���������
1
HEARING DAY TWO1
Atomic Energy of Canada Limited:2
Application for the renewal of the Chalk River3
Laboratories Nuclear Research and Test4
Establishment Operating licence5
THE CHAIRPERSON: The Commission6
is conducting three parallel hearings on the Chalk7
River Laboratories, MAPLE and the New Processing8
Facility. The Commission notes that the9
facilities are within the same general site and10
share a number of common systems, facilities and11
programs. Therefore, to reduce repetition and12
ensure there is a complete record for all three13
hearings, the Commission, in making its decisions,14
will consider any relevant information regarding15
those common elements as it is presented during16
the course of the hearings.17
The first item on the agenda today18
is Hearing Day 2 on the application by Atomic19
Energy of Canada Limited to consider an20
application for the renewal of the Chalk River21
Laboratories Nuclear Research and Test22
Establishment Operating licence.23
The first day of the public24
hearing that I referred to earlier on this25
���������
2
application was held on January 15, 2003.1
The public was invited to2
participate either by oral presentation or by3
written submission on Hearing Day 2 today. March4
10th was the deadline set for filing by5
intervenors. The Commission received 45 requests6
for intervention.7
MR. LEBLANC: CMDs 03-H3.43 to 03-8
H3.47 were received after the deadline. Based on9
its consideration of these matters, a panel of the10
Commission accepted the interventions. A further11
submission received significantly after the12
deadline was rejected by the panel of the13
Commission. The Commission strongly urges all14
parties to file their submissions within the15
deadlines set in the public notice of hearings, in16
compliance with the CNSC Rules of Procedure. A17
Record of Decision will be published on our Web18
site and sent to affected parties.19
The Notice of Public Hearing 2003-20
H-1 was published on November 8, 2002.21
Presentations were made on Day 122
by the applicant, Atomic Energy of Canada Limited,23
under CMDs 03-H2.1 and 03-H2.1A and by Commission24
staff under CMD 03-H2.25
���������
3
April 2nd was the deadline for1
filing of supplementary information. It is noted2
that supplementary information has been filed by3
the applicant and by the CNSC staff.4
THE CHAIRPERSON: We are now ready5
to start.6
7
03.H2.1C to 03-H2.1G8
Oral presentation by Atomic Energy of Canada9
Limited10
THE CHAIRPERSON: We will now11
start with the oral presentation by Atomic Energy12
of Canada Limited as outlined in CMD Document 03-13
H2.1C.14
I would turn it over to the15
President and Chief Executive Officer of AECL, Mr.16
Van Adel.17
Mr. Van Adel, you have the floor,18
and welcome.19
MR. VAN ADEL: Thank you very20
much.21
Before we begin, I will ask Paul22
Lafrenière to introduce our team here today, and23
then I will make my remarks.24
M. LAFRENIÈRE: Bonjour chez nous.25
���������
4
I would like to first of all1
introduce Bob Van Adel, Paul Fehrenbach, Jean-2
Pierre Létourneau and myself.3
We are very proud to have you here4
today among us. With that, I will turn it over to5
Bob.6
M. VAN ADEL: Merci, madame Keen7
et membres de la Commission pour la possibilité de8
vous parler aujourd'hui. Je suis Robert Van Adel.9
Je suis président et directeur-général de l'EACL.10
On behalf of AECL employees and11
management, I want to thank you for scheduling the12
Day Two licensing hearings in the community in13
which we operate at Chalk River Laboratories and14
providing a venue for our neighbours to become15
personally involved in the process.16
My presence here today has several17
purposes: first, to inform you that I regard the18
licensing process as critical to our business.19
Chalk River Laboratories are essential to AECL's20
future as the research and other deliverables21
produced here have national and international22
impact.23
And second, to support the efforts24
undertaken by AECL's management team with respect25
���������
5
to the three licensing applications being heard1
today.2
And finally, to hear the3
community's concerns.4
We insist on openness with respect5
to our operations, and we welcome the6
stakeholders' input. We appreciate today's7
opportunity to immediately address any concerns8
that we might be able to.9
If there is one message that I10
would like to impart, it is that AECL is totally11
committed to meeting and exceeding one of our12
primary objectives: the safe and environmentally13
responsible operation of our site, both now and in14
the future.15
As CEO, I have placed this vital16
commitment at the heart of AECL's vision.17
The first vision element, as you18
can see on the slide, is to protect the health and19
safety of our employees, the public and the20
environment. Statistics relating to our21
performance in all three areas prove that our22
track record is excellent. That message is being23
widely recognized, and we thank those who have24
come forward today to support us.25
���������
6
Our business comprises research1
and development, nuclear products and services and2
reactor sales. To realize the second element of3
our vision, to be the top worldwide nuclear4
products and services company and achieve business5
success, we must build and modernize our6
infrastructure consistent with protecting the7
health and safety of employees, the public and the8
environment.9
We have made substantial progress10
in these areas during the current licence period,11
and I endorse all the continuing effort to improve12
even more.13
The third element is to minimize14
the nuclear legacy obligations for future15
generations. So in addition to securing Treasury16
Board funds for remediation projects related to17
legacy wastes, Natural Resources Canada, AECL and18
the CNSC are now entering into discussions on the19
long-term management of AECL's radioactive wastes20
and decommissioning liabilities, with a report21
back to Cabinet before the end of a two-year22
period with substantial recommendations.23
These initiatives take time,24
however, and many issues, including public input,25
���������
7
have to be considered. We are serious about1
sharing this information, and we will continue to2
inform the public of our intentions and seek their3
input as we move forward with these new4
initiatives.5
Meanwhile, we are further reducing6
environmental impacts by minimizing the upfront7
production of radioactive waste. The modular8
above-ground storage system is reducing low-level9
solid waste through segregation and compaction.10
When the new processing facility is operational,11
it will solidify liquid waste from the production12
of Moly-99 thereby eliminating the need for long-13
term storage of fissile and active liquid wastes14
in storage tanks.15
A safe operation is based on a16
positive safety culture. Excellent procedures and17
well designed systems help in this regard, but at18
AECL we recognize the value of encouraging and19
expecting staff to question the way they work.20
Identifying and becoming part of the solution of21
safety issues is paramount.22
Nowhere is this more manifested23
than in our recently launched value statement, the24
basis for the attitudes and behaviours we deem25
���������
8
acceptable for all staff. Our fundamental1
philosophy says we cannot protect the public and2
the environment if we don't protect ourselves3
first. Errors must be understood and corrected.4
Wilful violations are not tolerated.5
In this regard every effort is6
made to ensure that staff are fully trained, they7
understand what is expected of them and they8
proactively bring safety issues forward for9
action.10
As a corporation, we are11
continuing to ask ourselves three questions: Is12
safety stated a primary objective of our13
organization? Second, do we have meaningful14
safety culture philosophy and a program in place15
to deal with it? Third, do we know that it is16
effective?17
I am confident we are doing well18
on all three fronts. Our vision statement, which19
addresses the first question, is a key component20
of our corporate policies and safety is addressed21
in all aspects of our work. Philosophies and22
programs start at the top and are applied23
throughout the organization. Regular monitoring,24
oversight and reporting on the nuclear facilities,25
���������
9
health, safety and environmental performance is1
done through the line and is also independent of2
the line.3
Independent reporting is done on a4
quarterly basis to the board of directors and to5
me via the Science and Technology Committee.6
Numerous departments use balanced scorecards to7
track and report upwards on their safety8
performance. Safety issues are reviewed at the9
monthly Nuclear Laboratories Management Committee10
and Joint Union-Management Site Safety and Health11
Committee meetings.12
Our operating experience, OPEX13
Program, is active and our Occupational Safety and14
Health Group monitor issues like housekeeping.15
The Safety Review Committee, the16
SRC, assesses all new projects to ensure potential17
safety and environmental impacts are taken into18
account before any work proceeds. Furthermore, we19
never underestimate the value of training and20
helping staff learn the importance of protecting21
themselves, the public and the environment.22
So measuring our performance23
effectiveness is critical.24
Chalk River recently celebrated 125
���������
10
million person-hours without a lost time incident.1
Annual reports demonstrate the2
improving downward trend in both radiological3
exposures and releases. Employees are reporting4
more minor events, which ironically is positive5
from a safety culture perspective because it6
demonstrates openness.7
All of this indicates that we are8
successfully creating a transparent safety9
culture.10
Improvement means fine tuning our11
organization. For instance, you will note that12
the responsibility for AECL's Safety Review13
Committee rests with our Chief Engineer Basma14
Shalaby, who reports directly to me.15
One of the most significant16
demonstrations of our commitment to safety was the17
appointment of a chief quality officer to refocus18
our attention and activities on quality throughout19
the company.20
Reporting directly to me as well21
is Dr. Aly Aly, who in his previous role with the22
CNSC was well informed on areas requiring23
improvement at AECL. His organization has been24
expanded to ensure an effective, independent25
���������
11
corporate quality organization, and we welcome his1
leadership and vision in this area.2
He will elaborate on his3
activities soon, and I am confident that you will4
see that we are making good progress on the5
quality front across AECL.6
To be the top worldwide nuclear7
company, we must focus on safety, quality and8
product excellence while being responsive to our9
customers' needs and future market demands. We10
are undertaking this new challenge through a11
cultural shift. Employees must feel empowered to12
challenge and innovate. They must be committed to13
learning and teamwork.14
We encourage staff to accept15
personal responsibility and accountability and16
engage in honest open communications.17
I will give you a few examples of18
this demonstrable change.19
The corporate-wide Operations20
Management Team, or OMT, as we call it, was formed21
in 2001 and has responsibility for the day to day22
business activities of the firm. Under the23
oversight of the OMT the process is put in place24
by a number of associated committees, such as the25
���������
12
Resource Management Working Group, who ensure that1
issues such as safety and quality have2
accountability in our daily performance.3
The appointment of Paul Fehrenbach4
as Chief Operating Officer in June 2002, and more5
recently promoted to Vice-President of the Nuclear6
Laboratories Business Unit, puts special emphasis7
on the importance of this asset.8
Paul's responsibilities include9
integration and oversight of compliance program10
effectiveness, as well as all activities and11
policies being carried out at the labs.12
His participation in my weekly13
executive management meetings allows Paul to bring14
operational issues tied to the CRL licence-listed15
facilities, all of which have been moved to his16
organization with the exception of the items that17
you see listed on the slide.18
These changes improve the19
effectiveness of our activities and afford a means20
of priorizing resource allocation.21
The MMIR Executive Oversight22
Committee created in 2001 reviews the progress of23
the MMIR project, including quality and safety24
standards. I personally chair this committee. It25
���������
13
meets on a biweekly basis, and the two senior1
vice-presidents with operating responsibilities2
are also members.3
While all of these changes in my4
view facilitate cultural shift, additional5
transformations demand more focused attention.6
Improving the robustness of our safety culture7
requires strong management commitment. This8
commitment is supported by our vision mandate and9
value statements and a rigorous corporate planning10
process. All of these efforts are collectively11
helping to achieve the necessary cultural shift.12
While safety first is our working13
motto, safety culture can only be embraced when14
employees clearly understand their roles and15
responsibilities and the company's expectations.16
Our safety management system ensures they are17
fully informed of the company's safety18
philosophies, policies and procedures. Without19
safety knowledge and without employees' co-20
operation we cannot move forward.21
Communication therefore becomes22
crucial. We communicate regularly through23
quarterly staff updates that I personally deliver,24
which I did yesterday in Chalk River and the day25
���������
14
before in Sheridan Park. Through our employee1
newsletter "ReAction" I am involved in the2
editorial process to ensure that goals,3
objectives, visions and values are represented in4
this company-wide communiqué; and furthermore, I5
insist that managers share activities highlights6
so employees stay informed.7
Madam Chair, when we protect our8
staff first, we not only minimize the risk to our9
neighbours and the environment, we instill public10
confidence. It is for this very reason that I11
encourage employees to report all suspected and12
real events and to become familiar with our OPEX13
program.14
Examples of lessons learned are15
featured regularly in "ReAction", our magazine,16
often with key changes highlighted. To enhance17
the communication learning process, I have18
strengthened and empowered AECL management to19
follow through on lessons learned to prevent re-20
occurrences.21
As with large complex22
organizations, resourcing is an important issue.23
The decision to create the MMIR Executive24
Oversight Committee ensures that the right25
���������
15
engineering and technical resources needed for the1
MMIR commissioning are available. The Resource2
Management Working Group, which I mentioned is3
part of the OMT, has been charged with similar4
responsibilities for allocation of resources5
across the company.6
Management feedback must justify7
the actions taken to address issues like safety.8
Enhancements in process development require9
managers to quickly and carefully investigate and10
disposition any safety issue that is brought11
forward. Follow-up communication to employees is12
critical because feedback confirms our action or13
inaction. That is why we require staff to perform14
self-assessment and, when appropriate, to interact15
and benchmark with other organizations. The16
learning process, especially as we undergo this17
cultural shift, allows our attitudes and18
behaviours to broaden personal learning through19
continued interactions with our regulator,20
supplier and customers.21
In closing, Madam Chair and22
Members of the Commission, AECL has inspired and23
diligent professionals who continue to seek out24
innovative ways to enhance our operations each day25
���������
16
and every day. I am proud of the people who make1
AECL the company that it is.2
I would also like to note that3
AECL staff have been working closing with the CNSC4
staff to address all issues raised during the5
evaluation of our operations. We remain committed6
to improving in the areas noted in our efforts to7
interact with you.8
Merci, madame Keen et membres de9
la Commission. Je vais maintenant céder la parole10
à Dr. Aly Aly.11
DR. ALY: Thanks, Bob. Good12
morning, Madam Chair, Members of the Commission.13
For the record, my name is Aly Aly. I am AECL's14
Chief Quality Officer, reporting directly to Mr.15
Van Adel, the President and CEO of AECL.16
To outline my presentation on17
AECL's quality improvement program, I will start18
first with a brief introduction, to be followed by19
a summary of what we consider as the main elements20
of quality improvement and our success in21
addressing these elements.22
I will then summarize our current23
activities and priorities and conclude by24
describing the road map we are following today to25
���������
17
achieve excellence in quality.1
When I joined AECL last April, Mr.2
Van Adel assigned to the new corporate quality3
organization the broad responsibilities of4
ensuring that AECL adheres to the highest quality5
standards, prescribing quality requirements6
through company-wide manuals and procedures, and7
development and maintaining the overall management8
system.9
Needless to say, AECL's operations10
are very diverse and by the nature of the business11
are also very dynamic. These operations include12
research and development, design, procurement,13
construction, commissioning, operation of nuclear14
facilities, in addition to waste management and15
decommissioning activities.16
The main challenge is to put in17
place an effective management system that18
prescribes the company-wide high level19
requirements through company-wide manuals and20
procedures without impairing the ability of our21
diverse operational units to establish specific22
local requirements.23
In brief, I wish to assure the24
Commission that major improvements in corporate25
���������
18
quality are taking place today and that AECL is1
committed to the principle of continual2
improvements.3
For AECL, the main elements of an4
effective quality improvement program include an5
effective management system, an independent6
quality organization, effective corporate7
oversight, a healthy safety and quality culture,8
as well as a clear vision of where the company9
intends to go, which I refer to as a road map to10
excellence.11
The first element of quality12
improvement is the continual improvement of the13
overall management system. The shown pyramid14
indicates the main elements of AECL's overall15
management system.16
At the top is the AECL management17
manual, which is approved by the President and CEO18
and endorsed by all Executive Management Committee19
members. The AMM defines the purpose and20
describes the structure of the organization,21
provides roles and responsibilities of executives22
and senior management positions, provides roles of23
panels and committees, describes AECL's business24
process management and compliance management,25
���������
19
documents the code of conduct principles and1
policies and provides the management2
responsibility matrices.3
Below the AMM are the company-wide4
QA manual and its procedures and company-wide sub-5
tier QA manuals and procedures. These manuals6
include the corporate QA requirements and are7
owned by the corporate quality organization. The8
manuals also demonstrate the AECL commitment to9
comply with the CSA N286 series of standards.10
As indicated earlier, due to the11
diversity of AECL's operations, projects and12
facilities developed specific QA manuals and QA13
plans consistent with their respective activities14
but in compliance with the high level corporate-15
wide requirements.16
Seventy to 80 per cent of the17
procedures listed in these lower tier manuals are18
actually company-wide procedures. The remaining19
procedures are those that are specific to the20
project or facility. This is a significant21
improvement as compared to the status a few years22
ago, since the total number of procedures has been23
reduced from about 2,000 to just over 200.24
The lower base of the pyramid25
���������
20
indicates that evidence of compliance is obtained1
through audits, assessments, records, forms and2
reports. This management system is subject to3
periodic program reviews, and all manuals are4
updated regularly.5
The second quality improvement6
element relates to the independence of the quality7
organization. In the past few years, corporate QA8
at AECL was part of the office of the chief9
engineer and the technology unit. CNSC staff10
considered this reporting structure as a sign of11
lack of independence. With my appointment last12
April, and as shown in the org chart, the office13
of the Chief Quality Officer now reports directly14
to the President and CEO. This ensures15
independence of corporate quality from costs and16
schedules.17
I wish also to emphasize that at18
CRL senior quality representatives, or SQRs,19
report directly to general managers rather than20
facility managers to ensure independence within21
the line from costs and schedules.22
In addition, all SQRs have23
reporting lines to corporate quality to ensure24
adequate guidance on following requirements as25
���������
21
well as a further independence in reporting1
quality issues.2
The third quality improvement3
element is related to the effectiveness of4
corporate oversight. This has been also a CNSC5
staff issue in the past.6
When I joined AECL last April,7
corporate QA consisted of only one director and8
six QA staff. The structure reflected the9
decentralized QA model used at AECL in the past10
decade. We have moved over the last year into a11
new model where a balance between strong QA12
presence in the line, as well as a strong13
corporate quality organization, has been14
established.15
With the full support of the16
President and the Executive Management Committee17
and the Operations Management Team, the corporate18
quality office today has 22 positions, including a19
number of senior managers. Subject matter experts20
in design, procurement, construction,21
commissioning and operation QA have been22
redeployed to corporate quality to ensure23
effective and consistent oversight on all our24
projects and activities.25
���������
22
The dotted lines shown on the1
chart show additional venues available to SQRs to2
report directly quality issues, as indicated3
earlier. The Corporate Director, Nuclear4
Laboratories QA and Compliance is located at Chalk5
River and he reports directly to myself.6
I will now turn to our current7
activities and priorities.8
As Mr. Van Adel covered safety9
culture in his presentation, I intend to focus10
here only on quality culture.11
At the top of our priorities is a12
genuine effort to strengthen our customer and13
regulatory confidence. We intend to pursue this14
goal through strengthening our corporate oversight15
on quality, as indicated earlier, and by enhancing16
quality culture through awareness and training17
sessions.18
In that regard I wish to refer to19
a series of quality culture seminars delivered at20
all AECL sites last year to over 250 managers by21
an expert in safety and quality culture.22
We have also developed a new and23
robust corrective action program that has been24
issued for use last December to replace five old25
���������
23
procedures.1
In addition and as a result of a2
very comprehensive overall quality assurance3
program review that was completed just a few weeks4
ago, we are also proceeding to update and improve5
over 20 company-wide procedures and are following6
up on other recommendations for improvements.7
Finally, we are working diligently8
in developing a quality and quality assurance9
training plan to upgrade staff and management10
knowledge and skills.11
I wish also to advise the12
Commission that we intend to monitor our quality13
improvement progress on a quarterly basis through14
the use of a Quality Index that we have developed15
and also intend to improve trending at the project16
as well as at the corporate level.17
An important milestone this summer18
will be the migration from the ISO 9001:1994 to19
the ISO 9001:2000 certification company-wide.20
On my last overhead I have21
summarized what we consider to be a road map to22
excellence. This road map includes:23
(1) the solid management24
commitment that has been demonstrated at all25
���������
24
levels;1
(2) the quality management working2
group that I chair myself and includes 12 senior3
managers from all our operational units. QMWG is4
empowered by the Operations Management Team to5
lead in enhancing quality culture in the company.6
(3) comprehensive program reviews7
are being conducted company-wide;8
(4) a strategy to improve our9
business process management has been developed and10
is being implemented;11
(5) a strategy for ISO 9001:200012
certification has been developed and is being13
implemented, and we anticipate the company-wide14
certification this summer;15
(6) a comprehensive quality and16
quality assurance training requirement analysis17
has been completed and a training plan is near18
completion;19
(7) we have established effective20
communication channels with all our customers, as21
well as with CNSC staff, to address all quality-22
related issues in a timely manner;23
(8) we are committed to work with24
many national and international organizations in25
���������
25
our quest for continual improvements. This1
provides these organizations.2
Madam Chair and Members of the3
Commission, I trust that my presentation provided4
enough information to demonstrate AECL's solid5
commitment to quality and quality assurance and6
also identified real progress that should now be7
recognizable to CNSC staff.8
We will continue to work with CNSC9
staff to ensure that all quality or Chalk River10
specific quality issues will be adequately11
addressed.12
Madam Chair, this concludes my13
presentation. I wish now to invite Dr. Paul14
Fehrenbach to proceed with the presentation.15
DR. FEHRENBACH: Thank you, Aly.16
Madam Chair, Members of the17
Commission, for the record my name is Paul18
Fehrenbach, Vice-President of the Nuclear19
Laboratories Business Unit.20
As mentioned by Mr. Van Adel and21
as shown on the first slide, as of April 1st AECL22
has reorganized into five business units. The23
main thrusts of the new structure are to align24
fully with AECL values and business lines, to25
���������
26
ensure accountability, to permit rapid adjustment1
to market realities and to align our activities2
with customer and stakeholder needs and3
expectations.4
While it is not appropriate here5
to get into detailed organizational charts, I6
think it is worth mentioning that within the7
Nuclear Laboratories Business Unit the8
organizational structure at senior levels remains9
essentially the same as it was the last time we10
spoke to you: specifically, Paul Lafrenière11
remains general manager of Facilities and Nuclear12
Operations; Bob Speranzini is general manager of13
CANDU Technology Development; and Bill14
Kupferschmidt is general manager of15
Decommissioning and Waste Management.16
The primary roles and17
responsibilities of the Nuclear Laboratories18
Business Unit are:19
(1) to provide safe, responsible20
and cost effective operation of AECL's nuclear21
sites and facilities;22
(2) to ensure the safety,23
licensing and design basis of CANDU Technology;24
(3) to develop advanced, pre-25
���������
27
commercial CANDU Technology;1
(4) to support Canadian public2
policy and regulation for nuclear technology in3
Canada and elsewhere;4
(5) to manage decommissioning and5
radioactive waste on behalf of AECL and the6
Government of Canada;7
(6) to manage and operate8
commercial research reactor fuel manufacturing9
facilities at Chalk River Laboratories; and10
(7) to support the commercial11
application and development requirements of other12
AECL business units using Nuclear Laboratory13
facilities and expertise.14
As Mr. Van Adel alluded to, once15
the MMIR project is complete and the facilities16
are in operation, responsibility for operation of17
the new isotope production facilities will also18
transfer to the Nuclear Laboratories Business19
Units. At that time we will make application to20
the CNSC for appropriate modifications to the21
respective operating licences to reflect that22
change.23
To summarize, the responsibilities24
of the Nuclear Laboratory Business Unit therefore25
���������
28
include operation of the Chalk River and1
Whiteshell sites, decommissioning and waste2
management, nuclear laboratories research and3
development and support for the activities of4
other AECL business units.5
The authority for nuclear6
operations within AECL is delegated to me as Vice-7
President of the Nuclear Laboratories Business8
Unit. In turn, I am empowered to delegate9
authority to the site licence holders.10
To end the summary of my11
responsibilities and authority, I should mention12
that I chair the Nuclear Laboratories Management13
Committee, mentioned again by Mr. Van Adel, which14
provides regular oversight and co-ordination of15
health, safety, security, environmental and16
compliance activities at AECL's nuclear17
laboratories.18
With that, I would like to19
introduce Paul Lafrenière, General Manager of20
Facilities and Nuclear Operations and the site21
licence holder for Chalk River, to brief you on22
recent developments affecting our site licence23
application.24
Paul.25
���������
29
MR. LAFRENIÈRE: Thank you, Paul.1
Madam Chair, Members of the2
Commission, as site licence holder for the Chalk3
River Laboratories, I accept responsibility for4
ensuring that you receive the information you need5
from AECL in order to properly assess our licence6
request.7
I trust that you will have8
received the supplementary information package9
that AECL staff prepared and submitted to your10
staff on 2003 March 13. Supplementary information11
was compiled in response to your request made12
during the course of Day 1, and it includes13
summary descriptions of the fissile solution14
storage tank, or FISST; the environmental15
protection initiatives; radiation protection16
issues and performance; NRU safety17
characteristics; actions being taken by AECL to18
address "C" ratings; preventive maintenance; and19
an update on performance data from the year 2002.20
AECL staff have also responded to21
the issues raised in the CNSC staff's Commission22
Member Document tabled at the Day 1 hearing. A23
series of meetings were held with CNSC staff in24
the past two and a half months to reach a common25
���������
30
understanding of all issues. AECL is progressing1
well toward resolving these issues.2
The next few slides constitute a3
brief report card on AECL's responses to CNSC4
staff's constructive criticisms. Some items are5
dealt with quite briefly here because they are6
dealt with in depth later on in my presentation.7
AECL's safety culture has8
underpinned the success of operations at CRL for9
more than five decades. Management continues to10
emphasize safety first, and that is reinforced by11
the President right on down through the entire12
AECL organization.13
Later on I shall present examples14
of measures of AECL's solid and improving safety15
culture.16
Let me point out here that this is17
about continuous improvement. We are improving,18
and we will improve further.19
There were three corporate quality20
assurance issues of concern to CNSC staff in 200321
January. Dr. Aly subsequently led an AECL team22
which met with CNSC staff, and it was agreed that23
outstanding issues with the AECL overall QA manual24
would be closed pending CNSC feedback on two25
���������
31
issues.1
Similarly, CRL operations QA2
specialists met with CNSC staff in February and3
agreed on required revisions to the Nuclear4
Operations QA Manual and the supporting Conduct of5
Operations Procedures.6
The issues were use of mandatory7
language, prescriptiveness of procedures and8
properly characterizing the site licence holder as9
the single line of authority for all licence-10
listed facilities.11
As you are aware, AECL was12
assessed by CNSC staff on the quality of programs13
and their implementation in seven safety areas.14
In 2003 January CRL was assessed as having nine15
"Bs" and five "Cs". Since then we have been16
informed that on the basis of advances made in17
nuclear security implementation the rating has18
changed to ten "Bs" and four "Cs".19
We also understand that on the20
basis of recent CNSC staff observations,21
performance trends for performance assurance and22
radiation protection have been recharacterized as23
"improving" rather than "little change", as24
indicated by the characterization in January.25
���������
32
We are confident with the plans we1
have put in place to bring all ratings up to "Bs"2
in the near future.3
I will return to AECL's action4
plans to continue to enhance performance later on5
in my presentation.6
The AECL management manual now7
makes it clear that the site licence holder for8
CRL is the designated authority for all CRL9
licence-listed facilities. Also, changes that10
become effective 2003 April 1 transfer line11
management responsibility for the nuclear fuel12
fabrication facility to the general manager FNO,13
who also serves as the CRL site licence holder.14
The AECL management manual has15
been modified to define the mandate and16
responsibilities of the Nuclear Laboratories17
Management Committee, for which Dr. Fehrenbach is18
responsible.19
In addition, a new position of20
Corporate Director of QA and Compliance for CRL,21
reporting directly to Dr. Aly, the Chief Quality22
Officer, has been created to provide an23
independent oversight function, for instance, of24
CRL line management.25
���������
33
As I have reported to you on1
previous occasions, the CRL nuclear site2
management system has been under development for3
the past several years. Key to the system is a4
set of approved processes which define5
responsibilities for interaction between staff of6
nuclear facilities, compliance programs and other7
support groups.8
Shortly before the Day 1 hearing9
in January AECL was approached by CNSC staff with10
a view to making certain documents available to11
intervenors prior to the Day 2 hearing. AECL has12
co-operated with CNSC staff to make information13
available to intervenors in a timely fashion.14
The information transfer was done15
such that it does not establish a precedent,16
compromise security, and the action is without17
prejudice to AECL's rights under the Access to18
Information Act.19
As you know, AECL last year20
contracted with specialist consultants in the21
ecological assessments to provide AECL with an22
ecological effects review for the CRL site, the23
first draft of which has been provided to the CNSC24
in instalments for review.25
���������
34
Environmental monitoring on the1
CRL site and in the surrounding area has been2
conducted for many years. The quality of the data3
has been verified independently by specialists4
from Laval University.5
I would like to point out that Dr.6
Barbeau of Université Laval est ici aujourd'hui,7
if there are any questions.8
In Chapter 3 of the supplementary9
package, Figure 3.3 presented data indicating a10
manyfold decline in concentrations of three11
radionuclides, tritium, strontium 90 and cesium12
137, in the Ottawa River in the 1960s to present.13
The current levels are less than 1 per cent of the14
acceptable concentration for drinking water; in15
fact, less than a tenth of that.16
Concentrations at Rolphton and17
Deep River upstream from CRL are only marginally18
lower than for Pembroke downstream of CRL.19
The Rolphton water was sampled20
from upstream of the hydro dam, which is upstream21
of the NPD nuclear power demonstration facility.22
The relatively high concentrations of tritium,23
strontium 90 and cesium 137 in the 1960s were due24
to fallout from atmospheric nuclear weapons25
���������
35
testing elsewhere in the world. The comparison1
serves to illustrate how little the Ottawa River2
is affected by effluents from CRL.3
Following the Day 1 hearing in4
January AECL followed up on the Commission's5
suggestion and approached representatives of6
several unions and members working at CRL to come7
here and speak with you on the safety culture at8
CRL. I am happy to say they are available.9
The individual union members opted10
to have their umbrella organization, the Canadian11
Nuclear Workers Council, make a presentation to12
you on their behalf. I am pleased that Dave Shier13
of the CNWC is here today representing the14
unionized workers' viewpoint.15
I was pleased to note that AECL's16
security program has been re-evaluated to a "B"17
rating. CNSC staff audited the security18
arrangements at CRL in 2003 March and registered19
improvements in security training and in security20
systems programs that merited an overall "B"21
rating for the program.22
AECL acknowledges CNSC staff's23
recent trend rating of our radiation protection24
program to "improving", and we have agreed to a25
���������
36
series of actions and a schedule to implement six1
further enhancements to the program. The plan was2
summarized in Chapter 6 of the supplementary3
information package, and we are working now toward4
enhancing four areas: namely, organization and5
administration; radiation exposure and dose6
