Currency: US Dollars
Project No:
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Tender Title: Customs and Police Office Buildings
Original Issue: February 25, 2010
810
Customs and Police Office Buildings
NOTICE TO ALL BIDDERS - COMPLETE PROJECT PRICE:
3. Eventual claims for extra works are covered by project generaldocumentation of contract.
1. All bidders MUST examine the complete project documents. These
documents include the Drawings, BOQ, Schedules and Specifications.
Any discrepancies between these documents are to be brought to the
immediate attention of UNOPS Engineer.
2. Quotation given by the contractor on this BOQ are to cover any and all
additional materials, labor or associated costs to complete the works as
documented on the complete project documents.
UNOPS
UNITED NATIONS OFFICE FOR PROJECT SERVICES
BILL OF QUANTITIES
Ai Khanem Border Crossing Point Facilities
Takhar, Afghanistan
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
2/24
Ai Khanem Border Crossing Point Facilities
Takhar, Afghanistan
Customs Office Building
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
3/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total Cost
1. General
1.1 Preliminaries 1.1 Occupied Areas, 1.1 ExistingServices Schedule and 1.1 Items
to be supplied schedules
1 Pre-construction work, mobilisation activitiesincluding paper/ documentation tasks. LS 1.00 -
2 Post construction works and clean up.LS 1.00 -
1.2 General Requirements 1.2 Inspection notificationschedule and 1.2 Warranty
schedules
1 Testing and Operation/Maintenance Manuals.LS 1.00 -
Subtotal General -
2. Site
2.3 Earthwork 2.1 Identified hazardous materialsand 2.3 Earthwork schedules
1 Excavation (any soil type) for foundation.This item includes all excavations, disposal andtemporary support or shoring if needed. See
drawing and schedule for details.CU.M 246.00 -
2 Ground improvement under foundations.This includes supplying of filling materials and
compacting the layers according to schedule
and drawings. CU.M 110.00 -
3 Soil backfilling on RCC math foundation up toground level. This includes supplying of needed
materials. See drawings and schedules for
levels/dimensions and details. CU.M 190.00 -
4 Gravel compaction, Class 2, at any placesunder the PCC/RCC shown inside the building
or at sidewalk/ramp. This includes supplying of
needed materials. See drawing and projectschedules for dimensions and details.
CU.M 75.00 -
Subtotal Site -
3. Structure
3.1 Concrete-General 3.1 Non reinforced concrete, 3.1Reinforced concrete and 3.2
Concrete- Integral Finishes
schedules
1 PCC lean concrete (10 Mpa) under the RCCfoundations. CU.M 13.00 -
2 RCC (20 Mpa) foundations, rectangular andtrapezoidal foundation beams. CU.M 140.00 -
3 PCC, 40mm thick, lean concrete (10 Mpa) atthe floor over the gravel compaction. CU.M 19.00 -
NOTE: Cost for concrete items in this section
includes reinforcement, steel anchorage embedded
in concrete, shuttering, concrete, concrete curing
and all to the complete job.
Pos.
UNOPS
DETAILS OF COMPONENTVertical Structures Unit
3/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
4/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total CostPos.
4 PCC concrete, 100mm thick, (20 Mpa) at thefloor over the water-proofing layer. This item
includes the stairs steps at the entrances and
the ramps. CU.M 47.00 -
5 RCC Columns, includes all columns (from -1.65to +3.55) and supporting columns/ring beams
for trusses on the roof. CU.M 82.00 -
6 RCC (20 Mpa) slabs and beams. The itemscovers all slabs, beams and RCC floor for the
bank. CU.M 86.00 -
7 RCC Pavement (20 Mpa), for 1000mm-wideside walks. This includes entrances and ramps.
The cost includes expansion joint on side walk
surface as shown and as well as the broomfinish to the side walk/ ramp surfaces.
