7/28/2019 H-3 Power Point (Air Heater)
1/63
MITSUBISHI HEAVY INDUSTRIES, LTD.NAGASAKI SHIPYARD & MACHINARY WORKS
25 October 2009
SAUDI ARABIASHUQAIQ-2 IWPP PROJECT
COURSE- H-3
ITEM Boiler & auxiliaries
CONTENTS
Heater
7/28/2019 H-3 Power Point (Air Heater)
2/63
PAGE 2
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
Part.1
General
for
LjungstromAir Heater
7/28/2019 H-3 Power Point (Air Heater)
3/63
PAGE 3
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
1st topic Company Introduction Page 5
2nd topic General Explanation of Ljungstrom Regenerative
Air HeaterPage 8
3rd topic Heating element Page 13
4th topic Sealing System Page 18
5th topic Auxiliary Equipment for SHUQAIQ Page 21
Agenda
7/28/2019 H-3 Power Point (Air Heater)
4/63
PAGE 4
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
1st topic Company Introduction Page 5
2nd topic General Explanation of Ljungstrom Regenerative
Air HeaterPage 8
3rd topic Heating element Page 13
4th topic Sealing System Page 18
5th topic Auxiliary Equipment for SHUQAIQ Page 21
Agenda
7/28/2019 H-3 Power Point (Air Heater)
5/63
PAGE 5
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
Company Introduction
Company History of ALSTOM K.K.
1907 Founded as Gadelius Trading Co.1979 Merged into Flakt AB Sweden
1988 Merged into ABB Group
1999 Jointed with ALSTOM- formed
ABB ALSTOM Power2000 Transferred to ALSTOM Group
2007 100thAnniversary
Long Presence in JapanLong Presence in Japan
7/28/2019 H-3 Power Point (Air Heater)
6/63
PAGE 6
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
Company Introduction
ALSTOM Ljungstrom Group
Air Preheater Company
North America
Air Preheater Company
North America
Alstom KK EER
Asia
Alstom KK EER
Asia
APER GmbH Div. Air
Preheater Europe
APER GmbH Div. Air
Preheater Europe
Bammental,
Germany
Kobe, Japan
Wellsville, NY
(Headquarters)Osaka, Japan (NK)
Vinhedo,
Brazil
Concordia, KS
Engineering
Facilities
Manufacturing
Facilities
Shanghai, China
(CNEER)
Shanghai, China
(CNASAEER)
7/28/2019 H-3 Power Point (Air Heater)
7/63
PAGE 7
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
1st topic Company Introduction Page 5
2nd topic General Explanation of Ljungstrom Regenerative
Air HeaterPage 8
3rd topic Heating element Page 13
4th topic Sealing System Page 18
5th topic Auxiliary Equipment for SHUQAIQ Page 21
Agenda
7/28/2019 H-3 Power Point (Air Heater)
8/63
PAGE 8
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
AH
Boiler
FDF
EP
STACK
Function of LjungstromAir Heater
General Explanation of Ljungstrom
AirHeater
DeDe--SOxSOx
SystemSystem
SAH
7/28/2019 H-3 Power Point (Air Heater)
9/63
PAGE 9
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
HotSide
Cold
Side
General Explanation of Ljungstrom
Air HeaterAir and Gas Flows
HotSide
Cold
Side
Air
AirGas
Gas
7/28/2019 H-3 Power Point (Air Heater)
10/63
PAGE 10
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
General Explanation of LjungstromAir
Heater Construction of LjungstromAir Heater
Heating Element
Rotor Drive Unit
Guide Bearing
Housing Panel
Corner Duct
Pin Rack
Center Section
Soot Blower
Radial Seal
Bypass Seal
Axial Seal
RotorDiaphragm
Stay Plate
7/28/2019 H-3 Power Point (Air Heater)
11/63
PAGE 11
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
Ex.