control; respiratory protection; and personnel7
dosimetry.8
AECL's radiation protection9
program has been a success in that collective and10
average doses to CRL workers have declined11
steadily by factors of about two over the past12
decade or so.13
More than ten years ago AECL took14
the initiative to reduce and maintain maximum15
employee doses in NRU and elsewhere at AECL16
laboratory sites to below 20 milisieverts per17
annum rather than AECB's regulatory limit of 5018
milisieverts per annum. We have not only achieved19
our objective of keeping the maximum doses below20
20 milisieverts, but we are pleased to note that21
we are continuing to achieve reduction in doses.22
In 2002 NRU workers not only remained below the 2023
milisievert limit for the year, but also the doses24
for all workers were below 15 milisieverts.25
���������
37
As mentioned earlier, AECL has1
just been reorganized effective April 1st. The2
organization chart for Facilities and Nuclear3
Operations is shown on this slide. The two4
central columns deal with the operating nuclear5
facilities and programs, some of which are6
company-wide compliance programs to ensure7
compliance with safety, security and environmental8
protection requirements.9
Facilities and Nuclear Operations10
is a division of the Nuclear Laboratories Business11
Unit, whose Vice-President is Dr. Paul Fehrenbach.12
Turning now to safety culture. It13
is a senior manager's responsibility to14
demonstrate an overriding commitment to safety15
throughout all our diverse activities. I invest a16
good portion of my time praising good practices17
and challenging poor ones. I encourage18
conservative decision-making and prohibit19
shortcuts from being taken where there are20
potential deleterious safety culture safety or21
environmental considerations.22
During the past year there have23
been several occasions when managers of the NRU24
reactor and the Moly-99 hot cell production25
���������
38
facility put production on hold to ensure safety1
concerns were properly addressed.2
I provided praise for putting3
safety ahead of productivity and publicly thanked4
the managers for their demonstrated devotion to5
safety culture in the pages of the "ReAction"6
newsletter. When managers and staff do the right7
safety things, it is important that senior8
managers reinforce those behaviours so that safety9
culture, like quality culture, becomes a natural10
way of doing business.11
Our efforts to emphasize safety12
were rewarded in 2002 when CRL celebrated a13
milestone in which over one million person-hours14
were worked without a single lost time injury.15
We believe that satisfied16
employees are more likely to work safely. We all17
know that to be true.18
Over the past three years we have19
been measuring employee job satisfaction and have20
noted a 50 per cent increase in job satisfaction21
in that period. Morale has improved for a variety22
of reasons, not the least of which is the kudos23
strong performers are receiving in the pages of24
the "ReAction" newsletter. Recognition by their25
���������
39
managers and peers means a lot to our employees.1
This is key to people.2
Managers and senior management at3
CRL regularly visit the workplace, reinforcing4
good practices and gathering feedback from5
employees.6
I would like to take the time7
right now to thank our President and CEO for the8
vision that he has put in front of us. I can9
assure you that has been a most positive step.10
It has been my experience that11
organizations that look deep in the grass for12
fairly innocuous unplanned events and report them13
and analyze root causes are the organizations14
least likely to incur serious unplanned events.15
The lessons learned from non-16
reportable unplanned events could include lessons17
needed to prevent precursors of more serious18
accidents. Thus I make no apologies for having19
gone out of my way to encourage CRL staff to be20
vigilant in reporting relatively minor events so21
that lessons learned could be shared with others.22
Regulators could further reinforce23
this positive aspect of safety culture by24
accepting an increasing number of non-reportable25
���������
40
events as a positive indicator.1
Commitment to safety culture and2
environmental responsibility is considered in3
personnel performance appraisals of AECL employees4
at all levels of the organization. It gives me a5
lot of pleasure to acknowledge the 126
organizations, identified by this slide, who have7
stepped forward in support of AECL's licence8
application. We appreciate your vote of9
confidence, and we pledge in turn to continue10
operating Canada's foremost national nuclear11
laboratory safely, responsibly, and to be a good12
neighbour to those of you located in the upper13
Ottawa Valley.14
Similarly, we appreciate the15
support offered by several CRL unions who have16
asked Dave Shier of the CNWC to represent them17
collectively at this hearing. We acknowledge that18
there are individuals or groups who express19
concerns about nuclear safety and environmental20
issues. We want to reassure them that we are21
running a reliable and safe operation.22
AECL has responded positively to23
the potential additional security challenges since24
the terrorist attacks in the U.S. of September 11,25
���������
41
2001. Since then we have doubled the strength of1
our nuclear security guard force. It was2
gratifying that AECL became the first licensee to3
comply fully with the CNSC Annex Order with4
respect to site access clearances.5
After investing $20 million in6
security enhancements and working very hard to7
comply with all applicable regulations, there8
should be no doubt that AECL is very good value9
for the "B" rating recently awarded by your staff.10
Turning now to the longer term11
future of NRU, AECL has informed the CNSC in a12
President to President letter, dated 2003 February13
18, that we wish to operate the NRU reactor beyond14
2005 December 31.15
Three key factors influenced this16
decision.17
First, AECL has a comprehensive18
safety analysis of NRU completed, including seven19
major safety upgrades installed in the past few20
years. The NRU reactor is now capable of21
operating safely beyond 2005.22
Second, access to a research23
reactor is essential to maintain and advance CANDU24
nuclear power technology and to support other25
���������
42
Canadian applications of nuclear technology, such1
as the NRC program of material science using2
neutron scattering.3
Finally, a commitment to build a4
Canadian neutron facility, a reactor proposed to5
replace the research capability of NRU, has not6
yet been made by our shareholder. The new safety7
analysis of using up to date analytical tools and8
based on modern analytical standards demonstrated9
that NRU is safe.10
Furthermore, the analysis showed11
that there were no technical reasons why NRU12
should not be operated beyond 2005.13
In addition, we have initiated14
work to systematically assess NRU's capability to15
meet continued demands. We believe that safe16
operation in 2006 and beyond can, and will, be17
demonstrated to the satisfaction of the CNSC staff18
and this Commission.19
If at any time for any reason that20
situation were to change, we would not of course21
proceed with the upcoming request to extend the22
licence of NRU beyond 2005.23
Before leaving the topic of NRU, I24
would like to mention to you Chapter 5 of the25
���������
43
supplementary information package entitled "NRU1
Safety Characteristics". This short document2
captures the high degree of redundancy, diversity3
and, as a result, depth of the safety features of4
the reactor with respect to concept, operating5
design, safety systems, mitigation and emergency6
preparedness.7
Having worked extensively in power8
reactors and now with several years of experience9
in research reactors, I can assure you this is a10
safe reactor.11
This slide shows that NRU's12
reliability has been improving over the past few13
years, and the number of reactor trips have been14
decreasing. This is testimony to the performance15
of our employees.16
One of the most notable17
achievements at CRL over the past ten or twelve18
years has been the reduction of radiation doses.19
The data provided in Chapter 8 of the20
supplementary information package indicated21
continuation of the downward trend in collective22
and average worker doses in 2002. For the first23
time in half a century no workers at CRL received24
a whole body dose of 15 milisieverts or higher.25
���������
44
The ALARA practices at CRL are paying off. In the1
two previous years the number of workers with2
doses exceeding 15 milisieverts were 12 and six3
respectively, and in 2002 there were none.4
I am going to show you a slide5
illustrating the dose reduction and another that6
is a composite more broadly based index designed7
to enable management to evaluate, through a single8
parameter, how well CRL is performing in9
industrial and radiological safety.10
This graph shows the collective11
dose reduction at CRL from 1991 to 2002. Please12
focus on the trend rather than the absolute13
values, because there are different numbers of14
employees and of course facilities at a large15
national laboratory and the various types of16
nuclear power plants that are also depicted on the17
figure.18
In the years 1991 to 2000 CRL19
exceeded the WANO reductions in year over year20
reductions by over 50 per cent. This indicates21
effective ALARA practices were implemented.22
The CRL employee safety23
performance index is a composite index comprising24
66 per cent radiological safety parameters and 3425
���������
45
per cent industrial safety parameters. The red1
line indicates an improving overall trend.2
Much progress has been made in3
addressing the CNSC audit of November 2002. AECL4
has formulated action plans and submitted them to5
the CNSC staff 2003 March, and they are already6
being implemented.7
Finally, Madam Chair and Members8
of the Commission, on the subject of licence9
duration, AECL accepts CNSC staff recommendation10
for a licence period of 38 months. This increased11
confidence on the part of CNSC staff will be12
heartening to my staff, who have worked hard,13
developed a sound safety culture and obtained14
tangible performance improvements.15
The CRL team is committed to16
continuous improvement and the laboratories will17
be operated safely, securely and with due18
consideration for the health of employees and19
public and protection of the environment.20
Madam Chair, that concludes my21
presentation. Thank you.22
THE CHAIRPERSON: Are there any23
further comments, Mr. Van Adel, at this time?24
MR. VAN ADEL: No, that is it.25
���������
46
1
03-H2.B2
Oral presentation by CNSC staff3
THE CHAIRPERSON: I would like4
then to turn to CNSC staff for their presentation5
before we open the floor for questions.6
With that, I turn to Mrs. Cait7
Maloney for an oral presentation, as outlined in8
CMD Document 03-H2.B.9
Mrs. Maloney.10
MS MALONEY: Good morning, Madam11
President, Members of the Commission. I am Cait12
Maloney, Director General of the Nuclear Cycle and13
Facilities Regulation.14
With me today are Barclay Howden,15
Director of the Research Facilities Division, and16
Mr. Glenn Martin, CNSC's single point of contact17
for the Chalk River Laboratories.18
CNSC staff has reviewed the19
operation of the Chalk River Laboratories and the20
application from AECL to continue to operate the21
Chalk River Laboratories and has formed a position22
on the application and put forward recommendations23
for your consideration.24
I will now turn the presentation25
���������
47
over to Barclay Howden, who will outline these for1
you.2
MR. HOWDEN: Good morning. My3
name is Barclay Howden.4
Atomic Energy of Canada Limited5
has applied for the renewal of the licence to6
operate the Chalk River Laboratories. CNSC staff7
prepared CMDs 03-H2 and 03-H2.B for the Commission8
on this application.9
This presentation provides a brief10
overview of the key issues of this application and11
CNSC staff's recommendations.12
Our presentation is broken down13
into five sections: updates since Hearing Day 1; a14
revised proposed licence length; a proposed new15
licence condition for NRU; our overall16
conclusions; and our recommendations to the17
Commission.18
This slide shows a summary of CNSC19
staff's ratings of the safety areas as they apply20
to the Chalk River Laboratories site. Changes to21
the ratings since Hearing Day 1 are shown in the22
shaded boxes. I will speak briefly to the changes23
only.24
For performance assurance, AECL25
���������
48
has resolved the issues related to their overall1
quality assurance manual. AECL has also completed2
a formal collective review of the effectiveness of3
its quality assurance program, in response to a4
finding from our November 2002 comprehensive5
audit. AECL has developed a comprehensive plan to6
address remaining deficiencies identified by CNSC7
staff during that same audit.8
This progress is sufficient for9
CNSC staff to upgrade the trend for this program10
to "improving".11
For radiation protection, AECL has12
completed its ALARA study of the Moly-99 facility.13
AECL has performed a significant amount of work to14
correct deficiencies identified in the CNSC staff15
November 2002 audit, and AECL has developed a16
comprehensive plan to address the remaining17
deficiencies.18
The progress on this safety area19
is sufficient for CNSC staff to upgrade the trend20
for this program to "improving".21
For nuclear security, AECL has22
acceptably addressed identified deficiencies such23
that CNSC staff has upgraded the implementation24
rating to "meets requirements".25
���������
49
Previously there was an improving1
trend for this program, and this continues to be2
the case.3
CNSC staff has just completed its4
risk assessment of radioisotope production. This5
assessment focused on the risks posed from the6
handling of the high level radioactive wastes that7
are being produced in the Moly-99 facility and8
will be produced in the new processing facility as9
part of the MAPLE reactor project.10
The primary conclusion from the11
study is that both facilities meet regulatory12
requirements but the new processing facility, when13
in operation, will pose lower risk to the14
operating staff, the public and the environment.15
AECL has undertaken a number of16
actions at the Moly-99 facility that should reduce17
the doses and the releases from the facility to as18
low as reasonably achievable, ALARA.19
CNSC staff is actively using its20
compliance program to make sure that AECL21
continues implementing these actions.22
For decommissioning plans for the23
site, AECL has met the application requirements by24
submitting all the required preliminary25
���������
50
decommissioning plans. The site-wide1
decommissioning plan is currently not acceptable2
to CNSC staff, and AECL has committed to revising3
it by July 31, 2003.4
This issue is part of a broader5
issue related to AECL's integrated plans for6
operation of the site, decommissioning of the site7
and remediation of legacy issues at the site.8
CNSC staff and AECL staff have agreed to a senior9
management meeting to discuss the broader issue10
prior to CNSC staff taking the next regulatory11
step in the process.12
CNSC staff has revised its13
position on the length of the proposed licence and14
now recommends a 38-month period. The basis of15
the recommendation is related to good progress16
made by AECL in the safety areas. As well, AECL17
has formally notified the CNSC of its intent to18
operate NRU beyond 2005.19
Given the significance of this20
issue, CNSC staff recommends that it be considered21
as a licensing issue separate from that of the CRL22
site licence. Further details on the proposed23
licence length have been provided in CMD 03-H2.B.24
To address the issue of NRU25
���������
51
operating being 2005, a licence condition is1
required to restrict NRU operation. The licence2
condition is outlined on this slide.3
CNSC staff concludes that no4
further environmental assessment pursuant to the5
Canadian Environmental Assessment Act is required6
as the conclusions of the 1996 environmental7
assessment and subsequent environmental8
assessments for several projects remain valid for9
the proposed licence renewal.10
AECL is qualified to carry on the11
licensed activities. AECL has made and in the12
opinion of CNSC staff will continue to make13
adequate provision for the protection of the14
environment, the health and safety of persons and15
the maintenance of national security and measures16
required to implement international obligations to17
which Canada has agreed.18
The overall performance of AECL at19
Chalk River during the current licence period is20
meeting requirements, and taking into account21
AECL's commitment to address identified weaknesses22
in certain programs CNSC staff is of the opinion23
that AECL will continue to meet requirements24
during the term of the proposed operating licence.25
���������
52
CNSC staff recommends that:1
The Commission accept CNSC staff's2
assessment that no further environmental3
assessment pursuant to the Canadian Environmental4
Assessment Act is required.5
Approve the issuance of the6
proposed operating licence for a 38-month period,7
to July 31, 2006. This recommendation is outlined8
in detail in Section 3 of CMD 03-H2.B and is not9
in agreement with AECL's original request for a10
licence term of 53 months.11
And delegate to the Director12
General of Nuclear Cycle and Facilities Regulation13
the exercise of authority to determine the14
acceptability of the financial guarantee to be15
proposed on the recommended licence condition16
12.1.17
That concludes my presentation. I18
will go back to Mrs. Maloney.19
MS MALONEY: Thank you, Mr.20
Howden.21
That ends staff's presentation.22
We are available to answer questions you may have23
of us.24
THE CHAIRPERSON: Thank you, Mrs.25
���������
53
Maloney.1
2
03-H2.1B3
Written submission from Atomic Energy of Canada4
Limited5
6
03-H2.A / 03-H2.C7
Written submission from CNSC staff8
THE CHAIRPERSON: I would like to9
note that AECL and the CNSC staff have filed10
written submissions, as outlined in CMD 03-H2.1B11
from AECL and 03-H2.A and 03-H2.C from CNSC staff.12
These are in response to a request from an13
intervenor, Mr. Hendrickson, to release some14
documents.15
Mr. Hendrickson is scheduled to16
present his submission later today.17
With those notes read into the18
record, I would like to now open the floor for19
questions from the Commission Members to either20
the applicant AECL or to CNSC staff.21
Dr. Barnes will start.22
MEMBER BARNES: It may be timely,23
Madam President, to take up that last issue that24
you mentioned, the material requested both by Mr.25
���������
54
Hendrickson and also I think by Mr. Martin, both1
of whom are on our agenda later today.2
The issue of freedom of3
information was raised at Day 1, and we have heard4
a good deal from AECL about limiting the5
environmental legacy and also a concern of a6
number of the local communities of the potential7
for that environmental legacy being a serious8
issue.9
So I was surprised, in looking at10
the material that had been provided to Mr.11
Hendrickson, how much of the material had been12
redacted, in other words blacked out, particularly13
dealing with decommissioning.14
I wonder if I could ask AECL and15
also staff why the extent of this blackening out16
was so extensive, given the fact that you have17
advocated throughout your presentation your strong18
commitment to environmental issues and limiting19
the long-term environmental legacy.20
DR. FEHRENBACH: Thank you,21
Commissioner, for your question. For the record,22
my name is Paul Fehrenbach.23
First of all, I want to reiterate24
that AECL wishes to be as open and transparent as25
���������
55
it can be with respect to our operations. We1
currently do make a significant amount of2
information relating to our activities publicly3
available; for example, through annual reports,4
business plans tabled in Parliament, annual5
reports to the CNSC on a range of our activities6
at Chalk River and other sites, that are in turn7
made available to the public. We also have open8
houses and meetings with the public and local9
governments at our sites.10
At the same time, we do have trade11
secrets, confidential, commercial, technical and12
business information relating to our technologies13
and businesses that, if disclosed, we feel would14
prejudice AECL's competitive position and harm our15
business.16
In addition, some information17
relating to AECL's Canadian sites is sensitive18
from a security standpoint. Accordingly, we must19
find a balance between the desire for openness and20
the necessity for maintaining some information21
that is confidential.22
The Supreme Court of Canada did23
very recently recognize the importance to AECL of24
it being able to maintain the confidentiality of25
���������
56
certain information in a case that had been1
brought by the Sierra Club.2
With respect to process, when3
government departments or agencies such as the4
CNSC receive access to information requests that5
relate to AECL information, and AECL is in turn6
asked for its input concerning the suitability for7
release, AECL staff carefully review the8
information. If the case for exemption must be9
made, it can be exempted from release under the10
Act for confidentiality or business, commercial11
reasons; i.e., under section 20 of that Act.12
AECL also makes recommendations to13
the government department with respect to any14
information that should be withheld on security15
grounds. But it is open to the requester to seek16
a review if they believe that more information is17
releasable.18
In the specific case of the19
preliminary decommissioning plans, a significant20
amount of information in those documents has been21
released. AECL's staff reviewed in detail a large22
number of the documents requested by the23
intervenors, determined what information in them24
should be exempted from release on confidentiality25
���������
57
grounds, and identified information that should be1
withheld on security grounds.2
In response to the complaint made3
by the requester, which AECL was made aware of4
only recently, we have again reviewed these5
documents and are making further submissions on6
exemption of information, as is provided for under7
the Access to Information Act.8
In short, we intend to comply9
fully with the provisions of the Access to10
Information Act.11
MEMBER BARNES: Is there any12
response from staff?13
MR. HOWDEN: Barclay Howden14
speaking.15
With respect to the information16
requested, there was a number of sets of17
information: decommissioning information;18
regulatory gap analysis; environmental effects19
review; and information on the risks of handling20
Moly-99 wastes.21
The last three sets were released22
with very little redaction done.23
With respect to the24
decommissioning information, in particular the25
���������
58
preliminary decommissioning plans, the information1
that was released was the same as that that was2
released to a requester in August 2002 under an3
Access to Information request.4
What has happened with regard to5
that request is that there was a complaint made to6
the Information Commissioner that came back to the7
CNSC. We looked at the complaint, and we agreed8
with the complaint that more information could9
have been released. We went through the10
documentation and assessed that a significant11
amount of it could have been released.12
However, under the process of13
Access to Information, we then had to send that14
information to AECL as part of the third party15
review. My understanding is that that the process16
is at that point, and AECL has been discussing17
other issues with the Information Commissioner.18
That is the status of that19
information right now.20
MEMBER BARNES: I can see the21
proprietary nature of a lot of the business that22
AECL is in, certainly in technical aspects. I was23
surprised, when looking at the decommissioning24
aspects here, with specific reference to the site,25
���������
59
that so much of the material was essentially being1
denied public information.2
Again, we could spend a lot of3
time going through the details of this, Madam4
President, but I don't think we need to.5
One, for example, in the document6
on preliminary decommissioning plan RC1933, would7
be on planning envelopes or the technical8
approach. The conceptual approach is that each9
planning envelope would be broken down into10
several work packages, and all of this is blacked11
out.12
Cost estimates, and so on, I fail13
to see why this is proprietary in a business sense14
for a decommissioning phase of this kind of15
facility.16
DR. FEHRENBACH: Paul Fehrenbach17
again.18
I think some of the information19
you refer to of course is information that would20
be used by us in assessing contracts which we will21
be seeking to perform that work. We feel it would22
compromise the cost effectiveness of our23
contracting process if our own internal cost24
estimates were made public ahead of time before we25
���������
60
received proposals and estimates from prospective1
contractors.2
MEMBER BARNES: Also on things3
like the operational history, going back to the4
1950s. Whole sections of this are taken out.5
DR. FEHRENBACH: In this case I6
think we are getting into potential security7
information, and I really don't want to elaborate8
further. It has to do with locations of9
particular materials on site.10
MEMBER BARNES: In the case of the11
public, in the case of the officials from the12
communities that we will hear about later, as you13
know from having read the material nearly all of14
them are in support but they express one concern,15
and that is the environmental quality of the site16
as it is eventually cleaned up and is part of the17
decommissioning plan.18
You must agree that it is very19
hard for communities and the public and other20
interest groups to have a clear understanding of21
the scope and capabilities of the decommissioning22
aspects when so much of the information that they23
have requested is simply not available to them.24
DR. FEHRENBACH: I can't really25
���������
61
agree with that statement, Commissioner. As I1
said earlier, we try our best to be open and make2
available necessary information for evaluation of3
our environmental performance.4
As you will see in the multitude5
of information that has been released, both in the6
supplementary information that was provided to the7
Commission on releases from the site and the8
monitoring programs, there is quite adequate9
information on environmental stewardship for10
members of the public to form their own judgments11
on the quality of our environmental performance.12
MEMBER BARNES: Does staff have13
any further comment? We may revisit this later in14
the meeting.15
MR. HOWDEN: Yes. Barclay Howden16
speaking.17
The Access to Information issue is18
with the Information Commissioner. What I would19
like to say is that when we revisited the20
information after the complaint, in hindsight we21
looked at it and basically took a very22
conservative review of the information originally23
based on post 9/11 considerations.24
However, what we did this time25
���������
62
around is there is a couple of exemptions under1
the Act that can be used. One is commercial2
sensitive and the other is security.3
We can't really judge the4
commercial sensitivity. We focused on the5
security aspects and sat down with project6
officers, decommissioning specialists and security7
specialists and our Access to Information Co-8
ordinator and went through the document primarily9
focusing on security.10
We did come to the conclusion that11
more information could be released. That is where12
we stand today. Again, it is back with the13
Information Commissioner.14
MS MALONEY: It is Cait Maloney,15
if I might just add to that.16
Mr. Van Adel in his presentation17
made reference to the fact that there is a process18
going on in which AECL and Natural Resources19
Canada are entering into discussions on20
remediation of the entire AECL site.21
CNSC will be involved in those22
discussions to the extent that we will be23
providing our expectations on the regulatory24
aspects of that. Obviously one of the areas that25
���������
63
we will be looking at is the amount of information1
that is made available to the public. So we will2
be working on that with the licensee.3
THE CHAIRPERSON: Dr. McDill,4
would you have any questions at this time?5
MEMBER McDILL: Thank you. I6
would like to go back to some comments made early7
in the presentation with respect to safety8
culture.9
I heard the quote "wilful10
violations are not tolerated".11
How do you distinguish between a12
wilful violation and a non-reportable event?13
Perhaps you elaborate on that.14
MR. LAFRENIÈRE: Paul Lafrenière.15
We have procedures in place and codes of conduct.16
We have a process whereby if we have a17
transgression, first the individual is corrected.18
It is brought to his attention through management19
supervision.20
The second step -- and it is a21
graduated process -- would be a letter on file.22
The third step, at that point we23
would probably be involving human resources and24
the union to say that this process is becoming25
���������
64
much more serious. After that the employee can be1
sent home or there can be more permanent action2
taken. So it is a graduated process.3
I can point out that we have4
several examples of that over the past few years.5
MEMBER McDILL: Do you find this6
is at odds with the desire to have employees7
report events of a safety nature?8
MR. LAFRENIÈRE: That is an9
excellent question. Let's be very clear that we10
encourage the reporting. We do not have a process11
that is retaliatory. In other words, we ensure12
that we are learning and we make sure that the13
employees feel that they are learning.14
I think our recent results in the15
employee job satisfaction survey indicate very16
clearly that we are on the right track. So it is17
employee morale, motivation and comfortableness18
with the milieu. I think in that area the results19
speak for themselves.20
That is a management21
responsibility.22
I would point out that this23
process goes to the ultimate level in very rare24
instances. Let's be very clear on that.25
���������
65
THE CHAIRPERSON: Dr. Giroux?1
MEMBER GIROUX: I have a few2
questions which I extract from the written3
document we received, the complementary document,4
and also to some of the presentations you made5
today.6
The first one is a bit technical.7
Discussing the fissile solution storage tank and8
criticality, my question is: How far are you from9
criticality?10
I know that is a major factor.11
How do you measure the distance to criticality?12
MR. LAFRENIÈRE: First of all, the13
FISST tank is safe. Let's be very clear about14
this.15
The criticality hazard has been16
considered, and there are design issues,17
engineered barriers and operational procedures18
around this.19
Just to give you a brief idea, we20
are talking in the Moly production facility we21
have ten barriers or administrative controls and22
inside the FISST tank, around the FISST tank23
itself, we have six barriers or administrative24
controls. This is independent of the design25
���������
66
itself.1
On the issue of criticality, the2
best way to explain it is we are currently3
applying for a limit of 7.6 grams per litre. For4
the uranium, the criticality limit that is placed5
on it, and conservatively so, is 11.6 grams per6
litre. Essentially, the overall process is a7
protection by concentration, or safe by8
concentration method. We control the9
concentration, and we have a process that ensures10
that with sufficient redundance.11
I hope that provides the answer.12
MEMBER GIROUX: I think it does.13
As a supplementary on that, you say you applied14
for 7.6. If I remember correctly, you have been15
applying in the recent past for increased limits.16
What is the present level or17
concentration of uranium?18
MR. LAFRENIÈRE: The current level19
or limit is 7.3, and we are very close to that20
limit today.21
MEMBER GIROUX: Thank you.22
The other question concerns the23
Ottawa River survey. I have seen Dr. Barbeau's24
report that there has been a survey done in 199925
���������
67
and a new one in 2001. That is the one he reports1
on.2
My question is: How far back does3
your monitoring go? What happened before 1999?4
Did you have monitoring of the same type?5
MR. LAFRENIÈRE: The monitoring6
goes back many, many years, but for the details I7
would like to ask Ray Lambert, our radiation8
protection and environmental specialist to answer.9
Ray.10
MR. LAMBERT: My name is Ray11
Lambert, AECL.12
AECL has been doing environmental13
monitoring for as long as I have been in the14
company, back in 1979. I can't off the top of my15
head think of a period before 1979 that it was not16
doing it. We have been doing environmental17
monitoring of the area and of the effects of Chalk18
River Laboratories for in excess of 20, 30 years.19
I don't have the results with me.20
We have done the independent21
monitoring with Laval University for two years,22
and we plan to make use of them again in the23
future.24
MEMBER GIROUX: Has that25
���������
68
monitoring been on the same parameters as what has1
been done -- what you did before 1999, was it2
looking at the same parameters as what has been3
done since then?4
MR. LAFRENIÈRE: Perhaps I could5
clarify. With Dr. Barbeau at the University of6
Laval, this was independent monitoring to provide7
additional assurances that our existing program8
was measuring what it was supposed to be measuring9
and providing the proper results.10
THE CHAIRPERSON: I wonder,11
though, Dr. Giroux, if that really answered the12
question.13
My understanding of the question -14
- and please correct me if I am wrong -- is if15
there was a set of parameters set out at a certain16
time period by AECL and you have continued to17
follow those parameters, that framework of18
monitoring, such that one would have history and19
one would have a sense of comparison data rather20
than necessarily an explanation of Laval.21
MR. LAFRENIÈRE: We do have trends22
going back many, many years, back to the 1960s,23
from the environmental monitoring program. It was24
provided in the supplementary information package.25
���������
69
So let's be very clear on that1
point.2
The information on the3
radionuclides such as tritium, strontium, et4
cetera, are monitored from a number of locations.5
We have the results going back to the 1960s. As6
well, in the environmental monitoring we do7
sediment monitoring, and the results are there to8
confirm these measured results.9
MEMBER GIROUX: I will now address10
your written presentation document on the ALARA11
process, which I found interesting to read. You12
mentioned that you take into account social and13
economic factors, and that is normally part of the14
ALARA process, but you are not very specific on15
how you treat them.16
Could you tell us what factors you17
have identified as being social and economic and18
whether you have actually included them in your19
analysis.20
MR. LAFRENIÈRE: That is a good21
question.22
Numerous ALARA analyses have been23
done. If we look at the recent analysis on the24
Moly production facility, which has been presented25
���������
70
to the CNSC and on which they have expressed1
satisfaction, what we have done in that is2
essentially we are looking not only at the dose3
and the public impact, the impact on the workers,4
as well we are making a comparison with the new5
production facility, the new MAPLE project under6
way.7
What we have done is essentially a8
comparison in terms of environmental impact,9
public impact and worker impact. There are many10
financial considerations that are included. So it11
is health and financial.12
If I may, we have not gone into13
the details on the benefit side of this ALARA14
analysis, and perhaps that is something that needs15
to be done.16
MEMBER GIROUX: Do you mean you17
have not reported on them but you have done them,18
or you have not done the analysis?19
MR. LAFRENIÈRE: The ALARA20
analysis contains all this information which I21
have just mentioned. So they are reported on in22
detail.23
MEMBER GIROUX: That is in the24
detailed version which we don't have.25
���������
71
MR. LAFRENIÈRE: That is correct.1
MEMBER GIROUX: Thank you.2
THE CHAIRPERSON: Dr. Dosman?3
MEMBER DOSMAN: Thank you, Madam4
Chair.5
My first question is to AECL. In6
your document CRL-00580-130-001, on page 51, with7
regard to the ratings on performance assurance8
implementation -- and in asking the question I9
would also recognize the steps AECL has taken and10
the improvements you have effected.11
I would like to ask for more12
clarification on the statement on 6.3.6(a) and13
also (b) and subsequently, where you state that14
the AECL statement "is not true and not based on15
objective evidence".16
I am wondering if you would be17
able to clarify somewhat on that statement.18
And then, Madam Chair, I might ask19
CNSC staff for a reply.20
It is up to AECL to reply.21
MR. LAFRENIÈRE: I will answer the22
question.23
I would like to point out that24
AECL has achieved an improved trending in the25
���������
72
performance assurance area on the basis of1
improvements to the management system, as well as2
a detailed plan and commitment to achieve them, as3
well as the progress that has been alluded to by4
staff.5
On the specific issues, there are6
