H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1 January 18, 2005 1
Beam Commissioning of LHC instrumentation
Chamonix XIV, January 2005
H.Schmickler on behalf of the AB-BDI group
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 22
For information: Outline of Talk of B.Holzer (Wednesday)
Beam Position Monitor (BPM) System Polarity errors Testing of electronics BPM Database issues Timing issues
Beam Loss Monitor (BLM) System Hardware set-up & testing Calibration Threshold determination
Emittance and Current Measurement Systems Sector Test Summary
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 33
Outline of this Talk
Prerequisites for a working instrumentation Action areas:
- design office support- coordinated effort for application programs
Two major lessons learnt from LEP:- Independence of beam synchronous timing- Deadlocks during hardware/software developments
Bringing the instruments (machine) to their nominal performance- orbit system- beam loss monitor system- time resolved tune and chromaticty measurements- beam current measurements, lifetime calculations- profile measurements- others
conclusions
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 44
Prerequisites (same slide as last year)
Working and exploitable instruments need:
- sensors and electronics : AB-BDIdetails see AB-LHC review; recurrent problem: Design support
- controls infracstructure : AB-CO, in progress
- RT software and expert tools: AB-BDI-SW will be based on FESAII framework
- Operational application programsAB-CO + AB-OP
work needs to be organized soon (that is the text of last year)
work needs to be organized now (see following slides)
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 55
Design effort still needed
There are still major BDI components, for which the mechanical design is not done / finished.
The situation was similar at Chamonix 2004.
After the workshop a significant improvement in design office support was notable.
With the QRL problem higher priorities defined, present support insufficient
Without the requested support - some special BPMs (= special BPMs of the normal orbit system and special BPMs for tune measurements)- the synchrotron light telescope- the wire scanners
will not be ready
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 66
Prerequisites: Software effort
Example: Time resolved chromaticity measurementsat day 0: We should not count on PLL tune tracking and momentum modulation use head-tail method (despite emittance growth)
SPS application program:
- needs visual inspection of result- gives chromaticty as number onthe screen
- needs:automation, integration into a measurement system…
Solution:
Define for the key system “System commissioners”and start definition, design and coding of the application programs
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 77
Lessons learnt from LEP (1/2)
Provide reduced functionality of instruments without beam synchronous timing (BST)
- BPM-system: works without BST, but no bunch/turn identification, reduced noise immunity
- BLM system: most of the system acquires data in an asynchronous 1ms rhythm
- BCT DC: no timing- BCT BB: needs beam synchronous timing,
was a problem for the downstream BCT in TI8, people are working on a input filter to stretch the signal for single
bunch operation- tune measurement systems:
tune kicker needs rough timing, tune meter will have one front-end not depending on timing basic functionality without BST
- all TV based monitors: will work without BST, obviously no bunch gating(sync-light telescope, ionisation profile monitor, screens)
- wire scanners and luminosity monitors: will have an acquisition mode without BST
- AGM and LDM: need the BST in order to work.
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 88
Lessons learnt from LEP (2/2)
Hardware can not be tested because software not ready,Software can not be developed because hardware not available…
- The FESA framework provides the possibility to have device emulation of missing hardware, such that the software can be developed and tested at a time when the hardware is still partially missing:
This feature will help having software/hardware ready in time
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 99
Commissioning with Beam: BPM system
Day 0 performance without adjustments
No BST adjusted,
1 pilot bunch; can measure orbit, turn by turn data possible with BST turn clock
Immediate!
Systematic check for inverted cables/planes/rings
Per ring and per plane non closed bumps with two correctors at 90^0 phase advance.
If well automated, one shift for detection of problems.Requirement for scripting tool.
If 5% error rate, one week to fix problems.
Adjustment of BST One circulating bunch;
Scan of timing setting for all front ends.
Two shifts interleaved by a few days; check for stability of settings
Systematic confirmation of system performance
Resolution as function of beam intensity, linearity over aperture, dependence on long. beam structure, crosstalk between beams
Long process. Several months.
Demands LDM to be operational.
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1010
BPM system:
Application software:
This should be in good shape:
System commissioner at work since years.
Application programs very similar to those of LEP and SPS.
Attention: The turn by turn analysis program as provided for the SPS needs more work.
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1111
Commissioning with Beam: BLM system
Day 0 performance:
All “slow (= 1ms)” monitors will deliver loss rates
Calibration of loss rates from simulation.Tolerated error: factor 5
Initial working condition.
Channel assignment tested with radioactive source.
Adjustment of BST for fast loss monitors (collimation region)
One circulating bunch.
Automated scan.
A few hours.
Repeated after some time to check stability.
Parasitic.
Verification of calibration. Delicate machine experiment. Calibrated loss rates have to be produced into the cryo-magnets
Dedicated experiment.
A couple of shifts.
Necessary step in order to establish dump thresholds.
Crosstalk between channels, in particular between the two beams, longitudinal coverage
Dedicated machine experiments
Crosstalk between beams simulated to be below 10%. Only a problem if beam currents very different.
Determination of dump thresholds
Many dedicated machine experiments and operational experience
See next slide
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1212
Beam Commissioning: BLM dump thresholds
There will be more than 3000 beam loss monitors. Each of them can be enabled to dump the beam.The dependence of the dump level as function of the duration of the loss (3 orders of magnitude) is realized with 11 different integrators with exponential staggering of integration times (about factor 2)The dependence on beam energy represents another 2 orders of magnitude (multiplication factor)
There will be 3000 * 11 dump thresholds with an energy dependent multiplication factor to be computed in simulation, to be implemented and to be tested!
