HC Precast System Mock-up Panel
Test by Panasonic Homes MKH Malaysia Sdn Bhd
Coring Test ( Between Wet Joint & Precast Panel Wall ) : - 19th July 2019
“ In Line With Government's Housing 4.0 Agenda for IBS for Superstructure Works ”
100 % Malaysia Technology With 6 IPs’
Comply UBBL & BSI code
GREEN BUILDING
- 19th July 2019 coring test : Coring by specialist appointed by Panasonic
- 19th July 2019 coring test : Coring test completed
- 19th July 2019 coring test : Setting out of coring point by Mr. Kenichi Togawa
- 19th July 2019 coring test : Coring by specialist appointed by Panasonic
3. 4.
5. 6.
7. 8.
2.
1.
- 19th July 2019 coring test : 8 nos of coring point
- 19th July 2019 coring test : Inspection of coring sample by Mr. Kenichi Togawa
- 19th July 2019 coring test : Inspection of coring sample by Mr. Kenichi Togawa
- 19th July 2019 coring test : Inspection on the core and taking photos
Precast panel wall
Ground floor slab
Cebex 100
Expendite cement
well expanded
Expendite cement well expanded between
ground floor slab and precast panel wall.
Standards compliance
Cebex 100 is a suitable
pre-stressing Grout admixture when
complying with BS 8110 Part 1, 1985,
section 8.9.4.6.
- 19th July 2019 coring test : Expendite cement between ground floor slab and precast panel wall
- 19th July 2019 coring test : Coring point
- 19th July 2019 coring test : Coring between wet joint and precast panel wall
Coring between wet joint
and modular shear keys
precast panel wall.
- 19th July 2019 coring test : Verticality checking by Mr. Kenichi Togawa & Mr. Hisashi Mac Matsumiya
- 19th July 2019 coring test : Verticality checking by Mr. Kenichi Togawa & Mr. Hisashi Mac Matsumiya
- 19th July 2019 coring test : Water penetration test – to check any hairline crack appears
- 19th July 2019 coring test : Water penetration test - to check any hairline crack appears
- 19th July 2019 coring test : Discussion on HC Precast System
- 19th July 2019 coring test : Discussion on the modular shear key by HCPS
- 19th July 2019 coring test : Inspection on training unit (12 years without any covering or waterproofing)
- 19th July 2019 coring test : Inspection on training unit (12 years without any covering or waterproofing)
- 19th July 2019 coring test : Hisashi “ Mac ” Matsumiya visit production yard
- 19th July 2019 coring test : Inspection on largest panel (6m x 6m) & storage frame
- 19th July 2019 coring test : Inspection on largest panel (6m x 6m) & storage frame
- 19th July 2019 coring test : Visit in-house engineering department
- 19th July 2019 coring test : Visit in-house engineering department
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
- 19th July 2019 coring test : Staircase mould installation and dismantle demo (4 Minutes)
THANK YOU