26 -VI- 1325
Element Total Height (mm)
Flow Type: V, VI=Vertical shaft, H=Horizontal shaft
AH Nominal Size: Related to Rotor Diameter
General Explanation of LjungstromAir
HeaterExplanation of LjungstromAir Heater type
7/28/2019 H-3 Power Point (Air Heater)
12/63
PAGE 12
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
1st topic Company Introduction Page 5
2nd topic General Explanation of Ljungstrom Regenerative
Air HeaterPage 8
3rd topic Heating element Page 13
4th topic Sealing System Page 18
5th topic Auxiliary Equipment for SHUQAIQ Page 21
Agenda
7/28/2019 H-3 Power Point (Air Heater)
13/63
PAGE 13
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
Heating Element
Explanation of where the HE are installed
Heating
ElementDiaphragm
Stay Plate
DUNDUNTMTMNFNF
7/28/2019 H-3 Power Point (Air Heater)
14/63
PAGE 14
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
CRLS*1.2NF300Cold
Mild steel0.6DUN1025Hot
MaterialThickness
(mm)
TypeDepth
(mm)
Layer
* CRLS : Corrosion Resistant Low-alloy
Steel
Heating ElementHeating Element Spec. of AH for Shuqaiq-2
7/28/2019 H-3 Power Point (Air Heater)
15/63
PAGE 15
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Pressure
Pressured
rop
d
rop
Thermal efficiencyThermal efficiency
NFNF
DUNDUNTMTM
DUDU
Heating Element
Element performance characteristic tendency
7/28/2019 H-3 Power Point (Air Heater)
16/63
PAGE 16
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
28-VIX-2400Crude Oil300MWEVN O MONVietnam
27-VIX-2150Oil---Lin-YuangChinese Petrochemical co. (Taiwan)
26-VIX-1950Oil250MWx3Seraya P.S. Unit1~3Power Seraya Ltd. (Singapore)
27.5-VI-1700(RT)Coal210MWMindanaoState Power Development Corp.(Philippines)
27.5-VIX-1800Oil300MWTula Power Plant Unit5Comision Federal De Electricida
(Mexico)
32.5-VI-1900 (RT)Coal700MWx2JimahSKS Power RDN.BHD. (Malaysia)
32.5-VI-1900 (RT)Coal700MWx3Tanjung Bin, JohorSKS Power RDN.BHD. (Malaysia)
33.5-VI-2450(RT)Coal1000MWHitachi-naka Unit1Tokyo Electric Power Co., Ltd. (Japan)
23-HRX-1250Oil & Gas250t/hChiba Plant CBL B15Sumitomo Chemiccal Co. (Japan)
23.5-VIR-1350Oil450T/HMizushima Unit3Mitsubishi Chemical Co. (Japan)
28-VIX-1025VR---Aichi Unit3Idemitsu Kosan (Japan)
26.5-VI-1800VR&Gas185MWMizue Unit1 IPPGenex Co., Ltd. (Japan)
30.5-VI-2525(RT)Coal500MWShin Onoda Unit1&2Chugoku Electric Power Co., Ltd.
(Japan)
28.5-VIX-2225N.Gas&Oil350MWCairo West Unit 7&8Cairo Electricity Production Corp.(Egypt)
24-VIRX-2200Oil158 MWCarlos Manuel De Cespedes
Unit No. 4Cuba
30.5-VI-1625 (RT)Coal226MWBlue Waters Unit 1&2Griffin Energy Pty Ltd. (Australia)
AH typeFuelCapacityPlant nameCompany name
Reference List - DUNTM Heating element (excerpted)
7/28/2019 H-3 Power Point (Air Heater)
17/63
PAGE 17
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
1st topic Company Introduction Page 5
2nd topic General Explanation of Ljungstrom RegenerativeAir Heater
Page 8
3rd topic Heating element Page 13
4th topic Sealing System Page 18
5th topic Auxiliary Equipment for SHUQAIQ Page 21
Agenda
7/28/2019 H-3 Power Point (Air Heater)
18/63
PAGE 18
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
W= VRPHV : Volume of rotor plenum (m3)
RPH: Rotor revolutions per hour
GAS
AXIALSEAL
BY-PASSSEAL
AIR
Radial Leakage
Axial Leakage
HOTSIDE
SIDECOLD
SECTORPLATE
RADIAL SEAL
SECTORPLATE
- Direct leakage
- Entrained leakage
Axial
seal
plat
e
ENTRAINED LEAKAGE
Sealing System
W=CA(2gP)C : Flow coefficient
A : Total areas of seal gap (m2)
g : Gravitational acceleration (m/s2
) : Specific weight of gas (kg/m3)P: Pressure difference between two
flows
