instruction manual CLASS 3 LIGHTWEIGHT ALUMINIUM TOWER 3 T-through the trap method Double width span: HD1004-3-8/12 Single width span: HD1004-3-8/12 Mobile access and working towers To BS1139 part 3: 1994 (HD1004) Maximum loading 2KN/m2 Total tower Loading including Self weight 1,000kgs Ladder frames Colour coded braces Aluminium folding toe board set Class 3 loading Wider frame Easy erection Platform fitted with windlock PRODUCTS LIMITED ® EIGER 500 PRODUCTS LIMITED ® Pop-Up Products Limited 2 Deeside Point, Tenth Avenue Deeside Industrial Park, Deeside CH5 2UA Tel +44 (0)1244 833 933 Fax +44 (0)1244 833 934 Email [email protected] www.popupproducts.co.uk (v.04.09)
Transcript
Page 1: Hire Station | Equipment and Tools | Construction and DIY

instruction manual

CLASS 3 LIGHTWEIGHTALUMINIUMTOWER

3 T-through the trap method

Double width span:HD1004-3-8/12

Single width span:HD1004-3-8/12

Mobile access and working towersTo BS1139 part 3:1994 (HD1004)

Maximum loading2KN/m2Total towerLoading includingSelf weight1,000kgs

Ladder frames

Colour coded braces

Aluminium folding toe board set

Class 3 loading

Wider frame

Easy erection

Platform fitted with windlock

PRODUCTS LIMITED

®

EIGER 500

PRODUCTS LIMITED

®Pop-Up Products Limited

2 Deeside Point, Tenth AvenueDeeside Industrial Park, Deeside CH5 2UA

Tel +44 (0)1244 833 933 Fax +44 (0)1244 833 934Email [email protected]

www.popupproducts.co.uk

(v.04.09)

Page 2: Hire Station | Equipment and Tools | Construction and DIY

EIGER 500

PRODUCTS LIMITED

®

instruction manual

2 27

Page

3noitcudortnI

5rewot eht gnisU

Equipment Overview 6

31ecneuqeS noitcerEfor Double Width 1450 Tower

Components - Double Width 17

02ecneuqeS noitcerEfor Single Width 850 Tower

Components - Single Width 22

Safe Working Loads 25

IND

EX

NOTES

Page 3: Hire Station | Equipment and Tools | Construction and DIY

EIGER 500 instruction manual

26

NOTES

PRODUCTS LIMITED

®

INTRODUCTIONThis manual provides the user with a step by step sequence of howto erect an EIGER 500 Aluminium Tower using the 3 T Method. The3 T applies to both Single and Double Width Towers, the enclosedillustrations show erection sequences for both. The sequence isdifferent for Even Platform Heights such as 2.20, 4.20, 6.20 mtrs etcand Odd Platform Heights such as 3.20, 5.20, 7.2 mtrs as shown.Prior to erection of the tower the user should familiarise himselffully with the contents of this document and pay particular regardto the various safety notes herein. On handover of the structure toany third party, a copy of these instructions should be passed overto ensure that they are aware of the permitted uses of the tower.

Safety NotesTwo operatives are required to erect the towers detailed in this manual.

Check that the ground upon which the tower is to be used is capable of withstanding the combined weight of the tower and any necessaryloading.

The maximum safe working load per individual platform is 294kguniformly distributed. Refer to page 17 for overall loadings.

Temporary means of gaining additional height e.g. stepladders or trestlesplaced on the top of the working platform must not be used.

Access to or from the working platform must be gained only via theladder access provided. In all cases the user must climb within thestructure of the tower – never by climbing the outer face of the tower.

Tower components must be raised/lowered in a controlled manner, neverthrown or dropped. If using a rope, a reliable knot such as a clovehitchor timber hitch should be employed. No hoisting arrangements shouldbe used without specific design from the manufacturer.

3

Page 4: Hire Station | Equipment and Tools | Construction and DIY

Where restricted ground space prohibits the attachment of stabilisersphysical ties (see page 8) or ballast weights must be employed – in suchcircumstances the supplier should be consulted for guidance.

Prior to erection, check via component schedules that all necessary partsare available and that they are in good working order.

For further information on inspection and maintenance – contact themanufacturer direct.

