Carlo Pagani FJOH School 2002 Alex C. Mueller 1
High Intensity Accelerators
4th LectureThe Driver Accelerator for an ADS
By Carlo Pagani
ADS requirements and status of the artPresent reference for a linac-based ADSTRASCO, IPHI-ASH, PDS-XADS
R&D effort: Italy, France and rest of the worldComments on the reliability issueGeneral Remarks
Carlo Pagani FJOH School 2002 Alex C. Mueller 2
ADS proton beam requirements
Very high duty cycle, possibly CW Energy of the order of 1 GeV, determined by
neutron production rate per GeV and per proton
(optimum value reached at ~1 GeV)energy dissipated in the input window
(rapidly decreasing with energy, when E<few GeV)
beam power from several MW up to tensof MW
few MW for a “demo” plant of ~100 MWth~30 MW for an industrial burner of ~1500 MWth
Very few beam trips per year accepted if longer then 1 secondNo limitation for very short beam trips: << 1 second
new challenges in the overall design of the accelerator
0
10
20
30
40
50
0 0.5 1 1.5 2 2.5
yiel
d / E
p (n
eutro
ns/G
eV)
proton energy, E_p (GeV)
Carlo Pagani FJOH School 2002 Alex C. Mueller 3
Most powerful proton accelerators
LinacsLAMPF/LANSCE (~1970)
800 MeV1 mA H+ average current Peak H+ current 16.5 mA @ 100 Hz and 625 µs pulse lengthNC accelerator
CyclotronsPSI – separated sector (1974)
Original design was for 100 µAFrom 72 to 590 MeV1.8 mA average currentBeam losses at extraction < 1 µAPlans for further upgrade (new cavities)
Both linac and cyclotrons were considered as possible ADS driversNo fundamental obstacles have been found so far for a linac to deliver ~100 mA at 1 GeV or more1 GeV and few mA are considered as limiting values for a cyclotron(multistage): possible for the demonstrator, not for the burner
Carlo Pagani FJOH School 2002 Alex C. Mueller 4
The ADS Linac
Linac benefits of impressive progresses in the field of SC elliptical RF cavities (CEBAF, LEP2, TRISTAN and KEK2, TTF-TESLA and now also SNS)R&D going on from several years demonstrated that this technology can be extended to proton linac down to β ~ 0.5Intrinsic modularity simplify reliability issues
Redundant design strategy based on the “spare-on-line” conceptStrong focusing and large beam aperture produce negligible losses
The scheme generally considered consists of four (three) different sections (the two first are often grouped and called injector)
The proton source: (proton energy ≈ 80-100 keV)The Radio Frequency Quadrupole (RFQ): (up to ≈ 5 MeV )A medium energy section, either NC or SC (up to ≈ 100 MeV )A high energy section made of SC elliptical rf cavities (up to final energy ≈ 1 GeV) most of the linac is here!
Carlo Pagani FJOH School 2002 Alex C. Mueller 5
Reference Linac Design
80 keV 5 MeV ~100 MeV 200 MeV 500 MeV >1000 MeV
3 section linac:85/100 - 200 MeV, β=0.47200 - 500 MeV, β=0.65500 – 1000/2000 MeV, β=0.85
Five(six) cell elliptical cavitiesQuadrupole doublet focussing: multi-cavity cryostats between doublets
704.4 MHz
5 - 85/100 MeV SC linac
Spoke cavities (352 MHz)Lambda/4 cavities (176 MHz)Reentrant cavities (352 MHz)
orNC Drift Tube Linac (DTL)
8βλ focusing
High transm
ission 90%30 m
A, 5 M
eV(352 M
Hz)
Microwave
RF SourceH
igh current (35m
A)
80keV
High Energy SC LinacISCLRFQSource
3 sections high energy SC linacProton Source RFQ Medium energy ISCL linac
Carlo Pagani FJOH School 2002 Alex C. Mueller 6
Injector: LEDA at LANL
130 mATotal Beam current
75 kVOperating voltage
0.2 π mm mradBeam emittance
110 mAProton Beam current
LEDA Source:
1.8 KilpatrickPeak Field
1.2 MW (structure)
670 kW (beam)RF Power
8 m (4 sections)Length
0.22 π mm mradBeam emittance
6.7 MeVFinal Energy
0.17 π deg MeV
100 mA (95 %)Beam current
LEDA RFQ:Source & RFQ fully operational since 1999
RFQ Concept
magelLorentz FF)BvE(qdtpdF
rrrrrrr+=×+⋅==
One Section of LEDA-RFQ
The LEDA-RFQ fully installed
Beam halo tests have been performed on the LEDA HEBT to compare simulation codes with experimental results
Carlo Pagani FJOH School 2002 Alex C. Mueller 7
Injector: SILHI at Saclay
1.2 %2 %Beam noise (rms)
95 kV
0.11 π mm mrad
157 mA (~83 % p.f.)
