Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 1
Horizontal Directional Ground Investigation – Reducing Tunnelling Risks by Minimising
Geological Uncertainty
CHRISTOPHER BROOK Geotechnical Engineer, Mott MacDonald Singapore Pte Ltd, Singapore
Abstract
Geological uncertainty represents the key risk in tunnelling projects. Ground investigation for these schemes has
traditionally focussed in the sinking of vertical and inclined exploratory holes along the tunnel alignment allowing for
the interpretation of the geology between these points. The spacing of the exploratory holes is principally determined
by assessing the perceived geological variation between holes and the project specific tunnelling risks while bearing in
mind both programme and cost.
Recent advances in drilling technology have enabled an alternate method of ground investigation to be considered for
tunnels in rock. Horizontal Directional Coring (HDC) allows for a continuous core to be obtained along a particular
path at, or adjacent, to the axis of the future tunnel. A specially designed steerable core barrel using a system of
pressure controlled packers and adjustable drilling bits are used to either drill from ground level at an inclined angle
turning to horizontal or directly horizontally depending on topographic conditions. HDC is a highly accurate drilling
technology which can reduce the need to interpolate in ground conditions which are complex, highly varied or not
well understood. The remote nature of the drilling also negates potentially difficult logistical, safety and
environmental constraints which may obstruct or restrict a conventional ground investigation from being undertaken.
The use of HDC in tunnelling projects, whilst initially a seemingly expensive outlay, is considered likely to result in
more meaningful baselines being produced in GBR/GIBRs (where used), reduced contractor assumptions and
contingencies resulting in lower tunnelling costs, reduced contractors claims and minimised problems during
construction. In addition, the increased certainty in the ground may also reduce conservatism in the design.
This paper presents an overview of Horizontal Directional Coring, highlights the benefits and limitations of the
investigatory method, and provides several case studies from around the region with particular experiences from a
recent project in Singapore. Project consideration and challenges relating to HDC are also shared and the future of
ground investigation for tunnelling schemes discussed.
Key Words: Horizontal Directional Coring; Ground Investigation; Tunnelling, Measurement-Whilst-Drilling (MWD)
Introduction
The importance of proper and adequate ground
investigation in construction projects is no greater
than in underground construction and tunnelling
projects where the most significant risks are
associated with uncertainty in the ground.
The use of Geotechnical Baseline Reports (GBR), or
Geotechnical Interpretative Baseline Reports (GIBR),
is becoming more regular and owners of projects are
gradually moving away from the traditional allocation
of risk for unforeseen ground in preference of a
process where a contractor is able to submit a more
precise and competitive bid without contingency
factors. With these contractual statements regarding
the anticipated ground conditions there is therefore
an ever increasing need to be provide meaningful,
reasonable and realistic interpretations (ref 1).
Until recently, ground investigation for tunnelling
projects has been generally limited to vertical and
inclined boreholes above and adjacent to the future
tunnel alignment. In other areas, topography
precludes any substantial investigation being
undertaken along the alignment. Elsewhere,
horizontal coring (without directional control) has
been undertaken either from the side of a hill or from
a shaft ahead of tunnel construction although this has
been fairly limited in length as it has not been
possible to control the orientation and inclination of
the hole. Notwithstanding the limited length
horizontal core holes, generally the existing nature of
investigations provide only a pin-hole view of the
ground and significant interpretation of the geology is
required.
The amount of ground investigation that is required
ahead of construction stage of a tunnelling project
can vary hugely depending on the complexity of the
geology, tunnelling construction method, site setting
(e.g. urban, greenfield etc) and procurement route.
There are no set guidelines for the spacing of
exploratory holes on tunnel projects and each project
requires consideration on a case by case basis. More
often than not a phased iterative ground investigation
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 2
is the most cost effective approach in order to obtain
adequate ground information. The ground
investigation must aim at accurately defining the
ground conditions and highlight and define the keys
ground related risks to the project
Horizontal Directional Coring enables a continuous
core (effectively a pilot tunnel) to be obtained along a
future tunnel alignment. This, in combination with a
reduced scope vertical borehole investigation and
testing, allows for a more comprehensive
understanding of the ground to be obtained. The use
of this technique in underground construction
projects, whilst initially expensive, is thought to be
hugely beneficial to a project and likely to result in
more meaningful GBR, GIBR baseline being produced,
reduced contractor assumptions and contingencies
resulting in reduced tunnelling costs, claims and
minimised problems during construction. In addition,
the increased certainty in the ground conditions can
reduced conservatism within design.