Repositioning of ComponentsSome Towers require the repositioning of components during the erectionsequence. Please refer to component repositioning table on page 17 of thisinstruction manual before commencing erection.

Moving the TowerCheck that the course to be followed is free of ground or overheadobstructions e.g. roof trusses, electricity cables, raised manhole/gratingsetc. The tower shall be moved only by manual pushing near to its base – never by any mechanical means such as forklift/towing etc. Great caremust be taken when moving a tower over uneven ground. Stabilisersshould be raised a minimum amount but not greater than 12mm (1/2")to clear the ground of any obstructions and the top platform height mustnot exceed 2.5 times the smallest base dimension. Neither men normaterials should be present on the tower while it is being moved.

Having re-sited the tower ensure that it is still level and that the stabilisersare correctly adjusted and secure. Ensure that the castors are relocked.Check that no environmental changes influence the safe use of the tower.

EIGER 500 instruction manual

4

PRODUCTS LIMITED

®

SAFE WORKING LOADS!INDIVIDUAL PLATFORMSThe maximum safe working loads per individual platform is 294Kguniformly distributed.

WORKING LEVELThe maximum safe working load per working level is 588Kg on DoubleWidth Towers, 294Kg on Single Width. A working level is created by theuse of 2 platforms DW, 1 Platform SW. The maximum number of workinglevels per tower is 2.

COMPLETE TOWER STRUCTUREThe maximum safe working load of the Tower structure including selfweight and ballast is 1,000Kgs.

COMPONENT REPOSITIONING TABLETower

PlatformHeight(Mtrs)

Reposition Platform& Guardrails

from 1st Rung 0.70mto working level

Reposition Platform& Guardrails

from 2nd Rung 1.20mto working level

Reposition Platform& Guardrails

from 3rd Rung 1.70mto working level

Reposition Platform& Guardrails

from 4th Rung 2.20mto working level

2.70

4.70

5.20

5.70

6.20

6.70

7.20

7.70

8.20

8.70

9.20

9.70

10.20

10.70

11.20

11.70

12.20

25

(v.04.09)

Page 5: Hire Station | Equipment and Tools | Construction and DIY

USING THE TOWERWind conditions have a considerable bearing on the safe use of a tower.Due regard must be paid to certain circumstances where wind conditionsare magnified e.g. in long open-ended buildings, between buildingswhere the wind may have a funnelling effect, or where the tower ispositioned close to the corner of a building. Never attach tarpaulins orother covering to a tower without first seeking the suppliers advice.

PRODUCTS LIMITED

®

5

(SW

) Ladder

Fra

me

AV

AIL

AB

LE IN

TW

O L

ENG

THS

1.8M

AN

D 2

.5M

SIN

GLE W

IDTH

WH

3.2

3.7

4.2

4.7

5.2

5.7

6.2

6.7

7.2

7.7

8.2

8.7

9.2

9.7

10.2

10.7

11.2

11.7

12.2

12.7

13.2

13.7

14.2

PH1.

21.

72.

22.

73.

23.

74.

24.

75.

25.

76.

26.

77.

27.

78.

28.

79.

29.

710

.210

.711

.211

.712

.2HA

TCH

PLAT

FORM

11

11

22

22

22

23

33

34

44

45

55

5HO

RIZO

NTA

L BR

ACE

66

66

1010

1010

1010

1014

1414

1418

1818

1822

2222

22DI

AGON

AL B

RACE

22

34

57

78

911

1112

1315

1516

1719

1920

2122

23TO

EBOA

RD S

ET S

W1

11

11

11

11

11

12

22

33

33

33

33

FIXE

D ST

ABIL

ISER

00

44

44

40

00

00

00

00

00

00

00

0TE

LESC

OPIC

STA

BILI

SER

00

00

00

04

44

40

00

04

44

40

00

0SE

MI J

UMBO

STA

BILI

SER

00

00

00

00

00

04

44

40

00

04

44

4BA

LLAS

T W

t(Kg

)0

00

00

00

00

00

01

23

00

00

00

00

TOTA

L TOW

ER W

EIGH

T 1.

