode (about 5 days).

In particular, when changing from mode (II) to mode (III) with a

Page 8: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

6

large increase in OLR (from 11.3 to 17.7 kg CODm-3d-1), COD

removal efficiency dropped sharply, then gradually ascended but

fairly slowly. Sludge concentration in the EGSB reactor at this

period was still not high, therefore the effect of OLR was very

clear. COD removal efficiency in the modes (I), (II), (IV) and (V)

are all over 80%, and that at OLR 19 kg CODm-3d-1, was 82.5%.

Although this efficiency was lower than those at OLRs of 7.7 and

10.8 kg CODm-3d-1, it was also a relatively high.

Figure 2.8. COD removal efficiency of EGSB reactor during

steady operation period OLR (kg CODm-3d-1): (I) = 7.7; (II) = 11.3; (III) = 17.7; (IV) = 19.0; (V) = 10.8

3) Biogas generation yield

Figure 2.13 showed that generated biogas amount increased

when OLR increased. The average generated biogas amount at

different OLR modes from (I) to (V) at standard conditions was

33.6, 44.5, 63.9, 76.6, and 44.2 L/day, respectively.

The results in Figure 2.15 showed that generated biogas

amount at standard conditions was directly proportional to the

amount of removed COD. The average biogas conversion yield

0

20

40

60

80

100

0

2000

4000

6000

8000

10000

85 95 105 115 125 135 145 155

CO

D r

em

ova

l eff

icie

ncy, %

CO

D, m

g/L

Operation time, day

COD in influent COD in effluent Efficiency

I II III IV V

Page 9: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

7

at the standard conditions for all study modes was 0.37 L/kg

removed COD.

Figure 2.13. Generated biogas amount in the steady period OLR (kg CODm-3d-1): (I) = 7.7; (II) = 11.3; (III) = 17.7; (IV) = 19.0; (V) = 10.8

Figure 2.15. The relationship between the generated biogas

amount and the amount of removed COD

y = 0.371x

R² = 0.9174

0

20

40

60

80

100

50 100 150 200 250

Gen

era

ted

bio

ga

s a

mo

un

t a

t

sta

nd

ard

co

nd

itio

n, L

/da

y

Amount of removed COD, g COD/day

20

40

60

80

100

5

10

15

20

25

80 90 100 110 120 130 140 150 160

Gen

era

ted

bio

ga

s a

mo

un

t a

t

sta

nd

ard

co

nd

itio

n, L

/da

y

OL

R, k

g C

ODm

-3d

ay

-1

Operation time, day

OLR Amount of biogas

I II III IV IV

Page 10: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

8

CHAPTER 3. RECOVERY OF NUTRIENTS BY MAP

PRECIPITATION

3.1. Materials and research methodology

1) Materials, chemicals and equipment

Wastewater: Wastewater used in this study was the effluent of

the EGSB reactor.

Chemicals: MgCl26H2O and H3PO4 were used as additional

magnesium and phosphate sources.

Equipment: A Jar-Test was used for MAP precipitation.

2) Research methodology

Experiments: MAP precipitation were performed at different pH

values and Mg2+ : NH4+ : PO4

3- molar ratios. After reaction, the

reaction solution was let to settle and filtrated to obtain the

precipitate. P-PO43-, N-NH4

+ and Mg2+ in the filtrate was analyzed

to determine treatment efficiency. The precipitate was washed,

dried, and used to determine MAP amount and composition of Mg,

N, and P elements in the MAP precipitate.

Analysis: MAP crystal dimension was determined by SEM

images. MAP composition was determined through EDX

spectrum analysis.

3.2. Results and discussion

1) MAP recovery without magnesium addition

NRP wastewater contained significant amounts of

magnesium, ammonium and phosphate. Therefore, increasing

wastewater pH to the appropriate value could result in MAP

precipitation by reaction (1.3).

Mg2+ + NH4+ + HPO4

2- + 6H2O MgNH4PO46H2O↓+ H+(1.3)

Page 11: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

9

The results in Table 3.2 showed that phosphate-P removal

increased from 15.6% at pH 7.5 to 44.7% at pH 9.5 and tended

to slightly increase as pH continued to increase to 11.5. On the

other hand, ammonium-N removal increased from 3.6% at pH

7.5 to a maximum value of 13.1% at pH 9.5, and then gradually

decreased to 4.1% as the pH continued to increase to 11.5.

