+ All Categories
Home > Documents > How is Utah’s Operations Management System (OMS) really working? 2010 WASHTO COMMITTEE ON...

How is Utah’s Operations Management System (OMS) really working? 2010 WASHTO COMMITTEE ON...

Date post: 31-Dec-2015
Category:
Upload: debra-butler
View: 213 times
Download: 0 times
Share this document with a friend
Popular Tags:
14
How is Utah’s Operations Management System (OMS) really working? 2010 WASHTO COMMITTEE ON MAINTENANCE
Transcript

How is Utah’s Operations Management

System (OMS) really working?

20

10

WA

SH

TO

CO

MM

ITT

EE

ON

M

AIN

TE

NA

NC

E

UDOT Organization• 1,750 employees• 5,887 miles of road• 16,520 lane miles• 24,700 surface

areas

• Central Office• 4 Regions, each split

into 2 Districts• $1.5 billion in

construction this year

Maintenance Organization• 580 employees• 85 maintenance stations statewide• Central Maintenance

– Maintenance Engineer and 14 core staff• Trans-Tech (construction/maintenance)• Approx $97 million in maintenance budget (fy10)

– $21 million in snow removal– $17 million in hard surface

• Zero Based Budget process to develop budgets

Maintenance System Upgrade• Replace existing MMS system

– Originally launched in 1993– Mainframe/Desktop application

Maintenance System UpgradeKey Business system

– 21 interfaces

OMS RFP Development• Began preparing RFP in 2004• Advertised in 2005• 4 companies responded, two start

from scratch, and two with COTS software.

• Refined questions and sent out a second RFP.

• Again same four vendors.• Contract awarded to AgileAssets in

2006

Implementation Project• Kicked off November 2006• Exercised contract options

– User Familiarization Area– On-site project manager– Train-the-Trainer approach to training

• Visited Wyoming July 2007 to get their input on what worked and what didn’t.

• “Go Live” November 2008

Rolling our System Training

• “Train-the-Trainer” approach– Adult teaching skills

• Three weeks of system training– Week 1: System Basics

• Practice after training

– Week 2: Advanced features• Practice after training

– Week 3: Review

• 28 trainers in two groups

Go-Live

• “Flip the Switch”– November 15, 2008– End of Pay Period

One Year Later2

01

0 W

AS

HT

O

CO

MM

ITT

EE

ON

M

AIN

TE

NA

NC

E• Feature Inventory

– Still an Achilles Heel for complete system integration.

• MMQA– Realizing our need to tie condition

assessment to feature inventory– Re-evaluate what we measure

• Understanding the implications of Owning vs. Renting the code

• Pavement Management Module implemented

How are we going forward? (1 of 2)

• Most employees accept the system, but don’t use it to its full potential

• Better integration with other business data. (State Financials, GIS)

• Field Data Collection Pilot project– LiDar vs. handheld

• GPS equipped mobile workforce– True cost reporting and performance

measurement

• Reporting to Legislature/Taxpayer

20

10

WA

SH

TO

CO

MM

ITT

EE

ON

M

AIN

TE

NA

NC

E

• Hired a retired maintenance analyst– Focus on getting system operating to its full

potential.– Help with training.– Lucky to have been able to hire the best of the

best.

• Develop our Zero Based Budget Process– Improve MMQA reporting– Complete Feature Inventory– Develop local Activity Standards– Work with Construction to update changes.

• Better GIS/GPS tools– Some in OMS, some in-house developed.

How are we going forward? (2 of 2)

• Feature Inventory– Finding the right methodology, and getting

resources for it– Link to MMQA, and to work order creation– Using feature inventory in budgeting process

• MMQA– Making it useful for station supervisors– Making snow log reporting easy and useful

• System enhancements– Weaning ourselves from AgileAssets– Creating our own reports

• Cost of support and maintenance

Outstanding Issues

Questions?Lloyd Neeley, P.E.Deputy Maintenance Engineer

801-965-4789

[email protected]


Recommended