Date post: | 03-Jun-2018 |
Category: |
Documents |
Upload: | nuruddin-aziz |
View: | 228 times |
Download: | 0 times |
of 33
8/12/2019 Heat Integration-Chap4a Lecture
1/33
Application of PINCH Analysis Software
CBB 4313 HEAT INTEGRATION
So far, you have been taught on how to determine the energy target and design the heat exchanger
network that will attain it respectively
Temp.
Enthalpy (H)
QC
QH
DTmin
COLD UTILITIES
HOT UTILITIES
PINCH
POINT
Composite Curve Problem Table Algorithm
and Heat Cascade Diagram
alternatives
HOT 1
HOT 2
COLD 1
COLD 2
180 C 80 C
130 C 40 C
30 C120 C
60 C100 C
Cp Q
20
40
36
80
2000
3600
3240
3200
8002400
1080
70 C 43 C
60 C
2000
160120
90 C
115.56 C
PINCH
Energy Targeting
Maximum Energy Recovery Design
8/12/2019 Heat Integration-Chap4a Lecture
2/33
CBB 4313 HEAT INTEGRATIONCBB 4313 HEAT INTEGRATION
Now we will learn on how to use a software that can perform the PINCH Analysis ..
The software is called STARand was developed by University of Manchester
8/12/2019 Heat Integration-Chap4a Lecture
3/33
CBB 4313 HEAT INTEGRATION
Let us suppose we do the data extraction for the process below .
R1
S1S2
CW
FEED
T = 30 C
T = 200 C T = 350 C
BOILER FEED WATER
MP STEAM
T = 220 C
T = 90 C
MP STEAM
T = 220 C
T = 100 C
T = 250 C
T = 150 C
T = 60 C
T = 130 C
T = 150 C
T = 180 C
T = 120 C
MP STEAM
T = 220 C
T = 150 C
CW
T = 40 C
PROD 1
T = 60 C
PROD 2
T = 40 C
PROD 3
T = 40 C
CWCW
LP STEAM
T = 120 C
8/12/2019 Heat Integration-Chap4a Lecture
4/33
CBB 4313 HEAT INTEGRATION
So where are the streams ?
R1
S1S2
CW
FEED
T = 30 C
T = 200 C T = 350 C
BOILER FEED WATER
MP STEAM
T = 220 C
T = 90 C
MP STEAM
T = 220 C
T = 100 C
T = 250 C
T = 150 C
T = 60 C
T = 130 C
T = 150 C
T = 180 C
T = 120 C
MP STEAM
T = 220 C
T = 150 C
CW
T = 40 C
PROD 1
T = 60 C
PROD 2
T = 40 C
PROD 3
T = 40 C
CWCW
LP STEAM
T = 120 C
8/12/2019 Heat Integration-Chap4a Lecture
5/33
CBB 4313 HEAT INTEGRATION
FEED30 C200 C
S1 REB130.1 C 130 C
130 C150 C S1 EFF
180.1 C 180 C S2 REB
350 C 100 CREACTOR EFF.
S1 COND60.1 C 60 C
180 C 40 C PROD 3
S2 COND120.1 C 120 C
120 C PROD 240 C
UTILITIES : COOLING WATER, MP STEAM AND LP STEAM
These are the set of streams extracted from the process flowsheet.
H (Enthalpy change)
2,500 kW
3,000 kW
1,200 kW
2,000 kW
600 kW
2,500 kW
3,500 kW
150 kW
2,300 kW
8/12/2019 Heat Integration-Chap4a Lecture
6/33
CBB 4313 HEAT INTEGRATION
To start with, go to the file option and click new.
8/12/2019 Heat Integration-Chap4a Lecture
7/33
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
8/33
CBB 4313 HEAT INTEGRATION
Go to the edit menu .
Click at stream data
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
9/33
CBB 4313 HEAT INTEGRATION
You will be required to fill up all the streams data
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
10/33
CBB 4313 HEAT INTEGRATION
After filling up the stream data click ok
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
11/33
CBB 4313 HEAT INTEGRATION
Go to the target menu .