8m(K

g)73

.6276

.6910

0.311

06.93

137.0

4145

.8615

0.291

59.59

166.2

2175

.0417

9.472

14.77

251.6

8285

.5031

4.932

70.11

276.7

4285

.5628

9.993

25.29

331.9

2338

.5434

5.17

TOTA

L TOW

ER W

EIGH

T 2.

5m(K

g)69

.6485

.21109

.2811

6.351

52.63

162.3

5166

.7817

6.531

83.61

193.3

3197

.7623

9.232

77.53

312.2

5341

.6830

3.973

11.05

320.7

7325

.2036

6.673

73.75

380.8

2387

.90

INTER

NA

L/E

XTER

NA

LIN

TER

NA

L U

SE O

NLY

24

Page 6: Hire Station | Equipment and Tools | Construction and DIY

EQUIPMENT OVERVIEW

EIGER 500 instruction manual

4 RungFrame - DW

Width 1450mmHeight 2000mmWeight 9.15Kg

3 RungFrame - DW

Width 1450mmHeight 1500mmWeight 6.86Kg

2 RungFrame - DW

Width 1450mmHeight 1000mmWeight 4.95Kg

4 Rung LadderFrame - DW

Width 1450mmHeight 2000mmWeight 11.8Kg

3 Rung LadderFrame - DW

Width 1450mmHeight 1500mmWeight 8.85Kg

2 Rung LadderFrame - DW

Width 1450mmHeight 1000mm

Weight 5.9Kg

W

H

Double Width Frames= 1450mm Span

Double Width Ladder Frames= 1450mm Span

6

(SW

) Ladder

Fra

me

AV

AIL

AB

LE IN

TW

O L

ENG

THS

1.8M

AN

D 2

.5M

SIN

GLE W

IDTH

WH

3.2

3.7

4.2

4.7

5.2

5.7

6.2

6.7

7.2

7.7

8.2

8.7

9.2

9.7

10.2

10.7

11.2

11.7

12.2

12.7

13.2

13.7

14.2

PH1.

21.

72.

22.

73.

23.

74.

24.

75.

25.

76.

26.

77.

27.

78.

28.

79.

29.

710

.210

.711

.211

.712

.2CA

STOR

44

44

44

44

44

44

44

44

44

44

44

4AD

JUST

ABLE

LEG

44

44

44

44

44

44

44

44

44

44

44

42

RUN

G LA

DDER

FRA

ME

00

10

01

10

01

10

01

10

01

10

01

12

RUN

G EN

D FR

AME

02

10

01

10

01

10

01

10

01

10

01

13

RUN

G LA

DDER

FRA

ME

01

01

01

01

01

01

01

01

01

01

01

03

RUN

G EN

D FR

AME

01

01

01

01

01

01

01

01

01

01

01

04

RUN

G LA

DDER

FRA

ME

10

11

21

22

32

33

43

44

54

55

65

64

RUN

G EN

D FR

AME

10

11

21

22

32

33

43

44

54

55

65

6

INTER

NA

L/E

XTER

NA

LIN

TER

NA

L U

SE O

NLY

23

(v.04.09)