This paper gives on overview of the key aspects of
Horizontal Directional Coring and its application in
tunnelling projects. The key benefits and limitations
are highlighted and broad guidance on the design and
supervision of the works are given. Several case
studies are presented and discussion is given on the
potential advances in ground investigation for
tunnelling projects in the future.
Geological Uncertainty in Singapore
The geology of Singapore is highly variable over a
small area. Triassic granitic rocks of the Bukit Timah
Granite occupy the central spine and basement of
Singapore while the sedimentary rocks of the Jurong
Formation dominate the west of the isle with the
younger Old Alluvium in the east (Figure 1).
Figure 1. Geological Map of Singapore (DSTA, 2009)
It is widely appreciated that there is still some
considerable uncertainty regarding the geological
history of Singapore, the structural geology and
stratigraphy in relation to the Malaysian Peninsula.
Notably, the stratigraphy and structure of the folded
and faulted sedimentary rocks of the Jurong
Formation is poorly understood as are the geometries
and location of igneous intrusions and faulting within
the Bukit Timah Granite.
Singapore is now densely populated, with significant
tunnels associated with transportation, power, water
and sewerage etc, which are located at various levels
in near sub-surface. Singapore continues to develop
and new trenchless infrastructure must be positioned
at deeper levels of strata. This leads to new
challenges in tunnelling and indeed challenges for the
ground investigation industry. As technology
improves, ground investigation techniques must
evolve to allow for a better understanding of the
ground prior to underground construction.
Figure 2. Conceptual Ground model and a selection of risk
features in tunnelling in sedimentary rocks
Figure 2. shows an indicative ground model for a
tunnel project in layered highly weathered and
faulted sedimentary rocks including karst features. A
conventional borehole investigation for a tunnel is
shown with boreholes placed at set intervals along
the alignment and targeted boreholes at known
geological features of concern. The benefit of using
HDC in this situation as a supplementary investigation
is clear as a full appreciation of the risks associated
with the ground would not have been gained
otherwise.
Horizontal Directional Coring
Overview of Technology
HDC is an adaption to the conventional borehole
coring process and utilises much of the same
equipment as that to core a deep non-directional
borehole. The key to the technique is a specially
designed steerable core barrel mounted to a
conventional drill string attached to a powerful
drilling rig capable of drilling.
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 3
HDC makes it feasible to control the direction of
coring in sub-vertical or horizontal boreholes along a
set alignment and investigate a linear tunnel scheme
within rock along or adjacent to the actual future
tunnel (See Figure 3 and 4).
Figure 3. Overview of HDC trajectory from ground level (HK AGS,
Ref 4)
For inclined holes, the works can be carried out from
a remote location negating potentially difficult
logistical and environmental constraints which may
obstruct or restrict a conventional vertical or even
inclined borehole from being undertaken.
Figure 4. Overview of HDC trajectory in topography
Horizontal Directional Coring should not be confused
with Horizontal Directional Drilling which is an
alternative technology that was born in the oil & gas
industry. Directional drilling is a relatively complex
technology and there are a number of ways to drill a
deviated hole (e.g. mudmotors with bent sub etc).
Horizontal Directional Drilling is the construction of a
drillhole without a core sample being taken - typically
the materials in which the hole has been constructed
through has been ground up during destructive
drilling often being recovered in the drilling mud as
chippings. HDD techniques are available for use in soil
and rock conditions and are frequently used in the
installation of pipelines where trenchless solutions
are required.
Directional Core Barrel
The first Horizontal Directional Core barrel was
developed in the 1980s by a Norwegian firm who
have continually improved the technology since and
lead the market in the development, manufacture
and use of HDC technology.
The directional core equipment consists of a long
wireline operated core barrel that replaces the
standard core barrel in steering sections. The core
barrel is operated under the same parameters as a
standard core barrel and requires no additional
equipment or significant adjustments to the drill rig
or drill string. The steerable core barrel was designed
to operate in hard, competent rock conditions.
