+ All Categories
Home > Documents > High RE Penetration in Horizon’s Remote Power · retailing of electricity Introduction to Horizon...

High RE Penetration in Horizon’s Remote Power · retailing of electricity Introduction to Horizon...

Date post: 10-Feb-2021
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
35
Laurie Curro General Manager Power System Services Horizon Power High RE Penetration in Horizon’s Remote Power Systems CS10# 4781077
Transcript
  • Laurie Curro

    General Manager Power System Services

    Horizon Power

    High RE Penetration in Horizon’s Remote Power

    Systems

    CS10# 4781077

  • Agenda

    • Who is Horizon Power

    • History of Renewable Energy

    • Insatiable demand for Renewable Energy

    • Trends

    • Storage – a game changer

    • Multi-flow networks

    • Control systems

    • Trials and projects

  • • Western Australia's regional and remote electricity provider

    • State Government-owned and commercially focused

    • 38 systems of which 36 are remote microgrids

    • Serve 35,000 residential connections and 9,000 businesses,

    including major industry over 2.3 million square kilometres

    • One customer every 53.5 square kilometres of terrain!

    • Responsible for the generation, procurement, distribution and

    retailing of electricity

    Introduction to Horizon Power

  • POWER SYSTEMS DATA

    Total installed capacity: 435MW

    Total Peak Load: 275MW

    Current limit on Hosting Capacity:

    88MW Comprising of

    Centralised 40MW

    Distributed (PV) 48MW

    Current Installed Renewable Energy

    Generation: 48MW Comprising of

    Hydro – 30MW

    Wind – 9MW

    Solar – 1MW centralised

    Solar – 8MW distributed PV

    Renewable Energy Hosting Capacity

    All Networks

  • Horizon Power – Expertise in Microgrids

    6

  • Insatiable Demand for PV

    & Hosting Capacity

  • Increasing investment

    in renewables

    Decreasing demand for centralised generation

    Rising electricity

    prices

    Falling cost

    of new technology

    KEY TRENDS

    2015 2025 2050

    Standalone

    Distributed Energy Resources

    Centralised

    HOW WE RECEIVE ELECTRICITY WILL CHANGE

    2015 2025

    453,655 SOLAR CONNECTIONS IN WA BY

    2025

    ↑142%

    2015 2025

    11%

    11% OF TRANSPORT NATIONALLY IS EV BY 2025

    Latest Trends

  • Latest Trends

    9

    New Technology Cost Curve

    CSIRO – Modelling the Future Grid Forum Workshop

  • Smart Inverters

    • Shift of intelligence and capability to the inverter

    • Fronius SYMO

    • Connectivity and monitoring Systems

    • Home energy management

    • Easy interface with Energy Storage

    • Smart grid ready

    • Open Data Communications – Sunspec Alliance,

    SCADA and Home Automation

    Reposit Power

    SunVerge

  • Storage Benefits

    Spinning Reserve

    Peak Shifting

    Renewable Smoothing

    Delay Diesel Start

    Network Support

    Value $

    Transition path to distributed energy future and storage

    Diesel off options

    will increase these

    benefits

    Storage – a Game Changer

    Benefits

    11

  • Continuing Journey of Storage at Horizon Power

    • Carnarvon Energy Storage Trial project

    – (2000kWh 2MW of Battery Storage to

    optimise spinning reserve of power station

    and trial utility scale renewable energy

    smoothing)

    • Carnarvon saturation trials

    • Onslow distributed RE and storage

  • Renewable Energy Stability impact

    fOPF x kWD

    (Output Fluctuation)

    fDIV x ( kWA + kWB + kWC + kWD )

    (Diversity Factor)

    kW A kW B

    kW D

    kW C

    Local issue - Voltage

    fluctuations - Power quality - Ability to Export

    Local issue - Voltage

    fluctuations - Power quality - Ability to Export

    Upstream issues - Voltage

    fluctuations - Frequency

    response - Reverse Power

    Upstream issues - Voltage

    fluctuations - Frequency

    response - Reverse Power

  • Blueprints

  • Business as Usual

  • Centralised Renewables & Storage

    Centralised

    battery and PV

    plant

    Centralised

    battery and PV

    plant

    Communications Network

  • Distributed Energy Resources (DER)

  • Blueprints

    2016 2025 2050

    Graphs: Breakdown of Horizon Power systems per most economic business future including a 25% reduction in LCOE for DER systems.

  • Renewable Energy Optimisation

  • Distributed Generation New Network Study

    • Objective: Define the most economically efficient

    way to design a system as customer density and

    customer PV penetration increases.

    • Key Questions: Customer Density? Additional

    Equipment? Suitability of existing networks?

    Technical Limitations?