essentially close to, I would say, ten process7
areas. An example would be the modification8
process in a nuclear facility.9
One of the issues raised -- and I10
am just giving you an example -- is that the11
procedure was not properly documented to the12
detail that the CNSC staff expected.13
In that area, we accepted that and14
we said we would proceed to improve that area.15
There were other examples, and16
this was generalized to apply across the site, in17
which case we did have some issues with some18
facilities. Many of the facilities were in19
accordance.20
I think our point here is that we21
accept all the specifics and they are being dealt22
with. The generalization we had some difficulty23
with.24
MEMBER DOSMAN: The statement on25
���������
73
6.3.6(a) that "was not based on objective1
evidence", would you be willing to comment on that2
statement?3
MR. LAFRENIÈRE: I would like to4
ask our QA manager Siv Sivarajan to respond,5
please.6
MR. SIVARAJAN: Hello. I am Siv7
Sivarajan, Process Manager, Nuclear Safety and8
Quality Assurance.9
Just to expand on what Paul10
Lafrenière was saying, certain facilities and11
certain processes were audited as part of the CNSC12
audit. While they have objective evidence that13
they have scrutinized and arrived at some findings14
in terms of saying that these are the deficiencies15
they have noted, we do agree that that is true.16
Generalizing it right across the17
site for facilities where it was not audited, we18
believe that is not true. That is the intent that19
was tried to be conveyed in 6.3.6(a).20
MEMBER DOSMAN: Madam Chair, if I21
might, I think I am referring, in addition to the22
substance of the question, to the somewhat strong23
language. I am wondering if I might ask CNSC24
staff for their interpretation and their comments25
���������
74
on this issue.1
MR. HOWDEN: Barclay Howden2
speaking.3
In terms of these findings, the4
audit was very comprehensive. We were there for5
two weeks, looked at about five programs and had6
many staff there. However, the site is very7
complex and large, and we didn't look at8
everything.9
However, when we find findings in10
a few places, we start to roll them together.11
If this is not true across the12
whole site, that is a good thing. However, what13
we expect is that, based on our findings, AECL not14
just address the finding in terms of in a certain15
facility or area; they should go out and confirm16
that it is either an isolated finding or it is17
widespread. That is our expectations of follow-18
up.19
In our discussions with AECL, they20
have indicated they are going to do that. The21
strong language, it doesn't cause us too much22
grief. I think we have an understanding of what23
the next steps are, and I think they are24
appropriate to deal with these issues or determine25
���������
75
that they are not as broad as they may be.1
MEMBER DOSMAN: If I might, Madam2
Chair, are you saying, Mr. Howden, that the3
recommendations made by AECL were indeed based on4
objective evidence then?5
MR. HOWDEN: Do you mean the6
directives issued by CNSC staff?7
MEMBER DOSMAN: Yes.8
MR. HOWDEN: Yes, we do.9
MEMBER DOSMAN: I am sorry to10
prolong this, but then would you disagree with the11
statement in 6.3.6(a) that these comments were not12
based on objective evidence?13
MR. HOWDEN: Yes, we would14
disagree with that.15
THE CHAIRPERSON: Mr. Graham.16
MEMBER GRAHAM: Thank you. The17
first question is a follow-up to Dr. Giroux's18
question with regard to the fissile solution19
storage tanks, and as a lay person have you20
clarify something.21
In the report it says that22
uncertainties exist. The next proposed increase23
would permit about 30 more weeks of storage24
capacity, and then it goes on and if you read25
���������
76
through that whole page it talks with regard to1
small leaks have been developed and reviewed2
regularly by CNSC. Although a large leak is very3
unlikely, the current strategy needs to be4
examined to make sure that it can be extended, if5
required.6
I would like to hear from AECL7
worst case scenario, if there was a large leak,8
how that can be contained and how it can be9
monitored. I guess monitored first and then10
contained.11
MR. LAFRENIÈRE: First of all,12
FISST is a double-walled, stainless steel tank in13
a concrete vault, seismically qualified. I think14
we can put that part of the issue to rest.15
There is leak detection and there16
are pumps available to ensurer that if a leak did17
develop, we are able to deal with it; pump it back18
into a tank, as required.19
In that case, we would cement it.20
We would pump it back to the Moly production21
facility and cement it. So we do have22
contingencies around it.23
In terms of the design, it is to24
modern standards. It is a very good safety case.25
���������
77
All the monitoring that is1
required to back up the safety case is available,2
as well as the contingencies.3
MEMBER GRAHAM: Then if I4
understand it, if there was a major leak, it would5
be pumped back into the tank but solidified,6
cemented. Is that what you are saying?7
MR. LAFRENIÈRE: No. What would8
happen is that it would be pumped back to the9
Moly-99 production facility.10
MEMBER GRAHAM: My next question11
is inspection. I could be wrong on this, but my12
understanding is that that tank facility was built13
in 1986. Is that correct?14
Or the Moly unit was built in15
1986?16
MR. LAFRENIÈRE: If I may, I would17
like to ask Paul Tonner. I believe he is here18
today.19
MR. TONNER: The FISST tank is20
1986.21
THE CHAIRPERSON: For the record,22
the tank was built in 1986?23
MR. TONNER: Yes.24
THE CHAIRPERSON: The FISST tank?25
���������
78
MR. TONNER: Yes.1
THE CHAIRPERSON: Yes, for the2
record.3
MEMBER GRAHAM: Then my question4
is: If it was built in 1986, what is the5
inspection procedure? How often is it inspected6
with regard to deterioration of metals, and so on7
and so forth?8
MR. LAFRENIÈRE: Again I would9
refer to Mr. Paul Tonner.10
THE CHAIRPERSON: Would you please11
approach the microphone.12
MR. TONNER: Thank you. My name13
is Paul Tonner. I am the Manager of the Moly-9914
production facility.15
The FISST tank in the reports that16
we have has shown no signs of degradation. As17
Paul Lafrenière mentioned, it is a double-walled18
stainless steel tank with leak detection between19
the two stainless steel cylinders, and also leak20
detection in the concrete vault which the tank21
sits in.22
MEMBER GRAHAM: A question then:23
The leaks, the small leaks that have been detected24
are not in the tank. They are around the25
���������
79
couplings and around other areas? Or are there1
starting to be fractures shown in the tank?2
Where are the small leaks that3
have been detected?4
MR. TONNER: The material that was5
submitted indicated that in the unlikely event6
that a small leak occurred, it could be detected.7
There have been no small leaks.8
MEMBER GRAHAM: Thank you.9
I have two other questions that10
don't relate to that. May I have one?11
THE CHAIRPERSON: The next round.12
MEMBER GRAHAM: Thank you.13
THE CHAIRPERSON: My question is14
to CNSC staff and also then to AECL with regard to15
the request for licence length.16
It is very unusual for the17
Commission to receive varying numbers going back18
and forth on licence length requests. There is19
usually a reason for a licence length request.20
For us to see varying numbers is quite unusual.21
So I think it is important for us22
to know exactly the justification for the licence23
length.24
Perhaps staff could start with25
���������
80
what you are proposing now; why you proposed1
something else before; and what it has to do with2
the procedure I believe the staff follow with3
regard to licence length request.4
If we could start out with that,5
we will go the applicant after.6
MR. HOWDEN: Barclay Howden7
speaking.8
Right now we are recommending 389
months. Previously it was 31 months. So it is a10
change of seven months.11
The main reasons are that we have12
seen progress in the safety areas in terms of13
improving trends, and that is based on actual14
progress being made by AECL on the deficiencies15
that we have noted, as well as putting together16
comprehensive plans to address the remaining17
deficiencies.18
We have seen progress, so I think19
that is one positive thing.20
In looking at the progress and in21
looking at the management system that AECL has in22
place and the explicit commitments they have made23
to upgrade it to meet the N286 standard gives us a24
level of assurance that the site will continue to25
���������
81
be operated safely for a longer period of time.1
One of the things we are looking2
at is the changes that are required to the3
programs are exactly that: they are programmatic4
improvements that have broad implications across5
individual programs but also crossing between6
programs. Therefore, in our view they need to be7
developed systematically. To do that takes time.8
At the same time, we want the9
changes to be made and implemented by AECL and put10
through their management cycle to determine that11
they are indeed effective. We can then come in,12
review the programs and audit the programs.13
As well, we look back at the14
operating results at the facility over the past15
three licensing periods. We didn't mention the16
last two in our submission. Basically, the doses17
remain low and they are dropping. Emissions18
remain low. The failures that might concern you,19
like serious processing failures, are not20
occurring. The safety systems that govern the21
operation of their facilities, especially the NRU22
reactor, are meeting reliability targets.23
Basically the safety envelopes24
that are defined in the facility authorizations25
���������
82
are being respected, and we don't see any erosion1
in those safety margins.2
THE CHAIRPERSON: When we look at3
the overall ratings -- and just acknowledging for4
those of you that may or may not be aware of the5
rating system, it is relatively new at the CNSC.6
Looking at the rating system that7
they have used over the various areas, the fact8
that the applicant did not score at a "B" level in9
some areas, meaning "meets requirements now", with10
due consideration for the plans and the program11
going forward, what role did that bear in your12
recommendations for licence length?13
MR. HOWDEN: What we did was when14
we looked at these facilities that are rated as15
"below requirements", it is because they did not16
meet the required standards.17
However, we also have to18
acknowledge that a lack of full compliance does19
not equate to an immediate or potential breakdown20
of safety. We see that they are still in a range21
where there is a low risk of breakdown in programs22
that could lead to problems.23
We also view that because AECL is24
aiming for a very high standard for their25
���������
83
management system, it means that we will get1
enhanced assurance that they will be able to2
operate the site safely for a long time into the3
future.4
Our view is that we simply cannot5
rely on that assurance alone until the management6
system is up to N286. However, it doesn't mean7
that there are immediate safety problems. What we8
have done is we have continued to maintain an9
enhanced regulatory oversight to continue to10
satisfy ourselves that the site is being operated11
safely.12
THE CHAIRPERSON: My question in13
terms of the ratings is to me particularly14
important because we are talking about site-wide15
programs that affect in fact even licences that we16
are talking about separately. That is why I am17
focusing on site-wide ratings as well.18
How will the Commission be aware19
of this progress?20
I think we have talked in the past21
about interim reporting that may or may not be22
suitable; that you may decide to make a23
recommendation or not, which I may assure the24
audience has nothing to do with binding the25
���������
84
Commission's decision.1
I am aware that there is progress.2
I am aware that there is a change. I am aware3
that there has been recent progress in putting in4
new processes and new procedures.5
Sitting here as the Commission,6
how will the Commission be aware of this, aware of7
progress and maintenance and sustainability of8
progress?9
MR. HOWDEN: Barclay Howden10
speaking.11
In terms of progress, we have12
committed to a mid-term report to the Commission,13
which would occur in 19 months if a 38-month14
licence was issued by the Commission. So you15
would get an update of where things stood at that16
particular time.17
Also, in terms of our compliance18
activities, if there was a case of where there was19
a deterioration in performance where we wanted to20
take enforcement action to the point where there21
might be an order, that has to be referred to the22
Commission. So you would be aware of it there.23
As well, we could propose licence24
conditions that the Commission could impose. So25
���������
85
you would be aware there.1
That is if there is degrading2
performance. If performance continues to improve3
as expected, in terms of the Commission you would4
be informed at 19 months.5
Also, if any significant actions6
come up, we have the option through significant7
development reports to the Commission on a monthly8
basis.9
THE CHAIRPERSON: Thank you.10
This question is to the licensee.11
You proposed a longer licence period. You now12
agree with the staff.13
Could you give me, and the rest of14
the Commission Members, a justification for your15
original request and why you now think 38 months16
is suitable.17
MR. LAFRENIÈRE: Yes, in two18
parts.19
First, I would like to point out20
there are four things that are critical here.21
One is we have done a root cause22
analysis of the CNSC directives, observations.23
That was input into our action plan which has been24
submitted to the CNSC. We are acting on that. We25
���������
86
have progressed on it.1
The second point is that we have2
our nuclear site management system which has shown3
great progress and great promise, and we are4
committed to improving it.5
The other element, of course, is6
the progress made and our explicit commitments.7
With that, I would like Dr.8
Fehrenbach to comment.9
DR. FEHRENBACH: Thank you. Paul10
Fehrenbach, for the record.11
As noted, we feel that our12
performance has been improving; has been very good13
and is improving. In those areas where the CNSC14
staff have judged there is further improvement15
required, as Paul just noted, we have definite16
actions in place to address that.17
So overall we felt initially that18
our request for a 60-month licence period was19
reasonable.20
Part of the reason for that, of21
course, is to manage our costs, our licensing22
costs, and specifically trying to separate in time23
the licensing activities for particular24
facilities.25
���������
87
However, at the end of the last1
Day 1 hearing before we left, I assured the2
Commission that when we came back on Day 2 we3
would agree with the staff on the length of4
licence.5
I am pleased to say that we have6
agreed that a 38-month licence will go a long way7
to meeting our requirements as well as meeting the8
staff requirements. That is why we agree with a9
38-month licence period.10
THE CHAIRPERSON: Thank you. We11
will now start with round two and start now with12
Mr. Graham.13
MEMBER GRAHAM: Thank you. I have14
a question with regard to radiation protection15
program as indicated on your graph on page 18 of16
your presentation this morning.17
I gather from that graph that the18
CRL is about two times greater than the average19
for CANDU. And the average for CANDU, is that the20
average for CANDU reactors at other nuclear sites?21
That question is to CNSC staff.22
MR. HOWDEN: Barclay Howden23
speaking. We didn't prepare that information, and24
I am not sure that we are prepared to answer that25
���������
88
question.1
MEMBER GRAHAM: Thank you. I will2
ask AECL then.3
MR. LAFRENIÈRE: Yes, thank you.4
Paul Lafrenière.5
This graph is part of our6
benchmarking program. We have done extensive7
benchmarking in many, many areas, particularly in8
the health and safety areas. What you have seen9
is a comparison with the nuclear power plant10
industry as a whole.11
As you may realize, the World12
Association of Nuclear Operators back in the early13
1980s established long-term 20-year goals on dose14
reduction targets. What we have done is similar.15
We have tracked not only their progress but our16
own. Because of the difference in the types of17
facilities and the workforce, et cetera, we can18
monitor or compare ourselves on the rate of19
reduction. We take into account that if a20
facility is shut down, we ensure that we compare21
apples with apples.22
What you see here is the utility23
industry has managed a 5 per cent per year24
reduction over the long term; we have managed a25
���������
89
7.5 per cent reduction per year over the long1
term.2
MEMBER GRAHAM: Two questions.3
Your comparison with theirs only goes to the year4
2000 where yours goes to mid-2002. Has the trend5
continued downward with regard to the other three6
that only go to 2000?7
Is the gap still broader or is the8
gap narrowing?9
MR. LAFRENIÈRE: For those10
particular details I will ask Mr. Ray Lambert to11
respond.12
Ray.13
MR. LAMBERT: Thank you. For the14
record, my name is Ray Lambert.15
In response to your question, the16
information for the average collective dose for17
the various power reactors was taken from an ISOE18
annual report that was published in 2000. I have19
not yet found the equivalent report published in20
2001 or 2002, so I can't answer how the facilities21
have performed in those two years.22
MEMBER GRAHAM: Then one other23
question, and I won't belabour it.24
This goes to early 2002 for AECL.25
���������
90
Is the trend continuing down since that or not?1
Or is it remaining static?2
MR. LAMBERT: We have only had a3
few months into 2003 at the moment, so it is too4
early to make a statement as to how the trend is5
proceeding. Initial data looks positive that we6
are continuing to come down, but it is still too7
early in the calendar year.8
MR. LAFRENIÈRE: I would add that9
I was looking at the data last night, and the10
trend is coming down. Again, we have to run our11
course over a year to make sure.12
MEMBER GRAHAM: Thank you. I have13
just one other question, and it is perhaps just to14
clarify for a lay person.15
You talk about non-reportable16
events, and you say that you had 142 compared to I17
think it was 54 back in 1998, or something to that18
effect. Are there more events happening? I know19
it is good to have them reported, but are there20
more things happening than what there was in 1998,21
or is it just that the trend -- it is kind of hard22
to understand with the tripling of the amount.23
MR. LAFRENIÈRE: Thank you.24
First, the reportable unplanned25
���������
91
events are investigated thoroughly by AECL to1
determine their causable factors and to ensure2
that any remedial actions are taken to prevent3
reoccurrence. This information is shared with all4
managers and staff at the other nuclear facilities5
and the support programs so that the lessons6
learned are applied to all our operations.7
Second, the number of reportable8
events in 2002, what you will notice is that9
essentially the ratio of reportable events to10
total events has decreased dramatically, by a11
factor of four, over the last five years.12
So in the past, if we went back to13
say 1998, the ratio of reportable events to total14
events was about 25 to 30 per cent. It is now15
under 10 per cent, I believe, 7 or 8 per cent.16
What this indicates is the average17
significance of events is decreasing. So what we18
are doing is we are encouraging more reporting.19
As we know, culture follows behaviour. So the20
behaviour is there; culture is coming.21
MEMBER GRAHAM: Thank you. So the22
trend is downward and that is what I was23
questioning.24
Does CNSC want to comment on that?25
���������
92
MR. HOWDEN: Barclay Howden1
speaking.2
In terms of the reportable events,3
they are going down, which is a good sign and we4
have not seen any specific negative trends5
identified; that is, the same thing cropping up.6
Also, AECL uses an enhanced human7
performance evaluation system for investigating8
these events, which is acceptable to us.9
In terms of the non-reportable10
events, we have not looked at them specifically11
because they are non-reportable. However, what we12
have seen is that this is part of their OPEX,13
their operating experience program. What we see14
is that when that type of program is working well,15
it is a key component of safety culture.16
So we see it as a positive sign on17
safety culture, but we cannot give you any18
specific assessment on the non-reportable events19
themselves.20
THE CHAIRPERSON: Dr. Dosman.21
MEMBER DOSMAN: Thank you, Madam22
Chair.23
My question is for Mr. Van Adel.24
Mr. Van Adel, I am coming back to25
���������
93
page 52 on the document by AECL and again item1
6.3.6(b). There is some improvement in some2
licence facilities. It indicates that some of the3
licence-listed facilities have not yet completed4
their 2001 program reviews.5
I am not asking for comments6
specifically but rather more generally.7
Recognizing that culture is very difficult to8
nudge even a small amount and recognizing the9
complexity of the site, how engaged is your board10
in setting the tone for culture on the site? And11
recognizing that standards are changing, how12
completely does your board engage and champion13
safety culture in your organization?14
MR. VAN ADEL: We have the Science15
and Technology Review Committee of the board,16
which is a committee of the board which focuses17
precisely on safety and environment, as well as18
reviewing the technology aspects of AECL's19
activities, with a view to giving the board at20
large an expert opinion on these areas.21
The board is chaired by an eminent22
person, a scientist in his own right, that23
committee of the board, and populated with people24
who have relevant experience from the science25
���������
94
community.1
We have been very satisfied that2
that committee reviews not only in detail the3
quarterly and semi-annual reports it receives from4
the Safety Review Committee but also actions5
those, encourages management to action them where6
there are deficiencies.7
As well, the Chief Engineer, Basma8
Shalaby, reviews those activities and reports to9
me directly and gives me a briefing from time to10
time, not only on the content of the reports that11
are coming and the activities of the various12
committees but also raises anything of concern13
that she has with respect to her independent view14
and therefore the possibility perhaps of her15
wishing to influence things that she feels that16
may be -- if she is not being listened to, for17
example, which happens very rarely given the18
nature of Basma's personality and her19
responsibilities.20
Yes, the board is very engaged.21
You saw the vision statement which we put out, the22
mandate vision statement and the values which have23
been rolled out into the company. Those have been24
driven into the company not only by myself but25
���������
95
they were approved by the board. We report at1
every board meeting, not just at the committee, on2
our progress towards changing the culture.3
Frankly, I think that we have made4
dramatic advances in AECL in the last two years in5
terms of the culture, the culture of openness,6
attention to safety.7
We started off taking three of the8
values out of that whole chain to say these are9
the most important that we need to focus on10
immediately. They were customer satisfaction,11
quality and safety.12
I believe that employees of the13
company understand that I care about these things,14
that the executive does and that the board does.15
As a consequence of that, there is increased16
attention.17
In fact, in my remarks yesterday18
to all staff, I literally myself, and this time my19
executive team, spent a two-hour session with our20
entire staff. And we just did another one within21
two months previous to that. We talked about22
these values and we in particular emphasized the23
safety aspects.24
So I think it is working very25
���������
96
well, and I think that the board is extremely1
engaged.2
In addition to that, there is an3
advisory committee to the board made up of eminent4
scientists. That committee is in place, and it5
provides independent advice to the Science and6
Technology Committee of the board on matters7
relating to Chalk River's activity, on the8
research R&D programs. Generally, it represents a9
third party opinion from independent people.10
That also is an area that is able11
to make comments on these reports as they come12
forward. So I am very satisfied that the board is13
engaged.14
MEMBER DOSMAN: Thank you.15
THE CHAIRPERSON: With that, I16
would like to take a break. We will be resuming17
this line of questioning after lunch.18
I have 12:45. We will be back19
here in one hour. I would like your co-operation20
to ensure that you are in your seats, because we21
will be starting in exactly one hour.22
Thank you very much.23
--- Upon recessing at 12:45 p.m.24
--- Upon resuming at 1:46 p.m.25
���������
97
MR. LEBLANC: While you are taking1
your seats, just a reminder that there are2
headphones for translation, and they can also be3
used if you have difficulty hearing the4
proceedings. Turn them to the language of your5
choice, and you may be in a position to hear a6
little better.7
THE CHAIRPERSON: Ladies and8
gentlemen, we will resume Hearing Day Two on the9
matter of AECL.10
We are still in round two of11
questioning.12
Dr. Giroux.13
MEMBER GIROUX: Thank you. I have14
a question first for AECL.15
We have heard several references16
by you and by staff for this hearing, and for17
preceding hearings also, about the lack of18
compliance with the CSA Standard N286. It seems19
to me that this standard has been in force for a20
number of years and that AECL appears to be slow21
in complying with the standard.22
My question is: Is there a23
reluctance on your part or a disagreement with24
what the standard says? What is the reason for25
���������
98
the delay in complying with the standard?1
MR. LAFRENIÈRE: The N286 standard2
was designed for the nuclear power plants. It was3
not created originally for other types of nuclear4
facilities. That is just a clarification.5
In my experience working in the6
nuclear power plants, there was a lot of attention7
applied to the N286. It became a priority8
starting in the 1980s and 1990s, and there was9
continuous attention to it.10
I can only speak about AECL and11
the time period that I have been there since 1998.12
From my observations, the main issue was that AECL13
was more based on a job-specific or a person-14
dependent method of ensuring quality. In other15
words, they put heavy emphasis on on-the-job16
training and on the individuals.17
I would say in 1990s it became18
very clear that the 286 standard would be applied19
fully, or as much as practicable -- I will use20
that word -- to the other nuclear facilities; for21
example, on a lab site.22
So there has been an evolution in23
the thinking. Again, with the tradition of CRL24
going back 50 years, it was more a military-based25
���������
99
operation. It was more based on, as I would point1
out, on-the-job training and on individuals.2
The transition to a procedure3
based -- and I think I can qualify the N286 code4
system as a procedure-based approach. This has5
been occurring. I would say in the past ten years6
it has been emphasized.7
I can't go any deeper into detail8
with the past.9
The issue has been -- we have to10
interpret N286 for our facilities, and the CNSC11
has raised a number of specific observations and12
has provided a set of directives. We have13
performed a root cause on these directives.14
The major issue that we found on15
numerous issues was related to procedural16
adherence. The issue of procedural adherence is17
related to first of all having documented18
procedures, good quality procedures, combined with19
the culture part of it, the procedural adherence20
aspect.21
All I can say is there is an22
historical issue here, and there is also a23
technical issue here. We have done the root24
cause, and we have committed to solving that25
���������
100
problem.1
MEMBER GIROUX: In your2
presentation this morning when you showed us the3
pyramid for quality management, the second and4
third levels from the top referred to N286. So5
the implication is that you recognize it as a6
particular standard.7
The question is: When you come8
around for the next licence, if the proposal is9
accepted -- that is going to be after 38 months --10
can we expect to have full compliance with N286?11
MR. LAFRENIÈRE: Our objective is12
to have full compliance with the N286 standard.13
The N286 standard is a sweeping14
standard. There is an issue of calibration. In15
other words, how do we apply the articles to16
specific types of facilities? There is going to17
have to be some discussion and dialogue with the18
CNSC on this, but the general principles we are19
committed to meeting.20
MEMBER GIROUX: Thank you.21
I have a question for staff now.22
Concerning the report card, I23
would like to come back to that briefly. You24
upgraded security implementation from "C" to "B".25
���������
101
We heard that and we read that in the documents.1
This is quite unusual in our experience here, to2
have a change of rating between Day 1 and Day 2.3
Normally report cards, in the4
reports that we have usually for licensing, are5
essentially a snapshot established at some point6
in time, which indicates a judgment, an assessment7
on the operations and all that.8
The hearing process of course9
takes several months, and the time of writing10
documents, by the time we reach Day 2 I think the11
first document you gave us must be six months old12
very likely.13
The point of my question -- and I14
would like you to discuss that -- is: Is moving15
from "C" to "B" revisiting your decision or your16
evaluation of last fall, or are you trying to take17
into account new elements of information which18
have come up between the time of writing the19
document and the time of making the presentation20
now?21
Linked to that is also a question22
-- and I am not trying to be facetious. But have23
you been pressured by AECL to raise the rating?24
THE CHAIRPERSON: Before you25
���������
102
start, Mr. Howden, I would like to caution you1
that if this matter goes into security matters, it2
should not be discussed in public. Please notify3
us and we will do an in camera session.4
MR. HOWDEN: Thank you. Barclay5
Howden speaking.6
With regard to security, our first7
assessment, which was completed late last fall,8
was the "C" rating. Since the time of that9
writing and the time that we submitted the last10
update to you, which was about a week ago, is11
about a four-month period.12
The "C" rating was based on a13
number of specific deficiencies that required very14
specific actions to be done, actions that could be15
accomplished in a short period of time. AECL16
completed -- I don't remember the number, but a17
large percentage of those.18
For the remaining ones, the19
actions that they have proposed and that we have20
accepted are to be completed within the next21
approximately one-month period; so a very short22
time frame for very specific things that were23
identified during a previous audit.24
That is why we have been able to25
���������
103
upgrade from "C" to "B". We were considering our1
initial position and is there actually a delta2
change since that time to now. And the answer is3
yes.4
In terms of how we were able to do5
that, two ways. One is we reviewed what they had6
done in response to the audit. The second was we7
did a focused inspection in the middle of March of8
this year. As we came out of that inspection,9
right away we knew that a large number of items10
had been closed at the meetings there.11
So we were able to make that12
assessment quite specifically.13
In terms of pressure, no, we had14
no pressure from AECL. We were putting the15
pressure on AECL. They were not putting the16
pressure on us. We put the pressure on them to17
improve.18
MEMBER GIROUX: I understand your19
answer, but in terms of future licensing hearings20
and other licensees, can we expect this to be a21
regular procedure or exceptional: that you might22
revise your rating?23
MR. HOWDEN: I think that is24
difficult to answer. However, I would say this is25
���������
104
an exceptional item. Most of the issues that we1
raise in the report card format are programmatic2
issues. Generally programmatic issues take a much3
longer time to correct because of the fact that4
they sweep through a program and then they have5
the cross links with the other programs.6
Programmatic issues generally7
don't move at this pace.8
MEMBER GIROUX: Thank you. A9
final question, if I may, again for staff.10
There is a recommendation that you11
made to us that for the financial guarantees this12
be delegated to a designated officer.13
When that decision comes,14
especially for the applicant we have here, it is15
going to be a major analysis, I think. Would it16
very much be lost in terms of efficiency or17
otherwise if the Commission reserved the decision18
for itself for this first round?19
MR. HOWDEN: Barclay Howden20
speaking. The answer is no.21
THE CHAIRPERSON: Dr. McDill, do22
you have a question for round two?23
MEMBER McDILL: Thank you. My24
questions, if I may, relate to Document 03-H2.C,25
���������
105
the Molybdenum-99 container.1
On page 6 you refer to the lack of2
an alternate reservoir in the event of a serious3
problem with the tank.4
I understand the tank is double-5
wall stainless steel in a seismic vault. What is6
the medium between the two layers of steel?7
MR. LAFRENIÈRE: I am going to ask8
Mr. Paul Tonner to respond to that question.9
MR. TONNER: Paul Tonner, Manager10
of the Moly-99 processing facility.11
The medium is air between the two12
tanks.13
MEMBER McDILL: Thank you. How14
often do you test the pump?15
MR. TONNER: I'm sorry, I don't16
have the answer to that question.17
MEMBER McDILL: Is there a regular18
inspection procedure associated with the pump?19
MR. TONNER: There is ongoing20
instrumentation that would detect anything in the21
gap, and we have never detected anything in the22
gap.23
MEMBER McDILL: Have you ever24
tested the pump, in the event that there is25
���������
106
something in the gap?1
MR. TONNER: I will have to refer2
to documents before I could answer that question.3
MEMBER McDILL: All right. I will4
continue then.5
If there is a serious detected6
leak, how much can you pump back and contain?7
What percentage of the tank can you pump back and8
contain?9
MR. TONNER: The material that is10
pumped back into the cell can be cemented in the11
cell at a rate of -- I would be guessing. I will12
have to again check the documents.13
We can cement at a rate of14
probably eight litres or more in a period of a15
day.16
MEMBER McDILL: Eight litres per17
day. Is that correct?18
MR. TONNER: Yes. But I do need19
to check those numbers.20
MEMBER McDILL: The tank is 24,00021
litres. Is that correct?22
MR. TONNER: That is correct.23
MEMBER McDILL: So you have a 23-24
year-old stainless steel tank, and there is some25
���������
107
suggestion that there are some corrosion1
prediction studies going on. What is the nature2
of the corrosion prediction studies and what kind3
of monitoring do you have in place, apart from the4
gap, on the stainless steel?5
MR. TONNER: The corrosion6
prediction studies show that there is minimal or7
no iron content in the liquid in the tank,8
indicating that corrosion is not occurring.9
I'm sorry, could you repeat the10
second question?11
MEMBER McDILL: The monitoring12
that you are doing, are you doing numerical13
corrosion studies as well or are you doing14
experimental corrosion studies just seeking iron?15
MR. TONNER: There may have been16
numerical. I would have to check.17
The analysis was done within a18
couple of years, and there is no iron content in19
the tank, which would indicate corrosion of the20
tank.21
MEMBER McDILL: Are you detecting22
substantial chromium oxide?23
MR. TONNER: I will have to check24
the numbers to tell you. But at present, no, I do25
���������
108
not believe so.1
MEMBER McDILL: Thank you.2
THE CHAIRPERSON: Dr. Barnes.3
MEMBER BARNES: I wanted to pose a4
number of questions regarding the environmental5
monitoring and sampling around the CRL plant.6
Much of this comes out of Chapter 3 of our Binder7
2, and Appendix C, which includes the Laval8
University Report prepared by Dr. Barbeau.9
Could I first ask AECL: In the10
sampling strategy, particularly that adopted by11
the Laval group, who defined the strategy of12
sampling? Is this AECL or is it the contractor?13
How is that defined?14
MR. LAFRENIÈRE: Université Laval15
was totally responsible for defining their program16
and their strategy. There was no involvement on17
AECL's part.18
MEMBER BARNES: That group did or19
did not do the 1999 study.20
MR. LAFRENIÈRE: They performed21
the 1999 study and a subsequent study I believe in22
2001.23
The whole idea behind the24
independent monitoring is that they decide where25
���������
109
and what they monitor for.1
MEMBER BARNES: I would like then2
to ask the question -- I will pose the question to3
AECL, but I would appreciate comment from CNSC4
staff as well.5
Obviously when one does6
environmental monitoring one wishes to have a7
strategy sufficient to prove that the results that8