CU.M 15.00 -
3.3 Pre-cast RC Concrete 3.3 Precast Concrete PrototypesSchedule
1 Precast RCC (20 Mpa) exterior window sill forall windows as per drawings. This includes all
work need for complete installation.Lin M 29.00 -
3.5 Brickwork 3.5 Brickwork constructionschedule
1 Second Class Brick masonry with mortar. Thisincludes all brick walls/ brick masonry in the
entire building. The cost includes steel bars
shown in the walls and their connection to the
perimeter RCC elements. CU.M 60.00 -
3.9 Light Timberwork 3.9 Light Timberwork schedule,6.6 Interior painting and 6.6
Exterior painting schedules
1 Roof timber structure on the trusses. The costincludes 30mm thick wooden planks as shown
on the drawing. This also cover all auxiliary and
needed materials and supplying and installation
of members including painting to make the
surface ready for folded metal sheet roofing
according to the drawing, schedule and
specifications. SQ.M 680.00 -
3.10 Concrete Unit Masonry 3.10 Concrete Unit Masonry
1 CMU masonry with mortar. This item covers allCMU works shown on the drawings for the
building. The cost includes all needed
materials, steel bars, anchors etc and works. CU.M 60.00 - 3.11 Structural Steel 3.11 Structural Steel Schedules
1 Steel support, purlin, at the metal sheet roof as(C-shape 140x65mm + L-shape 50x50mm).
See drawing for details. Lin M 560.00 -
2 Steel truss (TRUSS 1) at the roof. See drawingfor details. No 6.00 -
3 Steel truss (TRUSS 2) at the roof. See drawingfor details. No 4.00 -
4 Steel truss (TRUSS 3) at the roof. See drawingfor details. No 2.00 -
NOTE: Cost for steel related items in this section
includes supplying materials and installation to the
complete condition for all members, gussets,
fasteners, connections, welding and other
accessories and works needed to complete the job.
The cost also includes painting according to the
schedules and specifications for steel member
painting, which is at least on coat of anti-rust
followed by 2 other coats of oil-based painting for all
surfaces and sides of the steel members.
4/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
5/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total CostPos.
5 Steel truss (TRUSS 4) at the roof. See drawingfor details. No 8.00 -
6 Steel truss (TRUSS 5) at the roof. See drawingfor details. No 2.00 -
7 Steel truss (TRUSS 6) at the roof. See drawingfor details. No 2.00 -
8 Steel truss (TRUSS 7) at the roof. See drawingfor details. No 8.00 -
9 Steel truss (TRUSS 8) at the roof. See drawingfor details. No 2.00 -
10 Steel truss (TRUSS 9) at the roof. See drawingfor details. No 4.00 -
11 Steel truss (TRUSS 10) at the roof. See
drawing for details. No 4.00 - 12 Steel truss (TRUSS 11) at the roof. See
drawing for details. No 1.00 -
13 Steel frame fixed ladder inside the toilet as theaccess way to the roof. The work and the cost
includes construction of fixed later to the wall
and the opening pane, its hardware and other
accessories to complete the installation as per
drawing and schedule. This also includes
painting according to the schedules and
specifications for steel surfaces painting.LS 1.00 -
Subtotal Structure -
4. Enclosure
4.1 Waterproofing 4.1 Waterproofing systemschedule
1 Bitumen water-proofing coat. This is a 3-5mmthick hot bitumen painting coats on dried PCC
surface. The item applies on 40mm PCC at the
floor beneath the 20 Mpa, 100mm thick PCC
layer. This cost includes supplying and applying
the coats with all needed accessories and work
to do the job as per manufacturer's data and to
the full satisfaction of UNOPS engineer.SQ.M 470.00 -
2 Single layer bitumen membrane at the floor andwalls of toilets/kitchen. This includes
preparation of base layers shown on the
drawings. Refer to schedule/drawing for details.
