Date post: | 27-Mar-2015 |
Category: |
Documents |
Upload: | evan-burke |
View: | 218 times |
Download: | 3 times |
HOC-664 Hocking Hills StudyStakeholder Meeting
August 15, 2008Hocking Hills State Park
Welcome, Introductions, and Purpose of Meeting
Meeting Purpose
• Update project stakeholders on the status of the Hocking Hills Study
• Present the Draft Preliminary Engineering Study
• Seek discussion/comment on the recommendations of the study and begin moving toward concurrence
Project Summary
• Study portion of the project to complete Steps 1-4 of the ODOT PDP for Minor Projects
• Project kick-off was held on October 21, 2006
• Public involvement meeting was held June 25, 2007– Preliminary alignments for the relocation alternative were
presented to the public and legislative representatives
– Based on comments received at this meeting, a pedestrian bridge alternative, which had been previously considered, was brought back as an alternative for further evaluation
• The Preliminary Engineering Study was then developed to further evaluate the alternatives and recommend a preferred alternative for advancement into detailed design
Preliminary Engineering Study
Purpose and need Statement (cont’d)
• Given the existing alignment of SR 664 and the safety and environmental concerns it creates, the following Purpose and Need Statement was developed.
The purpose of the Hocking Hills Study is to improve motorist and pedestrian safety on SR 664 in the vicinity of the Old Man’s Cave section of Hocking Hills State Park while considering future transportation and recreational needs. In order to fulfill this purpose, an effective solution must address the following needs as identified by the project team and stakeholders:
• Correct geometric deficiencies to maximize safety features where pedestrian safety is most compromised.
• Achieve effective and appropriate integration of the roadway and park for the benefit of both pedestrians and motorists.
Purpose and need Statement (cont’d)
• In addition to the identified needs, goals and objectives were established to help ensure that the interests and concerns of all project stakeholders are successfully met. The project goals include:
– Protection of the gorge and park setting from potential environmental damage resulting from the proximity of SR 664. Concerns include noise and water pollution and damage from vibration
– Incorporation of context sensitive solutions to improve the aesthetic character of both the state park and SR 664 and to reduce the permanent footprint of the project.
Overview of Alternatives
• Two build alternatives, along with the No-Build, are described and evaluated in the Preliminary Engineering Study.– No-Build: Required by the PDP to serve as baseline in
comparison of other alternatives. Simply involves maintaining the existing facility and carrying out any committed work.
– Alternative A: Relocates approximately 1 mile of SR 664 to new alignment north of the main parking lots. Is a hybrid of options B and C presented at the public meeting last June. The existing alignment would be abandoned and converted to a new use consistent with park development plans.
– Alternative B: Pedestrian bridge extending over SR 664 from the main parking lots to the south side of the road near the picnic shelter and visitor’s center.
Overview of Alternatives
Overview of Alternatives
• Two build alternatives, along with the No-Build, are described and evaluated in the Preliminary Engineering Study.– No-Build: Required by the PDP to serve as baseline in
comparison of other alternatives. Simply involves maintaining the existing facility and carrying out any committed work.
– Alternative A: Relocates approximately 1 mile of SR 664 to new alignment north of the main parking lots. Is a hybrid of options B and C presented at the public meeting last June. The existing alignment would be abandoned and converted to a new use consistent with park development plans.
– Alternative B: Pedestrian bridge extending over SR 664 from the main parking lots to the south side of the road near the picnic shelter and visitor’s center.
Overview of Alternatives
Overview of Alternatives
• Two build alternatives, along with the No-Build, are described and evaluated in the Preliminary Engineering Study.– No-Build: Required by the PDP to serve as baseline in
comparison of other alternatives. Simply involves maintaining the existing facility and carrying out any committed work.
– Alternative A: Relocates approximately 1 mile of SR 664 to new alignment north of the main parking lots. Is a hybrid of options B and C presented at the public meeting last June. The existing alignment would be abandoned and converted to a new use consistent with park development plans.
– Alternative B: Pedestrian bridge extending over SR 664 from the main parking lots to the south side of the road near the picnic shelter and visitor’s center.
Overview of Alternatives
Evaluation of Alternatives:Purpose and Need
No-Build Alternative A Alternative B
Improves Pedestrian and Motorist Safety
No
Yes – Eliminates pedestrian safety concerns and all
geometric deficiencies but one
No – Is unlikely to improve pedestrian
safety* and corrects no geometric deficiencies
Improves Integration of
Roadway and ParkNo
Yes – Allows for expansion of visitor’s
center and parking, and creation of recognizable
and uniform park entrances. Creates
smooth transition from auto-oriented to
pedestrian-oriented areas
No – Conflicts with park planning efforts by precluding future expansion of park
facilities. Further disrupts the park setting by
introducing a large bridge over the road in the middle of the park.
* - Based on research of pedestrian bridge usage (National Center for Safe Routes to School)
Evaluation of Alternatives:Goals and objectives
No-Build Alternative A Alternative B
Reduces Pollution From Run-Off (Application of
BMP’s)No Yes No
Improves Aesthetics for Park Visitors and
MotoristsNo
Yes – Screens the road from view of the park. Better matches rest of Hocking Hills Scenic
Byway. Includes context sensitive design solutions to establish a more natural
feel to the road.
No
Reduces Potential Vibration Issues (Based on Distance to Gorge)
No Yes No
Reduces Noise Impacts on Park (Based on Distance to Gorge)
No Yes No
Evaluation of Alternatives:Environmental Impacts
No-Build Alternative A Alternative B
Potential Indiana Bat Roost Trees Impacted
No 74 0
Unique/High Quality Habitat Impacts
No No No
Stream Impacts (Linear Feet & Anticipated Permit)
No1,475 – Individual 404/401 Permit
0
Impacts to Observed Endangered Species
No No No
Potential for Cultural Resource Impacts
No No No
Section 4(f)/6(f) Impacts No
Moderate – Large land conversion, but small
impact to park facilities
Moderate – Small land conversion,
but large impact to park facilities
Evaluation of Alternatives:Impacted Land, Facilities, & Cost
No-Build Alternative A Alternative B
Footprint of Completed Project (Acres)
0 4.97 0.12
Estimated Cost $0 $5,454,630 $960,000
Land Impacted By Project Construction (Acres)
0 19.20 0.12
Impact to Park FacilitiesPrevents
future improvements
Low – Temporary access changes at east & west ends of
park. Removed parking lot adjacent to
Culp Rd. Converts existing SR 664 to
walking path & allows for improvements to
existing facilities.
High – Removes 60-65 parking spaces and
eliminates west drive from
highest demand lot. Prevents
future improvements.
Overview of Alternatives