Date post: | 31-Dec-2015 |
Category: |
Documents |
Upload: | annis-douglas |
View: | 216 times |
Download: | 3 times |
Healthcare Facility Standards – a P3 Bid Director’s Perspective
December 8, 2014 – Toronto, Ontario
Presentation by
J. Paul Boucher, PEng MBAVP Infrastructure DevelopmentCarillion Canada Inc.
Agenda
Facility “standards” in a P3 bidding environment Why “push the boundaries” of building standards? Challenging healthcare facility standards: risks,
benefits, constraints Some Examples How can you encourage win-win proposals for
healthcare infrastructure?
Facility Standards in a P3 Bidding Environment
“Regulatory” Standards Third Party standards such as Ontario Building Code,
AODA, technical standards/certifications Requirements of “Authorities Having Jurisdiction” (e.g.,
conservation authority) Local bylaws, SPA requirements or building permit
conditions, “administrative practices” “Discretionary” Standards
Voluntary technical standards and guidelines (e.g., CSA) Project Specifications to capture evidence-based design
principles (e.g., PSOS) Intended to be output based but often prescriptive
The two extremes co-exist in many contract documents, leading to interesting conflict situations
Regulations Codes Bylaws Project Specifications
Voluntary Standards
Change
Regulatory Discretionary
Why “Push the Boundaries” of Building Standards?
Bidders are incentivized to search for design solutions that meet or exceed client objectives and yet score higher than “strict compliance” with standards (and scoring is heavily weighted to favour low cost!)
But with the advanced risk transfer of a P3 structure … Bid period for design tradeoffs is compressed Facility design-build time is compressed (time=money) Design decisions are a risk-adjusted, whole life cost/benefit assessment Oversight from many stakeholders ensures risk allocation and risk
management are appropriate
Therefore, although bidders are motivated to challenge project standards and specifications, they have an appropriate bias toward:
Schedule certainty (predictable processes and with some means to accelerate if necessary)
Cost certainty (related to schedule, too) Ability to manage risks (as opposed to “taking risks”)
“Compliance” is a complex concept: Many specifications are conflicting, ambiguous, or cannot be achieved Many are un-bounded because of they contain absolutes (all, every) or superlatives (maximize,
minimize) Most quantitative specifications have a qualitative objective “behind” them
Dimensions of Efforts to Challenge Healthcare Facility Standards
Many Few
Regulations Codes Bylaws Project Specifications
Voluntary Standards
Decision makers
Judicial ContractualChange Mechanism
Very Low HighCost and Schedule Certainty
Change
Regulatory Discretionary
Barriers to Challenging “Regulatory” Standards in a P3 Environment
Contrasts in risks/benefits: Challenging a standard can be highly uncertain with respect to
time and cost but P3 project delivery is specifically designed to minimize time and cost uncertainty!
A change in a particular standard may benefit many similar projects but P3 projects are “ring fenced” with respect to risks and benefits!
The lengthy procurement/approval process for healthcare facilities is championed by a particular hospital without incentives or resources to “trail blaze” for its peers!
The P3 bidding process requires that bidders “commit to achieve” rather than “promise to try”.
Success reinforced by objective oversight P3 project financing is only repaid if project is
successful Lenders would recognize that contractors cannot
manage the cost and time risk of changing certain types of standards
Example #1 – Piping Expansion Joint
Piping in a new Ontario hospital will be subject to thermal, seismic movement
Owners engineer specifies that traditional (but complicated) bellows or sliding expansion pipe joints must be used
Advances in materials means that a “flex loop” can be used. Product is approved by UL and TSSA, and is certified for use in Ontario
Project saves schedule, capital cost and maintenance cost
Not compliant but functionally equivalent Note that bidder required change in project
standards but not regulatory standards!
Example #2 – CCC Space Planning
A hospital wanted to deliver the therapeutic benefits of outdoor access to its Complex Continuing Care patients in its new hospital
Owners engineer specifies that CCC must be located on the ground floor
Bidder locates CCC on second floor with rooftop gardens
Bidder not compliant but … Better patient privacy Improved patient security Lower capital cost
Customer agreed to waive ground floor requirement for CCC
How Can You Encourage Win-Win P3 Proposals?
If you want your project to challenge a “regulatory” standard, do it before P3 bidding starts
Share your vision and objectives Specify the required outcomes not the inputs Question superlatives and absolutes in specifications Challenge yourself and your technical advisors … “Are
our standards biased by a pre-conceived solution?”
Win-Win from higher performance at lower cost … innovation without compromise!
“You won’t find a winner and a loser in a P3 relationship. It’s either two winners or two losers.”
Questions? To continue the dialogue…
J. Paul BoucherVP Business Development(905) [email protected]
Carillion Canada Inc.7077 Keele StreetConcord, ON L4K 0B6