Helmholtz Centre for Ion Research
G. Moritz, Cryogenic Expert meeting, GSI, September 19/20 2007
(courtesy of D. Krämer for the FAIR Design Team)
Current Status of the FAIR Project
The Pillars of the FAIR Complex
Antiprotonproduction
100 TmSynchotron
scSIS100
Collector & CoolerRing
AccumulatorRing
Deceleration
Rare isotopeProduction &separator sc
HighEnergy
Storage Ring
HESR&
PANDAnc or sc
NewExperimentalStorage Ring
CompressedBarionicMatter
experiment
NESR
300 TmStretcher
Ringsc
SIS300
From existing GSIUNILAC & SIS18& new proton linac
+ Experiments:E-I colliderNuclear PhysicsAtomic PhysicsPlasma PhysicsApplied Physics
sc
Technical Realization of FAIR
100 m
UNILAC
SIS 18
SIS 100/300
HESR
SuperFRS
NESR
CR
RESR
FLAIR
Radioactive Ion Production Target
Anti-Proton Production Target
Existing facility: provides ion-beam source and injector for FAIR
Existing facility: provides ion-beam source and injector for FAIR
New future facility: provides ion and anti-matterbeams of highest-intensity and up to high energies
New future facility: provides ion and anti-matterbeams of highest-intensity and up to high energies
The International Committee Structure(for XFEL & FAIR)
PAC QCD
PAC NUSTAR
PAC APPA
TAC
Observes:
FCIFull Cost Issues
AFI Working GroupAdministrative + Funding Issues
LFILegal Framework Issus
STI Working GroupScientific + Technical Issues
ISCInternational Steering Committee
Delegates from partner states
CORECost Review Groups
Reviews• Cryogenics• Warm magnets •Cold magnets• Power Supplies• Beam Instrumentation• p-Linac
Austria China Finland France Germany Greece India Italy Poland Spain Sweden Russia Great Britain Romania
• Baseline Technical Report - accelerator TR's - experiment proposals - civil construction plans (~ 3500 pages)
• PAC & TAC Review Reports
• Cost Book
• Cost Review Reports - accelerator & civil construction (CORE-A) - experiments (CORE-E)
• Convention
• Articles of Association
• By-Laws
• Final Act Document
• Legal Framework Report (LFI)
• Full Cost Structure Report (FCI)
FAIR Project
2000 2002 2004 2006
Wor
ksho
ps /
Whi
te P
aper
s: e
xplo
ratio
n of
sci
ence
opp
ortu
nitie
s
Wis
sens
chaf
tsra
t-E
valu
atio
n
BM
BF
Pre
ss
Rel
ease
CD
R S
ubm
issi
on
Preparation of CDR700 scientists
WR – ESAC – ETAC – EMAC -- EAC
Inte
rnat
iona
l S
teer
ing
Com
mitt
ee
ISC STI PAC's / TAC / miniTACs
CORE-A / CORE-E
AFI (LFI / FCI )
Inte
rnat
iona
l M
oU
Accelerator R & D
coordinated by GSI
Proto-Collaborations
international community
Civil Construction Planning / Regulatory Processes / UVS
Preparation of FBTR 2400 scientists
FB
TR
S
ubm
issi
on
Project Costs
Accelerator investment costs 533 M€Civil construction costs 289 M€Baseline experimental facilities( incl Super-FRS ) 180 M€Investment budget 1002 M€Manpower (2400 person-years) 185 M€
Total Construction Costs 1187 M€
Commissioning Costs 28 M€Operation Costs up to 2025 1485 M€Sum 2700 M€
Germany committed part of funding
25% of funds have to come from non-
German partners
Scrutinized by CORE, TAC, STI …
FAIR Work Packages94 WPs defined, following WBS, FBTR and Cost Book schematics
13 subprojects
15 te
chni
cal s
yste
ms
interest to take WP indicated
in-kind
Recent decision by German Minister Ms. Schavan:
Start of the International FAIR Project
on November 7, 2007
together with all partners that have expressed their commitment on FAIR.