The drilling trajectory is controlled by the toolface
angle while dog leg angle controls the curvature of
the corehole (Ref 4). A robust inflatable packer at the
rear of the core barrel maintains the toolface position
during steering. As with conventional wireline
systems the inner barrel of core can be removed from
the end of the borehole by lowering an overshot on
the end of a wireline into the hole. The overshot
attaches to the back of the core barrel inner tube and
the wireline is pulled back with the inner tube
disengaging itself from the barrel.
Figure 5. Schematic and photograph showing the working of the
proprietary HDC core barrel. (HK,AGS, Ref 4)
A corehole is typically undertaken using a
combination of conventional wireline drilling with
non-directional coring tools for straight line sections
with the specially design core barrel used in steerable
sections. When a change in direction is required as
determined through borehole survey (see below), the
directional barrel is preferentially modified. After the
steering correction is completed, normal straight line
drilling is resumed until another correction is
required.
The steerable core barrel yields a DV size core of
31.5mm in diameter (Photograph 1) and produces an
N sized (76mm diameter) hole. A conventional
wireline NQ core barrel obtains core of 47mm in
Planned tunnel trajectory
Exploration bore hole
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 4
diameter in comparison (Photograph 2). The max.
bending angle is 9 deg/30m i.e. a radius of 180m. This
limit is partially due to limitations in the drilling
method but also in view of the flexibility and strength
of the drill string and the potential for breakage or
shearing to occur.
Photograph 1. DV size (31.5mm) core obtained in a deviated
section of the HDC
Photograph 2. NQ size (47mm) core obtained in a straight line
sections of the HDC corehole
It is noted that the proprietary HDC system detailed
above is not the only option for directional coring
investigation as a similar core (albeit non-continuous)
can be obtained using a combination of non-coring
directional downhole tools and conventional wireline
drilling technology.
Surveying
Locating the corehole is key to accurately controlling
the directional coring works and this must be
carefully managed throughout the operation.
Downhole survey tools are typically placed at the rear
of the steerable core barrel during drilling allowing
real time inclination and orientation data to be gained
which is feedback to the HDC engineer controlling the
works at the surface.
The corehole is typically surveyed at set intervals, and
as and when required, using a magnetic downhole
instrument. The survey tool measures inclination,
azimuth and orientation of the hole and allows for the
accurate determination of the ‘as drilled’ corehole
alignment. Other non-magnetic surveying tools, also
of high accuracy, are available for use in situations
where there may be background magnetic
interference. These tools are calibrated by the
manufacturing in a test hole of known position and on
site using conventional survey methods.
Corehole Considerations and Challenges
Technical Considerations
The following is a broad overview of the technical
considerations which should be given by the HDC GI
Drilling Contractor and the Engineer in the design,
specification, planning and construction of a long
directional corehole. For each project it is important
the aim of the investigation is clearly defined and
actions taken to ensure that these aims are, so far as
possible, met with during the investigation.
Alignment
The alignment of the HDC will depend on the project
specific requirements, the environmental settings,
the geology and the alignment of the future tunnel
alignment to which the investigation will relate.
As outlined earlier in Figure 3 & 4, depending on
topographic conditions an HDC corehole may either
commence on sidelong ground horizontally or from
ground level at an inclined angle in which the
corehole will need to drill through the soil overburden
before turning to horizontal in rock to meet the HDC
alignment at depth.
The position of the HDC corehole relative to the
tunnel alignment must be decided. As above, this will
depend on a number of factors but will focus on
addressing the major geological features and
potential construction risks associated with a
particular tunnel project. For example, should a
corehole be positioned at the axis level of the future
tunnel then it might be most representative of the
weathering conditions at this level while a corehole at
the invert of a tunnel could investigate the possibility
of encountering hard abrasive ground or cavities
which could impact the tunnelling works. Elsewhere,
for a mined tunnel a corehole in the crown of the
tunnel might be the most beneficial area to
investigate.
Whilst a corehole within the future tunnel face may
give the most representative view of the ground
conditions that the tunnel will be constructed through
it is recommended that this is avoided and the
corehole is offset from the tunnel face. There is a
potential for the HDC drill string to snap in the
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 5
borehole which might lead to additional obstruction
risks being added to the tunnel project, further, if not
properly grouted upon completion, the corehole may
create a man-made pathway for water ingress to the
tunnel face.
