HOSPITAL PENGAJAR UNIVERSITI SULTAN ZAINAL ABIDIN (HPUniSZA) LAPORANKEMAJUAN PROJEK Ogos 2020 Disediakan Oleh: Pusat Pembangunan Hospital Universiti
Transcript

HOSPITAL PENGAJAR UNIVERSITI

SULTAN ZAINAL ABIDIN

(HPUniSZA)

LAPORAN KEMAJUAN PROJEK

Ogos 2020

Disediakan Oleh:

Pusat Pembangunan Hospital Universiti

KEMAJUAN KESELURUHAN

2

Ogos 2020

Physical Schedule

Actual

Ahead/Delay

71.62% 71.60%

-0.02% /-2 Days

Financial Schedule

Actual

Ahead/Delay

55.04% 50.31%

-4.73%

KEMAJUAN FIZIKAL

3

Physical S-Curve (Cumulative)

4

KEMAJUAN KEWANGAN

5

Financial S-Curve (Cumulative)

6

PROGRESS PHOTOGRAPH FOUR CORNERS

PHOTOS

7

View 4

View 3

View 1

View 2

21-02-2019

Four Corners Photos

Four corners photo / View 1

17-01-2019

21-02-2019

Four corners photo / View 2

21-02-2019

17-01-2019

Four corners photo / View 3

21-02-2019

17-01-2019

Four corners photo / View 4

21-02-2019

17-01-2019

Progress Photograph /Ogos 2020 DOOR LEAF INSTALLTION

AT LEVEL 2

Progress Photograph /Ogos 2020

SCREEDING WORK AT LEVEL 4

Progress Photograph /Ogos 2020

INTERNAL FINAL PAINTING

INTERNAL FINAL PAINTING

Progress Photograph / Ogos 2020 CEILING WORK AT LEVEL 3&2

Progress Photograph / Ogos 2020

TILING WORK AT LEVEL 3

Progress Photograph /Ogos 2020

DRY WALL WORK

AT LEVEL 2&3

Progress Photograph / Ogos 2020 SELF LEVELLING VINYL AT LEVEL 1

Progress Photograph / Ogos 2020 PU EPOXY AT LEVEL 1

Progress Photograph / Ogos 2020 VENTILATION BLOCK

M&E WORK PHOTO;

AT LEVEL 7

PRESSURIZATION FAN INSTALLATION MOTORISED FIRE DAMPER AT

STAIRCASE

PIPING WORKS AT FRP TANK ROOFTOP PRESSURIZATION FAN C/W DUCT

INSTALLATION

M&E WORK PHOTO;

AT LEVEL 6

SUBMAIN TRUNKING & CHILLED WATER

PIPING WORKS TRUNKING WORKS IN ELV RISER ROOM

HR DRUM & BREAKGLASS/BELL

INSTALLATION HIGH LEVEL TRUNKING & PIPING WORKS

M&E WORK PHOTO;

AT LEVEL 5

DUCTWORKS SUBMAIN TRUNKING & CHILLED WATER

PIPING WORKS

HOSEREEL DRUM, BREAKGLASS & BELL

INSTALLATION FCU UNIT C/W DUCT INSTALLATION

M&E WORK PHOTO;

AT LEVEL 4

FCU UNIT C/W DUCT & CHILLED WATER PIPE

CONNECTION DUCTWORKS & FINAL SUB CABLING

DUCT INSTALLATION FOR AHU OT FINAL SUB CABLING

M&E WORK PHOTO;

AT LEVEL 3

DUCT INSULATION & FINAL SUB CABLING DUCT INSULATION & PENDANT BRACKET

INSTALLATION

CHILLED WATER PIPING CONNECTION TO

AHU UNIT DUCTWORKS FOR HEPA FILTER AT OT ROOM

M&E WORK PHOTO;

AT LEVEL 2

27

DUCT & CHILLED WATER PIPING

CONNECTION TO AHU UNIT

DUCT & CHILLED WATER PIPING

CONNECTION TO AHU UNIT

LIGHT FITTINGS ,SPRINKLER

HEAD,SPEAKER, SUPPLY & RETURN GRILLE

LIGHT FITTINGS ,SPRINKLER HEAD & AC

DIFFUSER

M&E WORK PHOTO;

AT LEVEL 1

28

• AVSU PANEL FOR MEDICAL GASES EM LOCK FOR CARD ACCESS SYSTEM

DUCTWORKS FOR KITCHEN HOOD

DB INSTALLATION

M&E WORK PHOTO;

AT ENGINEERING BLOCK

29

MAIN CABLING WORKS AT MSB ELECTRICAL MAIN CABLING WORKS AT MSB ELECTRICAL

GANTRY MAIN CABLING WORKS FROM ENGINEERING

BLOCK TO GANTRY

THANK YOU

• Facebook:Pusat Pembangunan Hospital Universiti

• 09-6688008

• https://www.unisza.edu.my/pphu/

Disediakan Oleh:

Fara Fauzia Udin