SQ.M 55.00 - 4.2 Roofing 4.2 Roofing materials, and 4.2
Gutter and Down pipe Schedules
1 Standing seam metal roofing (using GI sheetgauge 24). This includes all accessories
required for installation of roof on the prepared
timber plank (see item 3.9.1 for the cost of
timber plank on roof). The cost also includes all
flashings, capping etc needed on the metal roof.SQ.M 680.00 -
2 Metallic gutter around the roof (using GI sheetgauge 20). The cost includes all accessories
required for complete installation of gutter such
as supplying, fixing and others as per drawing
and schedules.Lin M 116.00 -
3 Down pipes, PVC pipe class-B. This includesall accessories required for complete installation
such as supplying, fixing and others as per
drawing and schedules.Lin M 45.00 -
5/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
6/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total CostPos.
4.3 Windows and Window Hardware 4.3 Window, 4.3 WindowHardware, 4.5 Annealed Glasses,
and 4.6 Glassblock work
schedules
1 Wooden frame windows. The work includesmaking, transportation, installation, hardware,
glazing, glass-block work around window,
insect screen, 3 coats of oil-based painting, and
other accessories required for complete
installation as per drawings and schedule.SQ.M 63.00 -
4.4 Doors and Door Hardware 4.4 Joinery doors 4.4 PVC doors,4.4 Steel doors and 4.5 Annealed
Glasses schedules
1 Wooden frame doors. The work includesmaking, transportation, installation, hardware,
glazing, and other accessories required for
complete installation as per drawings and
schedule. SQ.M 76.00 -
2 PVC frame doors. The work includes making,transportation, installation, hardware, glazing,
and other accessories required for complete
installation as per drawings and schedule.SQ.M 6.00 -
3 Steel frame doors. The work includes making,transportation, installation, hardware, glazing, 1
coat of anti-rust followed by 2 other coats of oil-
based painting, and other accessories required
for complete installation as per drawings and
schedule.SQ.M 2.00 -
4.5 Glazing 4.5 Mirrors schedules
1 Mirrors (40x60cm) at toilets. This includescomplete installation. No 5.00 -
4.7 Insulation and Vapour Barriers 4.7 Insulation Schedules
1 Glasswool thermal insulation on RCC roof,beneath roof structure. See drawings and
schedules for details. SQ.M 640.00 -
4.8 Exterior Insulation and Finish System 4.8 EFIS Schedules
1 External wall insulation system, STOTHERMCLASSIC, (expanded polystyrene foam and
organically bound render) "or equivalent ". See
drawing and schedule for location and detail.
The cost includes one preparation layer of
cement render and all other process required for
a complete job as per product's manufacturer
data and UNOPS engineer satisfaction.SQ.M 310.00 -
Subtotal enclosure -
5. Interior5.4 Suspended Ceiling 5.4 Suspended Ceiling Schedule
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
6/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
7/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total CostPos.