Explanation of Leakage
7/28/2019 H-3 Power Point (Air Heater)
19/63
PAGE 19
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
BY-PASS SEAL
ANGLE
BY-PASS SEAL
(HOT)
T BAR
AXIAL SEAL
BY-PASS SEAL
(COLD)
HOLDING
STRIPPOST SEAL
(COLD)
ROTOR POST
RADIAL SEAL
(HOT)
HOLDINGSTRIP
ROTOR DIAPHRAGM
POST SEAL
(HOT)
SECTORPLATE (HOT)
HOUSING
Sealing System
Rotor Seals (Typical)
T BAR
RADIAL
SEAL
(COLD)
7/28/2019 H-3 Power Point (Air Heater)
20/63
PAGE 20
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
1st topic Company Introduction Page 5
2nd topic General Explanation of Ljungstrom RegenerativeAir Heater
Page 8
3rd topic Heating element Page 13
4th topic Sealing System Page 18
5th topic Auxiliary Equipment for SHUQAIQ Page 21
Agenda
7/28/2019 H-3 Power Point (Air Heater)
21/63
PAGE 21
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Rotor Drive Unit
Bearing
Lubricant Oil Circulation Unit
Sootblower
Fire Detecting Device
Water Washing Device
Fire Extinguishing Device (for Hotside)
Auxiliary Equipment of AH for SHUQAIQ
Rotor Drive Unit
Guide Bearing
Soot Blower
Lubricant Oil Circulation Unit
Fire Detecting Device
Water Washing Device
7/28/2019 H-3 Power Point (Air Heater)
22/63
PAGE 22
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Auxiliary Equipment for SHUQAIQ
Rotor Drive UnitRotor Drive Unit (RDU) consists of speed reducer, main electric motor and
auxiliary air motor. A pinion gear is mounted to the output shaft which engages a
pin rack. The rotor assembly, containing the heating elements, is rotated by this
RDU through the air and gas streams at approximately 1.8 RPM. The air motor,
coupled to the main electric motor, is used as auxiliary motor for emergency and
maintenance operation.
Electricmotor
Speed
reducer
Air motor
(Utility)
Electric power : 7.5kw
Compressed air : 4.1barg
4.0m3/min.Pinion gearcover
7/28/2019 H-3 Power Point (Air Heater)
23/63
PAGE 23
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Auxiliary Equipment for SHUQAIQRotor Bearing
Guide Bearing : #23052
The guide bearing is responsible
for supporting the redial loads at
the top of the air heater
Bearing
(Self-aligning
roller
bearing)
Bearing
(Thrust self-aligning
roller bearing)
Support Bearing : #29456
The air heater rotor is supported
by the support bearing at the
bottom of the air heater
7/28/2019 H-3 Power Point (Air Heater)
24/63
PAGE 24
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Auxiliary Equipment for
SHUQAIQLubricant Oil Circulation Unit (for Guide Bearing)
(Utility)
Electric power : 0.75kwCooling water : 2.9barg, 3.6ton/hr
The purpose of this unit is to circulate the
lubricant oil for cooling when the
temperature of the oil in the guide bearinghousing reaches 50 degree Celsius.
7/28/2019 H-3 Power Point (Air Heater)
25/63
PAGE 25
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Type : Half Retractable Type
Steam condition (Cold side)
Blowing Press.
11.8barg
Consumption
1.7ton/hr
Electric power : 0.1kw
Cleaning Heating element surface by superheated
steam
Heating element
Steam
Auxiliary Equipment for
SHUQAIQSootblower (for Cold side)
7/28/2019 H-3 Power Point (Air Heater)
26/63
PAGE 26
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Auxiliary Equipment for
SHUQAIQ Fire Detecting System (FDS)
Detecting sensor : Thermocouple
Installation position of
Thermocouple :
Gas outlet duct : 4 pcs.
The purpose of the system is to monitorthe gas temperature leaving the air heater
and detect the fire at early stage. If hot
spot become present in the rotor, the gas
temperature will increase unexpectedly.