Achievements
95 kVOperating voltage
0.2 π mm mradBeam emittance
110 mA (90 % p.f.)Beam current
SILHI Goals: The SILHI source is fully operationl
ECR type: 110 mA, 95 keV
Several reliability tests were performed on the source
3 before extraction system changes: 99.96% availability (1 stop in 104 hours of operation)
2 with new extraction system:99.8% availability (8 stops in 162 hours, automatic restarting in 2.5 min, MTBF=23.1 hours)
Carlo Pagani FJOH School 2002 Alex C. Mueller 8
Injector: IPHI RFQ at Saclay
IPHI RFQ under fabrication
Two 1.3 Mw klystrons required
First RFQ beam expected in 2004
Picture of the first IPHI RFQ section ready for brasing
View of the vanes from the low energy side
1.7 KilpatrickPeak field
1.2 MW (structure)
500 kW (beam)RF Power
8 m (3 sections)Length
0.2 π mm mrad TBeam emittance
5 MeVFinal Energ
0.2 π deg MeV L
100 mA (99.2%)Beam current
IPHI RFQ parameters:
Carlo Pagani FJOH School 2002 Alex C. Mueller 9
Linac Injector: TRASCO at INFN
RFQ e.m. simulations
TRIPS, similar to SILHI with some extraction improvement and overdesign for reliabilityECR source: 35 mA, 80 keV (operating)
Different optimization w/respect to LEDALimit to 1 klystron (1.3 MW CERN)Lower design current: 30 mAPeak field limited to 33 MV/mLower power dissipation: ~ 600 kW
RFQ short models to set technology RFQ Ansys simulationsRFQ cross section
Cooling channels
Main brasings
Carlo Pagani FJOH School 2002 Alex C. Mueller 10
Medium Energy Section
The intermediate energy section, from 5 to ≈ 100 MeV, is the most controversial one: two basic solutions are possible:
Well proven NC structures (DTL or similar): as chosen for SNSNo realistic “spare-on-line” strategyHuge power dissipation in CW operation Rather small beam bore higher beam losses
Independently phased SC cavities: as chose for RIA and EURISOLWider energy acceptance “spare-on-line”Linac design can tolerate loose of few cavitiesLarger beam bore lower beam losses
The 0-order refernce deign being implemented for PDS-XADSNC DTL section up to ≈ 25 MeV2 sections of “Spoke” cavities (2 or 3 gaps) up to ≈ 100 MeVThe first part could be superconducting (e.g. the Frankfurt proposal)
Carlo Pagani FJOH School 2002 Alex C. Mueller 11
R&D in Italy and France
DTL at Saclay in the framework of the IPHI programDesign finalized up to 20 MeVFew electrode prototypes builtQuadrupoles inside the electrodesFirst tank in construction
Spoke cavity prototypes constructed and to be tested soonAt Orsay one β = 0.35 cavity done with CERCA2 β = 0.175 cavities done at ZANON for LANLin collaboration with INFN Milano
Other cavity geometries under study and test at INFN Legnaro
λ/4 and λ/2 structuresat 88 MHz and 176 MHz
respectively
“Reentrant” cavityat 352 MHzalready built and tested
Carlo Pagani FJOH School 2002 Alex C. Mueller 12
Linac High Energy Part
All designs are based on the technology of SC RF elliptical cavities(developed for electron accelerators)
very good efficiencyrelatively high field gradients (shorter length of the accelerator)large bore radius that is negligible beam losses lower operating costs with respect to NC for CW operation
The low velocity of protons, varying from β=0.43 at 100 MeV to β=0.88 at 1 GeV, imposes a variable length of cavities
3 sections, matched at three β values, are required for energies above ≈ 500 MeV.
