Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005
Transcript
Page 1: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Hilfiker Spiralnail Successfully Completed

Projects 2004 – 2005

Enayat Aziz December 2005

Page 2: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Spiderweb®

Steepened Slope

North Camano Drive Spiderweb Steepened Slope

March 2004for Island County Public Works

Page 3: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Steepened SlopeSpiderweb® Reinforced

Page 4: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

steepened slope spider driving

Page 5: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

completed spider mounted to spiralnail

Page 6: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

March 2004

Page 7: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

driving spider

Page 8: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

completed

spiderweb slope

Page 9: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Crescent Harbor Road Shoulder RepairSpiralnail Trinity WallMarch 2004for Island County Public Works

Page 10: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

trinity cage & spiralnail

shoulder repair

Page 11: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

one Giant step for Spiralnail system

Page 12: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

spiralnail and spiders over highway shoulder

Page 13: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Frostad Road Shoulder Repair Spiralnail Trinity Wall

August 2004for Island County Public Works

Page 14: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Frostad Road September 2004

Page 15: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

typical shoulder widening or slide stabilization

Page 16: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Parker Road Slide Repair Spiralnail Trinity WallOctober 2004for Island County Public Works

Page 17: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

driving spiders,nail pullout

testing

Page 18: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Parker Road“before”condition

Page 19: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Parker Roadnon-destructive

shoulder repair/widennni

ng

Page 20: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Survey Office Foundation Spiralpile Wood Beam FoundationMarch 2004for Island County Public Works

Page 21: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Yuodelis House Slide Repair Spiralnail Trinity WallFebruary 2005for Mr. and Mrs. YuodelisKenmore, Washington

Page 22: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Spiralnail Trinity Wall

Page 23: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Youdelis House

Trinity Wall

Page 24: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

filling trinity cages

Page 25: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

North Queen Anne Drive Bridge Retrofit Shoring WallsApril 2005for Seattle Public Utilities

Page 26: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

the ugly shoring wall

Page 27: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Shotgun Creek Slope Stabilization

Spiralnail Spiderweb Slope

March 2003

for Seattle Public UtilitiesCedar Lake Reservoir

Page 28: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Cedar River Watershed Road #20 Slide Stabilization

Spiralnail Slope ReinforcementFebruary 2003

for Seattle Public Utilities

Page 29: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Miller Creek Bridge

Spiralnail Trinity Bridge Abutment Walls

October 2005

for Lower Columbia River Watershed Council

Clatskanie, Oregon

Page 30: Hilfiker Spiralnail Successfully Completed Projects 2004 – 2005 Enayat Aziz December 2005.

Madrona Way Structural Steepened Slope

Coupeville, WashingtonOctober 2005

for Island County Public Works