come out are meaningful. You are sampling a9
number of components within the environment, and10
you are trying to see whether the pollutants from11
the site, whether it be airborne or waterborne,12
mainly in the Ottawa River, are concentrated13
locally or dispersed over a wide area. For that14
it requires a number of sampling locations.15
We don't have I think in our16
documents the report from 1999, but we do have the17
one that was done by Laval, completed in 2001.18
I will just note that, for19
example, the milk sample was a single sample from20
Pembroke. The fish were sampled with three21
individual fish within the river, widely22
separated. Vegetables seem to be reasonable; that23
it was from three farms again down in Pembroke but24
a variety of samples.25
���������
110
I note that the air monitoring1
samples that are best shown, I think, in the CRL2
Figure 3.2 on environmental sampling locations --3
and I am not sure if they are your sample4
locations or those for the Laval study -- again5
has very limited number of sample locations around6
the limits of the CRL. In fact, there are none on7
the entire east side, which one would perhaps want8
to monitor, assuming that most wind directions are9
coming from the west.10
The river sediments, which I think11
are again interesting, the ones reported by the12
Laval group, which are on page 14 of that report,13
have a number of issues to me, which again are not14
clear in the brevity of the report.15
It says in the second line:16
"As in 1999, only coarse-17
grained sediments were found18
along the shores of the19
river."20
And that is basically where the21
samples were taken.22
If you compare that with the more23
detailed report on river sediments that is24
contained in Chapter 3, reporting data in 1991,25
���������
111
they clearly indicate that if one was looking for1
a hot spot -- they refer to it as a target area --2
most of the contaminants come out of the process3
sewer pipe located within the river, not along the4
shore. One would not expect to find, I think,5
contaminant like this in coarse-grained sediments.6
If you were looking for coarse-grained sediments,7
you probably wouldn't want to sample along the8
beaches.9
There may be practical reasons for10
the ease of acquiring sediments, to wander along11
the beach as opposed to the cost of renting boats12
and so on.13
The third line says:14
"The seven grab samples15
consist of material taken as16
deep as 80 cm in order to17
include any suspended18
material..."19
It doesn't tell me how that grab20
sample was taken, whether it was through a piston21
core or a box core, or just simply digging down22
into the sediment.23
If one looks again at the 199124
report -- again this is referring to more fine25
���������
112
silty material. One would know that the age of1
the sediments -- it is a very slow sedimentation2
in the vicinity of the outfall -- that 803
centimetres would take you down into quite old4
sediment. But again, if this is shoreline5
sediment, it would be an entirely different means6
of sedimentation.7
I raise these as specific examples8
of sampling of the environment and trying to9
convince the public, I guess, that the CRL site is10
not significantly contaminating the environment.11
I agree that looking at the tables12
that are reported in the Laval study there does13
not appear to be any major contaminant. The point14
I am getting at is that if you are trying to show15
this, it very much depends where you are basing16
your sampling strategy.17
If you have a widely dispersed18
sampling strategy -- in this case, if you sample19
one week in the year and you sample, for example,20
three fish, this surely is insufficient to21
demonstrate the level of potential contamination.22
I would like your response and23
then turn to CNSC staff.24
MR. LAFRENIÈRE: Thank you. I25
���������
113
would like to provide a response in several parts1
here. For the first part I would like Ray Lambert2
to provide a bit of background to some of the3
questions and clear up a few points regarding the4
tables that you mentioned. Then I would call upon5
Dr. Barbeau to explain the University of Laval6
sampling strategy.7
Ray.8
MR. LAMBERT: Ray Lambert, AECL.9
You asked some very good questions.10
First off, the environmental11
monitoring program is based on a more in-depth12
strategy than what is presented here. I would13
have to go into the annual reports to get into a14
little bit more depth as to what is covered.15
There are indeed more sampling locations on the16
site, but without the annual report present I am17
not able to bring them forward.18
That is the first point.19
The second point is the Laval20
study was not intended to be all-encompassing. It21
was intended to be more of a random sampling to do22
comparisons of some of the locations or areas23
within the area that we monitor as a means of24
verifying our more aggressive program.25
���������
114
Without being able to pull out the1
annual reports, which I don't have with me at the2
time, I can't tell you which particular areas we3
sample daily, monthly, or on a continuous basis.4
They are done on a more frequent basis than just5
once a year.6
MEMBER BARNES: Could I just7
interrupt.8
For example, the Figure 3.2 in9
Chapter 3 is produced by CRL. This is10
Environmental Technologies Branch, CRL, dated11
April 2001. It doesn't have a scale on it -- this12
is this large map -- but it does have the13
locations of the principal means of monitoring.14
If, for example, you look at the15
tritium air, the square box, unless my eyes16
deceive me you will see that there are only two17
locations of that on the site, one at the very18
southern tip and one at the very northwest tip of19
the area. If you look at the one for fish, they20
are nowhere near the CRL site.21
I presume this is taken from your22
annual report.23
MR. LAMBERT: That is correct.24
This is one of the figures taken from our annual25
���������
115
report that is showing the monitoring locations1
along the Ottawa River outside our site.2
Again, without the annual report3
present I can't point to exactly where within the4
site we do the monitoring for tritium.5
All I can say is that the6
environmental monitoring group has a model they7
use, a strategic approach, where they look at the8
-- they look at the model used, and keep in mind9
that the monitoring program was originally based10
on human dose. So they looked at the model in use11
to derive the release limits, and they develop a12
strategic monitoring program at the moment to be13
able to compare what we know we are releasing to14
what we see in the environment and do a15
comparison.16
Again, without the annual reports17
present I don't feel I can answer specifics on it.18
DR. FEHRENBACH: If I may add to19
that, Commissioner, this figure in this section of20
the supplementary document was provided in21
response to Commission interest in off-site22
monitoring. So this goes into some detail on our23
off-site monitoring activities.24
In fact, I draw your attention to25
���������
116
the title of the figure: "CRL Environmental1
Monitoring Locations Outside CRL Boundary".2
As Mr. Lambert mentioned, within3
our annual reports which are submitted to the4
CNSC, and which I believe have been made available5
to you as part of the Day 1 package of6
information, the information with respect to7
monitoring within the site boundaries also include8
it.9
There are certainly, as you10
suggest, monitoring sites within the yellow11
boundaries of that box.12
THE CHAIRPERSON: I believe there13
was a second part where you were going to call on14
Laval.15
Before you do that, I wonder, Dr.16
Barnes, if the staff should comment on this; if17
they have had a chance to evaluate this.18
MR. HOWDEN: Barclay Howden19
speaking.20
Dr. Patsy Thompson will comment.21
DR. THOMPSON: Good afternoon.22
For the record, my name is Patsy Thompson. I am23
Director of the Environmental Protection and Audit24
Division of the CNSC.25
���������
117
CNSC staff over the last several1
years have done technical reviews of the design of2
the monitoring program for AECL at Chalk River, as3
well as conducted an audit of how the program is4
being managed, in 1997.5
Having said that, the monitoring6
program was designed essentially to confirm that7
emissions of radionuclides were not resulting in8
doses to members of the public that would be9
unreasonable.10
The design and monitoring program11
essentially looks at the various sources of12
radionuclides on the Chalk River site and, through13
modelling exercises looking at environmental14
pathways, have identified exposure to critical15
groups, members of the public off-site,16
essentially in Pembroke and a couple of other17
areas along the Ottawa River.18
The monitoring program looks at19
air and drinking water and milk and some vegetable20
samples. The sediment samples are essentially21
beach sediment, to reflect potential exposure of22
people walking along the beach just outside of the23
Chalk River site.24
The program is not extensive. It25
���������
118
wasn't designed to look at environmental1
contamination in general. It was essentially2
designed to confirm what the emission monitoring3
shows us, which is that doses to members of the4
public through the modelling and the source5
measurements are low.6
CNSC staff requested that AECL7
modify the design of their monitoring program to8
capture essentially the change in our regulatory9
mandate with the coming into force of the Nuclear10
Safety and Control Act and Regulations.11
In order to do that, we have to12
have a better understanding of other sources of13
radionuclides on the site, as well as hazardous14
chemicals being released from the site, as well as15
on site.16
The ecological effects review that17
AECL is conducting will serve as a baseline of18
information to look at modifications on the19
monitoring program, to essentially capture the20
design changes to the program that have to be done21
to reflect modern environmental protection22
concerns of not just controlling doses to members23
of the public but also to demonstrating pollution24
prevention; and that members of the public are25
���������
119
being protected from hazardous chemicals but also1
that non-human biota are being protected from both2
hazardous chemicals and radioactive substances.3
We expect that the next step, once4
the environmental effects review has been5
finalized, that the risks identified from6
releases, both on-site and off-site, will serve as7
the basis for modification of the program, and8
that that program will be implemented and we will9
be conducting technical reviews of the design as10
well as audits of how the program is implemented.11
MEMBER BARNES: Thanks. I think12
that clarified some things. On the other hand, we13
are meeting here under the new Act, which does14
specify that an applicant, in this case AECL, is15
responsible for potential contamination of the16
non-human biota. That Act has been in force now17
for some while.18
If we are seeing results, if the19
data being brought to us is in a sense using an20
old strategy designed to address just the21
potential environmental effects on the public, I22
think it is in a sense only part of the story that23
should be being brought forward today.24
I noticed in the material that we25
���������
120
do have, as you just mentioned, there has been an1
ecological effects review that has been completed2
by AECL and given to staff, at least by March3
31st, maybe a week or so ago.4
Can you say whether that has been5
received and whether you have had a chance to look6
at it and whether it raises any major issues or7
concerns that you think the information from it8
should be brought to us perhaps at the later9
meeting?10
MR. HOWDEN: Barclay Howden11
speaking.12
The last two chapters of the13
ecological effects review was submitted on time,14
as expected. We expect that there is going to be15
an iteration on that as we review it and comment16
on it and AECL revises it.17
In terms of comments on it so far,18
Dr. Thompson can correct me if I am wrong but we19
have not had a chance to look at it in any depth.20
MEMBER BARNES: One final comment,21
just because it is interesting to compare one22
licensee from another on occasion. Perhaps at the23
last meeting we were looking at Bruce, and there24
was certainly concern about the thermal effects25
���������
121
and possible contaminant at Bruce and the effects1
on the fish. The fish are attracted to the warm2
thermal water that comes out of that.3
In this case we have a plant that4
is generating it, and 80 per cent of the potential5
contaminants come out of that process through a6
pipe into the river. That 1991 study documented7
that sort of the target hot spot, which is quite8
low in terms of contamination, but if you were9
looking for any kind of hot spot it was in the10
general vicinity and a little bit downstream of11
that.12
Could you tell me whether the13
monitoring that is going on at the present time --14
or maybe I should address this to AECL -- is15
actually attempting to sample fish that might be16
somewhat resident, as much as fish ever are,17
around the general location of that outfall in the18
river.19
MR. LAFRENIÈRE: I would like to20
give the question to Mr. Lambert, please.21
MR. LAMBERT: Ray Lambert, AECL.22
To your question about whether we23
sample fish in the area of the outfall, the answer24
is yes. Whether we currently do a correlation to25
���������
122
the thermal effect specifically, no.1
The ecological effects review that2
Dr. Thompson mentioned does address the question3
of the thermal effects. As the work was done by a4
consultant, we ourselves are still reviewing the5
findings of their report.6
They have identified a thermal7
effect discharge from the coolant of NRU. They8
have made some initial findings and found that the9
effects of the water thermal plume on aquatic life10
are expected to be minor. However, as Dr.11
Thompson mentioned, the document is still being12
reviewed technically, and there may be iterations13
of the report.14
That is the initial finding by the15
consultant.16
THE CHAIRPERSON: Yes, Dr.17
Fehrenbach.18
DR. FEHRENBACH: Paul Fehrenbach,19
for the record.20
May I provide some supplemental21
information to that.22
Dr. Barnes, you have correctly23
suggested several times that if you were going to24
look for concentrations of contaminants it would25
���������
123
be in the outfall area of the process sewer. In1
fact, we have done extensive sampling in the area2
of the river around the process sewer.3
One of our environmental4
scientists, Dr. David Lee, is in the process of5
publishing a paper on that. We refer to it in6
Section 3.3 of the supplemental information that7
was provided to you.8
We did not only a broadbase survey9
of the river bottom all around the area10
surrounding the outfall to the process sewer, but11
we actually did coring in the hottest spot we12
could find. We submitted those samples for13
toxicity testing, and the results of that toxicity14
testing showed that there was no measurable15
effect.16
MEMBER BARNES: I was looking for17
some information that one could compare with the18
Laval study. If I look at the references at the19
end of Chapter 3, as 3.6, the citations for Dr.20
Lee are dated 1991, 1991 and 1992. So it is more21
than a decade old.22
If there is something in press23
that's fine, but the information we have does not24
give that information.25
���������
124
I think the report on 3.3, which1
is pages 13 to 15, and so on, as far as I can see,2
doesn't that come from the 1991?3
That is the latest thing, is it?4
DR. FEHRENBACH: Yes. We have5
attempted to summarize the paper that is in6
process in Section 3.3.7
THE CHAIRPERSON: I believe there8
was an outstanding intervention from Laval.9
MR. LAFRENIÈRE: Yes. I would10
like to call on Dr. Claude Barbeau, Université11
Laval, to come forward and provide some12
explanation on the sampling strategy.13
DR. BARBEAU: Claude Barbeau,14
Université Laval.15
Our group at Laval University has16
been doing some survey, what I call more of a17
surveillance radiological environmental process18
which, for example, for the last ten years we have19
been doing around Gentilly II; we have been doing20
a survey.21
This means that we don't do22
monitoring. We just pick up samples, the type of23
samples we want, when we want, how we want them,24
and we do the analysis. After that we do our25
���������
125
report describing the samples, the results and try1
to put it in perspective with other results in2
similar situations, either in Canada or in the3
United States or in Europe.4
In fact, we don't do any5
conclusions. We just try to do a type of audit of6
the environment.7
It is not a monitoring process.8
Therefore, we cannot take a very large number of9
samples. We try to get some samples that are10
representative of integration of radionuclides.11
Dr. Barnes asked about the12
sediments. In a river like the Ottawa River, to13
find fine sediments where radionuclides can be14
absorbed and deposited on the bottom is quite15
difficult. We try to look only for fine16
sediments, because in coarse-grained sediments we17
are not susceptible to finding radionuclides.18
We do our sampling at the end of19
August where the river is at its lowest. We look20
for downstream sediments and we compare then with21
upstream sediments. These are the reasons why we22
don't have that many samples. We are restricted23
in numbers and it is difficult to find fine24
sediments.25
���������
126
So they are really representative1
of the river around the AECL site.2
As for air, we do a sampling3
during only a 24-hour time, because we don't4
sample monthly periods. Sometimes, for example in5
Gentilly, we find very low values and sometimes we6
find very high values.7
If you look at our survey in 2000,8
you will find that the air content in Deep River9
was high in tritium. This was a very foggy day.10
Actually, we had the possibility of having a wind11
in the direction of Deep River, and we got a high12
tritium value.13
So we cannot decide on which site14
is the weather or the winds, but we try to sample15
during our stay in the region, which is about four16
or five days, we try to go where the wind17
direction is and to find some sample for air.18
So the sample for air just gave us19
tritium values above the detection limits.20
As for water, we take water in the21
Ottawa River and upstream also from AECL.22
Vegetables are probably the best23
samples that can integrate what has been emitted24
in the atmosphere. As you can see, we have some25
���������
127
vegetables and the radionuclides there that were1
found mainly was tritium. To do a type of survey2
that could be of certain use, we went south or3
east, down to Pembroke, and we went upstream. You4
have the results there.5
As far as Chalk River and Deep6
River, they are similar to what we find mostly7
nearby Gentilly II in terms of tritium content in8
vegetables.9
THE CHAIRPERSON: Dr. Barnes.10
MEMBER BARNES: Perhaps I could11
make some comments. I don't know the details of12
the contract, the size of the contract, and what13
is expected of the Laval group by AECL. I will14
just give the following impressions that I have15
here.16
The report is given to us as part17
of the justification of AECL that there is not a18
problem. The report is entitled "Radiological19
Environmental Survey Outside the Chalk River20
Laboratories Site". There was no, in a sense,21
terms of reference, no clear statement of what the22
survey is to do, except if I take the first23
paragraph it says:24
"A mandate was received in25
���������
128
2000, from Atomic Energy of1
Canada Limited (AECL), to2
execute a radiological3
environmental survey outside4
the Chalk River Laboratories5
(CRL) site."6
That could mean various things,7
but what you told us and what AECL told us is that8
it is random sampling. But it goes on to say in9
that first paragraph:10
"For comparison purposes the11
survey covers the same area12
and the same radionuclides as13
in the 1999 report."14
So at least there is some little15
bit of time series developing here. Again, that16
may not be of much value if one is not sampling, I17
would say, in a strategic manner.18
The last sentence in that first19
paragraph says:20
"The samples and analyses21
chosen had to reflect a22
potential impact of the23
activities carried at AECL, on24
the environment outside the25
���������
129
site."1
In the second paragraph it says:2
"The chosen samples are3
representative of the4
environment around CRL5
site..."6
I don't know how you could say7
that three fish caught in the river are8
essentially representative.9
If I just come back to the issue10
of the sediments, which you said coarse sediments11
are not going to give you any data, in Section 3.612
dealing with radioactivity in river sediments --13
and that is what it is trying to characterize:14
whether there is any problem with river sediments15
-- the second sentence says:16
"As in 1999, only coarse-17
grained sediments were found18
along the shores of the19
river."20
Which means that you found them in21
1999. You admitted there was no point in sampling22
them. They were sampled again in 2001, and one23
has the impression that it is not a problem.24
I understand that you probably are25
���������
130
just taking a few samples here. I am just trying1
to point out that I am not convinced here that the2
scale of sampling that had been asked to do, or3
that you volunteered to do on behalf of AECL, is4
sufficiently detailed evidence to convince me, and5
perhaps the public, that this is a sufficient6
amount of sampling to prove the point that you are7
trying to show: that there is essentially very8
little impact of the activities carried on at AECL9
on the environment outside the site.10
This is the only point I am trying11
to make, but I think Dr. Thompson may have a12
point.13
DR. BARBEAU: You are correct. We14
are not trying to prove anything. We were just15
asked to do a survey.16
As I said at the beginning, we do17
that for Gentilly. We have done that also for18
Defence in Ottawa. We just take samples and we do19
measurements, and that's it. We are not trying to20
prove any point in a sense of what you said, to21
the type of sample. We could find only coarse-22
grained sediments, but the location we stayed on23
to get these sediments was as close as possible to24
the river and could contain very fine sediment.25
���������
131
That was the most we could get.1
MEMBER BARNES: I take it that you2
may not be wishing to prove a point, but there is3
a purpose for this survey being undertaken. I4
think part of the purpose for bringing it forward5
today is to show to us and to the public that6
there is not significant impact by the activities7
of AECL on the surrounding environment. There is8
a point in there.9
THE CHAIRPERSON: AECL and then10
staff. Then I am going to call a close to this11
particular question.12
MR. LAFRENIÈRE: Thank you.13
As Dr. Barbeau pointed out, this14
was an environmental audit. The purpose of the15
audit was to validate independently our16
measurement systems. We do extensive sampling, as17
pointed out in the material, the supplementary18
information package. The University of Laval was19
asked to independently validate this data. This20
shows their own sampling strategy.21
The results have indicated to us22
that yes, our measurement systems have been23
validated by the Laval results. That was the24
purpose.25
���������
132
We are not purporting to say that1
the Laval study demonstrates that there is no2
issue at all with the sampling.3
THE CHAIRPERSON: CNSC staff and4
then back to Dr. Barnes.5
DR. THOMPSON: For the record6
again, my name is Patsy Thompson.7
I wanted to clarify that8
essentially the regulatory program that AECL has9
in place to meet requirements, to demonstrate that10
doses to members of the public are ALARA, as low11
as reasonably achievable.12
The design that we have accepted13
as meeting our requirements was for fish sampled14
in the areas that would be representative of where15
members of the public or members of the critical16
group could obtain fish from recreational fishing.17
Essentially the samples are taken18
about 28 kilometres upstream of the Chalk River19
site as a reference, and other samples are taken20
from 5, 9 and 42 kilometres downstream. That sort21
of corresponds to the location of where the22
critical members of the public have been23
identified.24
The number of fish samples are not25
���������
133
high, but they have been deemed sufficient. There1
is a trend essentially where concentrations over2
several years have been close to natural3
background concentrations.4
We have doses to members of the5
public from consuming fish from those samples that6
are approximately 3 to 4 microsieverts per year,7
which is quite a bit lower than the 1,0008
microsievert or 1 millisievert dose to members of9
the public.10
So we have deemed that in relation11
to the risk that the facility poses, the number of12
samples taken were sufficient to demonstrate the13
performance of the Chalk River site in terms of14
protecting members of the public.15
The expectation is that with the16
baseline that is being gathered through the17
ecological effects review, the monitoring design18
will be a lot more rigorous and based on not just19
confirming doses to members of the public but also20
looking at patterns of contamination and to21
validate the information that AECL has provided in22
the ecological effects review in terms of sources23
of substances being released from the site.24
Just to clarify, the information25
���������
134
is valid in terms of confirming that doses or the1
radionuclides are well controlled and that doses2
to members of the public from fish consumption are3
well below the public dose limit.4
THE CHAIRPERSON: Dr. McDill, I5
would like to return to you just for the6
clarification about the information issues.7
MEMBER McDILL: Perhaps with8
respect to the question on the pump and the9
chromium oxide, maybe AECL could report that to10
staff.11
Would that be satisfactory?12
MR. LAFRENIÈRE: Certainly.13
THE CHAIRPERSON: I guess my next14
question is with regard to the decommissioning15
plan and the financial guarantees.16
I believe it is correct in saying17
that the Commission expected these to be ready for18
this licensing hearing, and it is not. As you19
have answered Dr. Giroux's question, you are20
asking for the delegation.21
I am not so interested in22
exploring the delegation as I am in exploring23
exactly where the preliminary decommissioning plan24
is and the status of the information on the25
���������
135
financial guarantees.1
My purpose is to have you, from2
the staff's point of view, assure the Commission3
that this is moving along at a pace that is4
satisfactory and that the information will be5
available and will be of the quality that we6
expect in these areas.7
MS MALONEY: Thank you, Madam8
President. Cait Maloney here.9
I will start with the10
decommissioning plans.11
We have received preliminary12
decommissioning plans for all of the parts of the13
Chalk River site. We have also given notice to14
AECL that we want to discuss an overall plan with15
them. That is an essential thing to have. That16
is one of the things that we will be discussing in17
the context of an overall plan for the site, not18
just for decommissioning; obviously remediation19
and future activities.20
That is part of some ongoing21
discussions that we will report on at mid-term and22
sequentially after that.23
With respect to the financial24
assurance, we are aware that AECL is working with25
���������
136
the federal government to establish an appropriate1
financial assurance there. We have worked with2
AECL to ensure that they understand the3
requirements of our policy. We believe that the4
way they are proceeding will be consistent with5
those requirements and should be concluded by the6
end of this calendar year.7
We are monitoring what is going8
on, but we do not as yet have the draft in front9
of us to look at.10
THE CHAIRPERSON: I guess my11
question then is to AECL: as to whether you can12
assure the Commission that you clearly understand13
the requirements being placed on you in these two14
areas, the preliminary decommissioning plan and15
the financial guarantees, and that you see no16
problem in moving towards the quality and time17
frame that has been discussed by the staff.18
DR. FEHRENBACH: Paul Fehrenbach.19
By way of background and20
clarification, I would like to indicate first of21
all that what we are talking about here is a22
rather unique situation at Chalk River, because we23
anticipate the site will be operational for the24
next hundred years.25
���������
137
So when we are preparing a1
decommissioning plan, what we are talking about is2
a plan for decommissioning obsolete facilities as3
they become obsolete, while we are adding new4
facilities and operating facilities which are not5
yet obsolete.6
So the total estimates for what7
will be required to address this over the next8
hundred years, still even with the latest models9
for decommissioning cost estimating, still have10
some significant degree of uncertainty associated11
with them because some of the activities we are12
anticipating are well into the future.13
As well, we are dealing with some14
things which started well in the past, 50 years15
ago in some cases. There is a fair amount of16
physical characterization which must be done17
before we can come up with a full-blown cost18
estimate of what remediation, if any, will be19
required before the situation can be put into20
permanent disposal or otherwise decommission.21
With that as background, I would22
like to turn the question over to Mr. Van Adel.23
MR. VAN ADEL: I basically agree24
with the comments made by Cait Maloney on behalf25
���������
138
of the CNSC. We understand the issues, and we are1
engaged in a discussion with the shareholder about2
the implications. We do understand the time3
frames.4
As Paul indicated, I think it is a5
complex issue but one that we are all seized with6
and are working towards a resolution.7
In other respects, in terms of8
what you might consider to be the ongoing day-to-9
day activities of AECL and how it might respond to10
situations that require exceptional amounts of11
cash or response by way of standby guarantee, I12
will point out to you that AECL is an agency of13
the crown and as such engages the full faith and14
credit of Her Majesty in all its activities.15
Our contracts, our other16
obligations, are backed by the Government of17
Canada. Whenever we enter into a substantial18
contract of any kind, we often are asked to obtain19
a statement from the Department of Justice20
verifying that very aspect of our operation. We21
obtain that readily because by statute, by law, we22
do engage the crown in our activities.23
With respect to our day-to-day24
operations, we maintain adequate cash balances to25
���������
139
cover operations and contingencies. Our current1
cash balance is in excess of $164 million. We2
have contingencies over and above that for other3
matters but could be drawn on should we require4
cash.5
We have a "rust-out" program, as6
you know, which relates at least to the7
decommissioning and clean-up of facilities, which8
have cash commitments from the government through9
to the end of 2005. A negotiation is under way as10
part of this exercise with the government to look11
at the possible revision of those costs on a go-12
forward basis, which cover more than just13
decommissioning of the Chalk River site but the14
full range.15
There is a full recognition on the16
part of the shareholder that that discussion needs17
to take place and indeed we need funding18
commitments beyond the period in which the current19
fiscal framework covers.20
In respect of the ongoing clean-up21
activities with respect to waste and the surety of22
funding from the shareholder for those,23
irrespective of the fact that if we called on them24
for cash they would be compelled to provide it, we25
���������
140
have ongoing sources of revenue and income.1
The heavy water sales, as you are2
aware, and the income from that is dedicated to3
fund the "rust-out" activity, and there are cash4
flows ongoing in the order of about $30 million a5
year for that.6
The total liability at this point7
for decommissioning and waste management, some8
$2.6 billion over the hundred-year time frame, is9
on our books at $386 million now as the net10
present value liability amount, and that is11
recognized formally by the government as an12
obligation that while it is charged to AECL's13
books and we carry the liability on our books, in14
fact the liability is borne by the government.15
As part of this discussion and how16
we proceed from this point on, all of these issues17
need to be looked at. In the meantime, we believe18
that we are in excellent shape, both in terms of19
our financial viability, our ability to raise cash20
in the event that we need it to cover emergencies21
or difficult situations, or to reallocate funds in22
the event that there is a need to do so while this23
discussion is taking place.24
THE CHAIRPERSON: Thank you. I25
���������
141
appreciate your comments.1
The Commission recognizes the2
complexity of the site that you have and the fact3
that you are talking about legacy issues as well4
as looking at new projects.5
Because of the Commission's6
responsibility for safeguards, we also have an7
added interest in making sure that we understand8
the nature of the site and making sure that we are9
also able to honour our international obligations.10
You are well aware of that as well.11
I believe it would be appropriate12
on behalf of the Commission to register at the13
hearing, for the ears of the Government of Canada,14
the concerns of the Commission to make sure that15
AECL receives the funding necessary in order to be16
able to adequately address, in the manner which I17
think the public would expect, the issues of18
decommissioning and to make sure that you do have19
the funds necessary to address a site that has20
been in place for many, many years and has served21
various uses in the Government of Canada's policy22
envelope.23
So I think it is appropriate for24
that to be registered.25
���������
142
Are there further questions?1
Mr. Graham.2
MEMBER GRAHAM: Thank you. I have3
two questions.4
One, which I didn't get answered5
this morning, is with regard to the fissile6
solution storage tanks.7
You talk about capacity has been8
extended a couple of times. The recent one is a9
short-term solution.10
What is the long-term solution as11
far as expansion? I didn't get that answered.12
MR. LAFRENIÈRE: The solution is13
to transfer to the new MAPLE facilities. This14
will resolve the problem in the immediate term in15
terms of the ongoing production of the liquid16
waste that is stored in the FISST tanks.17
The other part of that is the18
ongoing project at this time, the "rust-out"19
project, which is the stored liquid waste, which20
is funded and well under way, which will21
disposition the waste and put it into a dry22
storage facility.23
MEMBER GRAHAM: My second question24
was with regard to -- I think at a prior hearing25
���������
143
we had heard about the underground sewage system,1
whether it be storm or sanitary. A lot of them2
had been improved or upgraded at the site.3
Has that been completed? I think4
we heard at one time that some of the pipes had5
not been connected or had been disconnected. Have6
all of the contaminated soils and so on been7
cleaned up, and are the sanitary and storm sewage8
systems completed at this time?9
MR. LAFRENIÈRE: I believe you10
were referring to the active drain line system.11
That system is now in active commissioning. So it12
is in use.13
On the second question, how we14
have proceeded -- for example, if there was a pipe15
break, we have cleaned up in the area of the break16
and we have dispositioned that and put any17
contaminated soil into storage.18
MEMBER GRAHAM: So there are no19
more contaminated soils on the site in relation to20
leaks or poor workmanship of the sewer system.21
Is that what you are saying?22
MR. LAFRENIÈRE: What I am saying23
is on the old active drain line system, where we24
had a problem or a break, they were cleaned up.25
���������
144
MEMBER GRAHAM: Thank you.1
Madam Chair, one more question?2
Thank you.3
We have heard a lot today about4
quality assurance. We have heard more or less the5
major things that have been done or contemplated6
since Day 1 of the hearings.7
I guess for satisfaction as a8
Commissioner, on Day 1 CNSC was very critical of9
AECL with regard to their failure to conduct or10
complete reviews effective on quality assurance11
programs for the year 2001 and they went on that12
after being presented with the weaknesses, AECL13
senior management committed to conduct overall14
reviews, and so on.15
We have heard what you have done16
today and what you plan to do, with the overheads,17
and so on. My only question is: Why the about-18
change so quickly?19
If we had not had this application20
before us and there had not been a Day 1 or a Day21
2, would things have changed as quickly as they22
have between Day 1 and Day 2?23
MR. LAFRENIÈRE: I would like to24
say that our results today that we have25
���������
145
demonstrated have shown that there has been a1
continuous improvement going on for many years2
now.3
In this particular area the CNSC4