7/28/2019 H-3 Power Point (Air Heater)
27/63
PAGE 27
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Auxiliary Equipment for
SHUQAIQ
Type : Stationary Multi Nozzle Type
(at gas inlet & gas outlet duct)
Water Condition
Blowing Press. : 4.9barg
Consumption : 96ton/hr/each side
WaterWashing Device
7/28/2019 H-3 Power Point (Air Heater)
28/63
PAGE 28
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Auxiliary Equipment for
SHUQAIQ
Type : Stationary Multi NozzleType
(at gas inlet)
Water ConditionBlowing Press. : 4.9barg
Consumption : 192ton/hr
Fire Extinguishing Device (for Hot side)
The fire extinguishing device consist of 1
stationary multi nozzle pipe located in thegas inlet duct. The device is used in
conjunction with the water washing
device. The device is design to emit large
amount of water onto a concentrated
area of the heating element surface.
Fire extinguishingdevice
Socket
Nozzle
Washing
Tube
7/28/2019 H-3 Power Point (Air Heater)
29/63
PAGE 29
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
Operation and Maintenancefor
Ljungstrom Air Heater
Part.2
7/28/2019 H-3 Power Point (Air Heater)
30/63
PAGE 30
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
1-1. Pre start-up checks
1-2. Cold-run inspection
1-3. Hot-run adjustment
1-4. Start-up instructions
1-5. Shutting down instructions
1-6. Rotor stoppage due to motor failure
1-7. Operation procedure of soot blower
1st Operation
Agenda
7/28/2019 H-3 Power Point (Air Heater)
31/63
PAGE 31
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
2-1. Daily inspections
2-2. Periodical Inspections
2nd Maintenance
3rd Safety precautions
2-3. Water washing
Agenda
7/28/2019 H-3 Power Point (Air Heater)
32/63
PAGE 32
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
1-1. Pre start-up checks
1-2. Cold-run inspection
1-3. Hot-run adjustment
1-4. Start-up instructions
1-5. Shutting down instructions
1-6. Rotor stoppage due to motor failure
1-7. Operation procedure of soot blower
1st Operation
Agenda
PAGE 33
7/28/2019 H-3 Power Point (Air Heater)
33/63
PAGE 33
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
1-1.Pre start-up checks
To determine whether or not the Air Hater is ready for service,a complete inspection of the Air Heater and its auxiliary equipment
is required. The operator should be concerned with all components
being installed correctly, clean, and correctly lubricated.
Prior to start-up, the operator must pay particular attention to the
following areas to ensure safe and efficient operation of the AirHeater.
Instructions
PAGE 34
7/28/2019 H-3 Power Point (Air Heater)
34/63
PAGE 34
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
1-1.Pre start-up checks
FINAL CHECK-OUT
LUBRICATION
ROTOR INSPECTION
ROTOR SEALS
GUARDS AND COVERS
PLANT UTILITIES
ELECTRICAL CONNECTIONS AND CONTROL SYSTEM
ROTOR ROTATION
SOOT BLOWER STEAM PIPING
Instructions
PAGE 35
7/28/2019 H-3 Power Point (Air Heater)
35/63
PAGE 35
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
1-1. Pre Start-up checks
1-2. Cold-run inspection
1-3. Hot-run adjustment
1-4. Start-up instructions
1-5. Shutting down instructions
1-6. Rotor stoppage due to motor failure
1-7. Operation procedure of soot blower
1st Operation
Agenda
PAGE 36B i f B ilB i f B il
7/28/2019 H-3 Power Point (Air Heater)
36/63
PAGE 36
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
1-2.Cold running test
Hot-run adjustment
Confirm unobstructed operation by air motor drive
Continuous running test
Back-up test
- Start the auxiliary air motor by opening the hand valve.
- Observe the rotor for unobstructed operation.Finish
Fin ish
- Energize the main drive motor and run the rotor
- Check the motor temp.,
abnormal sound,vibration...etc.