Table 3.2. P, N and Mg removal without magnesium addition

at different pH

pH

Concentration after MAP

precipitation (mg/L) Removal efficiency (%)

PO43-–P NH4

+–N Mg2+ PO43-–P NH4

+–N Mg2+

7.5 119 214 15.0 15.6 3.6 70.0

8.0 107 209 8.8 24.1 5.9 82.4

8.5 97 204 6.5 31.2 8.1 87.0

9.0 90 197 4.0 36.2 11.3 92.0

9.5 78 193 1.8 44.7 13.1 96.4

10.0 77 198 1.6 45.4 10.8 96.8

10.5 77 206 1.5 45.4 7.2 97.0

11.0 76 211 1.3 46.1 5.0 97.4

11.5 75 213 1.1 46.8 4.1 97.8

Because MAP is soluble in acidic environment, the suitable

environment for MAP precipitation is alkaline. However, in an

alkaline environment, Mg2+ also reacts with PO43- and OH- to

form precipitates of Mg3(PO4)2 and Mg(OH)2. Therefore, the

higher pH was, the more precipitates form, resulting in reduction

of the magnesium source for the MAP forming reaction. Thus,

when pH was over a certain value, ammonium-N removal

Page 12: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

10

efficiency would decrease. This result explained why the MAP

precipitation optimally occured at a certain pH range.

The initial molar ratio of Mg : PO43- in the wastewater was

0.46 : 1.0 (in MAP, it is 1.0 : 1.0), therefore, theoretically, the

maximum phosphate-P removal via the MAP precipitation was

46%. At pH 9.5, the removal efficiency of phosphate-P was

44.7%, rather high in comparison to theorical value.

at pH 9,5

at pH 11

Figure 3.3. SEM image of MAP crystal

at pH 9,5

at pH 11

Figure 3.4. EDX spectrum of the MAP precipitate

In this study, suitable pH for MAP recovery was about 9 -

10. At this range, MAP precipitation was clearly observed.

MAP crystals were easy to settle and could be observed with

the naked eyes, and had a large length of 300 - 383 µm. The

70,6 µm

383 µm

328µm

Page 13: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

11

removal efficiencies of phosphate-P and ammonium-N at pH

9.5 were 44.7% and 13.1%, respectively. At pH 11, beside MAP

crystals with small size, hardly settable fine flocks also

appeared (Fig. 3.3). EDX spectrum (Figure 3.4) and data of

chemical composition showed that: the mass percentages of the

P, Mg and O elements in MAP at pH 9.5 were 14.3%, 10.8%

and 54.3%, respectively. These percentages were similar to

those in pure MAP. At pH 11, beside the above main elements,

there were many other elements such as C, Na, K and Ca in the

MAP precipitate. The mass percentages of P, Mg and O

elements were 7.4%; 6.0% and 44.2%, respectively.

2) MAP recovery with magnesium addition

In this study, the molar ratio of Mg2+ : NH4+ : PO4

3- in NRP

wastewater was 0.46 : 3.5 : 1.0, while this ratio in pure MAP was

1.0 : 1.0 : 1.0. Therefore, to improve the recovery of phosphate-

P, addition of external magnesium source was required.

Table 3.5 showed that removal efficiencies of phosphate-P

and ammonium-N reached the best value of 93.3% and 28,4%,

respectively, at the Mg2+ : PO43- molar ratio of 1.2 : 1.0.

Table 3.5. Effect of Mg2+: PO43- molar ratio on P and N removal

Mg2+ :

PO43-

molar

ratio

Concentration after MAP

precipitation (mg/L) Removal efficiency (%)

PO43-–P NH4

+–N Mg2+ PO43-–P NH4

+–N Mg2+

0.6 : 1 65.3 185 3.2 53.7 16.7 95.1

0.8 : 1 34.2 173 3.3 75.7 22.1 96.3

1.0 : 1 15.6 163 2.8 88.9 26.6 97.4

Page 14: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

12

Mg2+ :

PO43-

molar

ratio

Concentration after MAP

precipitation (mg/L) Removal efficiency (%)

PO43-–P NH4

+–N Mg2+ PO43-–P NH4

+–N Mg2+

1.2 : 1 9.4 159 2.5 93.3 28.4 98.1

1.4 : 1 9.2 161 3.4 93.5 27.5 97.8

1.6 : 1 9.1 174 3.6 93.5 21.6 97.9

3) MAP recovery with addition of magnesium and phosphate

MAP recovery efficiency

In order to increase the of ammonium-N removal efficiency

and MAP recovery, it was necessary to add external sources of

magnesium and phosphate.