Clear need for
a system-
commissioner
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1313
Beam Commisioning: BCTs
DCCT: will be checked with calibration wire.Will work from day 0. Verifications of EMC immunity, noise behaviour and appropriate improvements during the run.
Bunch to bunch system:Requires BST, will be available after a few hours of beam (setting of timing delays). Presently we study a filter to stretch the bunch shape by a factor 20. This should give then a measurement without the timing adjusted, but signal to noise for pilot intensity very poor.
Lifetime calculations:Noise of DCCT: 0.5 uA rms (1 Hz bandwidth)Pilot beam: 9 uA: 10h lifetime calculation needs 10-5 noise level for current measurement.
Take bunch to bunch system for lifetime. Noise level (single shot): 10-2 for pilot. Need 10^6 turns to gain factor 1000 in statistics: 200 s measurement time for lifetime or more bunches….
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1414
Beam Commissioning: Tune measurements
We will start with the basic method:
Kick as beam stimulus, FTT of beam motion:
Q-kicker: 9 us pulse length, needs rough timing set up (a few hours)BPM for tune measurements (for example BBQ system) does not need timing, data acquired with 24bit audio system (one acquisition per turn = 11k Hz).
Basic system will be operational at day 0.
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1515
Beam Commissioning: Tune measurements
Time resolved measurements, PLL tune tracking:
1) We will prepare the software for a sequence of kick stimulus and FFT based tune measurements (spectrogram). This contains more information than a PLL trace and it will be available straight away.
2) The PLL will need a few weeks to be set up (BNL: 3 years, FNAL after 1 year a preliminary system in one plane). US-LARP collaboration ongoing.
Difficult to say when first system will be operational.Compatibility with transverse damping so far unclear.
System Commissioner in AB-OP would help.
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1616
Beam Commissioning: Chromaticity Measurements:
Day 0: kick stimulus and Head-Tail analysis of resulting betatron motion. This system needs the BST to be set up ( a few hours).Condition: betatron oscillation has to last at least 20% of a synchrotron period.As already mentioned: Considerable software effort needed for automated repetitive (= time resolved ) chromaticity measurements.Alternative: Difference in tune for two discrete settings of beam momentum (sufficient to monitor decay during injection plateau)
Chromaticity tracking via periodic momentum modulation will be available as soon as the PLL works.
Again, considerable effort in the application programs will be needed to extract chromaticty data.
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1717
Coupling Measurements
Day 0:
Again kick as beam stimulus.
Coupling (in particular if large) from cross talk to other plane:
(software?) Day N:With PLL available: closest tune approach measurement
From ISR!
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1818
Transverse Diagnostics:
Clear two step approach:1) Day 0 with kicked beams and classical motion analysis2) Day N with PLL and more powerful time resolved methods.
This puts a high pressure on getting dedicated machine time in order to commission the PLL early.As long as emittance growth is not the major concern, the problems will be:- automation of parameter settings depending on beam conditions (filters, gain switches, timings)- phase scans in order to determine the correct PLL lock conditions
For operational beams the additional problems will be:- lowering the excitation level to an insignificant level- achieve compatibility with resistive transverse damping
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1919
Commissioning with Beam (2)
System Commissioning with beam
Dedicated or parasitic
Beam condition Time estimate
Synchrotron light monitor BSRT
Timing parasitic Stable pilot beam 4 hours, ASAP
Cross check with screen monitor for matching
dedicated Stable nominal bunch
4 hours
Diffraction, longitudinal acceptance measurement
parasitic Stable pilot or higher intensity
16 hours, ASAP
Cross calibration with wire scanner, after the previous steps have been completed successfully
dedicated Stable nominal bunch or higher intensity
Minimum 16 hours (probably to be repeated after processing of data)
LDM Bunch longitudinal profile and tail measurements
parasitic Stable beam 2 days
AGM Debug equipment Parasitic, access 1 or 2 times
Stable pilot 4 days
Abort system operation dedicated Stable beam A few days
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 2020
Commissioning with Beam (3)
System Commissioning with beam
Dedicated or parasitic
Beam condition Time estimate
Rest gas monitor
Gain adjustment to beam intensity and dimensions and adjustment to vacuum pressure
parasitic Gain adjusted remotely according to beam conditions.
1 hour per monitor in the ring where the beam is injected and circulates.
Cross calibration with wire scanner
Parasitic if compatible with wire-scanner operation
Wire scanner operation should be possible
1-2 hours per beam
Wire scanner
Prove of performance parasitic 1 pilot bunch to 2 batches nominal intensity
1 hour
luminosity Timing adjustments parasitic Any beam Done before collisions
Verification of 40 MHz performance
dedicated Specific bunch patterns Later MDs
H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 2121
Conclusions
The BDI group makes an attempt to have integrated into all instruments basic modes of operation, which will give acceptable measurements in the conditions of “bootstrap”.
The essential systems for commissioning have an acquisition mode independent of beam synchronous timing.
The BLM system for machine protection will need a considerable commissioning effort.
All systems need a large investment into the corresponding application programs.
The recently proposed concept of system commissioners should be implemented soon with the right people selected for the key beam instruments. This is for me the most urgent line of action.