has provided feedback and directives on some of5
our weaknesses. That is an opportunity for6
continuous improvement, and we are going to profit7
from it.8
With respect to the second part of9
the question, I am not able to answer that type of10
question. I can only point out that our record of11
improvement stands, and it will continue to12
demonstrate.13
MEMBER GRAHAM: The only other14
comment I would have is that a mid-term review I15
believe is necessary, hopefully that we could16
demonstrate to see even continued progress. That17
was one of the weaknesses that AECL had.18
There have been improvements, and19
there have been upgrades and so on. But yet it20
has to be ongoing. It just can't be at the time21
of application for a licence. It has to be a day-22
to-day-to-day operation, not just when you are23
coming before the Commission or coming looking for24
extensions or licence approvals.25
���������
146
MR. LAFRENIÈRE: Thank you. Our1
management system has been implemented extensively2
starting in 1998, and we have demonstrated3
progress. That progress is coming to fruition,4
and I think the results show that.5
I would like maybe our CEO to6
comment.7
MR. VAN ADEL: I would like to8
point out two things.9
I think that the whole regulatory10
environment, whether it be environmental, quality11
or whatever standard is applied to us, whether it12
be from the CNSC or whether it be from our13
customers, the yardsticks are moving continuously.14
So one can never say that one has15
reached an appropriate level of quality assurance16
or environmental standard or on any of these other17
issues. You mentioned yourself several changes in18
the regulatory environment that have taken place19
recently.20
We are constantly working in an21
environment in which the yardsticks are22
continuously moving. I think that not only do we23
accept that, but we embrace that.24
The real job for us is to ensure25
���������
147
that not only the processes but the culture is1
there in our company. We embrace the constantly2
moving yardsticks, and we are in a position to3
respond to that.4
We have made some major changes in5
our corporation in the last two years and in6
particular in the last year to respond to a number7
of these issues. I can see that one of the things8
that has made it easier to do -- because many9
people point out that a cultural change of the10
orders of magnitude that we have been going11
through often take between three to five years.12
Based on my experience, that is often the case. I13
have been involved in a number of such activities,14
both in the private sector and in the public15
sector.16
One of the things that has caused17
the turnaround in AECL which often leads to the18
comment "gee, did you just do this recently19
because we leaned on you" -- the fact is that we20
made progress so rapidly because we have in AECL21
across the board what I used to call pockets of22
excellence; that is, we have world-class or state23
of the art capability, whether it be in quality,24
project management, environmental standards.25
���������
148
The challenge for us is to drive1
those pockets of excellence or those high2
standards across everything we do. That is a3
challenge for an organization as diverse as ours,4
where we have commercial activities, national labs5
and other things. We are trying to drive the6
lessons learned from one group to another.7
I think the changes we have made8
in our structure, the changes we have made in the9
people and so on in the last while have really10
facilitated that.11
My response, in listening to you,12
is I have been on the job on that issue for more13
than two years, and the changes you are seeing14
today, which sometimes appear to take place in15
periods as short as three to four months or six16
months, are a result of that drive to drive that17
standard across the company.18
Dr. Aly's job on the quality side19
was to come in and take what we were doing by way20
of state of the art, say, on the China project,21
where we are doing an excellent job on quality,22
and drive that across the firm. So he is now23
empowered to do that.24
I think that is the real answer to25
���������
149
that question.1
THE CHAIRPERSON: Thank you very2
much.3
We are now going to move to the4
section of interventions.5
I would like to acknowledge that6
we have been informed that Mr. Van Adel is going7
to be leaving -- no? You will be able to stay for8
a while?9
I want to acknowledge that he did10
inform us of this, and we are aware of those11
restraints.12
MR. VAN ADEL: I will just mention13
that we were informed that things may go a little14
bit later, and I was able to make changes in my15
schedule.16
THE CHAIRPERSON: Thank you.17
Now we are going to move to18
interventions. This is where the people from the19
community particularly have a chance to talk to20
the Commission about their views.21
I would like to remind intervenors22
that all the Commission Members have received your23
written interventions and have had an opportunity24
to read them. They will be used in totality in25
���������
150
our discussion, our records of decision and our1
decision-making.2
With that in mind, I would like to3
note that we have allocated approximately ten4
minutes for each of the oral presentations. I5
appreciate your help to maintain that schedule so6
that we get to hear from the number of people who7
would like to talk to us today.8
Some intervenors have filed the9
same submission for Chalk River Laboratories,10
MAPLE and for the New Processing Facility.11
As mentioned earlier, to avoid12
repetition I will invite those intervenors to make13
their presentations at this hearing, and then they14
will be asked, as we move forward to the MAPLE and15
New Processing Facility hearings, if they want to16
have that presentation taken forward into those17
other matters or not.18
19
03-H2.320
Oral presentation by the Regional County21
Municipality of Pontiac22
THE CHAIRPERSON: With that23
preamble, I would like to move to our first oral24
presentation from the Regional County Municipality25
���������
151
of Pontiac.1
This is outlined in CMD Document2
03-H2.3.3
Je remarque que c'est une4
présentation bilingue. Alors c'est très bon pour5
nous aussi.6
We have Mr. Spence with us7
representing the Pontiac.8
Mr. Spence, you have the floor.9
MAYOR SPENCE: Good afternoon. My10
name is Denzil Spence. I am the Mayor of the11
Municipality of Alumette Island. With me today is12
Mayor Paul Ryan of Waltham.13
We are here today on behalf of the14
Regional County Municipality of Pontiac. To the15
Commission I would like to briefly describe the16
county to you.17
The MRC Pontiac that we refer to18
is the Regional Municipal County of Pontiac. It19
consists of 18 municipalities, and it represents a20
geographic area of approximately 8,000 square21
miles. We have a population base of approximately22
15,000 people.23
We are here today on behalf of MRC24
Pontiac. I have a prepared statement, so I am25
���������
152
going to read the statement from the Regional1
County.2
Madam Chair, the Regional3
Municipal County of Pontiac, MRC Pontiac, wishes4
to inform you, the Commission, that they fully5
support the request for renewal of permits for6
Chalk River Laboratories.7
Following is a list of8
interactions, including assemblies, that AECL9
participated in with MRC Pontiac over the past few10
years.11
One, Paul Fehrenbach, Paul12
Lafrenière and Donna Roach of AECL have provided,13
and continue to provide, annual updates to MRC14
Pontiac.15
Two, AECL held a "Meet and Greet"16
in Fort Coulonge following the September 11, 200117
tragedy.18
Three, AECL brought its19
information display to the annual Shawville Fair20
in the years 2000, 2001 and 2002. Shawville is a21
municipality within our region.22
Following up on interactions with23
MRC Pontiac around the public consultation program24
for the Modular Above Ground Storage, MAGS25
���������
153
project, Warden Mike McCrank and myself accepted1
AECL's invitation to attend the opening of the2
MAGS facility in May of 2002.3
AECL held an information session4
in Fort Coulonge related to its proposal to5
decommission the NRX fuel bays at CRL.6
Donna Roach, Manager, Community7
Relations, AECL, facilitated discussions relating8
to the development of a nuclear emergency plan for9
the Upper Pontiac in 2002.10
A number of MRC Pontiac mayors11
participated in emergency preparedness exercises12
as observers last fiscal year.13
AECL continues to sponsor air-time14
for non-profit organizations within the MRC15
territory on CHIP-FM station, which is located in16
Fort Coulonge, Québec.17
The many communities throughout18
MRC Pontiac are included in the mailing19
distribution of the AECL bilingual quarterly20
community newsletter.21
To this end, we the respected22
Mayors of MRC Pontiac would like to encourage AECL23
to continue with the excellent interaction and24
relationship that presently exists. And be it25
���������
154
known that we fully support the licensing of AECL1
Chalk River Laboratories.2
Hoping you will take special3
consideration of our request, Madam Chair, this4
concludes my presentation.5
THE CHAIRPERSON: Thank you.6
Are there any questions or7
comments from the Commission Members with regard8
to this presentation?9
I actually have a question, Mr.10
Spence.11
Did the Pontiac participate in the12
workshops that were held on emergency preparedness13
lately? There was one, I think, around the14
Gentilly area.15
MAYOR SPENCE: Yes, we did.16
Actually, I participated in the one that was held17
in Toronto, and I really enjoyed it.18
To add further to this19
presentation, this is my first time at a hearing20
like this and I am really impressed with the21
questions and the thoroughness of the Commission.22
I think I can go back to my Regional Municipality23
and say yes, this is for real. We have a24
Commission and they are looking out for us. I25
���������
155
thank you.1
THE CHAIRPERSON: Well, we hope we2
are.3
Thank you very much for coming4
today to both of you. We do appreciate that.5
6
03-H2.47
Oral presentation by the Canadian Nuclear Workers'8
Council9
THE CHAIRPERSON: We will move to10
the next presentation, which is an oral11
presentation by the Canadian Nuclear Workers'12
Council, as outlined in CMD Document 03-H2.4.13
We have with us today the14
President of the Council, Mr. Shier. The floor is15
yours, sir.16
MR. SHIER: Good afternoon, Madam17
President and Members of the Commission. As18
indicated, my name is Dave Shier. I am the19
President of the Canadian Nuclear Workers'20
Council.21
Our presentation today is endorsed22
and supported by 14 of the 15 unions at the Chalk23
River site.24
I know the one absent union will25
���������
156
raise a question, and I will answer that now. I1
will indicate that the union that is not in2
support of it is the Chalk River Technicians and3
Technologists Union.4
Their reasoning is that at this5
particular time they are in collective bargaining.6
When they are in bargaining, their philosophy is7
that they focus all their efforts in that area and8
they don't participate in any other issues.9
With me today, to my right, is Mr.10
Jim Arnott from the Power Workers Union on site.11
To his right is Ms Leslie Gibbons from the Office12
and Professional Employees International Union.13
Also with us, farther back, are14
representatives from the other unions:15
specifically Mr. Ken Philipose from the Chalk16
River Professional Employees Group; Mr. Hugh17
Clarke and Dennis Jameson from the Allied Trades18
Council.19
The Allied Trades Council is an20
umbrella organization that represents eight unions21
at Chalk River.22
We also have Pat Hagarty from the23
Chemical Energy Paperworkers Union.24
All of these people are available25
���������
157
to you if you have any questions for them on1
specific issues after our presentation.2
Our presentation covers the three3
licence applications that are in front of you4
today, and we will not be making a presentation on5
the other applications later today.6
The contents of our presentation7
will be brief as you do have our written8
submission. We would like to talk a little bit9
about labour relations, conventional health and10
safety, radiological health and safety, community11
perspective, and then we will offer our12
conclusions and recommendations.13
In regard to labour relations, as14
we indicated there are 15 labour unions on site.15
At first this may appear cumbersome to have this16
number of unions on site. However, if you look on17
the positive side of that, we suggest that does18
give a real good opportunity for the workers, the19
shop floor workers, the ratio being very low20
between the shop floor workers and union21
representatives, to be able to bring up issues of22
concern of the workers.23
Even though all these unions maybe24
have different philosophies, they do have a common25
���������
158
goal as far as health and safety goes. They all1
put health and safety as a high priority.2
The state of labour relations I3
suggest is very good. There is a lot of4
negotiations going on, grievances and meetings,5
and so forth. Actually, some of our people today6
had to leave at lunch time to sort out some7
grievances. So we look at that as good activity,8
a healthy environment, that there are issues that9
are being discussed.10
In the area of the Joint Health11
and Safety Committee, there is a mandated Joint12
Health and Safety Committee on site, a very large13
committee, 23 members. Each of the unions has a14
representative on that joint committee, again a15
very low ratio of workers to representatives on16
the committee. So this again ensures that worker17
problems are raised at the committee.18
The Joint Health and Safety19
Committee does work under the mandate of the20
Labour Act, and our information is that everything21
is up to date: inspections, regular meetings, and22
so on and so forth.23
One area of the health and safety24
performance has indicated that they even though25
���������
159
there are accidents, the performance is very good1
and that the joint health and safety committee2
does strive for continuing improvements in the3
area of health and safety.4
One area regarding workers' health5
and safety rights is the issue of workers having6
the right to refuse unsafe work. Even though7
these work refusals do occur, they are not8
recorded or logged. Sometimes they are looked on9
as being a negative. We suggest that the fact10
that these are occurring is a positive; that it11
shows that the system is working; that the workers12
are questioning issues. We have several examples13
of where work refusals have happened.14
As I indicated, the majority of15
them are sorted out right at the shop floor level16
between the worker and the supervisor. But it17
does bring that question forward that the workers18
do question health and safety issues.19
In the area of dose reduction, you20
did hear from the applicant on that. We would21
like to make a correction to our written22
submission. We indicated that we were going back23
over a decade. We went over a little more than24
that, and I guess from our perspective the error25
���������
160
we made and the correction we are making is1
actually showing a better improvement than our2
submission indicated.3
We actually went from 1991 to4
2002.5
We would like to correct that, our6
figure in the second paragraph of the second page7
of our written submission, where we indicate that8
the average exposure was 1.66. In effect, it was9
1.85 in 1992, and that makes an improvement of up10
to 40 per cent over that period of time.11
In this business, I think any time12
dose reduction is increased is a real positive.13
This has occurred for many reasons: new equipment,14
more training, the ALARA principle. But most of15
all it has been taken care of by the workers.16
These are the people that are more vigilant with17
the new equipment and training and able to reduce18
their exposures.19
On the community perspective, the20
workers at the site do live in the community and21
raise their families in the community. They are22
part of the community. In that role, they also23
answer a lot of questions about the site. Their24
neighbours, the people they are involved with, any25
���������
161
time they have concerns they ask these people. So1
they are basically ambassadors for the actual2
facility, to be able to let people know what is3
going on and answer questions.4
The labour unions are also5
affiliated with the Renfrew and District Labour6
Council. The labour councils are a group of7
unions in the area with like minded ideas, a lot8
of activists. Also, the labour council is9
supportive of the site for the members that belong10
to their organization. Also, any issues that come11
up, they have been addressed by union members from12
the Chalk River site.13
The Nuclear Worker Council, we14
have also had some involvement in the community15
here. We have done some presentations to the16
District Labour Council, and a year or two back17
some of our members did put up a display booth in18
the local mall to engage the public in some19
dialogue regarding the site.20
In conclusion, we would suggest21
that the workers on site, as they work on site and22
they live in the community, that the public can be23
assured if there are any health and safety issues24
on the site, they would definitely be raised by25
���������
162
the site unions.1
We encourage the CNSC to renew the2
operating licences for the three facilities at3
Chalk River.4
Thank you for your time. We would5
be open to any questions to myself or members of6
the unions on site.7
THE CHAIRPERSON: Thank you.8
Are there any questions or9
comments?10
Dr. Barnes.11
MEMBER BARNES: I was interested12
in why the work refusals would not be logged, not13
necessarily the individual concern but the kind of14
work they were refusing to do. I would have15
thought that might have been instructive to have16
that captured.17
MR. SHIER: That is a good point.18
There is no requirement under the legislation to19
log work refusals. As I indicated, lots of them20
are resolved right at the interface between the21
worker and the supervisor.22
As unions, we have suggested they23
should be logged and used as a lesson learned type24
of situation. Unfortunately, in my opinion there25
���������
163
has been a bit of philosophy that if you have work1
refusals, there is something wrong. We feel it is2
not; that it is something you should learn from.3
We have been trying to encourage4
employers to log them just for that particular5
reason -- not just this employer, but other6
employers we deal with.7
THE CHAIRPERSON: I think one of8
your colleagues behind wants to speak.9
MR. CLARKE: For the record, Hugh10
Clarke.11
We do log our work refusals. What12
happens is any time there is a work refusal it13
does go in front of the Health and Safety14
Committee.15
I myself was involved in an actual16
work refusal, and as soon as the call was made we17
were instructed automatically to cease what we18
were doing. At that time, we had our safety19
people, Bruce Laing and Neil Quisma, they came and20
inspected the site and saw what was going on21
exactly, and we shut the power completely down on22
what we were doing.23
It was raised at the site Health24
and Safety Committee level. Paul Lafrenière was25
���������
164
involved in it, and it didn't take long to get the1
wheels in motion and it was solved through that2
process.3
THE CHAIRPERSON: Dr. Dosman.4
MEMBER DOSMAN: Thank you, Madam5
Chair.6
Mr. Shier, do the various7
agreements between the unions and the employer8
include health and safety conditions?9
MR. SHIER: I will ask some of the10
union leaders here to say what they have in their11
specific agreements. As I indicate, there are12
many agreements; maybe some that do and some that13
don't. So I will pass that on to some of the14
other people to answer.15
MR. CLARKE: Again, Hugh Clarke.16
I am the President of the Allied17
Council. We encompass eight unions in our18
collective agreement.19
There is nothing specific in our20
collective agreement that states anything about21
health and safety, but we are legislated through22
law. Each of the unions do have members that sit23
on the Health and Safety Committee, which is24
comprised of management and the unions.25
���������
165
As a co-chair, I sit on it because1
of the amount of unions that we do have on site.2
I can only speak for the council.3
There is nothing actually in our collective4
agreement that states anything about health and5
safety. We do have a little clause that says we6
want to work as safe as possible, but there is no7
actual article in there that suggests that.8
MEMBER DOSMAN: Thank you.9
MR. SHIER: If I could, there is10
one of our other members here who I assume has11
something in their agreement.12
MR. PHILIPOSE: For the record, my13
name is Ken Philipose. I am Chair of CRPEG; that14
is Chalk River Professional Employees union.15
We do not have anything in our16
collective agreement as far as health and safety17
is concerned, but the safety culture that we have18
at the company very well takes care of it.19
MEMBER DOSMAN: Thank you.20
THE CHAIRPERSON: Dr. Giroux.21
MEMBER GIROUX: I would like to22
refer to quality assurance, which we have23
discussed quite a bit this morning.24
Quality assurance happens in the25
���������
166
executive offices of AECL and maybe in the union1
executive offices also. It also happens on the2
floor of the facilities and involves all of the3
workers.4
My question here is: Do you get5
feedback from the employees, your members, that6
they feel strained or pressured because of the7
overall objectives of quality assurance?8
Do they react as if they are9
affected negatively in their performance?10
MR. CLARKE: Again, Hugh Clarke.11
With respect to quality assurance,12
anything that any of our members do -- and13
specifically I can talk about any of our stuff14
that we do in the reactor with the loops. If we15
have any piping that is done there, there is a16
route sheet that is brought up through the QA17
process. Everything that is done is QA to18
specific recommendations and specifications to19
ensure that the actual equipment we are putting20
in, the piping we are putting in, as is said on21
the route sheet.22
Any of the welds that are done are23
actually x-rayed through the process on site, and24
that is our way of making sure that the quality of25
���������
167
our work is indeed reflected in the paperwork from1
the quality assurance people.2
MEMBER GIROUX: Very likely this3
is resulting in more demanding specifications for4
the workers. Do they have negative reactions to5
this, or do they understand it? Do they share6
their thoughts with you?7
MR. CLARKE: I have never had any8
of our members come back with anything negative.9
If anything, it proves that we are la crème de la10
crème, I guess you could say, when it comes to the11
nuclear work that we have to do on site.12
There are some things that we do13
that are so different from working in14
construction. I came from a construction15
atmosphere. I have been at AECL for 14 years now,16
and I have never in my life seen pride and17
workmanship as we do at AECL.18
So I have never seen any negative19
impact for quality assurance. If anything,20
quality assurance is nothing but a good thing in21
our eyes.22
THE CHAIRPERSON: Thank you very23
much.24
25
���������
168
03-H2.51
Oral presentation by Deep River Science Academy2
THE CHAIRPERSON: We would like to3
move then to the next intervention, which is an4
oral presentation by Deep River Science Academy,5
as outlined in CMD Document 03-H2.5.6
I believe Mr. French is with us7
today. Welcome.8
MR. FRENCH: Madam Chair,9
Commissioners. Good day, everyone. Bonjour, tout10
le monde.11
I am the CEO and Secretary of the12
board of the Deep River Science Academy, providing13
leadership over the Deep River Campus here in14
Ontario and the Manitoba Campus in Whiteshell.15
I have served in several16
capacities over the past nine years: as principal,17
as a member of the board, and now as the CEO. I18
have been a frequent visitor to the CRL site as19
part of our operations.20
The Deep River Science Academy,21
and henceforth DRSA, supports the renewal of22
AECL's licences to operate at the Chalk River23
Laboratories.24
The DRSA initiative is based on25
���������
169
community partnerships with professional1
laboratories and is endorsed by the financial2
support of local, provincial and federal3
government agencies, as well as corporations,4
foundations and private individuals.5
The two current campuses have been6
established in the science-rich communities of7
Deep River, Ontario and Pinawa, Manitoba, where8
several professional laboratories offer research9
opportunities for DRSA students. The partner10
laboratories voluntarily provide research11
opportunities and the use of their resources and12
scientists for the duration of the program because13
they all share DRSA's commitment to encourage our14
youth to pursue careers in science and15
engineering.16
DRSA has partnered with AECL at17
the Chalk River site for the past 16 years. Our18
business-education partnership has permitted over19
600 high school students and some 300 university20
students from across Canada to test drive careers21
in science and engineering. This success story22
would not have been possible without the vision23
and commitment of AECL management and staff.24
AECL has demonstrated responsible25
���������
170
corporate citizenship throughout our partnership.1
As we prepare for our 17th summer2
program, I know we can count on the senior3
management, department chairmen, scientists,4
engineers, technicians and all support staff to5
ensure that our students have an excellent, safe6
learning experience at AECL, as they have done for7
the past 16 years.8
All DRSA staff and students -- our9
university students are here on site for 16 weeks10
and our high school students for six weeks -- have11
always reported that AECL has operated their12
facilities in a safe and responsible manner. All13
DRSA workers and supervisors are required to14
complete a full-day safety seminar and WHMIS15
training each year.16
The DRSA 2002 annual report was17
provided to the Commission and our latest18
newsletter, sample Exhibit B, and our leaflet on19
the 2002 research projects. All of these20
documents are available -- I have extra copies21
should the Commission require these extra two22
documents -- to show how integral AECL has been23
and the commitment they have made to our24
operation.25
���������
171
They illustrate the significant1
corporate and volunteer commitment to our2
partnership. I encourage you to read the many3
testimonials from students. Many AECL employees4
at all levels have volunteered over the years to5
ensure the success of our program.6
All participants in the DRSA7
summer program have returned to their communities8
with stories of the significance of AECL's9
operations and the positive contributions of AECL10
to the nuclear industry.11
In conclusion, AECL has12
demonstrated responsible corporate citizenship13
throughout our business-education partnership. On14
behalf of the volunteers and staff of DRSA, I15
would lend our full support for the renewal of16
licences to enable AECL to continue to operate at17
the Chalk River Laboratories.18
Our motto for the DRSA students,19
namely, "real laboratory research, learn about20
your future" is only possible because AECL has21
taken all aspects of its operation seriously.22
Thank you for giving us this23
opportunity to support the application for24
renewal.25
���������
172
THE CHAIRPERSON: Thank you very1
much, Mr. French.2
The floor is now open for any3
questions or comments from the Commission Members4
with regard to this submission.5
Dr. Giroux.6
MEMBER GIROUX: I found this7
program quite interesting, but I have a question.8
Do you track what happens to your students, your9
participants, after they have been through school10
and as they start in their career?11
If you do, I would be interested12
to know what sort of proportion go back to work13
for AECL and what sort of proportion, if you know,14
joined the anti-nuclear movement.15
MR. FRENCH: Yes, Dr. Giroux, we16
do track our students, but it is rather difficult17
to do so. Funding is always a problem in our18
organization, and we have to use money from other19
foundations, and so on, to do our research.20
However, we do have assistance from the Ontario21
government to actually do the tracking, and we are22
pursuing that now.23
We have also developed on our Web24
site an alumni section. The funding from the25
���������
173
Ontario government has allowed us to phone the1
homes. We have all the applications of university2
and high school students going back 16 years, and3
we are going to phone the homes of their parents.4
We are going to track those down that we have not5
contacted and encourage them all to register on6
the site.7
We do have some information after8
our tenth year of operation -- and we are9
presently trying to do this again -- about where10
people went and what they are doing. Most of the11
graduates at that point, 85 per cent, were12
convinced that they should pursue careers in13
science and engineering as a result of this14
experience. It was a very positive one.15
One hundred per cent of our16
students leave Deep River with a positive17
impression of the nuclear industry. If they get18
there on site and have this hands-on experience,19
they realize that all the work that is being done20
is in the best interests of all Canadians and is a21
positive contribution to our Canadian society.22
We have yet to have anyone go away23
from here telling stories about this industry that24
are negative.25
���������
174
We had one university student who1
didn't come because his mother felt that he should2
not be working that closely to a reactor.3
THE CHAIRPERSON: Further4
questions?5
Thank you very much.6
7
8
03-H2.69
Oral presentation by Canadian Nuclear Association10
THE CHAIRPERSON: We would like11
now to move to the next submission, which is an12
oral presentation by the Canadian Nuclear13
Association, as outlined in CMD Document 03-H2.6.14
We have with us today the Director15
of Regulatory and Environmental Affairs for the16
CNA, Mr. Al Shpyth.17
Mr. Shpyth, the floor is yours.18
MR. SHPYTH: Thank you for the19
opportunity to speak. For the record, my name is20
Al Shpyth, and I am the Canadian Nuclear21
Association's Director of Regulatory and22
Environmental Affairs.23
In this capacity, our association24
lends support to our member companies, and we are25
���������
175
pleased to appear today in support of AECL's1
applications for the Chalk River facility and the2
associated facilities that the Commission will be3
hearing from today as well, the MAPLE reactor and4
the New Processing Facility.5
Recognizing the Chair's6
instructions, I will simplify our submission,7
which was going to speak to all three, and touch8
on the reasons why the CNA is supporting the9
applications that are being considered today,10
beginning with Chalk River.11
The Chalk River Laboratories have12
a long and very distinguished history of13
supporting, through research and testing, Canada's14
advanced nuclear industry, and significant work15
has been done at CRL with regard to reactor16
physics, chemistry, fuels, materials, engineered17
systems in support of the development of the CANDU18
reactor technology, as well as nuclear medicines19
and radioisotopes.20
With respect to the interests of21
the Commission, the CNA notes that AECL's22
application is supported by a number of site-wide23
programs. As we have heard today, these programs24
manifest themselves in many ways but including an25
���������
176
excellent safety record in the region of one1
million lost-time free hours.2
These programs, which cover3
environmental protection, quality assurance,4
emergency planning -- the range is well known to5
members of the Commission -- ensure that6
reasonable measures are in place to support7
emergency preparedness, environmental protection,8
radiation protection, nuclear security, safeguards9
and non-proliferation requirements as set out by10
the Commission and its staff. We believe these to11
be substantive.12
I also heard that AECL is13
committed to continual improvement. As with any14
overall commitment to manage programs, AECL's15
commitment to continual improvement has allowed16
them and resulted in them taking on and completing17
a number of projects to improve said operations,18
one of which has been noted today, the active19
drain replacement project, which promises not only20
a new state of the art approach to tracing and21
detecting leaks from drains, which will minimize22
the potential for uncontrolled releases to the23
environment, but will also allow them to take24
corrective and preventive actions to minimize the25
���������
177
likelihood of reoccurrence and further releases.1
Improvements in waste management2
practices and other improvements that have been3
identified by AECL will further reduce the already4
low exposures and emissions associated with5
operations at Chalk River.6
Given the scope of these7
activities and the many facilities at CRL, AECL8
undertakes a comprehensive community relations9
program to ensure members of adjacent communities10
are well informed and kept up to date with11
developments and performance.12
As we have heard today, such13
efforts are recognized and valued by the14
communities.15
Radioactive waste management16
issues often arise as a public concern in our17
industry, and information supplied by AECL18
provides evidence that overall radioactive waste19
management has been undertaken in an effective and20
responsible manner.21
We have heard doses to workers are22
down over the course of the current licence23
period, as are lost-time accidents, airborne24
emissions, liquid emissions.25
���������
178
We are also aware from submissions1
that the applications before the Commission2
concerning the MAPLE reactors and the associated3
New Processing Facility will effectively advance4
the technology to be used for medical radioisotope5
production; and not only in terms of production6
and security of supply, which are very important,7
but also with respect to health, safety and8
environment in forms again of lower dose, lower9
releases and lower potential consequences of10
accidents.11
These are all very positive12
developments that we see at the site.13
If I may touch briefly on those14
other associated facilities, the MAPLEs and the15
New Processing Facility, certainly the MAPLE16
reactors which are going to be constructed and17
operated by AECL at the Chalk River site are very18
important, not only to Canada but also to the19
future supply of nuclear medicine, and these20
reactors and the site will see a number of firsts:21
the first dedicated medical isotope production22
reactors in the world and the first new reactors23
in Canada since the completion of Darlington in24
1993.25
���������
179
As we heard, these new processes,1
the new facilities, the MAPLE and the New2
Processing Facility, will help Canada play a vital3
role in global supply of medical isotopes. But4
importantly, I think from a public perspective,5
these new facilities will represent very modern6
facilities, meeting all applicable regulatory7
requirements.8
Also, we believe, given the nature9
and the management systems in place, there will be10
very low risk associated with their operation, and11
it should receive support.12
Finally, the New Processing13
Facility, which is intimately tied with the new14
MAPLE reactors, is going to provide an improvement15
over current processing at Chalk River, in that it16
will bring forward advanced waste management17
techniques with the processing of the isotopes,18
offering the opportunity to further reduce19
potential environmental impacts associated with20
reactor produced medical isotopes.21
We believe the New Processing22
Facility is a major aspect of operations with23
respect to MAPLE and the site overall, bringing24
forward again key improvements and helping to25
���������
180
provide and continuing to provide the positive1
features of the site: safe and reliable production2
and safe and reliable series of nuclear activities3
in support of medical isotope production with a4
high degree of environmental protection.5
To conclude, our association is6
endorsing AECL's applications to renew the site7
operating licences for Chalk River and the MAPLE8
and New Processing Facility.9
Chalk River certainly is a10
cornerstone of Canada's power and research reactor11
industry. It makes positive contributions in a12
very significant way for both utilities,13
businesses, patients and students.14
We believe AECL works hard to15
ensure that Chalk River is a safe and secure place16
in which to conduct nuclear business, and its17
effort is being rewarded with good performance.18
We think the submissions that have19
been made demonstrate that AECL is operating the20
facilities at Chalk River safely and responsibly.21
We think AECL has demonstrated a strong commitment22
to health, safety, safeguards, security,23
environmental protection.24
We believe the renewal of these25
���������
181
site facilities licences presents low risk to the1
public, to the workers. There is a good record of2
releases being below regulatory limits; a system3
that is working, safety systems that are meeting4
requirements, and the overall performance of AECL5
is meeting requirements.6
We think this has all again been7