Set your DTmin.
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
12/33
As you change your DTmin, the energy target for hot and cold utility will also vary
The energy target for the
two utilities.
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
13/33
You can also go back to the target menu, and select to see the problem table, composite curve, grand composite
curve and design grid .
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
14/33
Composite Curve
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
15/33
Problem Tableactually heat cascade
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
16/33
Grand Composite Curve
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
17/33
Design Grid representing stream data.
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
18/33
Another software that can be used is called SPRINTand was also developed by the University of
Manchester.
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
19/33
In order to input the stream data, similar steps as applied in STAR is used.
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
20/33
You can basically obtain the same information for the MER target - Problem table, Composite
Curve, Grand Composite Curve, Design Grid etc.
You will also need to set the DTmin.
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
21/33
Consider the flowsheet for the Phthalic Anhydride Production Process below,
Perform the stream extraction exercise
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
22/33
Process Descr ip t ion
The phthalic anhydride is manufactured using controlled oxidation of o-xylene. The reaction uses a fixed bed
vanadium pentoxidetitanium dioxide catalyst. The reaction is carried out in vapour phase at a temperature
range of 380400 C. Reaction is exothermic. Reactor cooling is by means of a molten salt loop.
Air and o-xylene are heated and mixed in a venturi where the o-xylene vapourises. The gaseous reactor
product is cooled first by boiler feedwater before entering a cooling water condenser. The phthalic anhydride
forms a solid on the condenser tube walls and is cooled to 70 C. Periodically the condenser is taken off line and
the phthalic anhydride melted off the surface by recirculation of high pressure hot water. Two condensers are
used in parallel. The noncondensible gases contain small quantities of byproducts and traces of phthalic
anhydride are scrubbed prior to venting it to atmosphere.
The crude phthalic anhydride is heated and held at 260 C to allow some byproduct reactions to go to
completion.
Purification is by continuous distillation in two columns. In the first column, maleic anhydride, benzoic and toluic
acids are removed as the overhead. Pure phthalic anhydride is removed as the overhead in the 2ndcolumn
while the high boiling residues are removed as the bottoms.
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
23/33
The hot stream locations
Perform the stream extraction exercise
1
2
3
45
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
24/33
The hot streams on grid diagram .
Reactor Cooling377 C 375 C
376 C 180 C
180 C 70 C
280 C 279 C
197 C 196 C
Reactor Product Cooling
Product Sublimation
Column 1 Condenser
Column 2 Condenser
H
-7000
-3600
-2400
-400
-800
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
25/33
Perform the stream extraction exercise
1
2
6
3 4
5
Next, lets work out the cold stream .
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
26/33
Air Feed
O-xylene Feed
Product Melting
Holding Tank Feed
Column 1 Reboiler
H
200
1600
900
200
400
Column 2 Reboiler 700
160 C 60 C
130 C 20 C
180 C 70 C
260 C 160 C
291 C 290 C
236 C 235 C
The cold streams on grid diagram .
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
27/33
Overall
Reactor Cooling377 C 375 C
376 C 180 C
180 C 70 C
280 C 279 C
197 C 196 C
Reactor Product Cooling
Product Sublimation
Column 1 Condenser
Column 2 Condenser
H
-7000
-3600
-2400
-400
-800
Air Feed
O-xylene Feed
Product Melting
Holding Tank Feed
Column 1 Reboiler
200
1600
900
200
400
Column 2 Reboiler 700
160 C 60 C
130 C 20 C
180 C 70 C
260 C 160 C
291 C 290 C
236 C 235 C
8/12/2019 Heat Integration-Chap4a Lecture
28/33
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
29/33
Stream Data Entry
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
30/33
i. The Composite Curve
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
31/33
ii. Problem Table (Heat Cascade)
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
32/33
iii. Grand Composite Curve
CBB 4313 HEAT INTEGRATION
8/12/2019 Heat Integration-Chap4a Lecture
33/33
iv. Grid Diagram