Table 3.7. Effect of Mg2+ : NH4+ : PO4

3- molar ratio on P and N

removal efficiencies

Mg2+ : NH4+

: PO43-

molar ratio

Concentration after MAP

precipitation (mg/L) Removal efficiency (%)

PO43-–P NH4

+–N Mg2+ PO43-–P NH4

+–N Mg2+

0.6: 1.0: 1.0 214.0 154.3 8.2 56.5 30.5 96.4

0.8: 1.0: 1.0 117.0 138.6 9.6 76.2 37.6 96.8

1.0: 1.0: 1.0 36.5 106.5 11.3 92.6 52.0 97.0

1.2: 1.0: 1.0 27.4 61.2 13.2 94.4 72.4 97.1

1.4: 1.0: 1.0 19.6 42.4 15.6 96.0 80.9 97.1

1.6: 1.0: 1.0 15.2 56.4 22.7 96.9 74.6 96.3

1.8: 1.0: 1.0 14.3 97.1 28.4 97.1 56.3 95.9

The results in Table 3.7 showed that the highest ammonium-

N removal efficiency of 80.9% was obtained at Mg2+ : NH4+ :

PO43- molar ratio of 1.4 : 1.0: 1.0. As a result, the optimal Mg2+

Page 15: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

13

: NH4+ : PO4

3- molar ratio for the simultaneous removal of both

ammonium-N and phosphate-P was 1.4 : 1.0 : 1.0. , at which the

phosphate-P, magie removal efficiencies, obtained MAP amount

were 96.0% and 97.1%, and 4,85 g/L wastewater, respectively.

Analyzation of obtained MAP product

MAP sample obtained at pH = 9.5 and Mg2+ : NH4+ : PO4

3-

molar ratio of 1.4 : 1.0 : 1.0 was taken for SEM and EDX

analysises to evaluate the crystal size and composition of the

MAP product. The results showed that the precipitate was clear

crystals, and had white color mixed with dark brown color and

many stains on its surface (Figure 3.12), possibly due to the

organic components in wastewater and/or other precipitates

formed during the MAP precipitation. The mass composition of

the P, Mg, O elements was 13.6%, 11.4%, 59.4% respectively.

This composition was nearly similar to that in pure MAP (12.6%,

9.9% and 65.3%). In addition, the precipitate also contained

11.2% C and other substances.

(a) (b)

Figure 3.12. MAP precipitate (a) and its SEM image (b)

Page 16: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

14

CHAPTER 4. SIMULTANEOUS REMOVAL OF

ORGANIC MATTER AND NITROGEN IN MODIFIED

SBRs

4.1. Materials and research methodology

1) Materials, chemicals, and equipment

Wastewater: Wastewater in this study was the effluent of the

EGSB reactor.

Seed sludge: Activated sludge from an oxic/anoxic biological

tank of Hanoi Plastic Company was used as seed sludge.

Equipment: Two similar modified SBRs with an effective

volume and a working height of 15L and 1.34m, respectively,

were used (Figure 4.1).

1. Wastewater container

2. Wastewater supply pump

3. Wastewater supply pipe

4. Modified SBR

5. Automatic valve

6. Effluent tank

7. Air blower

8. Air flowmeter

9. Air diffuser

10. Controller

I. Oxic zone; II. Anoxic zone

Figure 4.1. Modified SBR system

2) Research methodology

Experimental procedure

Wastewater

2

8

7

1 6

Air

Eff

luen

t

3

10

9

4

5

I I

Page 17: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

15

Two modified sequencing batch reactors (SBRs), R1 and

R2, specially configured to consist of both oxic and anoxic zones,

and be operated with only a single simultaneous oxic/anoxic

phase in each treatment batch were used. R1 was operated with a

constant aeration, by contrast, R2 was operated with an air flow

varied from a lower rate in the early period of the reaction phase

to a higher rate in the later period. The operating strategy for the

reactors was also modified to combine the drawing stage of the

treated water from the previous batch and the filling stage for the

new batch into the same phase. The reactors was operated in a

sequential three-step cycle mode (simultaneous drawing and

filling; reacting; and setting) as shown in Table 4.1.

