+ All Categories
Home > Documents > H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC...

H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC...

Date post: 19-Jan-2016
Category:
Upload: laurence-quinn
View: 223 times
Download: 0 times
Share this document with a friend
21
H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 January 18, 2005 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler on behalf of the AB-BDI group
Transcript
Page 1: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1 January 18, 2005 1

Beam Commissioning of LHC instrumentation

Chamonix XIV, January 2005

H.Schmickler on behalf of the AB-BDI group

Page 2: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 22

For information: Outline of Talk of B.Holzer (Wednesday)

Beam Position Monitor (BPM) System Polarity errors Testing of electronics BPM Database issues Timing issues

Beam Loss Monitor (BLM) System Hardware set-up & testing Calibration Threshold determination

Emittance and Current Measurement Systems Sector Test Summary

Page 3: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 33

Outline of this Talk

Prerequisites for a working instrumentation Action areas:

- design office support- coordinated effort for application programs

Two major lessons learnt from LEP:- Independence of beam synchronous timing- Deadlocks during hardware/software developments

Bringing the instruments (machine) to their nominal performance- orbit system- beam loss monitor system- time resolved tune and chromaticty measurements- beam current measurements, lifetime calculations- profile measurements- others

conclusions

Page 4: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 44

Prerequisites (same slide as last year)

Working and exploitable instruments need:

- sensors and electronics : AB-BDIdetails see AB-LHC review; recurrent problem: Design support

- controls infracstructure : AB-CO, in progress

- RT software and expert tools: AB-BDI-SW will be based on FESAII framework

- Operational application programsAB-CO + AB-OP

work needs to be organized soon (that is the text of last year)

work needs to be organized now (see following slides)

Page 5: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 55

Design effort still needed

There are still major BDI components, for which the mechanical design is not done / finished.

The situation was similar at Chamonix 2004.

After the workshop a significant improvement in design office support was notable.

With the QRL problem higher priorities defined, present support insufficient

Without the requested support - some special BPMs (= special BPMs of the normal orbit system and special BPMs for tune measurements)- the synchrotron light telescope- the wire scanners

will not be ready

Page 6: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 66

Prerequisites: Software effort

Example: Time resolved chromaticity measurementsat day 0: We should not count on PLL tune tracking and momentum modulation use head-tail method (despite emittance growth)

SPS application program:

- needs visual inspection of result- gives chromaticty as number onthe screen

- needs:automation, integration into a measurement system…

Solution:

Define for the key system “System commissioners”and start definition, design and coding of the application programs

Page 7: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 77

Lessons learnt from LEP (1/2)

Provide reduced functionality of instruments without beam synchronous timing (BST)

- BPM-system: works without BST, but no bunch/turn identification, reduced noise immunity

- BLM system: most of the system acquires data in an asynchronous 1ms rhythm

- BCT DC: no timing- BCT BB: needs beam synchronous timing,

was a problem for the downstream BCT in TI8, people are working on a input filter to stretch the signal for single

bunch operation- tune measurement systems:

tune kicker needs rough timing, tune meter will have one front-end not depending on timing basic functionality without BST

- all TV based monitors: will work without BST, obviously no bunch gating(sync-light telescope, ionisation profile monitor, screens)

- wire scanners and luminosity monitors: will have an acquisition mode without BST

- AGM and LDM: need the BST in order to work.

Page 8: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 88

Lessons learnt from LEP (2/2)

Hardware can not be tested because software not ready,Software can not be developed because hardware not available…

- The FESA framework provides the possibility to have device emulation of missing hardware, such that the software can be developed and tested at a time when the hardware is still partially missing:

This feature will help having software/hardware ready in time

Page 9: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 99

Commissioning with Beam: BPM system

Day 0 performance without adjustments

No BST adjusted,

1 pilot bunch; can measure orbit, turn by turn data possible with BST turn clock

Immediate!

Systematic check for inverted cables/planes/rings

Per ring and per plane non closed bumps with two correctors at 90^0 phase advance.

If well automated, one shift for detection of problems.Requirement for scripting tool.

If 5% error rate, one week to fix problems.

Adjustment of BST One circulating bunch;

Scan of timing setting for all front ends.

Two shifts interleaved by a few days; check for stability of settings

Systematic confirmation of system performance

Resolution as function of beam intensity, linearity over aperture, dependence on long. beam structure, crosstalk between beams

Long process. Several months.

Demands LDM to be operational.

Page 10: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1010

BPM system:

Application software:

This should be in good shape:

System commissioner at work since years.

Application programs very similar to those of LEP and SPS.

Attention: The turn by turn analysis program as provided for the SPS needs more work.

Page 11: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1111

Commissioning with Beam: BLM system

Day 0 performance:

All “slow (= 1ms)” monitors will deliver loss rates

Calibration of loss rates from simulation.Tolerated error: factor 5

Initial working condition.

Channel assignment tested with radioactive source.

Adjustment of BST for fast loss monitors (collimation region)

One circulating bunch.

Automated scan.

A few hours.

Repeated after some time to check stability.

Parasitic.

Verification of calibration. Delicate machine experiment. Calibrated loss rates have to be produced into the cryo-magnets

Dedicated experiment.

A couple of shifts.

Necessary step in order to establish dump thresholds.

Crosstalk between channels, in particular between the two beams, longitudinal coverage

Dedicated machine experiments

Crosstalk between beams simulated to be below 10%. Only a problem if beam currents very different.