• Stage A: ? ; Stage B: SIS 300 and 300 Tm beamline
• 11/2007: official end of R&D-phase
• project money acc. costbook, no R&D money
SIS100/300 Design Parameters
First Stage: Second Stage:
Acceleration + Acceleration +
Compression Stretching
Reference Ions U28+
p
U28+
U92+
Magnet. rigidity 100 Tm 300 Tm
Circumference 1083 m 1083 m
Number of Particles
5 · 1011
5 · 1013
3 · 1011 /s
1 · 1010 /s
Energy 2.7 GeV/u
29 GeV
2.7 GeV/u
34 GeV/u
Beam time structure
25 – 90ns
50 ns
d.c.
slow ext.
Dipole flux density
2 T 4.5 T
Ramp Rate 4 T/s 1 T/s
SIS300SIS100
SIS300SIS100
Straight mark I full scale dipole magnetunder fabrication at BNG / WürzburgCurved mark I full scale dipole magnetunder fabrication at BINP / NovosibirskR&D continued at JINP / Dubna incl.Quadrupole prototype
Progress in SIS Magnet R&D
GSI001, first 4 T prototype by BNL6 T protoype under construction at DubnaCurved 4.5 T dipole magnetunder fabrication at INFN
BINP Novosibirsk
SIS 100 Dipole under Construction
Layout of Super-FRS
Bmax =20 Tm
SuperferricMultiplet
SuperferricMultiplet
3 x 9.75° Dipole Unit
MF2
MF1
SuperferricMultipleton-going magnet
activities: • conceptual design multiplett (Toshiba)• superferric dipole (China)• radiation resistant magnets (BINP)
The assembly of die First lamination punched
IMP LanzhouIPP HefeiIEE Beijing
CAS
Super-FRS Dipole Prototype Development in China
Coil fabrication Magnet design
High Energy Storage Ring
• Momentum: 1.5 – 15 GeV/c• Straights: Cooler and target section • Ring circumference: 573 m.
for antiprotons
Estimated Total Manpower for constructionas scrutinized and approved by CORE-A and STI in 2005/2006
Scientists Engineers TechniciansSystems Design 9 7 1 8 17 136
Interface Accelerator - Civil Construction 2 2 0 6 4 24Interface Accelerator - Experiments 4 2 0 6 6 36
Civil Construction 3 11 4 5 18 90
p-Linac 4 5 3 4 12 48SIS100/SIS300 10 6 0 5 16 80HEBT/Super-FRS 4 4 0 4 8 32Storage Rings 7 6 0 4 13 52
Magnets 9 9 6 6 24 144Power Supplies 5 9 8 5 22 110rf-systems 7 9 7 5 23 115Inj-/Extraction 3 7 6 5 16 80Beam-Diagnosis Systems 4 6 5 6 15 90Vacuum System 4 6 5 5 15 75Beam Cooling 5 6 5 5 16 80Cryo-System 4 9 5 6 18 108Control system 11 13 10 6 34 204
Magnet Testing 4 9 17 5 30 150Installations 2 6 16 6 24 144Commissioning 10 10 8 5 28 140
SUM 111 142 106 107 359 1938
Manpower Duration [years]
total Man Yearstotal FTE
0
5
10
15
20
25
30
35
40
45
50
1 2 3 4 5 6 7 8 9 10
Zeitlicher Personalbedarf SIS100 (Summe 126 FTE)
Reihe17
Reihe16
Reihe15
Reihe14
Reihe13
Reihe12
Reihe11
Reihe10
Reihe9
Reihe8
Reihe7
Reihe6
Reihe5
Reihe4
Reihe3
Reihe2
Reihe1
0
5
10
15
20
25
30
35
40
45
50
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
Zeitlicher Personalbedarf CR (121 FTE)
Control System
Cryo System
Beam Cooling
Vacuum System
Beam Diagnostics
Inj./ Extraction
RF-Systems
Power Converters
Magnets
Postproduction
Commissioning/ Beam
System Test
Mounting
Fabrication
Inquiry
Specifi cation
-
specification QA, construction
SIS 100
CR
Manpower Verteilung
0
50
100
150
200
250
300
350
400
450
500
2007 2008 2009 2010 2011 2012 2013 2014 2015
Jahr
An
zah
l
Re-directed
Beschleuniger
FAIR&FCC
ZT/WTI
Management
Man Power Resources(dominantly provided by GSI)
1950 man-years during 8 years required on site incl. 205 m-y for controls
FAIR Div.
Acc. Div.