1 Lasani wooden board, 16mmm, fixed ceiling forall soffits around the building. The cost includes
all framing, fixing, oil based painting and
needed work for a complete job to the full
satisfaction of Engineer. SQ M 152.00 -
2 Gypsum board, 16mmm, reflected ceiling forthe side entrances of the building. The cost
includes all framing, fixing, and needed work for
complete job. SQ M 4.00 -
5.5 Joinery 5.5 Joinery fixtures schedule
1 Wooden frame, MDF finish, wall mountedcabinet at the kitchen. See drawings for details.
The cost includes making, installation, framing,
hardware, finish, 3 coats oil-based painting and
all to the complete job.LS 1.00 -
2 Wooden frame, MDF finish, floor mountedcupboard at the kitchen. See drawings for
details. The cost includes making, installation,
framing, finish, hardware, stone table top,
splash back, 3 coats oil-based painting and all
to the complete job. LS 1.00 -
5.6 Metalwork 5.6 Metal Fixtures Schedule
1 Metallic plaster beads for outer corners at thecorridors only, including edge of walls. This
includes any needed work for complete
installation. See schedules and drawings for
details. Lin M 70.00 -
2 Toilet roll holders. This also includes installation.No 3.00 -
3 Grab rail for handicap toilet. One complete set.This includes supplying and complete
installation. LS 1.00 -
4 Soap dishes. This also includes installation.No 4.00 -
5.8 Fire Extinguishers and Blankets 5.8 Fire Extinguishers Schedule
1 Extinguishers, wall mounted, powder-type (9kg).No 4.00 -
Subtotal Interior -
6. Finish
6.1 Plastering 6.1 Plastering Schedule
Internal surfaces
1 Cement render medium CRM followed bycement render fine CRF on all internal surfaces
of walls/ ceilings/ beams/ columns/ reveals. See
schedule for detail. SQ.M 1,100.00 -
External surfaces
2 Gypsum board, decorative finish, at both mainentrances foreheads. The cost includes
supplying, making, installation and all to the
complete condition as per Engineer's approval.
SQ.M 40.00 -
6.2 Cementitious Toppings 6.2 Cementitious Toppings
ScheduleNOTE: Prior to work, samples must be approved by
UNOPS Engineer.
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
7/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
8/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total CostPos.
1 In situ colored chips, colored mortar terrazzo,including marble trims for joints, for all floors as
shown on the drawing. See schedule for details.
The cost also includes stainless steel nosing at
the outer edges of the stair steps at the
entrances. SQ.M 510.00 -
6.3 Tiling 6.3 Wall tiling and 6.3 Floor tilingschedules
1 Ceramic wall tiles for toilets, kitchen, around thedrinking water fountain and any place shown.
The cost includes bed preparation, bedding and
grout. SQ.M 70.00 -
2 Ceramic floor tiles for toilets including bedpreparation, bedding and grout. SQ.M 35.00 -
3 Marble skirting for all rooms and halls where didnot receive ceramic tiles. The cost includes
bedding and grout. Lin M 450.00 -
6.6 Painting 6.6 Interior/Exterior paintingschedule
Internal surfaces
1 Flat water based: Interior, on all surfaces thatreceive cement plaster. The cost includes wall
putty (gypsum filling) layer before painting and
all needed preparation of the surfaces for
painting. See schedule for detail on this paint
system SQ.M 1,100.00 -
Subtotal Finishes -
8. Water Services
8.1 Water Services 8.1 Water services samples, 8.1Water system piping, 8.1 Sanitary
fixtures, 8.1 Water heater
schedules and 8.1 Water
Services Testing schedules
NOTE: The cost for all pipes exposed to
weather includes glass wool thermal insulation
cover. The cost given for all GI and PVC pipes
with diameter less than 60mm includes all
required fittings, accessories and work for
complete system installation.
Water supply piping
1 GI water supply pipe D=32mm, includingfittings and installation. Lin M 30.00 -
2 GI water supply pipe D=25mm, includingfittings and installation. Lin M 22.00 -
3 GI water supply pipe D=20mm, includingfittings and installation. Lin M 25.00 -
4 GI water supply pipe D=15mm, includingfittings and installation. Lin M 50.00 -
5 Water supply bronze Valve D=32mm, includingfittings and installation. No 2.00 -
6 Water supply bronze Valve D=20mm, including
fittings and installation. No 1.00 - 7 Damp proof Insulation rubber tape for all GI
Piping. Lin M 150.00 -
8 Water supply inspection manhole less than1200mm deep. This includes excavation and
any needed work to make the manhole as per
drawings and schedule. No 3.00 -
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
8/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
9/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total CostPos.