Determination of dump thresholds

Many dedicated machine experiments and operational experience

See next slide

Page 12: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1212

Beam Commissioning: BLM dump thresholds

There will be more than 3000 beam loss monitors. Each of them can be enabled to dump the beam.The dependence of the dump level as function of the duration of the loss (3 orders of magnitude) is realized with 11 different integrators with exponential staggering of integration times (about factor 2)The dependence on beam energy represents another 2 orders of magnitude (multiplication factor)

There will be 3000 * 11 dump thresholds with an energy dependent multiplication factor to be computed in simulation, to be implemented and to be tested!

Clear need for

a system-

commissioner

Page 13: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1313

Beam Commisioning: BCTs

DCCT: will be checked with calibration wire.Will work from day 0. Verifications of EMC immunity, noise behaviour and appropriate improvements during the run.

Bunch to bunch system:Requires BST, will be available after a few hours of beam (setting of timing delays). Presently we study a filter to stretch the bunch shape by a factor 20. This should give then a measurement without the timing adjusted, but signal to noise for pilot intensity very poor.

Lifetime calculations:Noise of DCCT: 0.5 uA rms (1 Hz bandwidth)Pilot beam: 9 uA: 10h lifetime calculation needs 10-5 noise level for current measurement.

Take bunch to bunch system for lifetime. Noise level (single shot): 10-2 for pilot. Need 10^6 turns to gain factor 1000 in statistics: 200 s measurement time for lifetime or more bunches….

Page 14: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1414

Beam Commissioning: Tune measurements

We will start with the basic method:

Kick as beam stimulus, FTT of beam motion:

Q-kicker: 9 us pulse length, needs rough timing set up (a few hours)BPM for tune measurements (for example BBQ system) does not need timing, data acquired with 24bit audio system (one acquisition per turn = 11k Hz).

Basic system will be operational at day 0.

Page 15: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1515

Beam Commissioning: Tune measurements

Time resolved measurements, PLL tune tracking:

1) We will prepare the software for a sequence of kick stimulus and FFT based tune measurements (spectrogram). This contains more information than a PLL trace and it will be available straight away.

2) The PLL will need a few weeks to be set up (BNL: 3 years, FNAL after 1 year a preliminary system in one plane). US-LARP collaboration ongoing.

Difficult to say when first system will be operational.Compatibility with transverse damping so far unclear.

System Commissioner in AB-OP would help.

Page 16: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1616

Beam Commissioning: Chromaticity Measurements:

Day 0: kick stimulus and Head-Tail analysis of resulting betatron motion. This system needs the BST to be set up ( a few hours).Condition: betatron oscillation has to last at least 20% of a synchrotron period.As already mentioned: Considerable software effort needed for automated repetitive (= time resolved ) chromaticity measurements.Alternative: Difference in tune for two discrete settings of beam momentum (sufficient to monitor decay during injection plateau)

Chromaticity tracking via periodic momentum modulation will be available as soon as the PLL works.

Again, considerable effort in the application programs will be needed to extract chromaticty data.

Page 17: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1717

Coupling Measurements

Day 0:

Again kick as beam stimulus.

Coupling (in particular if large) from cross talk to other plane:

(software?) Day N:With PLL available: closest tune approach measurement

From ISR!

Page 18: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1818

Transverse Diagnostics:

Clear two step approach:1) Day 0 with kicked beams and classical motion analysis2) Day N with PLL and more powerful time resolved methods.

This puts a high pressure on getting dedicated machine time in order to commission the PLL early.As long as emittance growth is not the major concern, the problems will be:- automation of parameter settings depending on beam conditions (filters, gain switches, timings)- phase scans in order to determine the correct PLL lock conditions

For operational beams the additional problems will be:- lowering the excitation level to an insignificant level- achieve compatibility with resistive transverse damping

Page 19: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 1919

Commissioning with Beam (2)

System Commissioning with beam

Dedicated or parasitic

Beam condition Time estimate

Synchrotron light monitor BSRT

Timing parasitic Stable pilot beam 4 hours, ASAP

Cross check with screen monitor for matching

dedicated Stable nominal bunch

4 hours

Diffraction, longitudinal acceptance measurement

parasitic Stable pilot or higher intensity

16 hours, ASAP

Cross calibration with wire scanner, after the previous steps have been completed successfully

dedicated Stable nominal bunch or higher intensity

Minimum 16 hours (probably to be repeated after processing of data)

LDM Bunch longitudinal profile and tail measurements

parasitic Stable beam 2 days

AGM Debug equipment Parasitic, access 1 or 2 times

Stable pilot 4 days

Abort system operation dedicated Stable beam A few days

Page 20: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 2020

Commissioning with Beam (3)

System Commissioning with beam

Dedicated or parasitic

Beam condition Time estimate

Rest gas monitor

Gain adjustment to beam intensity and dimensions and adjustment to vacuum pressure

parasitic Gain adjusted remotely according to beam conditions.

1 hour per monitor in the ring where the beam is injected and circulates.

Cross calibration with wire scanner

Parasitic if compatible with wire-scanner operation

Wire scanner operation should be possible

1-2 hours per beam

Wire scanner

Prove of performance parasitic 1 pilot bunch to 2 batches nominal intensity

1 hour

luminosity Timing adjustments parasitic Any beam Done before collisions

Verification of 40 MHz performance

dedicated Specific bunch patterns Later MDs

Page 21: H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, 2005 1 1 Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.

H.Schmickler, AB-BDIChamonix XIV workshop, CERN January 18, 2005 2121

Conclusions

The BDI group makes an attempt to have integrated into all instruments basic modes of operation, which will give acceptable measurements in the conditions of “bootstrap”.

The essential systems for commissioning have an acquisition mode independent of beam synchronous timing.

The BLM system for machine protection will need a considerable commissioning effort.

All systems need a large investment into the corresponding application programs.

The recently proposed concept of system commissioners should be implemented soon with the right people selected for the key beam instruments. This is for me the most urgent line of action.


Recommended