HR2101 - Reducing Heat Loss Through Root Cause AnalysisProject Management Plan
PRESENTED TO GSEGNOVEMBER 11, 2012
CHRIS KAPLANINSTRUCTIONAL
DESIGNER
ContentsHR2101 - Project Management Plan
Goals of HR2101State of developmentResources needed for future developmentProposed development scheduleChallenges and considerationsSummary
HR2102 Goals HR2101 - Project Management Plan
Heat rate has been identified as a serious source of loss of efficiency and income for GSEG.
This online course project will add to GSEGs library of training resources a means to train control room operators to use root cause analysis to identify symptoms of plant inefficiency related to heat rate.
Status HR2101 - Project Management Plan
Work to date
Needs analysis
Design document
Prototype (in process
Next steps
Green light from management
Develop remaining modules
Migrate to production environment
Implementation, testing, and evaluation of complete course
Resources HR2101 - Project Management Plan
RESOURCE TASKS/PURPOSEHUMAN RESOURCES
Plant managersCoordinate scheduling of courses based on best known information regarding plant outages and planned maintenance.
Subject matter experts (SMEs)
Contractor specialist - Provides specialized knowledge about thermodynamics and heat rate for power generation
In-house engineering - Provides site specific information to contractor specialist about normal operating design thresholds and system dependencies
Maintenance Supervisors - Provides site specific information about day to day realities of plant operations to contractor specialist
Multimedia specialists Create media assets to be use in course implementation: Graphics, technical drawings, video
GSEG LMS administrator/team Deploy course assets to LMS
Instructional designerCoordinate with SMEs, multimedia team and LMS admin to facilitate communication, complete content development and deploy content to delivery platform.
Experienced control room operators Pilot testing an accelerated course. Limit to two locations.
MATERIAL RESOURCESLMS Course delivery platform
MAINTENANCE FACILITY Needed for production of visual (photo and video) materials to support other content.
Schedule HR2101 - Project Management Plan
TASK RESOURCE(S) START ENDReview Prototype
Plant Management/SMEs/Instructional
designerWeek 0 Week 0
Approve production Plant Management Week 0 Week 0
Develop Content ISD/Multimedia Team/SMEs Week 1 Week 12
Coordinate Implementation (technical) Multimedia Team/LMS admin Week 3, 11 Week 3, 11
Review content on development LMSInstructional Designer/SMEs Week 4 Week 12
Migrate Content to production server Multimedia Team/LMS admin Week 12 Week 12
Review content implementation (content)Instructional Designer/LMS
adminWeek 12 Week 12
Accelerated pilotExperienced CROs/(Two
locations)Week 13 Week 20
Review feedback from pilot Instructional Designer/SMEs Week 21 Week 21
Revisions based on feedbackInstructional
Designer/Multimedia team/LMS admin
Week 22 week 23
ReleaseInstructional Designer/LMS
adminWeek 24 Week 24
Challenges - Logistical HR2101 - Project Management Plan
Course design includes cross communication between teams at multiple plants creating a scheduling challenge
Course design includes using maintenance managers as periodic resources
Course design includes on-shift participation
Challenges - Developmental HR2101 - Project Management Plan
Using site specific content increase the complexity of course content development
Obtaining footage/images of dismantled systems may result in delays while waiting for scheduled outages.
Recommendations - Logistical HR2101 - Project Management Plan
Consider flexibility in the number of plants scheduled for training simultaneously.
Would allow for more combinations and possibilities of start dates.
Consider using single plant for a class
Would reduce benefit of learning from diversity of systems but should still result in competence
“Course design includes cross communication between teams at multiple plants creating a scheduling challenge”
Recommendations - Logistical HR2101 - Project Management Plan
Consider developing additional resources from maintenance managers vs. real time interviews.
Would allow for more consistency from class to class.
Ensure that the alternate CRO assignments are rotated consistently.
“Course design includes using maintenance managers as periodic resources”
“Course design includes on-shift participation”
Recommendations - Logistical HR2101 - Project Management Plan
Consider developing generic content.
The vast number of combinations of systems could be a non-starter for development of the course.
Generic content should be sufficient to teach the concepts of root cause analysis and heat rate
Site specific resources can be created as each class goes through the course and can be refined over time.
Consider creating animations and technical graphics a interim solutions which can then be re-used as support material as video and photographs become available.
“Using site specific content increase the complexity of course content development”
“Obtaining footage/images of dismantled systems may result in delays while waiting for scheduled outages.”
Summary HR2101 - Project Management Plan
Heat rate is a problem for GSEG - HE2101 is a part of the solution
Management is needed to review the prototype lesson and learning design with the instruction designer to green-light production
Successful implementation of the course design will require the participation of the instructional designer, plant managers, subject matter experts, media specialists, and experienced control room operators.
The number of plants affected make site specific training cost prohibitive at the outset, but generic content should result in significant ROI to justify initial expense