reflected in the high degree of support that Chalk8
River is enjoying from its neighbouring9
communities.10
Thank you again for the11
opportunity to speak. I would be pleased to12
answer any questions.13
THE CHAIRPERSON: Thank you very14
much for your presentation.15
Are there any questions or16
comments from Commission Members?17
Dr. Giroux.18
MEMBER GIROUX: I think we realize19
quite well that you are representing the nuclear20
industry, and AECL and MDS Nordion are members of21
the organization.22
In considering that, does the23
Association itself have any concerns concerning24
the report card which has been presented by staff,25
���������
182
which includes four areas out of fourteen which1
are below requirements?2
Does that concern the Association?3
MR. SHPYTH: As a whole, the4
industry association is interested in and is5
concerned with overall industry performance. As6
an industry association as a whole, we are7
supportive of efforts our members take to improve8
the performance, be it the reactor setting, in9
their capacity factors, in program evaluations.10
It is something we know and have come to believe11
has been demonstrated elsewhere; that solid12
performance with respect to environment, health13
and safety is very much tied to solid performance14
in other areas that the industry is interested in:15
economics. And both can make a significant16
contribution to the level of public support.17
We are pleased to see that the18
systems that AECL have in place are showing19
improvement in a number of those areas that were20
identified as concerns earlier and are supportive21
of our members' efforts to bring about those22
improvements in their programs.23
THE CHAIRPERSON: Dr. Dosman.24
MEMBER DOSMAN: If I might, Mr.25
���������
183
Shpyth, would I be correct if I surmised from your1
reply to Dr. Giroux that safety, at least until2
this time, has not been a major component of your3
Association's activities?4
MR. SHPYTH: If that is what I5
implied, I will apologize. It certainly was not6
the intent.7
The industry association is8
interested in not only its members' interests; it9
recognizes that for the nuclear industry to be10
successful, it has to also be able to respond11
positively to the public's interests.12
With respect to environment,13
health and safety, we see those are areas where14
the industry and the public and the regulator15
actually all share a common interest. We all want16
to see well-run facilities, safe for the workers,17
safe for the public, safe for the environment.18
So if I implied that it has only19
been a recent concern, then I was in error in20
giving you that impression.21
MEMBER DOSMAN: Thank you.22
THE CHAIRPERSON: Thank you very23
much.24
We are going to take a ten-minute25
���������
184
break. Then we will be back and resume our1
hearing.2
--- Upon recessing at 3:40 p.m.3
--- Upon resuming at 3:45 p.m.4
5
03-H2.186
Oral presentation by National Research Council7
Canada8
THE CHAIRPERSON: We will now move9
to the next submission, which is CMD 03-H2-18. I10
believe Dr. Root is with us today as Director of11
the Council.12
Dr. Root, please proceed.13
DR. ROOT: Thank you very much for14
the opportunity to make this presentation. As I15
am limited to 10 minutes and, as your letter16
points out, I will use my allotted time to17
emphasize key points of the letter that you have18
already received.19
I would like to focus on the20
importance of the unique facilities at Chalk River21
Laboratories for science, technology, education22
and society in Canada and worldwide, and I would23
like to amplify and explain the community that we24
are talking about.25
���������
185
This hearing is about1
communication and good management of the licensee2
with regards to the community. In my case, the3
community is an international community of4
scientists who use Chalk River Laboratories as a5
resource for their research.6
I believe there are slides.7
My name is John Root. I am the8
Director of the NRC's Neutron Program for9
Materials Research, which is operated at Chalk10
River all the time. A small staff of scientists11
and technicians who operate a suite of instruments12
at the NRU reactor as an international user13
facility.14
Next slide.15
In 1999 Canadian Bert Brockhouse16
won a Nobel prize in physics for the pioneering17
work he completed in Canada. He developed this18
technique called neutron scattering, which is a19
powerful and versatile method for looking at20
materials at the level of molecules and nano-21
structures.22
This is a very powerful probe of23
materials and the knowledge that you get with24
neutrons can be spun out into every aspect of life25
���������
186
and society. He was quoted as saying:1
"If the neutron did not exist2
it would need to be invented."3
In order to use neutrons to probe4
materials you need a neutron source and it needs5
to be a large-scale facility.6
Could I see the next slide,7
please.8
In Canada, our only suitable9
source of neutrons is the NRU reactor at Chalk10
River, which was built in 1957 as a multi-purpose11
neutron source. One of the things that we do is12
take neutrons out of the reactor through beams,13
direct them on materials to learn about their14
structures at the molecular and nano-level.15
This is still one of the top five16
neutron sources in the world for this kind of17
scientific research.18
Next slide.19
So we are running a neutron beam20
laboratory. It is a national facility. Around21
the NRU reactor on the main floor there are five22
neutron spectrometers. These are the instruments23
that use neutron beams from the reactor to probe24
materials.25
���������
187
The operation is managed by the1
National Research Council. We have users from2
university, industry and government laboratories.3
Across Canada we are dealing with over 204
universities and around the world people from5
every continent.6
Next slide, please.7
So there it is as a picture. It8
is not very easy to see. But it is truly a9
national program.10
There are over 350 people who are11
members of the Canadian Institute for Neutron12
Scattering, which is the advocacy group that13
represents the needs of neutron scatterers in14
Canada to decision-makers and funding agencies.15
Over 250 of those members are from16
Canada and they include professors, scientists17
from industry, students and interested persons18
from the public.19
Next slide, please.20
The research on materials has both21
academic and industrial applications.22
Just to give you an idea of how23
many human beings come to the laboratory each24
year, last year there were 91 different people25
���������
188
making 110 visits to the lab to get hands-on1
experience with the neutron beam instruments.2
Fifty-one of these were Canadians, 33 of them were3
students.4
They were in projects involving5
over 200 researchers, not all of whom visit, many6
of whom are connected from their home institution.7
The photographs give you an idea8
that the materials fall into many different9
disciplines, structural chemistry, materials10
engineering, biophysics, mineralogy, and so on.11
Next slide, please.12
So you can guess that there is a13
very important aspect of our operation to do with14
education, developing highly qualified personnel15
for Canada's innovation system. We are bringing16
these people to use an important nuclear17
technology to learn the scientific method, to work18
in a production laboratory and then to go out into19
society and make an impact.20
One of the roles that we see that21
is important at Chalk River is the development of22
highly qualified personnel, even for the nuclear23
industry. In our part of Chalk River we run24
summer schools, workshops, we have hands-on25
���������
189
experiments, projects at our graduate student1
theses and positions for post-doctoral2
researchers.3
Next slide, please.4
Although a large portion of our5
work has results that go into the public domain,6
publications and peer review journals, a certain7
fraction of what we do, about 15 per cent, is of8
direct impact on industry. By this we mean not9
the nuclear industry but all of industry.10
There are some photographs here to11
show examples. In the automotive industry we use12
neutrons to probe inside an intact engine block,13
which is a prototype. The question is asked of14
the car manufacturer: What are the stresses15
inside the block? Only neutrons can get that16
information out non-destructively. That has a17
bearing on new products, improved gas mileage,18
improved reliability of an industrial product.19
At the bottom left there is a man20
holding a black tank. That is a compressed21
natural gas cylinder. It is actually thin-walled22
aluminum, very light, suitable to carry around in23
a car. To give it the strength to hold the24
compressed gas is a carbon fibre epoxy. It is an25
���������
190
innovative product developed by a Canadian1
company.2
The question that neutrons are3
providing the answer for has to do with4
suitability or fitness for service of this5
pressure vessel, which is evaluated through6
computer modelling, but we need neutrons to test7
whether the computer models are true or not.8
There are other examples from other industries.9
These are talking about hard10
materials and the issues we deal with are public11
safety, economics, opening new markets and12
addressing regulatory concerns.13
Next slide, please.14
The laboratory is constantly15
innovating and we are moving into new areas. The16
growth areas right now in Canada's program are in17
the medical and life sciences, foods, polymers and18
information technology.19
These are the materials of the20
21st century where the length scale of structures21
is measured in nanometres rather than angstroms.22
So you are looking at things like membranes and23
proteins in living systems, you are looking at24
electronic devices that have layers that are25
���������
191
nanometres thick like plastic, light emitting1
diodes for computer displays, you are looking at2
foods.3
So we are dealing in general with4
soft materials now, issues of health and lifestyle5
and, again, economics, opening new markets and6
regulations.7
Next slide, please.8
One example to give you an idea of9
an impact neutrons can make on health. This is a10
new material which is a lipid. Basically it is a11
biological molecule that can be prepared in a way12
that creates little hollow spheres into which you13
can place a pharmaceutical. These spheres can14
then be injected into the body, they can be made15
site-specific, to be attracted to a tumour for16
example, and deliver the pharmaceutical over a17
suitable half-life in a most efficient way.18
Where neutrons play a role here is19
in learning about the size, shape and stability of20
the vesicles under various conditions so that the21
material and the product can be developed as22
quickly as possible.23
The final slide.24
To highlight comments related to25
���������
192
the licence, I think our experience working with1
the licensee at Chalk River has been very2
positive. The regulatory environment is3
challenging. The way that we interact with the4
licensee, through a contract with them, is to be5
effectively a branch of Atomic Energy of Canada6
Limited, so we are obliged to follow all of the7
same safety regulations, training protocols,8
procedures for working with radiological materials9
and radiation-emitting devices. We follow the10
same rules as the licensee and fit seamlessly in11
with their management of the safety issues.12
We find the communications with13
the licensee to be continuous, frank and14
practical. We feel that we get high quality15
support from the licensee and that they are, in16
effect, providing the support to an important17
national and international community.18
It is my sincere opinion that19
safety is a top priority for the licensee, just as20
it is for the National Research Council of Canada.21
It is very important to us that when we bring22
users on-site that they are not subjected to any23
undue risk from a radiation point of view.24
Thanks.25
���������
193
THE CHAIRPERSON: Thank you for1
your presentation.2
Are there any questions or3
comments for this presentation?4
Dr. Dosman.5
MEMBER DOSMAN: Thank you, Madam6
Chair.7
Dr. Root, I am impressed at what8
your laboratory does. However, in regard to your9
letter, your comments on security, I was wondering10
whether these comments had been approved by the11
President of NRC or the Board of NRC?12
DR. ROOT: This letter was13
reviewed by Corporate. Secretary General was the14
person who reviewed it and approved it.15
MEMBER DOSMAN: Thank you.16
THE CHAIRPERSON: Dr. Giroux.17
MEMBER GIROUX: That was my first18
question, so that is answered.19
The other question is: Your20
visiting scientists and students, are they21
considered as nuclear workers in terms of the22
dose?23
DR. ROOT: Yes. As I said, we are24
subjected to the same procedures as the other25
���������
194
employees of AECL. So the first step is to1
receive Group 4 training when they arrive on site,2
which is given to all contractors, and it is to3
inform them about the general safety issues of the4
site, the alarms, what to do in the case of an5
emergency, and at that time they are informed that6
they are designated to be nuclear energy workers.7
MEMBER GIROUX: I'm sorry, that is8
not exactly my question.9
DR. ROOT: Okay.10
MEMBER GIROUX: My question was11
concerning the allowable dose that they may12
receive in a year. If they are designated as13
nuclear workers the dose is, what, 5014
millisieverts in one year and 100 in five years.15
Otherwise it is the dose of the public.16
DR. ROOT: They are deemed to be17
nuclear energy workers at the lowest dose.18
THE CHAIRPERSON: Dr. Dosman.19
MEMBER DOSMAN: I was just20
wondering, Dr. Root, if you were aware that the21
Canadian Nuclear Safety Commission and the22
facilities that we regulate are on heightened23
security status at the present time?24
DR. ROOT: I am certainly aware of25
���������
195
that. We have to deal with it every day. Our1
visitors go through the same security checks. We2
have enhanced security clearance to allow them to3
have access to the controlled Area 1. To get the4
ability to have unescorted access in controlled5
Area 2 they have to have site access clearance.6
Not all of our users are able to7
get that clearance and the way we accommodate them8
is to provide continuous escort by our staff.9
THE CHAIRPERSON: Thank you.10
We have said this in a few letters11
lately so I will just repeat what is in the12
letters: The Commission makes no apologies for13
having a high standard of security. We feel that14
this is suitable. The ratings which AECL has15
received are commensurate with their application16
of the requirements that we put forward.17
It is, I think, the current18
reality and probably, I would predict, the future19
reality of facilities in Canada.20
So thank you very much for your21
presentation and thank you very much for coming22
here today.23
DR. ROOT: I certainly didn't mean24
to suggest any other than you have just said.25
���������
196
THE CHAIRPERSON: Thank you.1
DR. ROOT: I am just wanting you2
to recognize that it is a challenge and within3
that environment we are able to work with the4
licensee in a practical way.5
THE CHAIRPERSON: Thank you.6
7
8
03-H2.19 / 03-H2.19.A9
Oral presentation by Citizens for Renewable Energy10
THE CHAIRPERSON: We are now going11
to move to our next submission, which is an oral12
presentation from the Citizens for Renewable13
Energy, as outlined in CMD documents 03-H2.19 and14
03-H2.19.A.15
Mr. Ziggy Kleinau is going to be16
joining us, but he is joining us by teleconference17
today.18
I am just going to wait for him.19
I think he is on-line.20
Mr. Kleinau, are you with us?21
MR. KLEINAU: Yes, I'm here.22
THE CHAIRPERSON: Welcome today.23
Unfortunately you are not with us here in Chalk24
River, but we would like to hear your presentation25
���������
197
and the floor is now yours, sir.1
MR. KLEINAU: Thank you very much.2
Good afternoon, Madam Chair, Members of the3
Commission.4
Thank you very much for the5
opportunity to present a submission on the Chalk6
River Laboratories operating licence renewal on7
behalf of Citizens for Renewable Energy, a non-8
profit organization incorporated in Ontario seven9
years ago. A considerable number of our members10
reside in the downstream region of the Ottawa11
River.12
I am at a bit of a disadvantage by13
not being able to listen to the proponents and the14
CNSC staff presentations, so please keep that in15
context with our presentation.16
With your permission, I would like17
to go first to our supplementary submission, the18
H2.19.A. We would like to express our concerns in19
regard to the MOX fuels that have been shipped20
from the USA and Russia by air transport two years21
ago.22
We really are very upset that this23
plutonium -- actually is the plutonium from24
decommissioned nuclear warheads -- is being tested25
���������
198
there and treated. We are looking especially at1
the Russian MOX fuel has almost one-third more of2
the A-bomb plutonium 239 than MOX fuel from3
reprocessing for civilian reactor use.4
The A-bomb trigger has the unique5
propensity to go super critical. That needs to be6
especially pointed out in context with any7
accident scenario.8
We have looked at the emergency9
planning, first the CNSC staff. There are only a10
couple of small lines in the CNSC CMD. They are11
looking at on-site events only. I can't believe12
that nobody would ever figure that there couldn't13
be any off-site problems with events, emissions,14
especially with a lot of plutonium on-site.15
AECL has a few chapters on their16
emergency planning, but they are saying that full-17
scale simulated off-site tests are only done every18
five years. We are very upset about something19
like that. Over five years a lot of planning20
could go by the wayside and how effective would it21
be to have these tests only every five years?22
We really need to be assured that23
there are emergency planning tests on off-site24
events done more than a year, every year.25
���������
199
We also have a concern with the1
failure of AECL to submit the complete2
decommissioning plan, including full financial3
guarantees as required under any new or renewed4
licence. Apparently the CNSC let's them get away5
with having it in place only at the end of this6
year. I can't see how a licence can be given to a7
proponent under those circumstances.8
We also object to the9
discriminatory withholding of information from the10
public stakeholders, shareholders, necessary to11
judge safe and precautionary operation of the12
facilities.13
I have been trying to read the14
submission on the preliminary decommissioning15
plants and it certainly gives me a case of black16
out because of all the black ink in there.17
We have reviewed the CMD 03-H2 and18
are appalled at the way CNSC staff evaluates that19
operation of this huge nuclear research and test20
establishment operated by Atomic Energy of Canada21
Limited since 1952. Reading in the introduction,22
the last sentence on page 6 says it all:23
"Therefore, staff's conclusion24
is that the proposed further25
���������
200
operation of CRL is acceptably1
safe, even though the program2
portion of two safety areas3
and the implementation portion4
of 3..."5
Yes:6
"...3 safety areas are7
assessed as `below8
requirements'." (As read)9
Where is the logic? Do we not10
have to have at least a "meets requirements" "B"11
rating to let this highly dangerous research plant12
continue to operate?13
No improvement is expected,14
according to staff, in quality assurance and15
training programs. AECL has not bothered to16
address issues in its top tier Quality Assurance17
Manual setting out its general requirements and18
practices that CNSC staff found unsatisfactory.19
20
Processes are not clearly defined21
for, among others, environmental protection,22
procedure control and implementation and the23
disabling of certain safety equipment.24
The CMD goes on and on with more25
���������
201
than seven deficiencies that showed up in a 20011
audit which AECL has failed to address.2
We should stop right there,3
because obviously safety is not one of AECL's4
concerns.5
ALARA rules are not a priority to6
AECL, as argon-41 emissions assessment has not7
been completed to staff's satisfaction. Radiation8
protection is a significant part of the nuclear9
safety culture, however AECL failed to meet even10
some of its own requirements in addition to some11
CNSC regulatory requirements. That is found on12
page 22.13
Since fire protection is such an14
important safety issue, the proposed operating15
licence conditions 10.1 to 10.5 should have16
immediate implementation dates inserted. We don't17
see them in the draft licence.18
Since several of the safety system19
upgrades of the aged National Research Universal20
reactor, the NRU, are still outstanding, this unit21
should be taken out of service and not permitted22
to operate until fully safety tested and then23
definitely shut down at the previously agreed24
date.25
���������
202
Decommissioning plans and1
financial guarantees are not in place. We need a2
rigorous approach by the Commission to assure the3
public of upholding its mandate.4
We also find that there is quite a5
lack in the radiation monitoring, because the6
staff points out they have no figures, no7
estimates on what kind of Cobalt-60 and C-14 is8
going with the plume into the Ottawa River. That9
is something of great concern to us and our10
members.11
So we strongly recommend the12
Commission only issue a provisionary licence of13
six months, to force AECL to speedily correct all14
those serious safety shortcomings.15
Thank you very much for taking our16
deep concerns and our recommendations under17
serious consideration.18
I would like to stay on the line19
in case there are questions.20
THE CHAIRPERSON: Yes, please, Mr.21
Kleinau. Please stay on the line.22
MR. KLEINAU: Thank you.23
THE CHAIRPERSON: You are right,24
earlier in the day there was a fairly extensive25
���������
203
discussion of some of these issues. I would like1
to just start by asking CNSC staff if they could2
just give Mr. Kleinau an update with regards to3
the ratings that were discussed earlier and then I4
will open the floor for questions from the other5
Commission Members. There were a number of other6
issues that weren't discussed today or weren't7
specifically addressed.8
Mr. Howden.9
MR. HOWDEN: Barclay Howden10
speaking.11
Since Day 1 there has been changes12
to the ratings and those were included in our13
supplemental CMD that was issued on April 2nd.14
The changes are:15
for performance assurance the16
trend is now being shown as improving;17
for radiation protection the trend18
is being shown as improving; and19
for security implementation has20
been upgraded to "meets expectation" and the21
improving trend continues.22
MR. KLEINAU: Hello.23
THE CHAIRPERSON: You are still24
with us, sir.25
���������
204
MR. KLEINAU: Okay. Yes?1
THE CHAIRPERSON: We did explore2
this morning the reasons behind the changed3
rating.4
I will turn it over to my5
colleagues first for any questions for Mr.6
Kleinau.7
I guess I have a question for8
staff that comes out of your submission, sir, and9
that is with regards to fire protection.10
Are there any comments that staff11
would like to make with regards to Mr. Kleinau's12
presentation?13
MR. HOWDEN: Barclay Howden14
speaking.15
The five new fire conditions that16
are in the proposed new licence would come into17
effect the day the licence is issued, if it is18
issued, by the Commission.19
THE CHAIRPERSON: The second20
question would be with regards to MOX.21
Are there any comments that AECL22
would like to make about MOX?23
MR. LAFRENIÈRE: Yes. I think the24
first comment is, this was a program conducted at25
���������
205
the request of the Government of Canada.1
The other point I would like to2
make is that we are talking about quantities of3
MOX about the size of two "AA" batteries. So I4
think some of the allusions were not quite the5
actual situation.6
THE CHAIRPERSON: Are there7
further questions for Mr. Kleinau?8
That seems to be all the9
questions, sir. Thank you very much for10
participating. I realize by teleconference it is11
not quite the same as being in person, but thank12
you very much.13
MR. KLEINAU: It was pretty hard14
to get up there with about two feet of snow on the15
ground at this place here.16
THE CHAIRPERSON: Yes. It's hard17
to believe it's April.18
Thank you very much, sir.19
MR. KLEINAU: Thank you.20
21
03-H2.2022
Exposé oral par le Club Richelieu-Longpré23
LA PRÉSIDENTE: Nous allons24
maintenant passer au prochain mémoire, une25
���������
206
présentation du Club Richelieu-Longpré, tel1
qu'indiqué dans le CMD 03-H2.20.2
Je crois que le président, M.3
Bernard Sénéchal, est avec nous pour présenter le4
mémoire.5
Monsieur Sénéchal.6
M. LANGLAIS: Merci, madame la7
présidente et membres de la Commission pour me8
laisser la chance de vous parler aujourd'hui.9
Notre président, Bernard Sénéchal,10
ne pouvait pas venir et m'a demandé de le11
remplacer.12
Mon nom est Charles Langlais et je13
suis membre et ancien président du Club Richelieu-14
Longpré qui vient tout juste de célébrer 20 ans de15
d'existence dans la région de Pembroke.16
Notre club est exclusivement17
francophone. Son but est de promouvoir la18
francophonie par le biais d'activités sociales,19
culturelles et humanitaires, plus particulièrement20
orientées vers la jeunesse.21
Je vous dirai tout de suite qu'une22
bonne proportion de nos membres, qu'ils soient23
encore dans le milieu du travail ou à la retraite,24
proviennent des Laboratoires de Chalk River.25
���������
207
Notre club est donc très fier de venir soutenir1
l'Énergie atomique du Canada dans ses efforts de2
renouvellement de permis devant la Commission.3
Durant nos 20 années d'existence4
nous avons vraiment bénéficié de notre association5
avec l'Énergie atomique du Canada, autant pour6
notre club directement que pour les membres de la7
communauté.8
On doit dire que chez EACL ils9
pensent vraiment aux conséquences de leur10
opération sur les alentours. C'est un peu normal,11
me direz vous, car ces gens là vivent tous comme12
nous dans les villages et les villes entourant les13
laboratoires. Ils respirent le même air que nous;14
ils boivent la même eau et ils profitent de la15
merveilleuse nature qui nous entoure et que nous16
voulons préserver.17
Nous recevons régulièrement des18
nouvelles de nos voisins scientifiques afin de19
nous tenir au courant sur ce qui se passe à Chalk20
River. Par exemple, j'ai reçu à la maison le21
numéro 8 des � Nouvelles des Laboratoires de Chalk22
River � pour la période automne 2002/hiver 2003 où23
l'on offre un page entière, une mise à jour sur24
divers aspects du rendement aux Laboratoires de25
���������
208
Chalk River. Tous les paramètres montrés nous1
prouvent que l'Énergie atomique du Canada2
satisfait les normes réglementaires. On peut3
vraiment se sentir en toute sécurité.4
J'y ai même lu, Mme Keen, que vous5
êtes venue dans notre région en Octobre 2002. Je6
suis très heureux que vous soyez venue rencontrer7
les maires et autres intervenants de la région.8
Ce que je retiens le plus de votre discours c'est9
que la Commission canadienne de sûreté nucléaire10
travaille pour la population canadienne et non11
pour les titulaires de permis.12
Je suis tout à fait d'accord avec13
cette position, mais il ne faut pas oublier que14
l'Énergie atomique du Canada travaille aussi pour15
la population canadienne car lorsqu'on regarde ce16
que cette société de la Couronne a fait depuis 5017
ans on se doit de constater que tous les Canadiens18
profitent beaucoup de leur succès et de leur19
superbe technologie.20
En effet, ce sont les réacteurs21
CANDU qui fournissent aux Ontariens une grande22
partie de l'électricité dont ils ont besoin. Les23
réacteurs CANDU sont aussi présents dans d'autres24
provinces Canadiennes.25
���������
209
Aussi, ce sont les radio-isotopes1
médicaux qui sont produits ici à Chalk River qui2
aident à diagnostiquer et à sauver des milliers de3
patients à chaque année, et ce non seulement au4
Canada mais aussi dans plusieurs pays du monde.5
Que dire aussi des prestigieux6
hommages rendus à de célèbres chercheurs qui ont7
travaillé à Chalk River? En plus de ces grands8
personnages les Laboratoires de Chalk River ont9
aidé à former de nombreux professionnels qui10
oeuvrent dans la communauté canadienne et11
outremer.12
L'Énergie atomique du Canada13
participe à fond dans les causes humanitaires14
telles que Centraide à laquelle chaque année les15
employés de ce grand voisin contribuent très16
généreusement.17
Que dire des retombées financières18
très importantes car les quelque 2 000 employés19
des Laboratoires de Chalk River contribuent aux20
taxes locales, achètent dans les commerces de la21
région et aident énormément à faire tourner22
l'économie de la région.23
Je veux vous parler de quelques24
causes humanitaires auxquelles je vois les gens de25
���������
210
l'Énergie atomique du Canada participer. Vous1
connaissez sans doute le � Relais pour la vie �,2
une activité très spéciale qui a pour but de3
ramasser des fonds pour la recherche contre le4
cancer. Il faut vraiment vouloir aider son5
prochain pour passer une nuit entière à marcher ou6
courir avec des gens de partout dans la région,7
parfois des étrangers, afin de compléter le plus8
de tours de pistes possibles. C'est vraiment9
spécial et très touchant de côtoyer des survivants10
du cancer qui viennent nous dire � Que c'est beau11
la Vie! �.12
Eh bien, chaque année le Club13
Longpré participe à cette importante campagne de14
la Société canadienne du cancer et ce qui est15
vraiment particulier c'est qu'on le fait côte à16
côte avec nos amis de l'Énergie atomique du17
Canada. Je vous le dis : ces gens là ont le coeur18
à la bonne place!19
Je veux aussi parler de l'aide à20
l'emploi. L'Énergie atomique du Canada est un21
employeur de choix et favorise grandement les22
jeunes de notre communauté. La semaine dernière,23
soit les 4 et 5 avril, il y avait une foire à24
���������
211
l'emploi à Petawawa et l'Énergie atomique du1
Canada était là pour montrer aux jeunes du2
primaire et secondaire les possibilités pour ceux3
qui veulent apprendre un métier.4
Saviez-vous que l'Énergie atomique5
du Canada s'est affiliée avec une école de Cobden6
afin de montrer aux jeunes comment les techniques7
spécialisées et les métiers fonctionnent en8
pratique? Cet échange de connaissances fait en9
sorte que les jeunes sont beaucoup mieux équipés10
quand ils ont terminé l'école.11
En ce qui concerne notre club,12
nous avons une grande confiance dans les13
gestionnaires de l'Énergie atomique du Canada, et14
je crois qu'ils l'ont démontré constamment surtout15
à la population du comté de Renfrew et à nos16
voisins du Québec.17
Nous tenons donc à dire que nous18
sommes tout à fait en faveur d'un prolongement de19
permis le plus long possible du permis de20
l'Énergie atomique du Canada à Chalk River.21
Madame Keen et membres de la22
Commission, je vous remercie beaucoup pour votre23
attention. Je suis disponible pour répondre à vos24
questions.25
���������
212
LA PRÉSIDENTE: Merci beaucoup,1
monsieur.2
Est-ce qu'il y a des questions ou3
des commentaires?4
Monsieur Giroux.5
MEMBRE GIROUX: Avec votre6
permission, madame la présidente.7
Une première question de curiosité8
personnelle, monsieur Langlais, si vous permettez.9
Pouvez-vous me dire combien il y a de membres dans10
votre club?11
M. LANGLAIS: C'est variable.12
Présentement nous sommes 22 membres, plus ou moins13
un, si je ne me trompe pas. Nous avons eu jusqu'à14
25 membres, des fois une vingtaine seulement, mais15
ça varie aux alentours de ça.16
MEMBRE GIROUX: Merci.17
L'autre question plus de18
substance, j'ai lu que vous êtes une association19
exclusivement francophone. Au sujet des20
communications d'EACL avec la communauté, avec21
l'ensemble de la population, avez-vous22
l'impression que l'information est présentée, et23
publiée également, aussi rapidement en français24
qu'en anglais, et en particulier êtes-vous25
���������
213
sensibles aux questions des mesures d'urgence dans1
lesquelles on peut avoir à sortir de l'information2
très rapidement pour avertir la population?3
Avez-vous déjà eu l'occasion de4
participer, par exemple, à des exercices5
d'entraînement pour les mesures d'urgence et de6
vérifier si l'information vient aussi rapidement7
pour le français que pour l'anglais?8
M. LANGLAIS: L'information à9
laquelle j'ai référé plus tôt, que j'ai reçue pour10
l'automne et l'hiver, était dans les deux langues.11
Alors ça c'est fait régulièrement.12
Pour la sécurité, c'est le même13
genre d'information qui est en général publiée14
dans les deux langues. Je n'ai malheureusement15
pas participé personnellement à un exercice.16
Alors je ne sais pas.17
LA PRÉSIDENTE: D'autres18
questions?19
Merci beaucoup, monsieur.20
21
03-H2.2122
Oral presentation by Sierra Club of Canada23
THE CHAIRPERSON: We are now going24
to move to the next submission, which is an oral25
���������
214
presentation from Sierra Club of Canada which is1
outlined in CMD document 03-H2.21.2
Mr. David Martin is with us today3
to present the submission. He is a policy advisor4
with Sierra Club of Canada.5
Welcome, Mr. Martin.6
MR. D. MARTIN: Thank you, Madam7
President and Members of the Commission.8
I would like to say off the bat9
that the Sierra Club does not accept or feel that10
the rules of procedure of the CNSC are fair to11
public interest intervenors. I won't go into12
details because one of the problems is I only have13
10 minutes, but I would be happy to answer any14
questions on that.15
Chalk River is Canada's nuclear16
sacrifice area and it must be cleaned up. So far17
AECL and CNSC have fumbled the job. With a 100-18
year operational period to come and an additional19
300-year period of institutional control, the20
problem is clearly being left to our descendants.21
That is unacceptable.22
The Sierra Club isn't the only23
group concerned about Chalk River. Let me quote24
another public interest organization on the25
���������
215
disorganization and financial uncertainty that1
surround AECL's clean-up effort. This is a quote:2
"There is no consensus between3
... [AECL] and the government4
on how best to manage these5
activities..."6
Referring to radioactive waste7
management and decommissioning:8
"...or on which federal9
department or agency will be10
financially responsible for11
them beyond the five-year12
period..."13
That is of the current corporate14
plan.15
"While Atomic Energy of Canada16
Limited's commercial17
activities will assist in18
funding these activities, it19
is by no means certain that20
its contribution will provide21
all the funding required."22
That was the Office of the Auditor23
General in its December 2002 report.24
That statement, I would note,25
���������
216
directly contradicts Mr. Van Adel's assertion1
today that AECL is "in excellent shape" for2
decommissioning and waste management.3
I would like to thank Dr. Barnes4
for his earlier questions on the matter of5
disclosure. When Mr. Van Adel comes before you6
and says that AECL is "engaged in open and honest7
communication" and that AECL has a "information8
sharing culture" and that AECL is open and9
transparent, I have kind of a surreal sensation10
that I am saying the emperor has no clothes.11
The background here is that Sierra12
Club of Canada originally made an access to13
information request to the CNSC in February 200214
for AECL's decommissioning documents. We had15
partial releases in May and August of last year,16
but AECL withheld most of the material on the17
basis of security and commercial confidentiality.18
We subsequently appealed that to19
the Information Commissioner on the basis of20
public interest, and I can report to you that just21
this week the Information Commissioner has sent22
off a letter to AECL, with the support of the23
CNSC, and they now have 30 days to respond to that24
and I'm told then the only alternative is for the25
���������
217
Information Commissioner or Sierra Club to take1
them to court to obtain this information.2
I have no problem, let me say,3
with material being legitimately withheld for4
security and commercial reasons, but emissions5
data and names of buildings and decommissioning6
plans should not be kept secret. AECL is simply7
trying to keep the public in the dark about the8
environmental problems at Chalk River. That is9
not right and the CNSC needs to bring pressure to10
bear.11
AECL is withholding most of the12
ecological effects review, contrary to what Mr.13
Lafrenière said earlier when he said that emission14
data was released. He was referring to long-term15
emissions data. It wasn't in that package. We16
received simply a partial bit of the text. The17
appendices weren't included.18
Similarly, many other documents,19
including the preliminary decommissioning plans20
and the detailed decommissioning plans, are being21
withheld.22
Through you, Madam President, to23
Mr. Van Adel, I would like to ask: Is he prepared24
to release this information or are we going to be25
���������
218
in the position of having one Crown agency, the1
Information Commissioner, take another to court in2
order to obtain information, and waste taxpayer's3
money to obtain material that should be on the4
public record now.5
On the matter of the licence6
period, AECL originally asked for a 53-month, that7
is four-year five-month licence. CNSC staff then8