Page 7: Hire Station | Equipment and Tools | Construction and DIY

PRODUCTS LIMITED

®

W

H

Single Width Frames= 850mm Span

Single Width Ladder Frames= 850mm Span

4 Rung LadderFrame - SW

Width 850mmHeight 2000mmWeight 10.2Kg

3 Rung LadderFrame - SW

Width 850mmHeight 1500mmWeight 7.65Kg

2 Rung LadderFrame - SW

Width 850mmHeight 1000mmWeight 5.10Kg

4 RungFrame - SW

Width 850mmHeight 2000mm

Weight 7.5Kg

3 RungFrame - SW

Width 850mmHeight 1500mmWeight 5.62Kg

2 RungFrame - SW

Width 850mmHeight 1000mmWeight 3.75Kg

7

EIGER 500 instruction manual

COMPONENTS- SINGLE WIDTH

22

Page 8: Hire Station | Equipment and Tools | Construction and DIY

EIGER 500

DW 1.8mLength 1800mmDepth 150mmWeight 6.28Kg

DW 2.5mLength 2500mmDepth 150mmWeight 7.22Kg

SW 1.8mLength 1800mmDepth 150mmWeight 5.28Kg

SW 2.5mLength 2500mmDepth 150mmWeight 6.22Kg

Adjustable LegOverall Size 740mmAdjustment 330mmOverall Size 1.42Kg

Locking CastorSize 150mm

Weight 3.26Kg

Toeboard Set

Adjustable Leg and Castor

Platform 1.8mLength 600mmWidth 1800mm Weight 15.04Kg

Platform 2.5mLength 600mm Width 2500mmWeight 19.2Kg

Hatch Platform

EQUIPMENT OVERVIEWStandard Platform

Platform 1.8mLength 600mmWidth 1800mm Weight 13.9Kg

Platform 2.5mLength 600mmWidth 2500mm Weight 18.5Kg

instruction manual

8

PRODUCTS LIMITED

®

STEP 3Fit trapdoor platform onto 6th rung(3.20 mtr level) above the ladder.

STEP 4Locate 4 rung frames and fit diagonalsonto lowest rungs, attach stabilisers toeach corner.

STEP 5Access the platform and secureguardrail braces and diagonal brace at opposite end of tower.

STEP 6Fit Toeboard assembly.

Dismantling the Eiger 500 using the3 T MethodRemove Toeboard set and pass down the tower. Detach the furthest endof the 4 Guardrail and 1 Diagonal Brace and immediately go toprotected trapdoor position on ladder frame to detach braces fully.Reverse steps 7 to 1.

21

Page 9: Hire Station | Equipment and Tools | Construction and DIY

STEP 1Fit trapdoor platform onto 2nd rung of 4 rung frame, attach 4 guardrail braces onto both sides of platform on 3rd and 4th rungs from the ground. Fit diagonal braces.

STEP 2Access the tower through trapdoorplatform, locate 4 rung frames and fitdiagonal braces and stabilisers.

20

PRODUCTS LIMITED

®

Horizontal Braces Diagonal Braces

Stabilisers

1.8 metresHook Centres 1800mm

Weight 2.02Kg

2.5 metresHook Centres 2500mm

Weight 2.50Kg

1.8 metresHook Centres 2100mm

Weight 2.02Kg

2.5 metresHook Centres 2700mm

Weight 2.50Kg

FixedMax Outreach

1570mmWeight 3.91Kg

TelescopicMax Outreach

1950mmWeight 4.58Kg

Semi-JumboMax Outreach

2500mmWeight 5.88Kg

9

EIGER 500 instruction manual

ERECTION SEQUENCE For Single Width 850 Tower

3.2 Mtr Platform HeightThis erection sequence starts with 4 rung frames, showing the methodfor odd platform heights such as 3.20, 5.20, 7.20 etc.

Follow steps 1 to 3 in the erectionguide for the Double width Tower P12

Page 10: Hire Station | Equipment and Tools | Construction and DIY

EIGER 500

EQUIPMENT OVERVIEW

instruction manual

Stability of TowerStabilisers shall always be fitted where specified, these increase theeffective base area of the tower and increase its stability as a free standingstructure. Best effect is obtained from the stabilisers when they arearranged in a footprint as near to a square. (See Fig. 1) When using thetower against a strong wall they may be positioned as at Fig. 2, but thewall must be at least 2/3 of the height of the top working platform. Towersto be left unattended in exposed positions should be tied to a securestructure or alternatively dismantled. Horizontal forces, such as thatexerted against the tower during drilling into a building face, can generateinstability in the structure and must not be used as a means of access toany adjacent structure. Towers are not designed to be suspended.

Installation of StabilisersWhen locating stabilisers on towers, maximum stability will be achievedby positioning at an angle of 45°. Extend stabiliser leg to maximumadjustment and ensure that the top coupler is positioned to theunderside of the casting. Securely lock the top coupler before attachingthe lower arm to the frame upright. Ensure that the rubber foot is incontact with the ground surface.

10

(DW

) Ladder

Fra

me

AV

AIL

AB

LE IN

TW

O L

ENG

THS

1.8M

AN

D 2

.5M

WH

3.2

3.7

4.2

4.7

5.2

5.7

6.2

6.7

7.2

7.7

8.2

8.7

9.2

9.7

10.2

10.7

11.2

11.7

12.2

12.7

13.2

13.7

14.2

PH1.

21.

72.

22.

73.

23.

74.

24.

75.

25.

76.

26.

77.

27.

78.