A 2 section scheme is inefficientThe third section, with higher β, is the easiest and most efficient one
The same 3 sections allow an efficient energy upgrade up to ~2 GeV. The chosen energy sets the # of last section cryomodules
Carlo Pagani FJOH School 2002 Alex C. Mueller 13
Franco-Italian Design up to 1 GeV
655# cells/cavity
1 GeV500 MeV200 MeV
12.3 MV/m10.2 MV/m8.5 MV/mMax. Eacc (MV/m)
525440# cavities in section
13
8.5 m
500 MeV
110 m
0.85
27
4.6 m
200 MeV
124 m
0.65
20# periods
4.2 mDoublet period
85 MeVInitial/Final Energy
0.47Section β
84 mLength
704.4 MHzRF
TRASCO High Energy Linac:
0 50 100 150 200 250 3000.00
0.20
0.25
0.30
0.35
Tran
s. rm
s em
ittan
ces
[ π m
m m
rad]
Position along the linac [m]
εnx [mm mrad] εny [mm mrad] εz [deg MeV]
0.00
0.20
0.25
0.30
0.35
0.40
Lon
g. rm
s em
ittan
ce [π
deg
MeV
]
-2%
0%
2%
4%
6%
%
varia
tion
1
2
3
4
5
6
7
8
9
10
11
12
0 200 400 600 800 1000 1200 1400 1600 1800 2000Energy [MeV]
∆Ecav
∆Emax[MeV]
1 GeV
Design may be extended to ~ 2 GeV by only adding periods of the highest βsection
Maximum ∆E at conservative peak surface fields (50 mT)
Cavity ∆E in the design
Beam Dynamics calculations (fully 3D) predict small emittance variations due to nonlinear space charge
Approximately 320 m of linac are needed from 85 MeV to 1 GeV. <240 m to 600 MeV
Designed with high current beam dynamics criteria to avoid emittance growth (smoothness, tune resonances, ...)
Carlo Pagani FJOH School 2002 Alex C. Mueller 14
R&D Activities on SC Cavities
β=0.47
In the framework of the Franco-Italian collaboration for ADS, various reduced-β 700 MHz single cell cavities (bulk Nb) have been built and tested, yielding excellent performances, well above the design specifications:
β = 0.47 cavities from INFN/ZANON, tested at TJNAFβ = 0.65 cavities from CEA/CERCA tested at CEA/SaclayMulticell cavities under fabrication for both programs
1E+09
1E+10
1E+11
0 5 10 15 20 25 30
Test #3T = 2 K
TRASCO goal
Q0
Eacc [MV/m]
INFN/MI β=0.47 cavity
T = 2 K
1,E+09
1,E+10
1,E+11
0 5 10 15 20 25 30
ASH goal
Q0
Eacc [MV/m]
CEA/Saclay β=0.65 cavity
T = 1.5 K
Carlo Pagani FJOH School 2002 Alex C. Mueller 15
The SNS Example
Multicell structures have been built for the SNS project, for both the β=0.61 and the β=0.81 cavities
All tests reached the design goals with good marginsIndustrial fabrication for all the SNS cavities is in progessThe actual RIA linac proposed design uses the SNS cavities adding a
β=0.47 6-cell cavity section, as inthe European scheme
Prototype of β = 0.61 SNS cavity
1,E+08
1,E+09
1,E+10
1,E+11
0 2 4 6 8 10 12 14 16 18 20 22Eacc [MV/m]
Q0
Test #1
Design Goal
β = 0.61 SNS 6-cell cavity result
1,E+08
1,E+09
1,E+10
1,E+11
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19Eacc [MV/m]
Q0
Test #1
Design goal
β = 0.81 SNS 6-cell cavity result
Carlo Pagani FJOH School 2002 Alex C. Mueller 16
The 0-order Design for PDS-XADS