nominally supported a 31-month licence period.9
I would just like to observe that10
since the original licence expired back on October11
31st and they then got a seven-month extension,12
that was really a 38-month licence proposal, not13
31.14
CNSC staff in their Day 2 now15
nominally recommend the 38-month licence. In16
reality this is a 45-month, three-year nine-month17
licence, because of last year's seven-month18
extension.19
I believe that the CNSC already20
sent the wrong message to AECL by extending its21
licence for seven months, to May 31st, without a22
public hearing. It sent another wrong message23
with a proposed extended licence period. Now the24
situation has been aggravated even more.25
���������
219
CNSC staff argue that this is1
because:2
"The licensee shows a3
consistent and good history of4
operating experience and5
compliance in carrying out the6
licensed activity." (As read)7
I.e., consistent with the new8
staff approach to recommending licence periods.9
I believe that AECL has shown just10
the opposite of the consistent good history. The11
upgrade of the performance assessment from "C" to12
"B" for security implementation took place,13
however four of the 14 safety area categories in14
the seven safety areas are rated "C" still, i.e.,15
"below requirements". The balance are "B", that16
is "meets requirements". None of them, no one17
seems to have noted, are "A". Presumably that18
would mean "above requirements".19
That is definitely not the kind of20
performance that we would expect from an21
organization that Mr. Van Adel has referred to as22
"obsessed" -- "obsessed" no less -- "obsessed by23
quality, excellence and safety".24
AECL's lack of good operating25
���������
220
experience can also be seen in consistent delays1
in the decommissioning planning. Why has the2
Auditor General had to raise the red flag that he3
has?4
CNSC staff see only problem with5
their generous concession to AECL and that, of6
course, is the NRU reactor scheduled to be shut7
down at the end of 2005, which was the originally8
proposed licence expiry date. Now it will shift9
to July 31, 2006. So staff have inserted a10
licence condition that the NRU will remain shut11
down "unless otherwise authorized by the12
Commission". That was 13.1.13
Because AECL has already said it14
wants the NRU to continue operating past December15
31, 2005, the CRL extension has the effect of16
taking the NRU life extension out of the17
jurisdiction of a direct Commission decision --18
although I would be happy to be corrected on that,19
but it seems that is what is going on -- and I20
believe that is in appropriate. No direct21
Commission decision means no direct public input.22
CNSC staff are, in effect,23
rewarding bad behaviour by giving AECL an even24
longer licence period.25
���������
221
The opposite should be happening.1
Keeping decisions in the public domain is even2
more relevant to the decommissioning process.3
Staff have allowed AECL yet another extension to4
the deadline for arriving at a financial guarantee5
for decommissioning until the end of the year.6
It is for that reason that the7
Sierra Club of Canada strongly urges you to8
implement a one-year licence. This decision9
should not be delegated to staff, it should be a10
decision of the full Commission. I am referring11
to the decommissioning financial guarantee.12
AECL is not managing its13
radioactive waste and decommissioning14
responsibilities properly. This will affect not15
only the Chalk River site but the downstream16
communities for hundreds of years to come and this17
should be subject to public scrutiny and not18
settled, as usual, in the back rooms in Chalk19
River and in Ottawa.20
I have a question for the21
Commission: If you do not give Chalk River a one-22
year licence, what happens when AECL, predictably,23
again misses its deadline for producing a24
financial guarantee? What happens when AECL again25
���������
222
falls, predictably, behind on its decommissioning1
plans? What leverage will you have?2
On the question of full Panel3
assessment -- I'm sorry, I'm not following my4
time.5
THE CHAIRPERSON: You're fine.6
MR. D. MARTIN: Am I doing okay?7
On the question of a full panel8
assessment, Concerned Citizens of Renfrew County9
and Sierra Club of Canada have called for a full10
panel environmental assessment on the overall11
decommissioning plan for Chalk River.12
CNSC staff and the Minister have13
supported AECL in a narrow interpretation of the14
Canadian Environmental Assessment Act that a15
decommissioning plan does not constitute a project16
under the Act. So about 30-some-odd separate17
decommissioning plans for separate facilities at18
Chalk River have been undertaken with no publicly19
reviewed overall plan integrating them. We can't20
even, as you know, obtain copies of these isolated21
plans.22
This piecemeal, fractured approach23
will have several undesirable impacts. It will24
result in redundant and wasteful analysis; there25
���������
223
will be a failure to take into account synergic1
environmental and public health effects;2
potentially wasteful and ineffective remediation3
efforts will take place; a failure to determine4
the most desirable prioritization for5
decommissioning efforts may not take place; and,6
last but not least, public participation will be7
discouraged.8
I would argue this is in violation9
of section 4 of the Canadian Environmental10
Assessment Act. I won't read that out, but it is11
in my submission. You should also check out12
section 15(2).13
There is a reason, I would argue14
also, why the site licence holder authority has15
been consolidated for all of Chalk River licence16
facilities as Mr. Lafrenière noted. It makes17
obvious sense to me, as it did to him, to18
coordinate management of a complex facility like19
Chalk River Laboratories. There is a reason why20
CNSC staff assesses AECL performance at Chalk21
River not on the basis of individual facilities22
but on the overall site. That is why we have23
those seven safety areas.24
CNSC staff see the logic of this.25
���������
224
They act on it. AECL acts on this and sees the1
logic of it. I strongly urge you to re-evaluate2
the CNSC position. It is a very, very important3
matter.4
Then finally on environmental5
monitoring. Obviously in many respects off-site6
radioactive contamination from Chalk River is the7
most important environmental issue for CRL8
operations.9
The new CRL licence should include10
a licence condition requiring AECL to monitor11
radioactive airborne and waterborne releases,12
including contamination of both groundwater and13
surface water, and to make an annual public report14
on the findings.15
We intend to request emissions16
data from recent years and we ask you and AECL to17
release this information. I would also like to18
obtain, of course, the environmental effects19
review in full. There will be no environmental20
protection ultimately and no public accountability21
without true transparency and disclosure.22
Thank you.23
THE CHAIRPERSON: Thank you, Mr.24
Martin. You have raised a number of questions and25
���������
225
I will get my Commission Members to address some1
of those that they wish to do.2
I think I would like to start out3
first of all just for clarification. On the NRU,4
my understanding and my reading of this CMD -- and5
I just want to make sure I have it clarified with6
the staff -- is that there is an intention to put7
in a licence condition with regards to that.8
I would like the staff to address9
that, please.10
MS MALONEY: It is Cait Maloney11
here.12
You are correct, Madam President,13
staff has proposed a licence condition on that.14
In the condition we have specified that operation15
past 2005 would be at the discretion of the16
Commission. There is no provision for delegation17
of that and staff are not seeking that that18
decision would be made by anyone other than the19
Commission itself.20
MR. D. MARTIN: Can I assume that?21
THE CHAIRPERSON: You can assume22
that the Commission will take on --23
MR. D. MARTIN: It is a hearing24
level decision. Is that right?25
���������
226
THE CHAIRPERSON: Yes, it will.1
Yes.2
MR. D. MARTIN: Thank you for that3
clarification.4
THE CHAIRPERSON: The second5
question that I need to address, you asked me to6
ask Mr. Van Adel a specific question with regards7
to information disclosure. I would like to do8
that.9
Mr. Van Adel, would you like that10
repeated or are you comfortable with the question?11
MR. VAN ADEL: I believe it was in12
reference to a specific instance that is under13
consideration and we will conduct ourselves in14
accordance with the Freedom of Information Act.15
The gentleman from the Sierra16
Club, Mr. Martin, is quite familiar with the17
process. We have gone through a number of18
instances, I think, with the Sierra Club, one in19
particular where recently there was a ruling in20
our favour in terms of not disclosing certain21
information that was requested.22
The intention on our part is to23
conform, not only with the Act, but also to be as24
open as we can be. The areas where we withhold25
���������
227
information are areas that are legitimately1
recognized under the Freedom of Information Act in2
relation to either our commercial activities or3
security matters. The rest of the material should4
be and is available.5
At any point in time there may be6
disagreements about that, but it certainly does7
not reflect our view or intention to be secretive.8
I do appreciate the fact that9
public consultation, and so on, is absolutely10
essential, but I also point out that we are a11
highly regulated and overseen corporation,12
organization. Not only are we regulated by the13
CNSC, but we are overseen by Parliament, we do14
file annual reports, we have four set of auditors15
and we are subject to a great deal of public16
scrutiny.17
The Auditor General was quoted,18
for example, in their recent report which came out19
as a result of the five-year comprehensive audit,20
which I actually asked the Auditor General to21
accelerate so as to give me a view of areas in the22
company where we might improve. Because that23
cyclical five-year process of the comprehensive24
audit by the Auditor General is an extremely25
���������
228
intrusive and probing look.1
What was not quoted was the high2
marks that the Auditor General gave the company3
for its performance across the board, including a4
statement in the report that said that the Auditor5
General was satisfied that we were conducting6
ourselves and managing the operations at Chalk7
River at a high level.8
The reference to the Auditor9
General's desire that there be clarification or10
clarity brought to the issue of the long-term11
funding and obligations with respect to the12
decommissioning, and so on, is a matter that we13
have already discussed and action is being taken.14
The Auditor General did not feel,15
however, that even that consideration warranted16
sufficient attention to table the report in17
Parliament, which only happens in circumstances18
where the Auditor General feels that there are19
deficiencies that are sufficiently grave that they20
should be brought to the attention of Parliament.21
Rather, the report was tabled with management and22
a copy sent to the Minister for action and23
Minister Dhaliwal is responding to that particular24
comment. So just to point that out.25
���������
229
But no, I'm not prepared to1
address the specific request for information, but2
I will and do take such requests very seriously3
and we will try to work something out to the4
satisfaction of both parties.5
THE CHAIRPERSON: Thank you.6
The floor is now open for7
questions from the Commission Members. Dr.8
Barnes.9
MEMBER BARNES: I'm not quite sure10
what the last sentence means. I would just make11
an observation, just as an individual and a12
Commissioner, that we are well aware of the13
concerns of the public with the nuclear industry14
and nuclear power in general.15
One of the concerns is the16
disposal of radioactive waste, particularly high17
level waste, and obviously with the18
decommissioning of major facilities. We are19
clearly as a nation entering the next few decades20
where the decommissioning phase of the industry21
will become quite significant.22
Again, as a Crown corporation23
pledged to excellence across the board, I would24
hope that AECL would set, in a sense, very high25
���������
230
standards for the decommissioning process so that1
other major nuclear utilities would, in a sense,2
follow the lead there.3
I think because the public is4
particularly interested in this, in engaging in5
dialogue with the public so that they can6
participate in this transparent process, the7
public surely, as well as Commissioners, have to8
have a fair amount of information at our disposal9
and one would hope that only the most stringent10
material would be kept out of it.11
I gave some examples this morning12
that at least I was surprised at how much material13
was being excluded from the public information.14
You heard the comments from CNSC staff, although I15
guess you would have had their view anyway before16
today.17
Do I still hear you after today's18
hearings that at this stage you are not willing to19
consider changing the limitation that you have put20
on these restrictions?21
MR. LAFRENIÈRE: Yes, perhaps two22
clarifications.23
One, the emissions information is24
provided annually to the public and it is25
���������
231
available in the reading rooms on the total1
monitoring programs of the CRL site, on-site and2
off-site. That is one clarification. That has3
been available for 20 years I believe.4
The second point is the -- excuse5
me, I have lost my train of thought here.6
Mr. Van Adel.7
MR. VAN ADEL: With respect to8
your particular point, are we not prepared to9
change, what I am suggesting is that the only10
information we would withhold is information that11
we are required to withhold by virtue of our12
compliance with the Freedom of Information Act in13
respect of either commercially sensitive or14
matters which relate to security. It would not be15
in our interest to disclose those, or yours or the16
public. Those are vetted through the CNSC.17
With respect to information that18
the Sierra Club in particular may be requesting,19
there is due process that vets that information20
ultimately and a ruling is made as to whether or21
not it should be released. There is the Privacy22
Commission as well as ultimately recourse to the23
courts in the event that there is a dispute.24
If we were to go to court over a25
���������
232
matter, it would only be in circumstances in which1
we felt that there was a grave concern as to why2
the information not be released.3
So I think we are complying with4
not only the spirit but the intent of full5
disclosure.6
THE CHAIRPERSON: Dr. McDill.7
MEMBER McDILL: So it is your8
opinion, then, that building names would come9
under one of the two categories, to address Mr.10
Martin's question. A question of emissions data11
was just addressed and building names would come12
under one of the two categories?13
DR. FEHRENBACH: Yes. As a matter14
of fact in general that is true. In fact, we15
usually avoid naming buildings, we refer to them16
only by number. That is for security purposes.17
THE CHAIRPERSON: Further18
questions?19
Dr. Giroux.20
MEMBER GIROUX: I would like to21
have a clarification from Mr. Martin.22
In reading your presentation and23
hearing also the oral presentation on the full24
panel involvement of assessment, I'm not sure of25
���������
233
the conclusion you reach.1
You start out by saying that in2
your view the Minister has taken a very narrow3
interpretation of the Act and has decided that no4
panel assessment was required. Then you go on and5
argue essentially for a full panel assessment, but6
without recommending it completely.7
My question is: Are you asking us8
to set up a full panel assessment even though the9
Minister has decided that it is not required?10
MR. D. MARTIN: Yes. There are11
two issues. One is whether an overall -- I12
hesitate to use the word "comprehensive" because13
it would confuse the matter thoroughly, but the14
one issue is: Should an overall environmental15
assessment be conducted, at whatever level,16
whether it is panel or comprehensive, or screening17
for that matter, but an overall review of the18
entire site, subsuming all the facilities at Chalk19
River.20
A second issue is whether indeed21
that assessment should be a full panel review.22
Does that help? Is that the23
source of the confusion maybe?24
MEMBER GIROUX: Not really,25
���������
234
because there has been a decision by the Minister1
and your text could be interpreted as recommending2
to us to bypass the Minister's decision and to act3
on our judgment in a matter in which the Minister4
has authority.5
MR. D. MARTIN: Well, I guess I am6
assuming that the Minister was acting under7
advice. I am asking that the Commission8
reconsider its position.9
MEMBER GIROUX: Which is the10
Minister's position.11
MR. D. MARTIN: Correct.12
MEMBER GIROUX: It is quite13
fundamental because, in my view, if we start at14
one point going beyond what is the framework of15
our legal authority to act because you are not16
satisfied with the Ministerial or other decision,17
or even with the law, where do we stop? I don't18
see any outlet on that.19
MR. D. MARTIN: Let me consider20
that further and I will communicate on that21
matter. Thanks for the question though.22
THE CHAIRPERSON: I think this is23
a very important question and I would like staff's24
view. Then I would like to comment maybe a little25
���������
235
bit about the relationship of our Act and CEAA.1
That might be helpful.2
I will start with the staff3
comments.4
MS MALONEY: Thank you. It's Cait5
Maloney here.6
Perhaps I could clarify. The7
quotation from the Minister that is there actually8
was not in as a result of sort of a formal9
determination. This was a letter from a member of10
the public to the Minister about this.11
The fact that these individual12
plans have not been deemed to be projects is13
because these are preliminary decommissioning14
plans. They are simply documents that we require15
to ensure that planning is going on to do with16
decommissioning. It is not a commitment that AECL17
or any other company is going to be actually18
carrying out work at a specific time. That is why19
they are not subject to the environmental20
assessment process at this time.21
Obviously, if -- I should probably22
say when -- an overall plan is in place and we are23
considering that, that may well be something that24
is worthy of full consideration. That is to be25
���������
236
determined in the future.1
The other point, of course, is, as2
major decommissioning plans are committed to and3
are going ahead, those are subject to4
environmental assessment, but not these plans.5
THE CHAIRPERSON: Perhaps you6
could just also clarify the issue which I think7
is: Certainly the Minister of the Environment,8
Mr. Anderson in this case, is responsible for9
CEAA, et cetera, but the role of CNSC as a federal10
authority, specifically in general with regards to11
AECL and what role we will play in this. I think12
it might be helpful.13
MS MALONEY: I'm sorry, the role14
we would play in?15
THE CHAIRPERSON: As a federal16
authority.17
MS MALONEY: As the regulatory18
authority or the responsible authority we would be19
the organization, when faced with the decision to20
be made by the Commission, responsible for21
determining, first of all, if there were a22
project; then if the project were subject to the23
Environmental Assessment Act, what route should be24
taken, which is prescribed within the25
���������
237
Environmental Assessment Act.1
Staff would also make2
recommendations to the Commission, or to the3
designated officer, if there is one, on the4
desirability of a full panel, which would be5
guided by certain criteria that are laid out in6
the Environmental Assessment Act.7
THE CHAIRPERSON: So I guess it8
does clarify, Mr. Martin, that you are right,9
there is a definite role for the CNSC in this10
area.11
Do you want to comment?12
MR. D. MARTIN: If I could, just a13
question.14
I understand that these are15
preliminary decommissioning plans. Does it make a16
difference that these are progressing to the level17
that is called "detailed decommissioning plans" at18
some point? Some of them are there already. At19
that point is it feasible that an overall EA could20
be conducted? Is that what you are saying21
possible?22
THE CHAIRPERSON: That is a23
question to the staff and then Mr. Fehrenbach24
after that.25
���������
238
MS MALONEY: Cait Maloney again.1
As I indicated earlier, as plans2
move from being preliminary to detailed, that3
obviously is when one is moving towards actually4
doing the work. At that stage environmental5
assessment is undertaken and assessments are done6
and depending on the size of the project it would7
depend whether it came to the Commission or stayed8
down with staff.9
If I could just repeat, if we do10
get the overall plan that we are seeking and that11
moves to having major phases of detailed12
decommissioning plans and commitments to do work,13
those should be coming up as full environmental14
assessment. I will make no comment as to whether15
it would be a panel because that depends on the16
criteria, on the judgment at the time.17
THE CHAIRPERSON: I think, Mr.18
Martin, the staff are supporting the idea that a19
full plan is necessary. Whether that results will20
be evaluated at any particular time, whether it21
results in what category of a CEAA assessment is22
required at that time.23
Mr. Fehrenbach.24
DR. FEHRENBACH: Thank you, Madam25
���������
239
Chair.1
I just wanted to refer to a2
comment I made earlier on the uniqueness of the3
situation in that we are not talking about4
stopping operations at Chalk River next year and5
then beginning decommissioning as we were at6
Whiteshell. So the preliminary decommissioning7
plans that we have prepared have to be considered8
as living documents, because every time we prepare9
or install a new facility that will therefore10
require a change to the decommissioning plan.11
So Ms Maloney's comments are very12
relevant. The decommissioning plan itself cannot13
be considered a project in its entirety, but14
within the plan there will be, from time to time,15
specific decommissioning projects.16
THE CHAIRPERSON: I would just17
like to clarify before I move on to other18
questions. I think that one of the things,19
certainly CEAA is part of the responsibility20
portfolio, if I can put it that way, of the CNSC21
and we take it seriously. In fact, it takes a22
great deal of our time, the issues of planning.23
But I think CEAA requires that we24
have this planning document. I think that it25
���������
240
sometimes is forgotten that it is a planning1
document.2
The Nuclear Safety and Control Act3
gives the Commission and the Commission staff a4
pretty serious set of responsibilities overall5
with the environment, and I think that is what we6
take as sort of the day-to-day work as well is the7
monitoring of the environment.8
So I think that although it is9
important to talk about CEAA, I think a lot of the10
discussions when we talk about licensing are our11
responsibilities and what we carry out in terms of12
safety for the environment. We have talked about13
moving from human to non-human biota as well and I14
think the breadth of this responsibility is15
sometimes forgotten, not by you, sir, but just in16
general, the focus that is sometimes placed on17
CEAA. That is just a comment.18
Further questions, Mr. Graham.19
MEMBER GRAHAM: I will, then, have20
a question. I didn't want to belabour the issues.21
Page 6 of 6 regarding the22
environmental monitoring. Some quite strong words23
are used there in that first paragraph about leaks24
going into the Ottawa River and streams and25
���������
241
groundwater that flow into the Ottawa River are1
contaminated. We have gone through that I think2
already today and I think Dr. Thompson commented3
on this, but is it what is said here, that it is a4
major threat to drinking water to millions of5
people?6
I always get concerned when you7
read these things, but I would like to have the8
science that is in that. It is page 6 of 6.9
CNSC staff comment?10
DR. THOMPSON: For the record, my11
name is Patsy Thompson.12
The assessment that staff carries13
out on a day-to-day basis, and through either14
technical assessments or audits, and other15
compliance activities when they are required,16
focus on not just monitoring radionuclides and17
hazardous chemicals once they are released to the18
environment, but there are also powers under our19
Act to actually control or prevent the emission of20
material to the environment.21
That being said, we have assessed22
over quite a number of years the quality of23
drinking water downstream from Chalk River and24
there is no indication from the data that is25
���������
242
available for drinking water plants downstream1
from Chalk River that the drinking water has been2
negatively or adversely affected by releases from3
Chalk River.4
The information from the City of5
Ottawa, from Pembroke and from Petawawa, indicates6
that essentially concentrations of radionuclides7
that are monitored in raw water before treatment8
are essentially around background values, or what9
are called background values that essentially10
reflect natural occurring levels as well as what11
is left of weapons fallout. So there is no12
indication that releases of material from the site13
through the waste management areas of the process14
sewers have adversely affected drinking water.15
MEMBER GRAHAM: The other question16
I would have is: The testing is ongoing and is17
not just a -- these are ongoing tests with the18
drinking water, are they not?19
DR. THOMPSON: Yes, they are.20
They are being conducted in the case of the City21
of Ottawa, for example, by the City of Ottawa on a22
very regular basis.23
THE CHAIRPERSON: Dr. Giroux.24
MEMBER GIROUX: Coming back to25
���������
243
this question of detailed decommissioning plans,1
my interpretation of what I have heard from staff2
and from AECL is that AECL is there for decades of3
operations and so there will not be a detailed4
decommissioning plan for the whole facility within5
decades, if not more.6
So there will not be an7
opportunity to have a full panel assessment on a8
detailed decommissioning plan for the whole9
facility, but there might be panel assessment for10
specific facilities which may be decommissioned11
within decades. There is no clear plans for the12
coming years, if I understand correctly?13
MR. VAN ADEL: That is correct.14
MR. LAFRENIÈRE: If I may, just to15
clear up a point on the disclosure of information,16
we recognize that there is an issue with the17
quantity of information that has been withheld and18
we have further indicated to the CNSC that we19
would like to meet with them to discuss how we20
could rearrange our documents to ensure a21
publication of more information. This is not an22
easy matter and we are going to need some time to23
work this out with the CNSC.24
THE CHAIRPERSON: Just with25
���������
244
regards to Dr. Giroux's question, CNSC staff, do1
you have a comment?2
MS MALONEY: It's Cait Maloney3
here.4
I would rather not speculate about5
what could or could not go to a panel or come to6
the Commission in terms of public consideration of7
decommissioning plans at this time.8
I think it is appropriate that we9
consider the initiative that Mr. Van Adel10
discussed in his initial presentation, that is the11
work that will be done with Natural Resources12
Canada to look at the whole site, this report to13
Cabinet within two years. That may well be14
something that will influence future plans in this15
area significantly.16
THE CHAIRPERSON: Dr. Barnes.17
MEMBER BARNES: I'm sorry, I know18
it is getting late.19
My perception is rather different20
I think, at least from how Dr. Giroux phrased it.21
Surely a requirement under the Act22
for new licences such as the one that AECL is23
being considered for now, or for major nuclear24
utilities, is that they are required to submit a25
���������
245
decommissioning plan with the appropriate1
financial information. Is that right?2
The level of detail obviously is a3
question of semantics maybe, but at least in order4
to allow our staff to give an analysis of that5
financial information it has to be at a so-called6
fairly detailed level for any particular area on7
the plan. When it comes down to actual8
decommissioning, then obviously things will go up9
to a much more greater level of detail. Isn't10
that how the new Act requires new licensees to11
behave?12
MS MALONEY: It's Cait Maloney.13
The preliminary plans are required14
to be in enough detail for us to do costing on15
that as a basis for the financial assurance, yes,16
you are correct, but they are not a commitment to17
perform the work immediately.18
MR. VAN ADEL: If I can maybe just19
add?20
THE CHAIRPERSON: Mr. Van Adel.21
MR. VAN ADEL: Yes, thank you.22
Perhaps it is my misperception,23
but there is a decommissioning plan for waste24
disposal and for the decommissioning of the site,25
���������
246
various aspects of the site. It is a rolling plan1
that is submitted and it is updated from time to2
time depending on the developments. But it is on3
the basis that we are operating a site which we4
expect to occupy as a going concern for at least5
the next hundred years.6
The plan itself is a hundred-year7
plan for decommissioning and disposal. That plan8
had a certain budget estimate associated with it9
that was submitted to the government, the10
shareholder, along with the plan.11
As a result of that, there is a12
number on our balance sheet which identifies the13
net present value of the estimated hundred-year14
cost of the plan. That number is currently $38615
million.16
We are revising that number. In17
fact, it may go down a few million this year as a18
result of the rate of expenditure against that19
plan and the interest rate calculations that are20
imputed to get the net present value.21
But the total value of that plan,22
that net present value on a hundred-year basis is23
close to $3 billion. That is a plan that calls24
for the decommissioning of assets under AECL's25
���������
247
control, but given that it is a hundred-year plan1
it is firm in terms of what we are going to2
specifically do and accomplish by way of projects3
going forward to the balance of our five-year4
plan.5
Beyond that we can have notional6
plans as to what we are going to do in year 10 or7
11, but then if we build MAPLE reactors on the8
site or move things around or make changes in the9
plan or decommission one building versus another10
because there is a greater fire hazard or11
something, then that plan has to be updated and12
constantly resubmitted.13
Now, we are in the process of14
updating that plan today and we will be submitting15
a revised plan which has a hundred-year outlook16
and has a firm three to five-year forecast17
associated with our work plan for the next18
planning period. That will be approved and the19
number will be adjusted on the balance sheet20
upwards or downward based on commitments from the21
federal government, the shareholder, to fund that22
on a go-forward basis.23
The Auditor General's comments24
were simply to say: We encourage the government25
���������
248
to address the issues of the long-term funding by1
way of the plans that AECL submits and if the2
amount goes up it should be recognized.3
Now, the recognition on our4
balance sheet was a discussion that took place a5
few years ago with the shareholder whereby the6
liability, recognition of the liability which7
rests with the federal government, was a number8
that was not known. It wasn't quantified. AECL's9
financial statements were qualified each year by10
the Auditor General and the auditors because we11
did not have an imputed value of the long-term12
cost of decommissioning.13
Now, we do have that and our books14
are no longer qualified and they are signed off by15
our auditors, including the Auditor General,16
annually on the basis that that amount that is17
represented there is an adequate representation of18
what the 100-year plan is on a net present value19
basis. We revisit that from time to time. The20
Board of Directors examines it, we examine it in21
management and it goes forward to the government22
from time-to-time as part of our five-year plan.23
In this five-year plan submission,24
we have identified the possibility that in the out25
���������
249
years there may be more money required than is1
currently identified in the plan and that has been2
submitted as part of our corporate plan to3
Treasury Board and the government, in signing off4
on the plan, is recognizing that there is an5
unfunded amount that is an amount that may be in6
excess of what is currently recognized on our7
books that they have to address in the future, and8
they will address that as part of a revised9
hundred-year plan that we submit to them. That is10
the process we are talking about here.11
In addition to that, the12
Government of Canada has requested NRCan do a two-13
year study -- and it may not take two years, but14
they have given them up to two years to come back15
with an examination of whether or not the current16
disposition of liabilities as between AECL and the17
Government of Canada, as they are formally18
recognized, is the appropriate approach and19
whether or not there ought to be another20
institutional response or even another way of21
recognizing the liabilities, that is perhaps shift22
them back to the federal government and have them23
recognized and funded in a different manner than24
they are today. But when that study is done the25
���������
250
recommendations will go back through the Minister1
to the Cabinet for consideration.2
So I think that the action is3
being taken here to address this against a4
hundred-year plan. I don't see any particular5
problem in the next few years, even within the6
timeframe of this licence, that would impact on7
this question.8
I mentioned a number of mitigating9
factors, including the formal recognition by the10
Government of Canada, that they have obligations11
contained within our five-year plan that they must12
fund. And the funding for that is adequate, it13
comes from a number of sources.14
So I really believe that we are15
being responsible, as is the Commission, in going16
forward with the licence on the basis that this17
issue is not only adequately provided for today18
within the timeframe associated with the licence,19
but it is currently provided for adequately by not20
only recognition by the government but by the21
amounts represented on our books which the22
government signs off on and says: Yes, we23
recognize we have a net present value obligation24
of $386 million for decommissioning based on a25
���������
251
plan that we have today. We also recognize there1
may be additional amounts required.2
So I think we are in pretty good3
shape on this issue and that is the basis upon4
which in my opening remarks and later on I said5
that I felt this was an issue which was being6
adequately addressed.7
Thank you.8
THE CHAIRPERSON: Thank you very9
much, Mr. Martin.10
11
12
03-H2.2213
Oral presentation by The Corporation of the Town14
of Deep River15
THE CHAIRPERSON: We are now going16
to move to our next submission, which is an oral17
presentation from the Corporation of the Town of18
Deep River, as outlined in CMD document 03-H2.22.19
Mr. John Murphy, the Mayor, is20
going to present this submission.21
I would just like to note that it22
was during a visit with Mr. Murphy last year that23
he was the one who actually invited us up for Day24
2 of the hearing. We are not in Deep River, but I25
���������
252
would just to acknowledge his invitation started1
the process by which we are here today.2
Mr. Murphy.3
MAYOR MURPHY: Thank you, Madam4
President and Members of the Canadian Nuclear5
Safety Commission. Good afternoon and welcome to6
the Upper Ottawa Valley. Although I am a little7
late in the day to offer the welcome, welcome8
nonetheless.9
It is most appropriate that you10
have scheduled this day of the hearings on the11
applications from Atomic Energy of Canada Limited12
for renewal of the several licences for the Chalk13
River Laboratories here in the Chalk River.14
As the President has noted,15
although the Town of Deep River issued the16
invitation, the reality in smaller communities is17
often there are only one or two appropriate sites18
for a fairly large gathering and this particular19
building is one of probably the better ones that20
might have been chosen. So we have no problem21
with the fact you are actually meeting in Chalk22
River.23
It is a pleasure for me to have24
this opportunity to make this oral presentation on25
���������
253
behalf of the Town of Deep River to you to augment1
the Town's written submission on these2
applications before you today.3
We in Deep River and in the4
surrounding area regard this as the home of the5
Canadian Nuclear industry with the establishment6
of Canada's research program here in 1944.7
Nationally we feel very proud of8
the excellent work that has been done and9
continues to be done by our friends, neighbours10
and family members at the CRL. Therefore, we11
strongly support the renewal of the CRL nuclear12
research and test establishment operating licence13