- Test the automatic operation of the air motor solenoid valve
upon power loss to the main drive motor.Finish
Instructions
7/28/2019 H-3 Power Point (Air Heater)
37/63
PAGE 38Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
38/63
PAGE 38
MHI BUSINESSCONFIDENTIALMHI BUSINESSCONFIDENTIAL
Basic of BoilerBasic of Boiler
1-3.Hot-run adjustment
NOTE: This adjustment should be done at 100%-load during hot-run test
b. Soot blower blowing pressure adjustment
(1) Blowing pressure: 11.8 barg (Cold Side)
Instructions
PAGE 39Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
39/63
PAGE 39
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
1-1. Pre Start-up checks
1-2. Cold-run inspection
1-3. Hot-run adjustment
1-4. Start-up instructions
1-5. Shutting down instructions
1-6. Rotor stoppage due to motor failure
1-7. Operation procedure of soot blower
1st Operation
Agenda
PAGE 40Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
40/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
1-4.Start-up
The following operation sequence should be used to place the air heater
into service.
A. Start the air heater's main drive motorbefore the forced and
induced daft fans are started. The rotor must be rotating before emitting
hot flue gas through the air heater.
B. When firing the boiler on oil, start cold end soot blowing to the air heater
continuously during start-up using an auxiliary blowing medium until stableboiler conditions are achieved and the normal soot blowing medium is available.
C. Energize the guide bearings oil circulation units.
The pump motors will start upon oil temperature rise.
D. Start the air heater's auxiliary equipment control system.
E. After normal soot blowing medium is available, activate the air heater sootblower
Instructions
PAGE 41Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
41/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Basic of BoilerBasic of Boiler
1-1. Pre Start-up checks
1-2. Cold-run inspection
1-3. Hot-run adjustment
1-4. Start-up instructions
1-5. Shutting down instructions
1-6. Rotor stoppage due to motor failure
1-7. Operation procedure of soot blower
1st Operation
Agenda
PAGE 42Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
42/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
1-5.Shutting down
The following sequence should be used to remove the air heater from service.
A. Activate the soot blower to remove any deposits which may have
accumulated on the heating element surface.
B. Keep the FD & ID fans running during the cleaning operation so that the
air heater temperature will decrease more rapidly.
C. Deactivate the air heater soot blowers.
D. De-energize the air heater's auxiliary equipment control system.
E. Keep the rotor turning and the fans operating until the gas inlet temperatureat the heater inlet drops below 150C.This will evenly distribute the effects of thermal distortion, over the entire
rotor structure.
F. Shut down the FD & ID fans.
G. De-energize the rotor drive unit of the air heater.H. Close the manual valve to stop compressed air to the auxiliary air drive motor.
I. Deactivate the guide bearing oil circulation units.
Instructions
PAGE 43Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
43/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
1-1. Pre Start-up checks
1-2. Cold-run inspection
1-3. Hot-run adjustment
1-4. Start-up instructions
1-5. Shutting down instructions
1-6. Rotor stoppage due to motor failure
1-7. Operation procedure of soot blower
1st Operation
Agenda
PAGE 44Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
44/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
1-6.Rotor stoppage due to motor failure
! CAUTION
Trip!!
Instructions
Back-up startAir Motor
(Aux. Drive)
Elec. Motor
(Main Drive)
If operation mode is selected to manual mode, aux. air motor does not
start automatically.
Operation mode of aux. electric motor should select to AUTO at normal condition.
Over
running
clutch(ORC)
PAGE 45Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
45/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
NOTE: The air heater structure will not experience permanent damage
as long as the temperature of the gas entering the air heater does not
exceed 480. However, if the rotor cannot be restarted immediately(within approx.15 min), damage to some of the seals and/or sealing plates
is likely to occur due to non-uniform thermal expansion of the rotor.
Non-uniform
thermal expansion
of the rotor
Air side
Gas side
PAGE 46Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
46/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
1-1. Pre Start-up checks
1-2. Cold-run inspection
1-3. Hot-run adjustment
1-4. Start-up instructions
1-5. Shutting down instructions
1-6. Rotor stoppage due to motor failure
1-7. Operation procedure of soot blower
1st Operation
Agenda
PAGE 47Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
47/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
1-7.Operation procedure of Soot Blower
Frequency and occasion for soot blowing
(Standard operation frequency)
: once every 8 hours
for the cold side, in principle
7/28/2019 H-3 Power Point (Air Heater)
48/63
7/28/2019 H-3 Power Point (Air Heater)
49/63
PAGE 50Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
50/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
2-1. Daily inspections
2-2. Periodical Inspections
2nd Maintenance
3rd Safety precautions
2-3. Water washing
Agenda
PAGE 51Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
51/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
2-1.Daily Inspections
Rotor guide&support bearing
Check the rotating sound,oil level, gas leak.