  • Distributed Generation – Network Design

    Load Scenarios

    Peak Load Average Load Minimum Load

    Generation Scenarios

    Maximum Gen

    Output Average Gen

    Output Minimum Gen

    Output

    Storage Scenarios

    Maximum

    Storage

    Output

    Minimum

    Storage

    Output

    Balancing Charging

  • Current Value Chain

    Fuel Fuel

    Gen Gen

    Self

    Generation

    & Battery

    Self

    Generation

    & Battery

    Customer Customer

    Sub

    Customer

    Group A

    Customer

    Group A

    2 way flow

    of energy

    Third party

    load

    Third party

    load

    22

    Transformer Transformer

    Substation Substation

    Customer

    Group B

    Customer

    Group B Customer

    Group C

    Customer

    Group C

    Transformer Transformer Transformer Transformer

    Customer Customer

    Customer Customer

    Self

    Generation

    & Battery

    Self

    Generation

    & Battery

    Customer Customer

    3rd party

    Renewable

    Generation

    Intermittent

    3rd party

    Renewable

    Generation

    Intermittent

    3rd party

    Renewable

    Generation

    Intermittent

    3rd party

    Renewable

    Generation

    Intermittent

    Sw Sw

    X X

  • Network Topology without PV/Battery

    (Base Case)

    Total No. of Distribution Transformers: 23

  • Network Topology without PV/Battery

    (Optimised)

    Total No. of Distribution Transformers: 12

  • Network Topology with PV/Battery

    (Optimised Charging, Peak Load)

    Total No. of Distribution Transformers: 10

  • Multi-Flow Network Design

    Base Network Optimized

    Network

    Optimized

    Network +

    Battery

    Total Cost ($) 3.0 million 2.3 million 2.0 million

    No. of

    Transformer

    23 12 10

    Total Transformer

    KVA

    7,245 kVA 2,935 kVA 1,715 kVA

    Max transformer

    required

    630 kVA 315 kVA 315 kVA

    Conductor Size Smaller

    conductor used

    wherever

    possible

    Smaller

    conductor used

    due to reduced

    flow

  • Multi-Flow Network – Technical Issues

    • Power Quality & Fault Level Issues

    – Reduced Protection Sensitivity

    – Motor Starting

    – Voltage Control

    – Frequency Control

    – Harmonics & Flicker

    – Black Start

    – Earthing

    • Voltage & Frequency Control

    • Network Optimisation, Network Losses, Optimal Generator Placement

    • Real Power Balancing & Load Control

    • Managing Network Demand & Customer Expectations

  • Customer & Stakeholder Expectations

    • Customers are looking to take greater control of their

    energy to reduce energy costs.

    • Consumer demand for renewable energy is growing.

    • Customers expect a choice of energy options, including

    more renewable energy options.

    • Customers want fewer restrictions to taking up solar.

    • Customers want to see transparency, and active

    communication and education of the community on

    renewable and other energy options.

    • Energy costs should be as affordable as possible.

  • DER Long Term Vision

    Present Day

  • Intelligent System Control –

    Feed in Management and Storage

    Battery Battery

    Store excess power

  • Intelligent System Control - Feed in Management

  • Project Highgarden

    PV on AMI

    Distributed PV & Battery Trial (Meekatharra)

    Micro-Grid Trial Intelligent System

    Control

    ‘Distributed Energy Resources’ Business Future

    Multi-Flow Network

    DER Technology Trial

    Stand-alone Power Systems

    Modular Generation Capacity

    High Penetration Renewable Energy &

    Storage

    1.Business Model Development 2.Market Platform

    Intelligent Consumer Services

    Onslow Demonstration

    1.DER Monitoring and Control

    2.Protection Studies 3.Remote Sensing 4.Feed-In Management

    1.Distributed Generation Review

    1.Network Design Optimisation

    1.Generation Philosophy 2.Commercial Model

    Assessment

    1.Esperance SPS Trial

    2.NIS SPS Trial

    Onslow DER

  • The Highgarden Trials

  • Customers – Technical Requirements

    • Feed in Management

    • Sunspec

    • New requirements under AS4777 – Settings

    • Inverter reactive power capability

    • Extended Ramp Rate Installations

    • Changeover switches

    • Updated Testing Requirements

    • Updated Information requirements for Class III

  • Onslow Microgrid Works

    Main elements of scope:

    • To be constructed in 2017 (already tendered –

    award planned for December 2016):

    – Power station located in Lot 555 (expandable

    for the future)

    – Transmission line (tendered both O/H & U/G

    – TBA)

    – Zone substation located in Lot 880

    – Network extensions into the town (U/G)

    • To be constructed in 2018:

    – Solar and Battery Storage (siting feasibility

    studies underway – construction 2018)

    – Gas lateral: 23km 4” pipeline (complete - by

    others) and 87 km of 6 inch pipeline (existing)

  • 38

    Thank You & Questions

    Laurie Curro

    General Manager Power System Services

    0061 8 6310 1530

    [email protected]

    Marble bar centralised solar farm at night


Recommended