which you are presently considering.14
Those of us who have lived in this15
area for some time are well aware of the16
continuous improvements that have been made at CRL17
over the years in terms of worker safety,18
reductions in average radiation exposures, greater19
emphasis on employee training, the quality20
assurance program and a continuing focus on the21
protection of the environment. Of course we heard22
comments on some of those specific things earlier23
from other intervenors.24
As well, there has been a steady25
���������
254
progress in public consultation efforts by AECL1
over the years through several types of forums.2
Again, some of those have been mentioned and are3
mentioned in the written submission.4
Unfortunately, as a result of 9/115
and the ensuring much greater emphasis site6
security, access to the CRL site for visitors7
generally, and for briefings for local officials,8
et cetera, have obviously had to be curtailed.9
That is unfortunate. However, we are confident10
that alternatives will be put in place to allow11
these important public information and12
consultation processes to continue in the future13
as they are very necessary and important to public14
awareness and comfort level and an opportunity for15
input on AECL's activities and various projects.16
I should also note that there is17
excellent cooperation between AECL and the18
surrounding area on the Chalk River Regional19
Nuclear Emergency Preparedness Plan. This plan is20
well developed and regularly exercised, both at21
local, regional and provincial level scale22
exercises, and has been fairly highly complimented23
in the provincial level test that was carried out24
last year in the Chalk River region.25
���������
255
With regard to the MAPLE isotope1
production reactors and the related New Processing2
facility, we feel confident that the several3
issues of concern previously identified have been4
properly identified and either adequately5
addressed or are well under way to resolution.6
The CNSC and its staff have been diligent in this7
regard and AECL has addressed those problems8
responsibly.9
We believe it is timely,10
therefore, to renew the appropriate licence for11
these facilities so the secure supply of12
critically needed medical radio isotopes can be13
assured for the future.14
I might also note that those of us15
in Renfrew County who may have future need of16
medical diagnostic and treatment procedures using17
radio isotopes produced at CRL look forward to18
soon having access to these procedures much closer19
to home. When renovations and expansions20
currently under way at the Pembroke General21
Hospital are completed, that hospital will have a22
nuclear medicine department, to my knowledge for23
the first time.24
Finally, I would again note the25
���������
256
one concern that I addressed in the written1
submission with regard to the CRL site, and that2
is that there be adequate funds made available on3
an ongoing basis so that improvements in the long4
term management of radioactive wastes in the older5
waste management areas of the CRL site can6
proceed. These so-called legacy wastes we believe7
are equally the responsibility of AECL and its8
shareholder, the Government of Canada. We ask9
that the CNSC give serious consideration to this10
issue through ongoing discussions with AECL and11
the government.12
I have been listening to the13
discussion on this, including Mr. Van Adel's14
comments earlier, and it is quite reassuring to15
hear that a process that I wasn't really aware of16
is in place and there is provision on the books to17
address this. We certainly would like to see that18
proceed in the older waste management areas on a19
regular and ongoing basis.20
Again, thank you for the21
opportunity to address you today and I would be22
happy to answer any questions that the Members of23
the Commission might have.24
THE CHAIRPERSON: Thank you very25
���������
257
much.1
Are there any questions? Dr.2
Dosman.3
MEMBER DOSMAN: Thank you, Madam4
Chair. Just a short comment/question, Mr. Murphy.5
Perhaps it is just an accident of wording.6
On page 2 of your letter, the7
second paragraph, I take it that the first line in8
that paragraph does not mean that AECL is not9
fully responsible for all of the activities at the10
site?11
MAYOR MURPHY: You mean with12
regard to my comment on the historic or legacy13
waste?14
MEMBER DOSMAN: No. Your sentence15
states that:16
"One area of concern ...17
although we acknowledge it is18
not totally within the control19
of AECL."20
You go on to discuss the issue of21
the accumulated waste.22
My question is: I take it that23
this wording does not mean that you think that24
AECL is not fully responsible for all of its25
���������
258
actions at the site?1
MAYOR MURPHY: No, that was not my2
meaning or intent.3
What I was alluding to is that4
over the years the federal government has provided5
money to AECL through parliamentary appropriation6
that has been critical to the operation of some7
programs at the reactor.8
Although AECL is moving toward a9
more business-organized approach with revenues10
from other sources available to offset that11
dependence on government funding, at least for the12
legacy waste issues I was trying to make the point13
that we believe that the federal government has to14
recognize that ongoing responsibility for material15
that was generated and stored in the early years16
of the programs and not leave it solely to AECL to17
fund from other sources of revenue totally in the18
future.19
Not that AECL is not responsible20
for it, but that the source of the money to21
address it needs to be considered as a joint22
responsibility.23
THE CHAIRPERSON: Dr. Dosman, if I24
could, I think Mr. Murphy is saying that the issue25
���������
259
under the control is the funding availability, not1
anything to do with the waste or waste management.2
MAYOR MURPHY: That is correct.3
MEMBER DOSMAN: Perhaps it is a4
small point, but I guess I was making the point5
that I take it that you do not believe that AECL6
is not fully responsible for any actions on the7
site.8
MAYOR MURPHY: I agree that AECL9
is totally responsible for actions on the site and10
both managing and carrying out improvements11
certainly. Where the money comes to handle that,12
to my mind is slightly different than accepting13
responsibility totally as they would in terms of14
being responsible for looking after it and15
improving it.16
THE CHAIRPERSON: Okay? Is that17
fine18
MEMBER DOSMAN: Yes, Madam Chair.19
I think we are mincing words.20
THE CHAIRPERSON: I think we are.21
MEMBER DOSMAN: I just would like22
to table my view that AECL is indeed responsible23
fully for all actions on the site.24
THE CHAIRPERSON: Mr. Van Adel, I25
���������
260
think you concur. Is that correct?1
MR. VAN ADEL: Yes, I do indeed.2
If I could just make the comment3
that I think the lament or the idea here is that4
AECL has to operate within certain constraints.5
We have, at any point in time, to manage ourselves6
within reasonable resources, as does any other7
organization. We have to make the case for the8
things that we do and put a responsible business9
plan forward for the management of waste and we10
are doing so.11
But the government understands, as12
do we, that we have to meet the requirements and13
exceed them if we can and that we not endanger the14
health and safety of the public and that we not15
cut corners. And we do not.16
In the area of waste management,17
while we do have fiscal constraints, we always are18
governed by making sure that we are doing what is19
required. Then over and above that there are20
things we would like to do. We would like to21
accelerate some of the programs.22
We have some interesting new23
technologies that we are putting before the CNSC24
for waste mediation which we think are excellent25
���������
261
and even have the potential for commercial1
exploitation and we would like to apply them to2
the site. It will take funding to do that. We3
have to put a business plan forward and make the4
case.5
Those are the things we would like6
to do if we had unlimited funds but, in my mind at7
least, there is never a trade-off in the end8
between things that are necessary to be done and9
funding.10
THE CHAIRPERSON: Thank you very11
much, Mr. Murphy.12
We are going to take a 10-minute13
break. I have 5:20. In your seats by 5:30,14
please.15
--- Upon recessing at 5:25 p.m.16
--- Upon resuming at 5:35 p.m.17
18
03-H2.2619
Oral presentation from Concerned Citizens of20
Renfrew County and Area21
THE CHAIRPERSON: We would like to22
now move to the next submission, which is an oral23
presentation from the Concerned Citizens of24
Renfrew County and Area, as outlined in CMD25
���������
262
document 03-H2.26.1
We have Mr. Hendrickson with us2
today. Thank you very much for coming. The floor3
is yours, sir.4
MR. HENDRICKSON: Thank you, Madam5
President, Members of the Commission, ladies and6
gentlemen, for this opportunity to put some of our7
views on the table here.8
So who are we? We are the9
neighbours here, people who live mostly10
downstream, downwind of CRL. Our group has been11
making interventions at a number of past licensing12
hearings on Chalk River Labs, mostly stressing13
environment, safety and health issues.14
More recently we have started15
looking at some of the economic issues that you16
have talked about such as financial guarantees for17
decommissioning. Because we are also taxpayers of18
course and we are interested in how these assets19
are being managed.20
We are interested when Mr. Van21
Adel says that it is going to be $3 billion, give22
or take, for the next hundred years to finance the23
decommissioning here. My daughters I hope will be24
taxpayers. Hopefully they will have children who25
���������
263
will in this area as well. When we hear these1
kinds of figures and we understand that the2
shareholder or the federal government is expected3
to make a very significant contribution to these4
kinds of costs, we feel that we do have a right to5
have input on how those kinds of amounts of money6
are spent. We think we need some decision point7
along the line where we can look in a more8
comprehensive way at the liabilities on the site9
and how much it is going to cost and what needs to10
be done first, and so forth.11
From our perspective as members of12
the public there are some key issues here. I13
think all of these have been touched upon today,14
things like the Access to Information Act.15
This notion of a report card16
approach. This is a fairly new innovation and it17
has been noted that when I got a report card when18
I was a kid, that was it. I didn't go back to the19
teacher and have it changed and then take it home20
to my parents and say "Look, she changed it. She21
gave me better grades".22
On the other hand, maybe there is23
something to be said for having licensing hearings24
fairly often if this kind of pressure does25
���������
264
actually trigger some action on important things1
like security. If a "C" grade moving up to a "B"2
was the result of having a licensing hearing, I3
think that is a really strong argument for having4
licensing hearings more often than less often. So5
that strikes me as an argument for more frequent6
licensing periods.7
We talked about funding of8
decommissioning. I would like to get a little bit9
into what the Commissioners do versus what the10
staff does, particularly on the issue of financial11
guarantees, because I really think that this is12
something that should be the subject of a hearing.13
There was quite a good discussion on the Canadian14
Environmental Assessment Act and I want to make a15
few points on that.16
A bit tongue-in-cheek, we have a17
Nuclear Safety and Control Act. Part of the18
reason for having that Act was so that the19
regulatory agency no longer had the dual20
responsibility for promoting and regulating21
nuclear power, which is clearly a good thing and22
that is what the International Atomic Energy23
Agency wants regulatory agencies to do, have that24
clear regulatory function and not a promotion25
���������
265
function.1
But we are still, I think, in a2
bit of a transmission mode in terms of3
particularly the Commission staff doing things4
like mainstreaming environmental concerns, really5
taking on the environmental mandate in a proactive6
way.7
I guess I do have some concerns8
about how particularly section 24(5) of the9
Nuclear Safety Control Act which deals with10
financial guarantees is being applied to this11
Crown corporation that we are looking at today12
versus other corporations. For example, you are13
going to look at the financial guarantee for Bruce14
tomorrow and have a separate hearing on that. We15
really haven't had that sort of opportunity to16
have a hearing on financial guarantees for Chalk17
River Labs.18
I wanted in my submission to19
acknowledge some of the progress that has been20
made over recent years. Certainly the monitored21
above-ground storage facility is a real step22
forward. We are very pleased to see that, that23
sort of facility being put in place to handle some24
of the lower level waste. Certainly the liquid25
���������
266
waste treatment facility has reduced releases of1
radionuclides like cesium-137 into the Ottawa2
River. These are good things.3
But there are, as we have been4
discussing, legacy issues like the contaminant5
plumes. I guess there has been the question: Are6
there really significant threats to drinking water7
from these contaminant plumes?8
I would point out that in CMD 03-9
H2.1C, pages 10 to 12 describe some of the rather10
extraordinary measures that are in place to deal11
with some of these contaminant plumes. In fact,12
there are three special treatment facilities, the13
Spring B treatment facility; the chemical pit14
treatment facility; and the wall and curtain15
facility, all of which are in place to intercept16
plumes.17
Those are going to have to be18
maintained over the long term. That means that19
there are long-term operating costs. Those20
facilities wouldn't be in place if there weren't21
some significant concerns about strontium and22
cesium getting into the river in an uncontrolled23
fashion if those weren't in place.24
We have some concerns about the25
���������
267
way some of the high-level waste in waste1
management area "B" are managed.2
The tile holes. There have been3
water intrusion in some of those tile holes and4
there is not really a discussion on that in the5
CMDs that I have found, though I could have missed6
it.7
Certainly the ongoing issue of the8
high-level liquid, some of the reprocessing wastes9
and other wastes in the waste tank farm. It is10
not something that really gets talked about very11
much. There has been rather a reluctance to12
address that, though I think we will be looking at13
cementation of those kinds of wastes down the14
road.15
And of course the fissile solution16
storage tank, there has been a lot of discussion17
about that. That is going to soon become a legacy18
issue when we move over to the new processing19
facility which you are going to talk about later20
today.21
Before I go to the next slide, I22
want to say that not all the problems really are23
legacy problems either. We haven't talked very24
much about the argon-41 plume from the reactor25
���������
268
stack, but in my submission in the third paragraph1
I was actually congratulating AECL on having2
reduced argon-41 emissions by 35 per cent from the3
year 2000 to the year 2001.4
Now, regrettably, between the year5
2001 to 2002 those emissions went right back up6
and basically they are back up at the equivalent7
of 150 microsieverts per year. That level is well8
in excess of the ALARA level of 50 microsieverts9
per year. People living around AECL, the10
significant source of public dose really is that11
reactor stack and those argon-41 emissions. If12
you happen to be in an argon-41 plume, you are13
getting a sizeable short-term dose of radiation.14
It is disappointing that we15
haven't seen more progress on that issue. I don't16
know what the reasons are that that seems to be so17
difficult to address.18
We have again talked a lot about19
the need for making environmental monitoring20
results more accessible and more open.21
Of particular interest to us was22
in the previous two-year licence, which I believe23
was from October 2000 to 2002, there was a24
specific licence condition to establish a25
���������
269
groundwater monitoring program for the waste1
management areas and plumes and then that just2
sort of disappeared. We heard that AECL had3
submitted the groundwater monitoring program, but4
now we don't know: Is it being implemented? Was5
CNSC staff totally satisfied with all aspects of6
it? There is no point in doing a monitoring plan7
if you aren't implementing that monitoring plan.8
So it has been disappointing to us9
that that was an important licence condition and10
now we don't really see where the follow-up to11
that has been.12
Of course, when you look at these13
groundwater plumes you know they have particularly14
the major fission products of strontium and cesium15
and they are decaying in place, but also with time16
they are migrating further too. So there is a17
trade-off between these things, more and more18
areas getting into water bodies, getting into19
groundwater, migrating into the river and the time20
of decay of these fission products.21
So this is an area where there22
needs to be some analysis and discussion of this23
kind of trade-off.24
Then on the issue of25
���������
270
decommissioning. I think it is important to note1
that the preliminary decommissioning plans that2
had been tabled and are being sort of reviewed by3
CNSC staff, those are really aimed at the physical4
structures on-site and the waste management areas5
and associated plumes really are going through a6
different process even though there are obvious --7
very obvious links between decommissioning8
activities that might involve removing9
contaminated substances from physical structures10
and then moving them to waste management areas.11
I will get into a bit the NRX fuel12
bays for example. The sludge from those fuel bays13
has already been moved out and taken to the waste14
management area "B", but that is still only in15
storage. So what is the longer term fate of some16
of these significant contaminants? You need an17
integrated approach to looking at the physical18
structures and the waste management areas.19
In terms of environmental20
monitoring or ecological monitoring, clearly you21
can't just look at the emissions. You have to22
look at the components of the environment.23
Thank you, Dr. Barnes, for24
actually getting into some of this in some25
���������
271
considerable detail.1
We need some performance2
indicators. We think that, for example in3
drinking water, some of these substances are going4
down, maybe tritium is going up. We would really5
like to see what the trends are through time.6
The same with the beaches and the7
river sediments and the benthic organisms. We8
can't just rely on sort of one-off reports on9
"These are the levels". We need some sense of how10
things are changing through time, to know things11
are getting better or things are getting worse.12
One issue that we brought up a13
couple of times before that I think is worth is14
noting, mussels have been used as a sort of15
sentinel species in the downstream of many16
facilities, both facilities that release nuclear17
substances and chemical contaminants. They are an18
excellent way of assessing changes in19
environmental contamination through time. They20
are there, they are filtering the water.21
Mussels in particular also22
accumulate strontium-90 in their shell. So this23
is something that really could be very much24
incorporated into an ongoing, longer-term25
���������
272
environmental monitoring program.1
Fish and wildlife. We can't just2
look off-site at what fish are doing, because fish3
on the site, fish in Maskinonge Lake, waterfowl,4
fly in and out of Chalk River. Moose and deer,5
they don't know where the boundary of the plant is6
and when they wander off-site -- people in the7
valley hunt and fish. We are proud of it. We do8
a lot of it. There are concerns about how9
contaminated some of these fish and game species10
that are valued ecosystem components may be.11
So it is not enough to wait until12
something is off-site. We should have ongoing13
monitoring of fish and wildlife on the Chalk River14
property, not just off the Chalk River property.15
That I think is certainly in the public interest.16
THE CHAIRPERSON: I just want to17
mention that we have already given you over 1018
minutes.19
MR. HENDRICKSON: I have three20
more slides.21
THE CHAIRPERSON: Please give your22
three slides, but just to let you know.23
MR. HENDRICKSON: Okay. Thank24
you. I will be fairly quick.25
���������
273
I think there are some issues1
around the Regulatory Gap Analysis. We need some2
follow up on that. Clearly there are a lot of3
gaps and it is not clear to me in the licensing4
document how those gaps are going to be addressed,5
what the process is for that.6
The Environmental Effects Review,7
we have already heard that the key appendices that8
have some of the actual data are not -- due to the9
sensitive nature of the attachments they have been10
removed from those documents. We simply don't11
understand why that kind of environmental12
monitoring data is considered to be sensitive13
information.14
We think indeed to be proactive15
those kinds of environmental monitoring results16
should be made available over the Internet. Make17
them public. That is a good way of measuring18
performance.19
In terms of accountability, it20
should be the staff -- not the staff, excuse me.21
The Commission is accountable for things like the22
financial guarantees, the acceptability of the23
decommissioning plans. Certainly we have talked24
about the fate of the NRU and there is agreement25
���������
274
to have that subject to hearing.1
Public participation. We keep2
bringing this up because we don't think we have3
enough opportunities. Under Access to Information4
Act, the staff I don't think have faced up to5
their obligations under section 26.6
The Auditor General has actually7
noted that regulatory agencies should look at the8
balance between the provisions for security and9
commercial proprietary interests versus the10
provisions in section 26 which allow that kind of11
information to be released if the public interest12
in health, safety and the environment outweighs13
those commercial and security interests.14
So I think we need to see a bit15
more review of active participation of the staff16
so that things are worked out ahead of time and we17
don't have these prolonged processes that go to18
the Information Commissioner.19
The Canadian Environmental20
Assessment Act, we have talked about that.21
The NRX fuel bay screening, for22
example, has been ongoing since April 2001. It23
hasn't come to a conclusion yet. It is the second24
longest screening before the CNSC. That was so25
���������
275
narrow that the proponent looked at the facility,1
at the fuel bay, but didn't look at the plume that2
was coming from it. When one of the contributing3
departments, Environment Canada, looked at that4
screening they said: That just doesn't make5
sense. Why wouldn't you look at the plume that6
has come from this facility? So obviously there7
are some concerns there.8
Longer licences. I have mentioned9
that puts less pressure on the licensee and10
excludes the public.11
These ad hoc extensions like from12
July of last year to May, again: Do you want13
this, I guess? What is the rationale for14
excluding public interventions at the first15
hearing? We try to be helpful and we are not sure16
that you are valuing our input on these matters17
with some of the current processes.18
Just some final points which have19
been partly addressed here.20
We think that the Commission21
itself should have hearings on things like the22
financial guarantees. We think that there should23
be coordination of these decommissioning24
activities and they should be subject -- we should25
���������
276
have a point at which the Canadian Environmental1
Assessment Act does kick in so we can have that2
integrated look at the entire facility.3
I thank you very much for letting4
me go on a bit beyond the limit.5
THE CHAIRPERSON: Thank you very6
much for your presentation.7
I will now open the floor to8
questions, starting with Mr. Graham.9
MEMBER GRAHAM: Thank you.10
A question I have to the11
intervenor: How often do you meet with the12
officials of AECL with concerns and questions like13
you have? You talk about openness and public14
hearings and open houses, and so on. How often15
does your group meet with AECL to get information?16
MR. HENDRICKSON: We try to17
participate in any public open houses that may be18
available, but we haven't had special meetings19
ever with AECL that I can recall.20
MEMBER GRAHAM: A question, then,21
to AECL: A lot of these seem like ordinary22
issues, some of them. Some of them are maybe more23
complex, but some of these issues and some of24
these questions I guess are of a nature that25
���������
277
perhaps could be resolved through open meetings.1
Are you prepared to meet, not only Concerned2
Citizens of Renfrew County but other people, with3
regard to one-on-one issues that they might have?4
DR. FEHRENBACH: Yes. Thank you5
for the opportunity to reply.6
We would of course be willing to7
meet with Mr. Hendrickson and his organization and8
any other organization as well. Part of the9
reason for publishing our community newsletter is10
to reach people across the entire spectrum of the11
Counties of Pontiac and Renfrew and we are more12
than willing to meet with our local neighbours at13
any time.14
MEMBER GRAHAM: Thank you.15
THE CHAIRPERSON: Dr. Barnes.16
MEMBER BARNES: A question to17
staff.18
Mr. Hendrickson asked to complete19
and make public the Regulatory Gap Analysis and20
the Environmental Effects Review. Could you21
indicate what you see as the fate of these22
documents and public accessibility?23
MR. HOWDEN: Barclay Howden24
speaking.25
���������
278
We don't see any problem making1
this information available. A certain amount of2
the Regulatory Gap Analysis has been made3
available to Mr. Hendrickson. The latest response4
from AECL to us has just come in, so we will make5
that available to him.6
For the Environmental Effects7
Review, the intention is that all this information8
will be available to him.9
So far all the progress reports10
and chapters that have come in, except for the11
last two that were just received, I believe have12
been made available to Mr. Hendrickson.13
THE CHAIRPERSON: Dr. Giroux.14
MEMBER GIROUX: I would like to15
explore briefly a question of importing wastes16
from other sites to the AECL facilities. You17
imply in your written document that the volume of18
indigenous or local waste is going down and the19
volume of imported waste is going up. The volume20
of imported waste might even be the most important21
part of it.22
My question to you is: If this is23
part of the mission of AECL to store or to dispose24
of waste for users outside the facility, why25
���������
279
should that be a problem, beyond the "Not in my1
backyard" syndrome?2
MR. HENDRICKSON: I think the3
problem comes with what you said "store or dispose4
of". Right now there is no disposal plan for5
these wastes, they are in storage. So then the6
long-term fate of those wastes becomes a matter of7
public interest and can then potentially be caught8
up in issues of long-term financial guarantees.9
They are going into waste management area "B" I10
believe, many of these, and they are essentially11
being mixed with internally generated waste.12
There comes then a question of13
whether -- for example, the taxpayers, we will14
call it the stakeholder, the federal government is15
going to actually be expected, or is already16
subsidizing this commercial waste storage activity17
and whether there is sort of full cost accounting18
for the real long-term cost of managing those19
exogenous wastes.20
MEMBER GIROUX: Thank you. You21
raise a very interesting point about the financial22
responsibility of outside customers and maybe AECL23
and staff could comment on whether there is any24
plan to take that into account, not in computing25
���������
280
the costs of decommissioning but assigning the1
costs.2
MR. LAFRENIÈRE: Thank you. The3
costs associated with the interim management and4
ultimate disposal are being charged to commercial5
customers. Let's be very, very clear on this. if6
we had talked to the customers over the past year7
they would have voiced much displeasure with the8
fact that the rates have really gone up. So I9
think that aspect is being covered.10
Disposal charges are also being11
credited to the segregated decommissioning fund12
and the disposal charges are based on our13
knowledge of what those costs will be.14
MEMBER GIROUX: So you are15
recovering upfront right now. But this is for the16
last one or two years. How about historically?17
MR. LAFRENIÈRE: We have been18
recovering for many, many years. What we have19
done recently is we have brought them in line with20
our knowledge of the final disposal cost.21
THE CHAIRPERSON: Dr. McDill.22
MEMBER McDILL: This is the second23
submission in which it has been stated that24
strontium-90 is measurable in Ottawa. I wonder if25
���������
281
staff could comment on whether they agree with1
that statement.2
DR. THOMPSON: This is Patsy3
Thompson, for the record.4
The information we have obtained5
from the City of Ottawa is that strontium-90 in6
the Ottawa public drinking water network is at7
levels that are similar to background, which is8
essentially taking into account weapons testing.9
So there is no measurable impact in the City of10
Ottawa drinking water from activities at Chalk11
River. The same situation exists at Pembroke.12
MEMBER McDILL: Do you agree with13
that?14
MR. HENDRICKSON: I do not. There15
has been a study of that very issue and a fairly16
detailed analysis of the bomb testing source.17
From atmosphere testing we are still seeing a bit18
of that, versus the amounts that come from Chalk19
River. I will look for that study and I can20
provide it to you.21
THE CHAIRPERSON: If you could22
provide it to the staff, I think that would be the23
best place to send it. I think everybody is24
searching for the best information possible.25
���������
282
Any further questions?1
DR. FEHRENBACH: Madam Chair,2
could I request that we receive a copy of well? I3
would be most interested.4
MR. HENDRICKSON: You will get it.5
THE CHAIRPERSON: Yes. Either6
directly or through the staff we will certainly7
make sure you get it.8
Thank you. Other questions?9
Thank you very much, sir, for10
coming.11
03-H2.712
Written submission from the Ottawa Valley Tourist13
Association14
THE CHAIRPERSON: We would now15
like to move to the next submission, which is a16
written submission from the Ottawa Valley Tourist17
association, as outlined in CMD document 03-H2.7.18
Are there any questions or19
comments from the Members with regards to this?20
We will then move to a series of21
written submissions that have been grouped22
together since they reflect similar comments or23
requests of the Commission.24
I will ask the Secretary of the25
���������
283
Commission to read the list of intervenors, after1
which I will ask Members if they have questions on2
the issues raised in these letters as a totality.3
Monsieur Leblanc.4
MR. LEBLANC: Merci. The5
intervenors and the document numbers are:6
7
8
03-H2.89
Written submission from Beth McLaughlin10
11
03-H2.912
Written submission from Pierre Morin13
14
03-H2.1115
Written submission from Jim and Doris Sutherland16
17
03-H2.1518
Written submission from Beatrice Biederman19
20
03-H2.1621
Written submission from Lucy Sharrat22
23
03-H2.1724
Written submission from Kelly O'Grady25
���������
284
1
03-H2.232
Written submission from Kristen Ostling3
4
03-H2.245
Mémoire de Environnement Jeunesse6
03-H2.277
Written submission from Daniel J.H. Spence8
9
03-H2.2810
Written submission from Carolyn Topp11
12
03-H2.2913
Written submission from Pamela Shapiro14
15
03-H2.3016
Mémoire du Conseil régional du développement17
durable de l'Outaouais18
19
03-H2.3120
Written submission from Yosef D. Robinson21
22
03-H2.3223
Written submission from Concerned Citizens of24
Manitoba25
���������
285
1
03-H2.332
Written submission from Sierra Youth Coalition3
4
03-H2.345
Written submission from Ron Harshman6
03-H2.357
Written submission from Nancy Peckford8
9
03-H2.3610
Written submission from Randall Barnhart11
12
03-H2.3713
Written submission from Bevan E. Slater14
15
03-H2.3816
Written submission from Chantale Killey17
18
03-H2.3919
Written submission from Phillip Penna20
21
03-H2.4022
Written submission from Paul Dehler23
24
03-H2.4125
���������
286
Written submission from Lynn Jones1
2
03-H2.423
Written submission from Kristen Howe4
5
6
03-H2.447
Written submission from Tamara Di Saverio8
THE CHAIRPERSON: Are there any9
questions or comments arising from these written10
submissions on behalf of the Commission Members?11
Mr. Graham.12
MEMBER GRAHAM: I just had one13
comment with regard to 03-H2.8, and that was from14
Beth McLaughlin. I think it was noted there that:15
"The new CRL license should16
require AECL to monitor and17
make annual public reports..."18
All I'm just asking is that the19
openness that we have heard about today that is20
being committed, that that continue and that21
intervenors like this be notified of reports and22
so on that may be relevant with regard to23
radioactive contamination of groundwater in the24
Ottawa River, and so on, and that any reports that25
���������
287
are available be made public either through your1
library or whatever.2
THE CHAIRPERSON: Any comment from3
AECL?4
MR. LAFRENIÈRE: Thank you.5
AECL does prepare annual reports6
on the effluent and environmental monitoring7
results as required by the site licence and these8
are submitted to the CNSC staff. This information9
is available to the public and if a request is10
sent to AECL we will make sure it is sent out in11
timely fashion.12
THE CHAIRPERSON: Further13
questions or comments?14
Thank you very much.15
16
03-H2.1017
Written submission from Walter Robbins18
THE CHAIRPERSON: We will then19
move to the next submission, which is a written20
submission from Walter Robbins, as outlined in CMD21
document 03-H2.10.22
Are there any questions or23
comments from the Commission Members with regard24
to this submission?25
���������
288
1
03-H2.122
Written submission from The Lung Association of3
Renfrew County4
THE CHAIRPERSON: We will now move5
to the next submission, which is a written6
submission from The Lung Association of Renfrew7
County, as outlined in CMD document 03-H2.12.8
Are there any questions or9
comments from the Commission Members with regard10
to this submission?11
12
02-H2.1313
Written submission from Renfrew County District14
School Board15
THE CHAIRPERSON: We will now move16
to the next submission from Renfrew County17
District School Board, as outlined in CMD document18
03-H2.13.19
Are there any questions or20
comments from the Commission Members with regard21
to this submission?22
23
03-H2.1424
Written submission from Ken Birkett25
���������
289
THE CHAIRPERSON: We will now move1
to the written submission from Ken Birkett, as2
outlined in CMD document 03-H2.14.3
Are there any questions or4
comments from the Commission Members with regard5
to this submission?6
7
03-H2.258
Written submission from Ministry of training,9
Colleges and Universities10
THE CHAIRPERSON: We will now move11
to the written submission from The Ministry of12
Training, Colleges and Universities, as outlined13
in CMD document 03-H2.25.14
Are there any questions or15
comments from the Commission Members with regard16
to this submission?17
18
03-H2.4319
Written submission from Great Lakes United20
THE CHAIRPERSON: We will now move21
to the written submission from Great Lakes United,22
as outlined in CMD document 03-H2.4323
Are there any questions or24
comments from the Commission Members with regard25
���������
290
to this submission?1
2
03-H2.453
Written submission from Town of Laurentian Hills4
Volunteer Fire Department5
THE CHAIRPERSON: We would like to6
move to the written submission from the Town of7
Laurentian Hills Volunteer Fire Department, as8
outlined in CMD document 03-H2.45.9
Are there any questions or10
comments from the Commission Members with regard11
to this submission?12
13
03-H2.4614
Written submission from Town of Laurentian Hills15
THE CHAIRPERSON: We will now move16
to the written submission from the Town of17
Laurentian Hills, as outlined in CMD document 03-18
H2.46.19
Are there any questions or20
comments from the Commission Members with regard21
to this submission?22
23
03-H2.4724
Written submission from Ottawa Riverkeeper25
���������
291
THE CHAIRPERSON: We would like to1
move, then, to the written submission from the2
Ottawa Riverkeeper, as outlined in CMD document3
03-H2.47.4
Are there any questions or5
comments from the Commission Members with regard6
to this submission?7
With respect to this matter, then,8
I propose that the Commission confer with regards9
to the information that we have considered today10
and then determine if further information is11
needed or if the Commission is ready to proceed12
with a decision and we will advise accordingly.13