Table 4.1. Operation mode of the modified SBRs

Reactor

Time for

simultaneous

drawing and

filling, min

Time of reaction phase,

min Setting time,

min Air flow

0,4 L/min

Air flow

2,0 L/min

R1 10

0 145 25

R2 55 90

Experimental conditions

Study on effects of OLR, ammonium-N loading rate

(ANLR) and nitrogen loading rate (NLR) on the performance of

R1 and R2 was performed in the OLR and NLR ranges of 0.52 –

1.61 kg CODm-3d-1 and 0.071 – 0.32 kg Nm-3d-1, respectively.

Study on effect of COD/TN ratio on the performance of the

reactors was carried out in the COD/TN ratio range of 3.4 – 6.0.

Page 18: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

16

4.2. Results and discussion

1) Effect of OLR on the COD removal

The results in Figure 4.4 showed that both R1 and R2

almost reached steady state after only one week from the startup.

The average COD removal efficiencies of both R1 and R2 in all

phases were quite stable and over 95%. There was no significant

difference in COD removal efficiency for both R1 and R2.

Figure 4.4. COD removal efficiency of modified SBRs OLR (kg CODm-3d-1): I = 0.52, II = 0.73, III = 0.90, IV = 1.19, V = 1.61

2) Effect of ANLR on the ammonium-N removal

The results in Figure 4.7 showed that the ammonium-N

removal of both R1 and R2 became stable after only one week

operation. Ammonium removal efficiencies of R1 and R2 were

almost the same, averagely over 99%. Average effluent

ammonium-N concentration was less than 1 mg/L.

0

20

40

60

80

100

0

500

1000

1500

2000

2500

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80

CO

D r

em

ova

l , %

CO

D, m

g/L

Thời gian vận hành, ngày

Influent COD Effluent COD_R1 Effluent COD_R2

Removal_R1 Removal_R2

I II III IV V

Page 19: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

17

Figure 4.7. Ammonium-N removal efficiency of modified SBRs ANLR (kg ammonium-Nm-3d-1): I = 0.048, II = 0.064, III = 0.11, IV = 0.14, V = 0.21

3) Effect of NLR on the TN removal

Figure 4.10 showed that essential time for R1 and R2 to

achieve stable TN removal was 30 and 21 days, respectively.

Figure 4.10. TN removal efficiency of modified SBRs

NLR (kg Nm-3d-1): I = 0.070, II = 0.09, III = 0.16, IV = 0.21, V = 0.31

In the stationary period, the TN removal efficiency of R1

was quite high with an average of 88 - 92% in phases III – V. R2

was able to achieve a steady state faster than R1. The removal

efficiency of R2 was higher than that of R1, about 97% in phases

III and IV, and 94% in phase V.

96

97

98

99

100

0

100

200

300

400

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80

Hiệ

u s

uấ

t xử

N-N

H4

+,

%

N-N

H4+,

mg

/L

Thời gian vận hành, ngày

effluent N-amoni_R1 Effluent N-amoni_R2 Influent N-amoni

I II III IV V

0

20

40

60

80

100

0

100

200

300

400

500

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80

T-N

rem

ova

l, %

TN

, m

g/L

Operation time, day

Influent T-N Efluent T-N_R1 Efluent T-N_R2

Removal_R1 Removal_R2

Page 20: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

18

At the same NLR, the TN removal efficiency of R2 was

higher than that of R1. The TN concentration in the effluent of

R2 was significantly lower than that of R1, less than 25 mg/L in

all three experimental phases III - V, meanwhile, the TN

concentration in the effluent of R1 fluctuated within the range of

15 - 50 mg/L.

4) Effect of COD/TN ratio on COD removal

The results in Figure 4.13 showed that no significant

differences in the COD removal efficiencies versus COD/TN

ratio were observed. The COD removal efficiencies of both

reactors were similar, with an average of over 95%.

Figure 4.13. Effect of COD/TN ratio on COD removal

5) Effect of COD/TN ratio on ammonium-N and TN removal

The ammonium-N removal efficiencies of both reactors

were over 99%, and ammonium-N concentration in the effluent

was below 1 mg/L (Fig. 4.14).

TN removal efficiencies of both reactors tended to increase

when increasing in the COD/TN ratio. These results were

40

50

60

70

80

90

100

0

500

1000

1500

2000

2500

3000

3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0

CO

D r

em

ova

l, %

CO

D, m

g/L

COD/TN ratio

COD Influent

COD Effluent - R1

COD Effluent - R2

COD removal - R1

COD removal - R2

Page 21: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

19

consistent with expectations, since a low COD/TN ratio leads to

a shortage of organic substrates for denitrification, resulting in

low TN removal (Figure 4.15).