Section number 1 2 3 4 5 Input Energy [MeV] 5 17 95 200 490 Output Energy [MeV] 17 95 200 490 600 Cavity Technology Spoke Elliptical Structure βg 0.135 0.314 0.47 0.65 0.85 Number of cavity cells 2 2 5 5 6 Number of cavities 34 64 28 48 12 Focusing type SC quad doublet NC quad doublet Cavities/Lattice 1 2 2 3 4 Synch Phase [deg] -65 to -30 -30 -25 Lattice length [m] 1.3 1.9 4.2 5.8 8.5 Number of lattices 34 31 14 16 3 Section Length [m] 44.2 59.9 60.8 92.8 25.5 <gradient> [MV/m] 0.3 1.3 1.8 3.1 4.3
EzEyEx
TRACE_WIN - CEA/DSM/DAPNIA/SACM
Position ( m )25020015010050
Nor
m. r
ms
emitt
ance
s ( P
i.mm
.mra
d )
0.41
0.4
0.39
0.38
0.37
0.36
0.35
0.34
0.33
0.32
0.31
0.3
0.29
0.28
0.27
0.26
rms emittances in the whole linac
rms beam size along the linac
TRACE_WIN - CEA/DSM/DAPNIA/SACM
Position ( m )25020015010050
Ener
gy g
ain
per m
eter
( M
eV/m
)
5
4
3
2
1
0
Real Estate ∆E/m along the linac
Spokeβ=0.135
Spokeβ=0.315
5-cellβ=0.47
5-cellβ=0.65
6-cellβ=0.85
Output beam with 30% mismatch
SC Linac Section Parameters
Carlo Pagani FJOH School 2002 Alex C. Mueller 17
Reliability Example - CEBAF
0
240
480
720
960
1200
1440
Guns
8.1
%RF
6.1
%M
ag 5
.5%
Sft 4
.4%
Cryo
2.8
%Co
ntro
l Net
2.5
%FS
D Tr
ips 2
.1%
Vacu
um 1
.4%
Plan
t 1.4
%Ot
her 1
.2%
PSS
1.1%
MPS
0.8
%Di
ag 0
.6%
RAD
0.5%
SRF
0.3%
RF Problems
FSD Faults
SRF
0
120
240
360
480
600
Gun
s 11
.6%
FSD
Trip
s 4.
2%R
F 3.
4%M
ag 2
.7%
Ops
UT
1.6%
Cry
o 1.
5%O
ther
1.4
%Sf
t 1.4
%O
psST
1.4
%Va
cuum
1.1
%Pl
ant 0
.7%
Ops
0.6
%R
AD 0
.6%
PSS
0.5%
Con
trol N
et 0
.4%
MPS
0.3
%D
iag
0.1%
SRF
0.0%
PGun3 Valve/RF feedthru failure, Injector instabilities, Injector Setups
Klystrons & Tap ChangeFSD
Magnet Cooling
Lost Time Totals June'97-May'01 Lost Time Totals FY 2001
Reliability must be improved for ADS applicationsThe SC linac is modular and allows: overdesign, redundancy and “spare-on-line”Fast dedicated control electronics is crucialBeam can stay “on” when the linac is resetting itself to use spere-on lineSC cavity technology proved to be the minor concern
Carlo Pagani FJOH School 2002 Alex C. Mueller 18
Remarks on Linac Reliability
In order to meet the # of stops > 1 sThe beam startup procedure for a multi MW beam will be certainly > 1 s, so whenever is possible, operation with faulty components needs to be achieved
Linac must tolerate single failures of most of componentsProcedures for “adjusting” beam transport and repairing of components without interrupting the beam while marinating acceptable losses
As a consequence:Components and subsystems divided in two major categories if they lead to:
Failures requiring a beam stopFailures that can be repaired while the beam is on, or later…
As general rulesComponents falling in the first category should have the highest reliability
Typically passive components overdesigned and overtested with respect to operating parametersCabling, piping and connections
Components falling in the second category should have the highest accessibility for repairing or substitution
For example, this suggest the choice of a double tunnel design, with most of ancillaries situated in a free-access tunnel
Power supplies, RF generators, Control electronics, etc.