Figure 6. Schematic potential HDC alignments relative to future
tunnel face
Drilling Tolerance Envelope
After designing the HDC alignment a drilling tolerance
envelop must be specified in which the Contractor
must stay within during the drilling. The tolerance
envelope is varied depending on a specific projects
aims and objectives although this must be balanced
with programme and cost. Typical tolerance
envelopes vary between 2m and 7m depending on
the size of the tunnel and the area of ground which is
of interest.
The tighter the drilling envelope the more frequent
the survey and steerable sections will be and the
slower the progress of the hole. The more relaxed the
tolerance envelope, the faster the drilling works will
be and the less frequent the surveys (Figure 7).
Figure 7. HDC design alignment and tolerance envelope and
schematic to demonstrate the typical working procedure for a
HDC corehole (modified after Ref 4)
The contractor is required to carefully manage the
corehole alignment within the tolerance envelope to
minimise tight radius turns which could stress the drill
string, increase the possibility of the breakage of the
drill string and increase the torque which may limit
the overall length of the hole.
The works need close supervising and real time data
should be available to all parties during the works.
Drilling Rig
The selection of an appropriate drilling rig is
important in a successful drilling operation. The
choice of rig depends on a number of factors
including:-
- Rig capacity
The drilling rig selected must be powerful enough to
reach the scheduled termination depth bearing in
mind the alignment and drilling tolerance
requirements. For very long coreholes the rig will
need a very high torque to deal with additional forces
put on the elongated drill string. For efficient drilling
the maximum speed of the drilling rig should be
appropriate to the most efficient RPMs to core in the
prevailing rock conditions. Other key rig parameters
include the capacity of the main hoist and wireline.
- Rig footprint
In some situations the environmental constraints will
dictate the use of a more compact rig. For
underground projects such as tunnelling, should
investigation be carried out during construction
compact underground rigs are available which can
have a footprint of as little of about 8m by 3m.
Elsewhere where site conditions allow more efficient
larger footprint rigs can be used.
- Pump capacity
A pump with sufficient volumetric capacity must be
used in order to provide flush down the drill string
and core barrel and remove the cuttings at a
sufficient velocity in the annulus between the hole
side walls and the drill string.
- Crew and training
An experienced drilling crew familiar with a particular
drilling rig will limit any learning curve where
programme is critical. A number of service and
training agreements are usually available from the
drill rig manufacturing. The efficiency of a drilling
team usually led by a drilling manager will have a
direct impact on progress, quality and health and
safety.
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 6
- Support
It is paramount that the rig is properly maintained
and crucial spares are on hand during the drilling
works. This can reduce downtime in case of
breakages.
Drilling Tools
Drilling tools must be carefully selected. There are a
range of products for different ground conditions. A
carefully selected core bit can increase productivity,
the quality of core obtained and reduce wear on the
downhole tools For varied ground conditions many
difference tools are carried to optimise the works.
Drill String
A key risk in drilling operations is the possibility of
breaking or having drilling rods disconnect from each
other. Threads must be carefully looked after and
once damaged drill rods should not be used again.
Drilling Flush
The flush fluid is primarily for the cooling of the drill
bit but also to remove the cuttings from the base of
the hole back to the surface in the annular area
available between the wall of the borehole and the
drill string. The drilling mud used in operations will
vary from section to section depending on the
materials cored and other factors. It is paramount
that an adequate circulating system is in place to mix,
filter and recirculate drilling mud. In tricky drilling
situations it is important for the contractor to consult
with a suitable qualified mud engineer to optimise
the works.
Measurement-While-Drilling (MWD)
For a more complete geological record, a
Measurement-Whilst-Drilling (WMD) system should
be used. Through a drilling console (Photograph 3) or
data logger this enables real time drilling parameter
data to be viewed on site and the conditions in the
borehole more accurately determined. This is
particularly important when drilling in weak, faulted
or friable ground where it may be difficult to
reasonable obtain 100% core recovery. Multiple
drilling parameters are measured; thrust, torque,
flush pressure, rotation speed and drilling rate. These
results can be graphically presented against the
borehole records for further interrogation (Figure 8)
should it be required and allow for the best
interpretation of the ground to be made. The raw
data can be transferred to a PC via a USB which
downloads from the drilling console or data logger.