28.

79.

29.

710

.210

.711

.211

.712

.2ST

ANDA

RD P

LATF

ORM

11

11

11

11

11

11

11

11

11

11

11

1HA

TCH

PLAT

FORM

11

11

22

22

22

23

33

34

44

45

55

5HO

RIZO

NTA

L BR

ACE

66

66

1010

1010

1010

1014

1414

1418

1818

1822

2222

22DI

AGON

AL B

RACE

22

34

56

78

911

1112

1315

1516

1719

1920

2122

23TO

EBO

ARD

SET

DW1

11

11

11

11

11

11

11

11

11

11

11

FIXE

D ST

ABIL

ISER

00

04

44

44

40

00

00

00

00

00

00

0TE

LESC

OPIC

STA

BILI

SER

00

00

00

00

04

44

00

04

44

44

44

4SE

MI J

UMBO

STA

BILI

SER

00

00

00

00

00

00

44

40

00

00

00

0TO

TAL T

OWER

WEI

GHT

1.8m

(Kg)

91.77

96.43

104.8

2127

.5215

8.441

60.35

173.6

9180

.7518

8.192

00.88

206.1

2236

.6624

9.302

59.31

263.6

0289

.8929

7.333

07.34

312.5

8343

.1235

0.563

58.37

365.8

1TO

TAL T

OWER

WEI

GHT

2.5m

(Kg)

104.89

109.5

5118

.3914

1.541

78.63

189.5

4194

.7820

2.292

10.18

223.7

7229

.0126

5.722

78.81

289.7

2294

.9632

6.473

34.36

345.2

735

0.513

87.22

395.1

1403

.3741

1.26

INTER

NA

L/E

XTER

NA

LIN

TER

NA

L U

SE O

NLY

19

Page 11: Hire Station | Equipment and Tools | Construction and DIY

11

PRODUCTS LIMITED

®

BallastWhere shown in the component list, ballast must be used to stabiliseagainst overturning. Only use solid materials as ballast (ie: no loosematerials) and position to avoid overloading individual components.Ballast should be supported by base of tower and securely fastened toprevent removal.

Colour CodingColour coded trigger assemblies allow easy identification of componentsizes/brace types or horizontal/diagonal braces.Horizontal Brace RedDiagonal Brace Blue

Tying-inThe towers in this manual are designed for use as free standing units up to heights of 8m OUTDOORS/12m INDOORS. Towers in excess of these heights, where the optimum base dimensions cannot be achieved,will need to be tied to a secure structure. Special couplers, which will accommodate the differing diameters ofscaffold tube and alloy tube, are available from your supplier. Typical tiearrangements can be found below. Manufacturers instructions should befollowed where anchor bolts are to be used.

(DW

) Ladder

Fra

me

AV

AIL

AB

LE IN

TW

O L

ENG

THS

1.8M

AN

D 2

.5M

DO

UBLE W

IDTH

WH

3.2

3.7

4.2

4.7

5.2

5.7

6.2

6.7

7.2

7.7

8.2

8.7

9.2

9.7

10.2

10.7

11.2

11.7

12.2

12.7

13.2

13.7

14.2

PH1.

21.

72.

22.

73.

23.

74.

24.

75.

25.

76.

26.

77.

27.

78.

28.

79.

29.

710

.210

.711

.211

.712

.2CA

STOR

44

44

44

44

44

44

44

44

44

44

44

4AD

JUST

ABLE

LEG

44

44

44

44

44

44

44

44

44

44

44

42

RUN

G LA

DDER

FRA

ME

00

10

01

10

01

10

01

00

01

10

01

12

RUN

G EN

D FR

AME

02

10

01

10

01

10

01

20

01

10

01

13

RUN

G LA

DDER

FRA

ME

01

01

01

01

01

01

01

01

01

01

01

03

RUN

G EN

D FR

AME

01

01

01

01

01

01

01

01

01

01

01

04

RUN

G LA

DDER

FRA

ME

10

11

21

22

32

33

43

44

54

55

65

64

RUN

G EN

D FR

AME

10

11

21

22

32

33

43

44

54

55

65

6

INTER

NA

L/E

XTER

NA

LIN

TER

NA

L U

SE O

NLY

18

Page 12: Hire Station | Equipment and Tools | Construction and DIY

EIGER 500

EQUIPMENT OVERVIEW

instruction manual

Tying-in

TrainingPop-Up Products Limited are full members of the Prefabricated AluminiumScaffolding Manufacturers Association (PASMA), an association of the UK’smajor manufacturers of aluminium tower systems. PASMA membercompanies have their equipment approved to EN 1004:2004, andtherefore carry BS Kitemark, guaranteeing the user that stringent standardsof design and fabrication have been met.