Carlo Pagani FJOH School 2002 Alex C. Mueller 19
Rules for Reliability Analysis From a Deliverable of the PDS-XADS Program
The small number (few per year) of beam trips allowed during the accelerator operation, requires a detailed analysis of the accelerator availability and reliability, much deeper that in the past applications
The reliability analysis of a complex system is an iterative process, which starts from a preliminary design of the whole system and its components and is followed by the development of the Reliability Block Diagram (RBD).
This top-down approach needs to be complemented with the bottom-up approach of the FMEA/FMECA (Failure Modes and Effects Analysis, Failure Modes and Effects Criticality Analysis), that, on a particular system design, tries to identify the system failures (and failure modes) from the failure modes of the single components. This path should be used iteratively.
Carlo Pagani FJOH School 2002 Alex C. Mueller 20
General Remarks - 1From the conclusions of the Accelerator WG at the NEA Workshop
Technology options for a high power proton driver: cyclotron and linacCyclotron
the only suitable reference machine is the PSI accelerator complex, delivering a 1.2 MW proton beam at 600 MeV. No remarkable R&D programs are under way to sensibly extend these limits. A part the complexity its cost scales quadratically with the output energy. The reliability and availability obtained at PSI are very high, but their further improvement looks very difficult. The machine concept does not allow the application of the concepts of redundancy and spare on line.
Linear AcceleratorA worldwide R&D effort is in progress since a few years and the high potentiality of these machines has been proven. Sources and RFQs up to 100 mA have been built and successfully operated. SRF technology is chosen above 100 MeV. For the intermediate energy NC and SC solutions are considered. The cost per MeV is decreasing with energy.A part from the front end, which can be duplicated, the linac has an intrinsic high modularity, which increases with energy. This machine can be designed on the basis of a properly set redundancy to allow the use of the spares on line concept.
Cyclotrons of the PSI type should be considered as the natural and cost effective choice for preliminary low power experiments, where availability and reliability requirements are less stringent.CW Linear accelerators must be chosen for demonstrators and full-scale
plants, because of their potentiality, once properly designed, in term of availability, reliability and power upgrading capability.
Carlo Pagani FJOH School 2002 Alex C. Mueller 21
General Remarks - 2From the conclusions of the Accelerator WG at the NEA Workshop
Beam trip handlingSparks on high voltage components drive most of the beam trips. They can generally be handled in a small fraction of a millisecond and the beam can stay on. They are not counted.In principle a fast procedure to switch on the beam can be implemented to allow the use of redundancy and spares on line. Whenever losses are acceptable, beam will stay on during the linac re-tuning to compensate for a component failure.The chosen degree for over design and redundancy is a direct function of the duration and frequency of the scheduled shutdown for reactor maintenance.The number of some redundant components could be reduced if allocated in a different building or tunnel. General cost analysis will define the details.
Optimized DesignBecause slightly different designs are being studied at present, they should be compared in term of their potential degree of modularity, reliability of the used technology and cost. The final linac design has to be based on reliability and availability considerations, as defined for ADS application.
Control ElectronicsAd hoc fast digital electronics must be implementedRedundant fast electronics will be designed to avoid, in principle, the intervention of the last beam protection.
Safety IssuesThe safety rules for the accelerator and the reactor have to stay separate. The accelerator protections will be based on redundant active systems.The beam handling, in the reactor building will follow the reactor safety rules.