Figure 4.14. Effect of COD/TN ratio on ammonium-N removal

Figure 4.15. Effect of COD/TN ratio on TN removal efficiency

The mean TN removal efficiency for reactor R1 increased

from 70% to 92% when raising the COD/TN ratio from 3.4 to

6.0; meanwhile, that of reactor R2 increased from 80% to 97%.

The results in Figure 4.15 also showed that TN removal

efficiency of R2 was remarkably higher than that of R1 at all

COD/TN ratios investigated.

94

95

96

97

98

99

100

0

100

200

300

400

500

600

3.0 3.5 4.0 4.5 5.0 5.5 6.0

N-a

mo

niu

m r

em

ova

l, %

N-a

mo

niu

m,

mg

/L

Tỉ lệ COD /TN

N-amoni Influent

N-amoni Effluent - R1

N-amoni Effluent - R2

Removal - R1

Removal - R2

20

40

60

80

100

3.0 3.5 4.0 4.5 5.0 5.5 6.0

TN

rem

ova

l, %

COD/TN ratio

R1 R2

Page 22: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

20

CHAPTER 5. PROPOSAL OF AN APPROPRIATE

TREATMENT PROCESS FOR NRP WASTEWATER

5.1. Proposed treatment process

Through the results achieved in this study, an energy and

nutrients recovering wastewater process for NRP wastewater

integrating physicochemical and biological processes was

proposed in Figure 5.1.

Figure 5.1. Proposed appropriate treatment process for NRP

wastewater

5.2. Process material balance

Based on results of the material balance (Table 5.1 and

Figure 5.2), the proposed process could ensure that the effluent

quality could meet the discharge requirements according to the

Vietnam Regulation QCVN 01-MT: 2015 BTNMT. In addition,

with the scale of Ha Tinh Rubber Factory, about 320 kg MAP per

day could be recovered each day. The biogas amount that could

be recovered daily is about 352 Nm3, equivalent to around 200

Nm3 methane. In terms of energy, it is equivalent to about 200 kg

of oil or nearly 2,000 kWh.

Rubber latex

seperating

pond

Equalizati

on tank

EGSB MAP

prepicipation

Product drying

furnace

Intermediate

tank

Bio

ga

s

Wastewater

Efluent Modified

SBR

Stationa

ry pond

MAP

product

Page 23: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

21

Table 5.1: Influent parameters, calculation results for effluent

Parameters Unit Influent (1) Effluent (6)

COD mg/L 6,480 74.2

TN mg/L 285 31.0

TP mg/L 186 24.8

SS mg/L 500 50.0

Figure 5.2. Results of calculating the material balance

352 Nm3/ngày

Wastewater

(1) (2) (3) MAP

220,0 232,7 232,7 320 kg MAP/ngày

(4) 232,7

(5) (6) 212,1

232,7 Effluent

(7)

20,6 Sludge

overflow wastewater (8) Sludge (9)

12,7 7,9

Note: Number in diagram is flow by cubic metter per day

Điểm (1) (2) (3) (4) (5) (6) (7) (8) (9)

Q, m3/day 220 232,7 232,7 232,7 232,7 212,1 20,6 12,7 7,9

Q, m3/h 9,2 9,7 9,7 9,7 9,7 8,8 0,9 0,5 0,3

COD, mg/L 6480 6181,6 1854,5 1483,6 1483,6 74,2 - 1000,0 -

LCOD, kg/day 1426 1438,3 431,5 345,2 345,2 15,7 - 12,7 -

TN, mg/L 285 376,1 376,1 309,9 309,9 31,0 - 100,0 -

LTN, kg/day 63 87,5 87,5 72,1 72,1 6,6 - 1,3 -

TP, mg/L 186 177,2 177,2 35,4 35,4 24,8 - 24,8 -

LTP, kg/day 41 41,2 41,2 8,2 8,2 5,3 - 0,3 -

SS, mg/L 500,0 500,0 200,0 200,0 200 50,0 8000,0 500,0 20000,0

LSS, kg/day 110,0 116,3 46,5 46,5 46,5 10,6 164,7 6,3 158,4

Materials balance

MAP prepicipateDetention

tankEGSB

Intermediate tankModified

SBR

Slude

tank

Biogas

Page 24: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

22

CONCLUSIONS AND RECOMMENDATIONS

Conclusions

1) Generation of granular sludge in ESGB reactor after 3 months

startup was successfully performed. The reactor could be stably

operated in the OLR range of 7 - 20 kg CODm-3d-1 with average

COD removal of over 80%. Biogas conversion yield for NRP

wastewater was 0.37 L/g removed COD.