Photograph 3. Drilling console displaying RPM, fluid pressure,
rate of penetration and other drilling parameters
The data recorded, particularly the drilling rate, is a
direct reflection of the nature of the ground being
drilled. It is influenced by several factors including
strength, type and structure of the material being
drilled, the flushing media and pressure and other
drilling parameters. The widths of penetration rates
peaks and trough are particularly diagnostic and can
assist with the identification of, for example, voids
(e.g Karst landforms), fracture zones etc.
Figure 8. Graphical display of drilling parameters to assist in
interpretation of coreloss and other drilling events
In coring investigation drillers are required to balance
productivity with quality and wear on the drill bit they
are using and may adjust the drilling parameters
accordingly. For instance, in soft rock formations
where a harder matrix tool with large diamonds
should be used low RPMs may be most appropriate.
The recording of drilling parameters via MWD data
loggers is not only for rotary coring investigations,
they can also be used in boreholes using destructive
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 7
methods, using a drag or tri-cone bit, or percussion. In
these applications a continuous recording can be
undertaken with parameters. When parameters are
kept constant, only the penetration rate will fluctuate
which will provide an indication of the ground that is
being drilled through.
Attempts have been made to correlate the specific
energy of drilling (Ref 8 & 9), a product of the main
drilling parameters and defined as the energy needed
to drill a determinant volume of rock, with rock
properties. This is outside the scope of this paper
however the author will be following further research
and development in this area as MWD systems
become more frequently used.
Insitu Testing
Insitu testing may be undertaken within a HDC
corehole like any other borehole with special
considerations required for effective insertion of the
tools.
Typical insitu in HDC coreholes for tunnels comprises
of permeability testing in the form of:-
- Lugeon packer tests, and
- Inflow tests.
It is also possible to gain core orientation information
either through using a core locking system, core
marking system or downhole impression packers.
Grouting
Extensive grouting of the borehole both during the
construction of the hole and upon completion are
likely in long directional coreholes where lost
circulation or borehole instability is a problem (see
more below). The grout mix and method will vary
depending on the situation, and the depth of
borehole.
Photograph 4. Set type grouting packer – a sacrificial packer
equipped with a non-return valve for pressure grouting
Impact of small diameter core
In steerable sections, the diameter of the core is
31.5mm, which is smaller than the recommended
minimum size for standard rock laboratory tests. Non-
standard laboratory tests can be undertaken but
consideration with respect to scale affects and
suitable correlations/ corrections are required.
The smaller diameter core and difference in diameter
of core between steerable sections and straight-line
sections also requires core logging to depart from the
norm. Deere (1967) stated that a core diameter of NX
size (54.7mm) is the minimum which Rock Quality
Designation (RQD) should be recorded. This was to
discourage the use of excessively small core
diameters which could yield artificially low core
recovery through drilling induced core breakages.
Since Deere’s original definition, ASTM indicate that a
minimum core size of NW is acceptable, presumably
to account for the improvements in drilling
technology at smaller diameters since 1967 and
acknowledgement that in good ground conditions
with good drilling technique high quality core
recovery can still be obtained. In general the larger
the diameter of core the higher the core recovery and
less disturbance is achieved in the recovered core.
Core obtained from horizontal directional coring
ground investigation is below the minimum core size
recommended for recording RQD. It is therefore
imperative that logging must be more carefully
carried out particularly in weak friable rock conditions
by experienced geologists. Drilling induced fractures
may be greater in DV size core and the core recovery
could be poorer than if a larger diameter core barrel
was used in the same ground conditions.
Challenges
During the course of a horizontal directional corehole
geological conditions may challenge a drilling
contractor from achieving his objectives of reaching
the termination criteria and recovering representative
samples of the ground. The following section outlines
these key challenges:
Lost Circulation
Lost circulation, more frequently known in the
geotechnical drilling industry as waterloss, is the loss
of drilling fluid to discontinuities or pore space in the
rock being cored resulting in reduced or complete loss
of drilling fluids and a lack of flush and cuttings
returning through the circulation system.
Zones through which lost circulation can occur are
coined thief zones and may be highly fractured rock
with persistent wide aperture joints such as shear or
fault zones or highly porous mediums such a clean
coarse grained sandstones. In very long holes
cumulative lost circulation may occur and it may be
very difficult to identify the key thief zones which
require treatment.