Sanitation Piping
9 PVC pipe D=100mm, including supply andinstallation. This also includes supply and
installation of PVC pipe from GI sheet
downpipes to the open channel collector at the
side walks. Lin M 34.00 -
10 PVC pipe D=50mm, including fittings andinstallation. Lin M 50.00 -
11 Ventilation PVC pipes D=100mm (from toiletsto roof). This also includes supplying and
installation of PVC screen at the pipe inlets
inside the toilets. See drawing and schedule for
details. Lin M 15.00 -
12 Ventilation PVC pipes D=50mm (from toilets toroof). This also includes supplying and
installation of PVC screen at the pipe inlets
inside the toilets. See drawing and schedule for
details. Lin M 10.00 -
13 PVC Elbow D=100x100,45 , including supplyand installation. No 4.00 -
14 PVC Tee D=100x100, 45 , including supply andinstallation. No 8.00 -
15 Sanitation Grease Trap less than 1200mmdeep. This includes excavation and any needed
work to make the manhole according to the
drawings and schedules. No 1.00 -
Sanitary and other fixtures
16 Western toilet, including supply, installation and
accessories. No 3.00 - 17 Water fountain , including supply, installation
and accessories. No 2.00 -
18 Ceramic sink at toilets and labs, including mixerand all accessories, supplying and installation.
No 4.00 -
19 Floor trap D=50mm, including supply andinstallation. No 6.00 -
20 Stainless steel sink, including supply andinstallation. No 1.00 -
21 Ventilation cap D=100mm, including supplyand installation. No 2.00 -
22 Ventilation cap D=50mm, including supply andinstallation. No 1.00 -
23 Service Sink, including supply and installation.No 1.00 -
24 Electrical water boiler with capacity of 50 Liter,including supply and installation. No 2.00 -
25 Electrical water boiler with capacity of 30 Liter,including supply and installation. No 1.00 -
26 Sewer Manholes More than 1200mm deep.This includes excavation and any needed work
to make the manhole according to the drawings
and schedules. No 2.00 -
Subtotal Water Services -
9. Electrical Services
9.1 Electrical Services 9.1 Electrical systems, 9.1Electrical supply mains, 9.1
Electrical switchboard design, 9.1
Main 380VAC DistributionSystem, 9.1 Panel Construction,
9.1 Power accessories, 9.1
Lighting control and fittings, 9.1
Fire Detection Equipment
Schedule Schedules and the
Attachments
9/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
10/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total CostPos.
Note: for all items below the cost includes
complete/installations with all needed
accessories and works.
Switchboard and sub boards
1 Sub distribution panel, 750x500x250 mm,powder coated, weatherproof, outdoor mounted
metal. With Digital Measurement equipments.No. 1.00 -
2 Main circuit breaker, MCCB, 3x160Amps, Type-C. No. 1.00 -
3 Circuit breaker, MCB, 1x32Amps, Type-CNo. 16.00 -
4 Circuit breaker, MCB, 1x20Amps, Type-C
No. 38.00 - Distribution wiring
5 3 (1X6mm2) wires pulled in 24mm PVCConduit, assorted colors as per phase
requirement RST/UVW, white color for neutral
and green color for grounding. Lin M 600.00 -
6 3 (1X4mm2) wires pulled in 24mm PVCConduit, assorted colors as per phase
requirement RST/UVW, white color for neutral
and green color for grounding. Lin M 1,500.00 -
Fittings/Fixtures
7 Single pole/double pole or two way light switch.No 42.00 -
8 32W circular surface ceiling mount, IP54fluorescent light fixture. No 35.00 -
9 60W circular Pendant ceiling mount, IP54fluorescent light fixture with all accessories. No 21.00 -
10 60W Circular Surface ceiling mount, IP54fluorescent light fixture with all accessories. No 7.00 -
11 2x36W pendant ceiling mounted fluorescentlight fixture, IP-44.with all accessories. No 25.00 -
12 1x36W pendant ceiling mounted fluorescentlight fixture, IP-56. with all accessories. No 2.00 -
13 16 Amp Duplex power receptacle.No 98.00 -
14 16 Amp single water proof power receptacle.No 9.00 -
15 25 Amp single water proof power receptacle forelectrical water heater and kitchen. No 9.00 -
AC/Split Units and Exhaust fans
16 12000 BTU AC/ Split unit 220 V, 50 HZ
Samsung made in Italy with all accessories. No 15.00 - 17 Roof mounted exhaust fans .
