+ All Categories
Home > Documents > HiLumi-LHC / LARP Conductor and Cable Internal Review October 16 th and 17 th 2013 H. Felice LARP...

HiLumi-LHC / LARP Conductor and Cable Internal Review October 16 th and 17 th 2013 H. Felice LARP...

Date post: 02-Jan-2016
Category:
Upload: anne-jocelin-conley
View: 214 times
Download: 0 times
Share this document with a friend
Popular Tags:
14
HiLumi-LHC / LARP Conductor and Cable Internal Review October 16 th and 17 th 2013 H. Felice LARP Short Magnets Fabrication and Test experience relevant to QXF conductor and cable specifications
Transcript

HiLumi-LHC / LARP Conductor and Cable Internal ReviewOctober 16th and 17th 2013

H. Felice

LARP Short MagnetsFabrication and Test experience

relevant to QXF conductor and cable specifications

H. Felice 2

What is a successful magnet?

A magnet in which every single stage of fabrication has been successful

A magnet will be considered successful when I quench > 90 % Iss

10/17/2013

LARP history illustrates the involvement of each of these steps in magnet success and failures…

Cable Coil Fabrication Assembly - PreloadStrandDesign

H. Felice 3

Successful LARP Magnets

10/17/2013

Large parameter space covered by short models

H. Felice 4

From TQS02 series to TQS03 series

TQS02c •High RRR (>200)• 70 microns filament• 47 % Cu fraction• Jc (12T, 4.3 K) 2925 A/mm2

Tested at CERN

TQS03• High RRR (>200)• 50 microns filament• 54 % Cu fraction• Jc (12T, 4.3 K) 2770 A/mm2

Tested at CERN

205 – 210 T/m

220T/m

Moving from 54/61 to 108/127 improved performances at 1.9 KIn TQ

10/17/2013

220 T/m 238 T/m

H. Felice 5

TQS03 series and stress limit

-280-260-240-220-200-180-160-140-120-100

-80-60-40-20

0

Ti pole L1 pole L1 mp L2 pole L2 mp

Azi

mut

hal s

tres

s (M

Pa)

TQS03a

TQS03b

TQS03c

TQS03d

With Lorentz forces at 12 kA

10/17/2013

4 tests: TQS03 a, b, c and d

• performed with variable pre-stress• TQS03a: 120 MPa• TQS03b: 160 MPa• TQS03c : 200 Mpa• TQS03d: 120 MPa

After cool-down

-260-240-220-200-180-160-140-120-100

-80-60-40-20

0

Ti pole L1 pole L1 mp L2 pole L2 mp

Azim

utha

l str

ess (

MPa

)

TQS03a

TQS03b

TQS03c

TQS03d

H. Felice 6

TQS03 training

10/17/2013

TQS03 series demonstrated- Progressive degradation: but only 5 % from a to c- Permanent degradation beyond 200 MPa preload- QXF should have margin

• Magnet: pole turn (preload) / max midplane stress (excitation)• TQS03a: - 120 / -190 MPa• TQS03b: - 160 / -240 MPa• TQS03c : - 200 / -260 Mpa• TQS03d: - 120 / -190 Mpa

• Quench location:Midplane area

H. Felice 7

HQ series overview

HQ01 a-b-c-d-eMagnets with mixed coilsCoils 1-2-8-9 => 54/61Coils 3-4-5-6-7 => 108/127

Performance (LBNL and CERN)• 4 magnets => 70 to 85 % Iss at 4.4 K• HQ01e test at CERN => 85 % at 1.9

K

HQ02a and a2Same conductor in all coilsCoils 15-16-17-20 => 108/127

Performance (FNAL)• 98 % at 4.5 K• 89 % at 2.2 K

A. GodekeA. Godeke

10/17/2013

2 of each / magnet

H. Felice 8

HQ series performance overview

HQ01 series

HQ02

Reached 80% in 2 quenches

Good memory

What changed? • The coil fabrication

• Cable with Stainless steel core

HQM04

97% at 4.5 K

94% at 2.2 K

Maxim Marchevsky Guram Chladidze

10/17/2013

H. Felice 9

Impact of coil fabrication

Review of the coil fabrication process and designÞ High compaction of the winding during fabricationÞ Tooling and coil design oversight: no margin to allow for cable expansionÞ Risky end design

Suspected to be the cause of conductor degradation in potted coils

Main requirement for HQ02 coils: using the same tooling as HQ01•Accounting for dimensional changes and interlayer insulation

Smaller cable with smaller strand => 0.778 mm diameter strand => 14.8 mm x 1.375 mm

Axial gap size 4 mm/m•Revision of the end parts design

10/17/2013

Lead end

R, Hafalia, S, Caspi

H. Felice 10

HQ experience applied to QXFconductor

• Cable dimensional change accounted for in the magnetic design and tooling design

• 4.5 % in thickness and 2 % in width in ROXIE cross-section• Design made with reacted cable dimensions• Based on HQ and LQ experimental data

Importance to provide actual cable dimensional changes data for QXF cable to magnet designers

10/17/2013

H. Felice 11

Impact on coil fabrication schedule

Last HQ01 coil #9 completed end of 2010HQ01d and e tested starting April 2011

1st Mirror test at FNAL HQM01

2nd Mirror test at FNAL HQM02• 1 less turn• 91 % Iss at 4.6 K• 89 % Iss at 2.2 K

3rd Mirror test at FNAL HQM04• New end parts• New cable

HQ02 tested at FNAL

To validate compaction theory09/2011

05/2013

05/2012

04/2011

• Unforeseen change of cable in the case of HQ02 delayed strongly the magnet production

• QXF 2nd generation cable should be defined very early to facilitate implementation

10/17/2013

H. Felice 12

HQ Winding Experience

HQ01: 1st generation of coils• 2 pass cable• Mechanically stable

HQ02: 2nd generation of coils

• 1 pass cable to implement the stainless steel core• “Easy” popped strands noticed by technicians in some coils

• Easily fixable

HQ02 experience => Learning experience on how to handle less mechanically stable cables

10/17/2013

D. Dietderich - F. Borgnolutti

H. Felice 13

Impact of SS core in HQ performance

10/17/2013

X. Wang, J. DiMarco, M. Marchevsky – Guram Chladidze

HQ01 / HQ02 performance

• Beneficial effect on ramp rate dependence

• Beneficial effect on field quality

H. Felice 14

Summary

10/17/2013

• LARP short models performance widely influenced by all the production chain

• Best examples: HQ01 to HQM04 / HQ02• With coil fabrication improvement => performance improvement

• despite low RRR in coil 15

• What to remember from short model program for QXF

• Cable• Beneficial effect of the core cable on field quality and ramp rate dependence• let’s keep in mind the potential delay to implement a new cable design

• Coil fabrication / tooling design: • Data for Effective dimensional changes in the design

• Assembly: Stress level in conductor => TQS03 is a good guideline


Recommended