2) Applicability and appropriate conditions for MAP

precipitation in the nutrient recovery from the NRP wastewater

were clarified. The optimal pH for MAP precipitation was 9.5, at

which nearly 45% of phosphate-P in NRP wastewater could be

recovered without addition of magnesium source. In the case of

magnesium addition, the optimal Mg2+ : PO43- molar ratio and

phosphate-P removal efficiency were 1.2 : 1.0 and 93.3%,

respectively. When both magnesium and phosphate were added,

the optimal Mg2+ : NH4+ : PO4

3- molar ratio was 1.4 : 1.0 : 1.0, at

which the removal efficiencies of phosphate-P and ammonium-

N, and the obtained MAP amount were 97.1% and 80.9%, and

and 4,85 g/L wastewater respectively.

3) A new modified SBR capable of effectively and

simultaneously removing organic and nitrogen substances from

NRP wastewater was successfully developed. The performance

of the reactor was significantly improved compared to

conventional SBRs and nitrification/denitrification reactors. At

OLRs of 0.9 - 1.6 kg CODm-3d-1 and NLRs of 0.16 - 0.31 kg

Nm-3d-1, average removal efficiencies of COD, ammonium-N

and TN were 97 %, nearly 100% and 94 - 97%, respectively. The

Page 25: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

23

optimal COD/TN ratio for the reactor was in the range of 5 - 6,

relatively low compared to that for conventional SBRs and other

nitrification/denitrification reactors. Average concentrations of

COD, ammonium-N and TN in effluent were below 70 mg/L,

less than 1 mg/L and less than 30 mg/L, respectively, satisfying

the Vietnamese regulation.

4) A new energy and nutrients recovering wastewater treatment

process integrating physicochemical and biological processes for

NRP wastewater was proposed. The features of the process are: (1)

energy saving and recoverable; (2) N and P nutrients recoverable;

(3) organic matter and nutrients simultaneously removable.

Recommendation

1) Further study on microorganism composition and activity of

anaerobic sludge in EGSB reactor, as well as evaluate the

performance of EGSB reactor at OLR above 20 kg COD m-3d-1.

2) Study in pilot scale to complete the proposed technological

process and fully evaluate economic-technical indicators.

NEW CONTRIBUTIONS OF THE THESIS

1) Generation of granular sludge in an EGSB reactor treating

natural rubber processing wastewater was successfully

performed. Applicability, appropriate technological conditions,

as well as energy recovery potential of EGSB reactor in the

treatment of the NRP wastewater were evaluated.

2) Applicability and suitable conditions for MAP precipitation

in the recovery of nitrogen and phosphorus from NRP

wastewater were clarified.

Page 26: gust.edu.vngust.edu.vn/media/27/uftai-ve-tai-day27288.pdf · (textile; NRP; pulp and paper; brewery; and leachate) generating wastewater with high pollutant load, in Vietnam research

24

3) A new modified SBR capable of effectively and

simultaneously removing organic and nitrogen substances from

NRP wastewater with a simplified operation procedure and high

energy saving potential was successfully developed. The

performance of the modified SBR was significantly improved

compared to conventional SBRs.

4) A new energy and nutrients recovering wastewater treatment

process integrating physicochemical and biological processes for

NRP wastewater was proposed.

LIST OF PUBLICATIONS

1. Duong Van Nam, Phan Do Hung, Nguyen Hoai Chau, Dinh

Van Vien, Study on phosphorus recovery from natural rubber

processing wastewater by struvite precipitation method. Journal of

Agriculture and Rural Development, No. 21, 11/2017, pp 82 - 87.

2. Duong Van Nam, Phan Do Hung, Nguyen Hoai Chau, Dinh

Van Vien, High performance modified SBR for simultaneous

removal of organic and nitrogen matters from rubber latex

processing wastewater. Vietnam Journal of Science and

Technology B, Volume 22, No. 11, November 2017, pp 48 - 53.

3. Duong Van Nam, Nguyen Hoai Chau, Hamasaki Tatsuhide,

Dinh Van Vien, Phan Do Hung, Effect of COD/TN ratio and

loading rates on performance of modified SBRs in simultaneous

removal of organic matter and nitrogen from rubber latex

processing wastewater. Vietnam Journal of Science and

Technology 56 (2) (2018), p. 236 - 245.


Recommended