No 3.00 -
18 25 Amp single electrical non-fuse disconnectingswitch for AC/ Split unit. No 15.00 -
Emergency evacuation lighting
19 2x10 watt IP-65 wall mounted Emergency LightFixture. No 7.00 -
20 1X10W surface mounted IP-40 Exit light.No 4.00 -
Fire alarm system (including all associated
cabling, wiring, mounting, etc)
21 Addressable fire alarm panel, with allaccessories, to the complete and functioning
job. LS 1.00 -
22 Fire alarm push button, double action type, ULListed No 4.00 -
23 Fire alarmNo 4.00 -
24 Photoelectric type smoke detectors, UL ListedNo 22.00 -
Electrical Grounding and Lightning
Protection.
10/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
11/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Description of Work/Items Project Schedules Ref. Unit Quantity Unit Cost Total CostPos.
25 Lightening protection as mentioned in lighteningprotection drawing with air terminal, electrodes,
tape, connectors, clamp and grounding cableSet 1.00 -
26 Grounding system as mentioned in groundingdrawing with electrodes, tape, connectors,
clamp and grounding cable Set 1.00 -
Labeling
27 Proper and correct all circuits numbering, cablecircuit drawings, cable and switchboard labeling
to the full satisfaction of UNOPS engineer.LS 1.00 -
Subtotal Electrical Services -
11/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
12/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Customs Office Building
Original Issue: February 25, 2010
Work Type
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total for General
Total for Site
UNOPS
SUMMARY OF COMPONENT
Vertical Structures Unit
Total for Customs Office Building 0.00
Total for Electrical Services
Total for Structure
Total for Enclosure
Total for Interior
Total for Finish
Total for Water Supply Services
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
13/24
Ai Khanem Border Crossing Point Facilities
Takhar, Afghanistan
Police Office Building
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
14/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Description of Work/Items Unit Quantity Unit Cost Total Cost
1. General
1.1 Preliminaries 1.1 Occupied Areas, 1.1 ExistingServices Schedule and 1.1 Items to be
supplied schedules
1 Pre-construction work, mobilisation activities
including paper/ documentation tasks.LS 1.00 -
2 Post construction works and clean up.LS 1.00 -
1.2 General Requirements 1.2 Inspection notification schedule and1.2 Warranty schedules
1 Testing and Operation/Maintenance Manuals.LS 1.00 -
Subtotal General -
2. Site
2.3 Earthwork 2.1 Identified hazardous materials and2.3 Earthwork schedules
1 Excavation (any soil type) for foundation.This item includes all excavations, disposal
and temporary support or shoring if needed.See drawing and schedule for details.
CU.M 190.00 -
2 Ground improvement under foundations.This includes supplying of filling materials and
compacting the layers according to schedule
and drawings. CU.M 85.00 -
3 Soil backfilling on RCC math foundation upto ground level. This includes supplying of
needed materials. See drawings and
schedules for levels/dimensions and details.CU.M 147.00 -
4 Gravel compaction, Class 2, at any placesunder the PCC/RCC shown inside the building
or at sidewalk/ramp. This includes supplying
of needed materials. See drawing and project
schedules for dimensions and details.CU.M 60.00 -
Subtotal Site -
3. Structure
3.1 Concrete-General 3.1 Non reinforced concrete, 3.1Reinforced concrete and 3.2 Concrete-
Integral Finishes schedules
1 PCC lean concrete (10 Mpa) under the RCCfoundations. CU.M 10.00 -
2 RCC (20 Mpa) foundations, rectangular andtrapezoidal foundation beams. CU.M 108.00 -
3 PCC, 40mm thick, lean concrete (10 Mpa) atthe floor over the gravel compaction. CU.M 15.00 -
NOTE: Cost for concrete items in this section
includes reinforcement, steel anchorage embedded
in concrete, shuttering, concrete, concrete curing
and all to the complete job.
Pos.
UNOPS
DETAILS OF COMPONENTVertical Structures Unit
14/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
15/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Description of Work/Items Unit Quantity Unit Cost Total CostPos.