12

PRODUCTS LIMITED

®

COMPONENTS- DOUBLE WIDTH

17

Page 13: Hire Station | Equipment and Tools | Construction and DIY

Dismantling the Eiger 500 using the 3 T MethodRemove Toeboard set and pass down the tower. Detach the furthest endof the 4 Guardrail and 1 Diagonal Brace and immediately go to protectedtrapdoor position on ladder frame to detach braces fully.Reverse steps 9 to 1.

16

PRODUCTS LIMITED

®

13

Aluminium towers are designed to be erected and dismantled by operativeslacking in intensive skills and training. Provided that the erector can interpretthe basic instructions in the suppliers manual and can competently check thefinished structure then no problems should arise. PASMA recognise,however, that increasingly more specific training in the use of this type ofequipment is required. PASMA therefore sponsors a training course basedon a format agreed by all its member companies, the content of which hasbeen devised from their collective experience in all the industry. Hence it hasgreat value as a training programme and is widely recognised by the Health& Safety Executive as being the industry benchmark. Further details on thisprogramme are available on request.

ERECTION SEQUENCE For Double Width 1450 Tower

4.20 Mtr Platform HeightFrom the component schedules in this manual ensure that you have allthe parts necessary to complete the tower and check that they are in aserviceable condition.

Some Towers require the repositioning of components during the erectionsequence. Please refer to component repositioning table on page 17 ofthis instruction manual before commencing erection.

Ensure that the base onto which the tower will be erected is reasonablylevel and is capable of supporting the weight of the tower and its load.

Ensure that the interlock clips are disengaged. Two men will be neededto erect the tower in a safe manner.

EIGER 500

STEP 9Climb ladder and using the trapdoorplatform for protection sit with bothfeet on the ladder fit 4 guardrailbraces onto 9th and 10th rungs toboth sides of tower.

STEP 10Access the platform and secureGuardrails and Diagonal brace atopposite end of tower. NOTE: Ifbuilding the tower beyond the 4.20mtr level, continue with steps 4 and5 until desired working height isachieved, then follow step 8.

STEP 11Fit Toeboard assembly.

instruction manual

Page 14: Hire Station | Equipment and Tools | Construction and DIY

EIGER 500

PRODUCTS LIMITED

®

NB - For Single Width STEP 4 go to Page 14

STEP 1Insert castor / adjustable leg assembliesinto base of 2 rung ladder frame and onestandard end frame, allowingapproximately 75mm of extended leg forlevelling. Press down firmly on breakingmechanism to lock castors.

STEP 2Fit a horizontal (Red) brace onto thevertical member of one frame, restingdirectly onto the alloy casting at thefirst horizontal rung position. Ensurethat the sprung trigger faces to theoutside of the tower.

STEP 3Join second base frame to first ensuringbrace hook again rests directly ontoalloy casting. Fit second horizontalbrace in corresponding position. Levelaround base of tower by using a spiritlevel, making adjustments as necessaryto adjustable legs.

STEP 4Locate 4 rung frames and fitdiagonals onto lowest rungs, attach stabilisers to each corner.

STEP 5Locate trap door platform on 4thrung 2.20 mtr level above ladder.

STEP 6Climb ladder and using the trap doorplatform for protection sit with bothfeet on the ladder fit 4 guardrailbraces on 5th and 6th rungs abovetrap door to both sides of platformand secure diagonal brace. Accessthe platform and secure guardrailsand diagonal brace at opposite endof the tower.

STEP 7Fit next lift of 4 rung frames andattach diagonal braces.

STEP 8If working height of tower is achievedon this frame, locate standardplatform on 8th rung and slide acrossto opposite side of tower, locatetrapdoor platform above the ladder,this is the 4.20 mtr level.

instruction manual

14 15


Recommended