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 8
Lost circulation is a serious problem in the drilling of a
deep or long boreholes and the detection and
treatment of this problem is difficult and requires
considerable experience to effectively and correctly
address. Without circulation, cuttings from the
borehole cannot be expelled from the bottom of the
hole or the annular space along the borehole. This
can lead to core sticking events at the core barrel or
increased torque on the drill string which if significant
could stick the drill string and even contribute to
breakages. Although coring can be still be undertaken
if sufficient water supply is available the lack of flush
return may also lead to an increased deterioration in
the down hole assembled. All the above can also
reduce the quality of core gain and the rate of
progression of the corehole - lost circulation is a
costly problem and must be mitigated.
Minor losses can sometimes be mitigated by
modifying the drilling mud composition either by
increasing the density of the bentonite or drilling
polymer being used at the time.
Major losses are more difficult to deal with and
attention must be given to the likely cause of the
losses, the width of thief zone, the aperture of
fractures or porosity of the material to correctly
implement the right mitigation which could comprise
of :-
- The use of Lost Circulation Material (LCM), or
- Grouting.
The decision with respect to the way forward must be
a combined decision between the senior geologist on
site and the drilling manager who together have the
necessary skills to accurately define the problem and
choose the most appropriate solution.
Lost circulation materials to mitigate lost flush
generally come in two forms; fibrous and granular
materials. These are added to the drilling flush and
pumped into the hole to plug the gaps in the fractures
and/or pores. Many products are available on the
market which are environmentally friendly and
suitable for various applications. Some granular
hydrophilic LCMs are available which swell in size
when in contact with water.
In significant thief zones where it is a necessity to seal
the hole completely and LCMs are ineffective,
grouting of a particular section of corehole may be
required.
Borehole Collapse / Borehole Closure
A serious concern to the completion of horizontal
directional core holes is the progression of the
corehole through soil, or weak and highly fractured
ground which may squeeze onto the drill string or
collapse into the hole leading to re-drilling or, at
worst, having the core barrel and drill rods stuck in
the borehole.
In areas of weak ground pressure grouting using a
downhole packer introduced earlier may assist with
stabilising the hole and enable the drilling to continue
safely. As above, casing is not an option and should
soil conditions be encountered significant problems
may occur.
Loss of Steering
HDC technology is only possible in competent rock
conditions. In soil it is not possible to steer the HDC
core barrel with any accuracy.
HDC Case Studies
An Undersea Directional Corehole in Singapore
Recently a 1193m long horizontal directional corehole
was completed within the Triassic Jurong Formation
in southwest Singapore in an area of restricted access
which precluded other means of investigation. This
enabled a continuous core to obtained along and
adjacent to a future tunnel project where limited
information was available from conventional ground
investigation techniques in an area where undersea
docking of TBM’s may be undertaken in the future.
The investigation targeted a portion of the tunnel
alignment where is was suspected that the ground
could be faulted and there was high potential for
deep tropical weathering profiles to exist.
The corehole was designed to follow on the outside
and at the axis level of the tunnel. This alignment was
chosen to gain the most representative information
without adding to future construction risks and to
ease the drilling works themselves. A 5m tolerance
envelope was specified – a product of the tunnel
diameter and perceived geological variation balanced
with achieving a very tight programme for the works.
The corehole was launched at an angle of 27 degrees
and was steered to horizontal to meet the design
alignment with an elevation of ~70m below Chart
Datum. The ground conditions typically comprised of
slightly to highly weathered rocks of the Jurong
Formation composed of sandstones, conglomerates,
mudstones and siltstones.
The works were undertaken on a 24hr basis in shift
patterns and were completed within a 3.5 month
period. The average advance rate was ~5m per shift
inclusive of alignment corrections, grouting events
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 9
and in the treatment of lost circulation. The maximum
advance for a single shift was 22m. Core runs were a
maximum of 3m in length.
Photograph 3. HDC coring works in progress during a night shift
The drilling works were undertaken by an
experienced geotechnical GI contractor with
appropriate experience in the drilling of long length
directional coreholes. An Atlas Kopo U8 drilling rig
with an in-built Measurement-Whilst-Drilling system
and a wireline core-recovery system was used. The
works were carried out by a team of experienced
drillers. Specialist HDC engineers were on hand
throughout the investigation to control the hole
orientation and steerable sections. A combination of
DV size and NQ2 size core was obtained. This
approach balanced productivity rates, quality and the
wear on the tools. A total of 371m was cored with the
steerable barrel while 742m with a conventional
coring barrel, the balance was open hole drilled in the
soil overburden.
