D. Baden 1
HCAL Upgrade Workshop
(SLHC, where nothing is
certain)April 2010 Upgrade Week
4/29/10
D. Baden2
Timeline/MilestonesThe 2012 and 2015 shutdowns quantize things Will discuss HCAL goals for phase 1 upgrades with
these times in mind
4/29/10
D. Baden3
Towards 2012Back-end Plan to have at least 1 fully loaded uTCA crate of production modules ready Add fiber splitters on some number of data fibers, run VME and uTCA
simultaneously Spend the 2012 year commissioning the system. Goal: when we begin installing and commissioning FE electronics (2016?), we
want to have a solid BE in place Note: new FE requires new BE
HF Install new PMTs? Will depend on…
The need. LHC data will tell us much. The fix. Do we have a good tube candidate, what about neutrons, aging, etc.
R&D underway
HO Install Ring1 and Ring 2 SiPMs
Using current HCAL electronics of course
4/29/10
D. Baden4
Towards 2015Back-end Complete installation of uTCA
Abandon the VME infrastructure We hope to be able to do some of this quasi-statically over time
in the proceeding run
Front-end Install and commission with new back-end electronics, HB
and HE
Admittedly ambitious but…. Current HCAL FE was built in 2002. HTRs were built in 2004. We have built our upgrade project around these timelines.
We are guardedly optimistic and appropriately conservative
4/29/10
D. Baden5
This Week: FE Series of talks/discussion, focused almost entirely on front-end issues Back-end, simulation, software discussed elsewhere
Main issues covered: QIE10 progress GBT FE readout module (RM) design Some discussion of SiPM but not the main topic Radiation testing
4/29/10
D. Baden6
QIE10Specifications… Much already understood but much remains Some significant changes from QIE8 (current version)
4/29/10
D. Baden7
QIE10 Status1st stage in development, FE amp only, study AMS .35m SiGe bi-CMOS process Submitted 2/22/10, expect test bench measurement in May Compare to simulation models, if ok then move forward
Rad testing under way HCAL spec: 1011 n/cm2 for SEU and 5x1012 n/cm2 for bulk
damage
Decision taken at 2010 workshop, goal for full chip submission 2/2011 FNAL engineer Zimmerman, we do not have all of his time
unfortunately. And we will need it.
4/29/10
D. Baden8
GBT DiscussionTullio Grassi presented our requirements to Magnus and P. Moreira 160MHz DDR serial input to GBT 8B/10B data transmission protocol
P. Moreira provided much information, long discussion of GBT capabilities, possibilities, and HCAL needs GBT plan to have a “complete” prototype in 2010, followed by extensive
testing with a production version 2nd half of 2011 We have much homework to refine our specifications GBT may also give us a real path towards a more redundant slow controls
If GBT project can meet our needs then we can commit to being a customer We are concerned about the schedule. They are losing 2 or 3 key people.
Overall this was a very possible discussion. We are optimistic.
4/29/10
D. Baden9
FE readout module (RM)
4/29/10
Optical Interface Structure
Zecotek “EDU”
FPGA/GBT emulator and transmitter
Tullio presented our power/cooling requirements and options Design to 200W/RBX >> current usage 90W
Need a scheme for delivering more power, but cooling is adequate
We want to try to use the Cern MIC DC-DC converter (discussion…)
Chris Tully led a long discussion on the R&D issues Many issues. Too many for here. Much dependence of electronics integration with SiPM
vendor Whether we have an “EDU” or an “ODU”, sorry for the
jargon ADC cards are very ambitious, lots of pins.
Much prototyping now
D. Baden10
RM Integration
Development of the RM is largely driven at this stage by component development SiPM GBT (and GBT SCA) QIE10 LV regulators
It’s important to guide the parameters of these components as they are being developed
4/29/10
D. Baden11
Front-End R&D, near term
SiPM. R&D towards choosing a vendor Have a specific R&D with Zecotek (high density) to
reduce the response time and characterize lifetime and radiation response This is our “EDU”
Have a specific R&D to use large area SiPMs (lower pixels but very fast recovery times, adequate for HCAL) This is more like an ODU and opens up the vendor pool
RM R&D Work with GBT group Specify QIE10 inputs and outputs, and functionality
in concert with GBT and overall RM design
4/29/10
Depth 1
(Layer-0)
Depth 2
Depth 3
Depth 4
Baden12
Summary of Issues/Requirements(Always Evolving)
Item Comments
SiPM Narrowed down to 2: Zecotech & Hamamatsu. On the critical path
QIE10 Requirements & design. Coupled to GBT and overall RM integration
“GBT” (data & “TTC”)
Many issues, very much want to use GBT if at all possible.
FE logic/control FPGA technology (flash, anti-fuse, ASIC?) and overall design topology
FE Redundancy Reduce single points of failure, related to GBT
Power & Cooling Specs, R&D
RBX Mechanics Details!
FE bias/control, Peltier,…
Control, config, monitoring
BE uHTR timing Clocking, fast controls, TTCf-functionality
DCC and timing Combined function, maintain legacy capability but accommodate future
uHTR DCC uTCA backplane, DAQ issues
DAQ/FED Legacy, FED evolution, etc.
1/28/10