Draft loss and temperatureCheck and record the draft loss
both side and temperature
Rotor drive unit
Check the temp., vibration,current, oil level.
Soot blower
Check the blowingpressure and leak.
Rotor
Visual Check the elementsand seals condition from
observation port.
Lubricant oil circulation unit
Check the oil pressure andcooling water.
PAGE 52Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
52/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
2-1. Daily inspections
2-2. Periodical Inspections
2nd Maintenance
3rd Safety precautions
2-3. Water washing
Agenda
PAGE 53Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
53/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
- Repair.
- Replacement
1.Visual check
2.Measuring the Weight, thicknessHeating element
- Repair
- Replacement
1.Thickness measurement
2.Visual check
AH proper
- Cold side partition plate,
Cold side housing panel,
...etc
- Repair.
- Replacement
1.Overhaul2.Visual check
3.Leak test
4.Functional test
Lubrication oil circulationunit
- Oil pump,filter,cooler,
Safety valve
- Repair.
- Replacement.1.Hammering
2.Visual check
Rotor trunnion
- Trunnion bolts,Locking bar
- Repair.
- Replacement.
1.Visual check
2.Measuring the thickness
3.Liquid penetrate testing
Rotor proper
- Rotor post,Rotor,Pin rack
T-bar
- Repair.- Replacement
1.Visual check
2.Hand check
3.Oil sampling
Bearings
- Support,Guide,
Air seal cover
Contents of inspection Measures at abnormalComponents parts
2-2.Periodical inspections (Summary)
PAGE 54Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
54/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
- Repair.
- Replacement
1.Overhaul
2.Visual check
3.Measuring
Rotor drive unit
- Speed reducer,Elec. motor
Aux motor,Pinion gear
- Repair.
- Replacement
1.Visual check
2.Measuring the thickness
Stationary water washing
Fire extinguishing device
- Nozzle,Tube
- Repair.- Replacement
- Readjustment
1.Hammering
2.Measuring the thickness3.Measuring the seal clearance
4.Measuring the degree
of parallelism
Rotor seal
- Post seal, Radial seal,
Bypass seal, Axial seal,
Static seal,Sector plate
- Repair.
- Replacement
1.Visual check
2.Overhaul
3.Measuring
Soot blower
- Speed reducer, Carriage,
Feed tube, Lance tube,Wall box, Flanges
1.Visual check
Contents of inspection
- Repair.
- Replacement
Others
- Manholes, doors
Observation port
Measures at abnormalComponents parts
PAGE 55Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
55/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
2-1. Daily inspections
2-2. Periodical Inspections
2nd Maintenance
3rd Safety precautions
2-3. Water washing
Agenda
PAGE 56Basic of BoilerBasic of Boiler
2 3 W t hi
7/28/2019 H-3 Power Point (Air Heater)
56/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
2-3.Water washing
P Water
washing
OperationOut of service
Initial value
Water
washing
Operation
When pressure drop across the Air heater keeps increasing despite continued
use of the soot blower properly, it is a sign that the deposits have coagulated and
stick fast to the heating element surface.In general, we recommend that when the pressure drop exceeds the initial value x
1.5times, water washing shall be carried with the Air heater during out of service.
Instructions
Out of service
PAGE 57Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
57/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Operation procedure of water washing
Preparation
1) Make sure that the temperature of gas inlet is below 150.
It may cause damages on AH if it is higher than 150.
2) Line up the water line.3) Check the drain lines to be able to drain adequately.
4) Shut off steam valves for soot blower
5) Observe the condition of deposit on heating element.
Finish
Start water washing
8-12hr
- Measuring the pH value of drain water.
- Check the supply water pressure.- Check the piping for drain out.
- Check the conditions of washing.
The auxiliary air motor drive should be used to reduce
the speed to approximately to RPM.
Instructions
PAGE 58Basic of BoilerBasic of Boiler
Instructions
7/28/2019 H-3 Power Point (Air Heater)
58/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
Determine the completion
Complete
a) Completion may be determined from the difference of pH value
between washing water and drain water.
When the difference is less than 1, it may be completed in principle.
pHv
alue
b) Observe the heating elements over entire area to check deposit
being removed. If deposits still remain, continue washing.