Surveying was undertaken at a maximum of every
20m with additional surveys undertaken as and when
required to ensure the hole stayed within the
tolerance envelope.
Zones of lost circulation were identified during the
drilling works. Both grouting and use of lost
circulation products were utilised to progress the hole
and keep the drillhole in a suitable condition for
obtaining high quality representative samples. The
works were closely monitored by the Engineer.
Faults/ shear zones were encountered during the
investigation and drilling parameters obtained using
the Monitoring –Whilst –Drilling system were
paramount in the best interpretation of faulted zones
where core loss events occurred.
As with many tunnel projects, a project risk register
was developed for the HDC borehole (effectively a
micro tunnel in itself) prior to the investigation which
was updated and kept live throughout the project.
During construction this was owned by the Contractor
and was regularly reviewed by the team. This enabled
a clear understanding of risks and control measures
to be developed between the various parties on the
project and to ensure that best practice was being
followed.
In addition to the GI Contractors conventional
engineering geological descriptions in accordance
BS5930:1999, the consultant also undertook detailed
sedimentological logging of the core samples to gain a
better understanding of the structural geology along
the future tunnel alignment. Geological features
within and at the top and bottom of bedding were
noted which enable for a comprehensive
understanding of the stratigraphy and structure to be
developed which otherwise would not have been
possible from the standard engineering geological
logs.
The investigation allowed for a detailed
understanding of the ground conditions along the
tunnel alignment to be developed, shear zones to be
identified and the overall structure of the prevailing
geology to be ascertained with accuracy.
The completed borehole trajectory is shown in Figure
9.
Figure 9. As drilled profile of the HDC corehole
Other selected case studies
Table 1 provides a summary of selected HDC projects
undertaken within the region with details available in
the public domain.
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 10
Table 1. Selected summary of details of completed HDC ground
investigation projects within the region.
Key Advantages and Limitations
Advantages
The advantages of using HDC for ground investigation
of tunnel route are clear, providing a continuous
record of the ground conditions along the tunnel
alignment prior to construction. Gaining this
information will reduce the geological uncertainty
and risks associated with unforeseen ground
conditions by negating the need to interpolate
between stratum boundaries. HDC can be undertaken
remotely which is particularly advantageous in areas
where there is limited or no surface access to
conventional borehole positions such as beneath
environmental sensitive areas, busy waterways and
roads or even beneath buildings.
As consequence to the increased certainty in the
geology conditions it is considered that this could
further result in:-
- More meaningful and accurate GBR & GIBR
baselines being prepared;
- Reduced contractor assumptions and
contingency resulting in lower tunnelling costs;
- Reduced contractor claims;
- Minimised problems during construction;
- Greater confidence in risk, programme and
costs, and
- Reduced conservatism in design.
Limitations
The drilling and steering of small diameter rock coring
bit has certain inherent limitations which must not be
overlooked when giving consideration to the possible
use of the method. These limitations relate to the
geological conditions in which the coring may feasibly
take place and some initially reasonable
understanding of the likely ground conditions is
required.
A key limitation in the use of HDC is the expense and
difficulties in being able to demonstrate tangible cost
benefits from the use of HDC. A key challenge for HDC
is the changing of mindsets from what was done in
the past and worked to align with the improved
technology and the possible benefits.
As an emerging technique unfamiliar to many it is a
necessity for the works be specified and supervised
by experienced consultant and undertaken by a
suitably qualified GI Contractor with past experience
in similar works. Should an inexperienced contractor
undertake the works and with poor or no supervision
there is a considerable risk that the challenges and
considerations described in this paper might not fully
be appreciated. This could lead to early termination
of the corehole hole or worse, poor un-
representative, core samples being recovered which
could mislead consultants and contractors into
thinking the ground is worse than it actually is.
Conclusions
The use of Horizontal Directional Coring in association
with Measurement-While-Drilling technology,
undertaken by an experienced drilling contractor with
careful supervision and recording can enable for a
comprehensive picture of the ground conditions
along a particular tunnel route to be gained even in
the most varied rock conditions. Geological risks
which would have been unlikely to have been
uncovered in conventional investigations could be
identified.
It is in an owner’s best interest to invest in an
effective and adequate ground investigation – in
certain situations the technical benefit of horizontal
directional coring in complex, varied or constrained
environments in rock are clear and it is the author’s
opinion that these might outweigh the added cost at
the outset of the project.
Future Visions / Improvements
Tunnelling technology and practices continue to
improve and develop in order to mitigate and reduce
risks, make cost savings, and speed up construction.
The ground investigation industry must also respond
by moving with technology and in so doing potentially
having a major positive impact on the tunnelling
industry.
As underground space in urban settings becomes
more constrained the need to go deeper is inevitable,
which will likely mean that underground works will be
Project Name Description Length(s) Ground
Conditions
Comments
Eagles Nest Road
Tunnel comprises of
two, three-lane
tunnels – Hong Kong
2No directional
coreholes from
each side of the
mountain
516m &
1151m
Granite Coreholes
positioned at
axis level of
tunnels in-
between each
running tunnel
Jurong Island Rock
Cavern – Singapore
6No directional
coreholes
Total length
of 2400m
Longest
singular HDC
~600m
Siltstones,
Mudstones
and
Sandstones
HATS2A deep sewer
project – Hong Kong
6No directional
coreholes
Total of
5000m
Longest
singular HDC
~1250m
Understood
to be of
Granite,
Tuffaceous
To identify
location and
width of fault
zones
Tunnelling and Underground Construction Society (Singapore) Hulme Prize Competition 2013
Page | 11
located in rock conditions. It is the author’s opinion
that in Singapore and elsewhere around the world, as
has occurred in Hong Kong, deeper tunnel projects
will utilise HDC as a way to better understand and
define ground related risks. This in turn will force
improvements in the existing technology.
One area of development which requires further
consideration by the industry is the investigation of
ground along tunnel alignments in mixed face or soil
conditions. In the US, horizontal directional drilling
and soil samplers have been successfully used in
tandem in geo-environmental projects (Ref 5). For
geotechnical applications there will be always be
problems in gaining representative and undisturbed
samples in all but the softest of ground conditions.
The use of destructive (non-sampling) horizontal
directional investigatory solutions may also have their
applications both in soil and rock through increased
use of Measurement-Whilst-Drilling technology and
the possibility of correlations to define rock and soil
strengths and other properties. These technologies
could also be used together with Horizontal
Directional Coring in tunnel alignments where there is
both rock and soil.
Improvement to Ground Investigation for Tunnels in
Singapore
In Singapore, it is hoped that the ground investigation
industry for tunnelling projects may gain significantly
from the application of HDC to supplement and
enhance geotechnical data for complex tunnelling
projects. By proactive consideration and management
of the challenges associated with deep/long
coreholes, it is considered that risks from tunnelling
works can be better evaluated.
References
1. J, B, Longbottom. Geotechnical Baseline
Reports – Their Use & Abuse in Hong Kong.
ADR Digest Issue 13 Spring 2011.
2. R, Lindhjem & C, Tai. Directional Core Drilling in
Tunnel construction. World Tunnel Congress
2008 – Underground Facilities for Better
Environment and Safety – India.
3. M, P, Chan. The Use of Horizontal Directional
Coring Technique for Ground Investigation of
Tunnelling Projects in Hong Kong. Masters
Dissertation. June 2007.
4. Association of Geotechnical &
Geoenvironmental Specialists (Hong Kong).
Ground Investigation Guidelines – 04.9 –
Horizontal Directional Coring.
5. E, N Allouche, S, T, Ariaratnam, K, W Biggar & J,
Mah. Horizontal Sampling: A new direction in
characterisation. Trenchless Technology. Res.
Vol.12, Nos. 1-2, pp. 17-25, 1998
6. B, B, Bramble & M, T, Callahan, Construction
Delay Claims, Third Edition, pages 2-46
7. Underground Technology Research Council
(UTRC), 2007, Geotechnical Baseline Reports
for Construction, Technical Committee on
Geotechnical Reports of the UTRC, American
Society of Civil Engineers.
8. R, Teale, 1964, The concept of Specific Energy
in Rock Drilling. Rock Mechanics Mining
Science, Vol 2, pp 57-73.
9. B, Celada. The use of the Specifc Drilling Energy
for Rock Mass Characterisation and TBM
Driving During Tunnel Construction.