1) Close water valves
2) Open dampers in the inlet and outlet ducts
3) Remove the illumination light
4) Close drain lines
5) Dry up heating elements(It is desirable to dry by operating the fans)
6) Stop rotor rotation
Finish
pH Washing water
Drain water
-> pH value decreases due to sulfuric acid
Instructions
PAGE 59Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
59/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
DANGER: WASHING OF THE AIR HEATER HEATING
ELEMENT SHOULD ONLY BE CARRIED OUT WHEN THE AIR
HEATER IS OUT OF SERVICE AND THE GAS SIDE
TEMPERATURE IS COOL ENOUGH TO ALLOW MAINTENANCE
PERSONNEL ENTRY TO THE AIR HEATER AND ADJACENT
DUCTS. HOWEVER, IN NO CASE SHOULD WATER BE EMITTED
ONTO THE ROTOR UNTIL THE METAL TEMPERATURE OF THE
GAS INLET HEATING ELEMENT IS BELOW 150C.
CAUTION: BEFORE AND DURING WATER-WASHING,
INSPECT HOPPER DRAINS TO INSURE THAT THE DRAINS ARE
NOT PLUGGED. TREMENDOUS QUANTITIES OF WATER
MUST EXIT THE DRAINS OR THE CONNECTING DUCTS CANBECOME FLOODED
CAUTION: INSUFFICIENT WATER WASHING HAS ADVERSE
EFFECTS TO THE HEATING ELEMENT AND INCOMPLETE
DRYING WILL CAUSE RAPID PROGRESSION OF CORROSIONAND ACCUMULATION OF DEPOSITS ON THE HEATIMNG
ELEMENTS WHEN RETURNING TO SERVICE.
PAGE 60Basic of BoilerBasic of Boiler
A d
7/28/2019 H-3 Power Point (Air Heater)
60/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
2-1. Daily inspections
2-2. Periodical Inspections
2nd Maintenance
3rd Safety precautions
2-3. Water washing
Agenda
PAGE 61Basic of BoilerBasic of Boiler
! IMPORTANT
7/28/2019 H-3 Power Point (Air Heater)
61/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
DANGER: NEVER ATTEMPT TO ENTER THE AIR HEATER UNTILTHE FOLLOWING CONDITIONS ARE MET.
ALL ELECTRIC POWER TO THE ROTOR DRIVE UNIT AND THE
SOOTBLOWER UNIT HAS BEEN ISOLATED.
THE LOCAL COMPRESSED AIR HAND VALVE AT THE AIR
MOTOR SHOULD BE SECURED IN THE OFF POSITION.
THE SURFACE TEMPERATURE OF THE AIR HEATER IS
BELOW 100F (38C).
O2 AND CO2 CONCENTRATION ARE SATISFIED TO ENTER.
For detail operation and maintenance instructions, please refer to:
Operation & Maintenance Manual
! IMPORTANT
PAGE 62Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
62/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL
CAUTION: WHENEVER WELDING IS DONE ON THE ROTOR POST ORROTOR ASSEMBLY, THE ROTOR POST (MAIN SHAFT) MUST BE
CONNECTED TO AN EARTH GROUND.FAILURE TO PROVIDE A
PROPER GROUND MAY RESULT IN DAMAGE TO THE AIR HEATER
BEARINGS.
DANGER: NEVER APPROACH OR TOUCH ANY ROTATING PARTS
(SHAFTS, COUPLINGS, ETC.) DURING OPERATION.
LOOSE CLOTHING CAUGHT IN THESE ROTATING PARTS MAY
RESULT IN SEVERE INJURY AND/OR DEATH.
CAUTION: OPERATING THE AIR HEATER WITH GAS INLET
TEMPERATURES IN EXCESS TO THE MAXIMUM DESIGN
TEMPERATURES CAUSE THE ROTOR SEALS TO CONTACT THE AIR
HEATER STRUCTURE AND RESULT IN PREMATURE WEAR ORPOSSIBLE PERMANENT DAMAGE TO THE SEALING SYSTEM.
PAGE 63Basic of BoilerBasic of Boiler
7/28/2019 H-3 Power Point (Air Heater)
63/63
MHI BUSINESS
CONFIDENTIAL
MHI BUSINESS
CONFIDENTIAL