4 PCC concrete, 100mm thick, (20 Mpa) at thefloor over the water-proofing layer. This item
includes the stairs steps at the entrances and
the ramps. CU.M 36.00 -
5 RCC Columns, includes all columns (from -1.65 to +3.55) and supporting columns/ring
beams for trusses on the roof. CU.M 66.00 -
6 RCC (20 Mpa) slabs and beams. The itemscovers all slabs, beams and RCC floor for the
bank. CU.M 66.00 -
7 RCC Pavement (20 Mpa), for 1000mm-wideside walks. This includes entrances and
ramps. The cost includes expansion joint on
side walk surface as shown and as well as thebroom finish to the side walk/ ramp surfaces.
CU.M 12.00 -
3.3 Pre-cast RC Concrete 3.3 Precast Concrete PrototypesSchedule
1 Precast RCC (20 Mpa) exterior window sill forall windows as per drawings. This includes all
work need for complete installation.Lin M 23.00 -
3.5 Brickwork 3.5 Brickwork construction schedule
1 Second Class Brick masonry with mortar. Thisincludes all brick walls/ brick masonry in the
entire building. The cost includes steel bars
shown in the walls and their connection to the
perimeter RCC elements. CU.M 46.00 -
3.7 Light Steelwork 3.7 Light Steelwork, 6.6 Interior painting
and 6.6 Exterior painting schedules
NOTE: The following steel items include
painting according to the schedules and
specifications for steel member painting for
complete installation. See drawing for details.
1 Steel frame cabinet for First-Aid-Kits at thehall of Police Office Building. The item and its
cost include making, transportation,
installation, hardware, finishes and all other
accessories and work required for a complete
cabinet to the full satisfaction of the Engineer.
LS 1.00 -
2 Steel frame cabinets for W eapon Storages atthe hall of Police Office Building. The item and
its cost include making, transportation,
installation, hardware, finishes and all other
accessories and work required for a complete
cabinet to the full satisfaction of the Engineer.
LS 1.00 -
3.9 Light Timberwork 3.9 Light Timberwork schedule, 6.6Interior painting and 6.6 Exterior
painting schedules
1 Roof timber structure on the trusses. The costincludes 30mm thick wooden planks as
shown on the drawing. This also cover all
auxiliary and needed materials and supplying
and installation of members including painting
to make the surface ready for folded metal
sheet roofing according to the drawing,
schedule and specifications.
SQ.M 495.00 -
3.10 Concrete Unit Masonry 3.10 Concrete Unit Masonry
15/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
16/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Description of Work/Items Unit Quantity Unit Cost Total CostPos.
1 CMU masonry with mortar. This item coversall CMU works shown on the drawings for the
building. The cost includes all needed
materials, steel bars, anchors etc and works.
CU.M 46.00 -
3.11 Structural Steel 3.11 Structural Steel Schedules
3.7 Light Steelwork Schedule
1 Steel support, purlin, at the metal sheet roofas (C-shape 140x65mm + L-shape
50x50mm). See drawing for details. Lin M 440.00 -
2 Steel truss (TRUSS 1) at the roof. Seedrawing for details. No 3.00 -
3 Steel truss (TRUSS 2) at the roof. Seedrawing for details. No 4.00 -
4 Steel truss (TRUSS 3) at the roof. Seedrawing for details. No 2.00 -
5 Steel truss (TRUSS 4) at the roof. Seedrawing for details. No 8.00 -
6 Steel truss (TRUSS 5) at the roof. Seedrawing for details. No 2.00 -
7 Steel truss (TRUSS 6) at the roof. Seedrawing for details. No 2.00 -
8 Steel truss (TRUSS 7) at the roof. Seedrawing for details. No 8.00 -
9 Steel truss (TRUSS 8) at the roof. Seedrawing for details. No 2.00 -
10 Steel truss (TRUSS 9) at the roof. Seedrawing for details. No 4.00 -
11 Steel truss (TRUSS 10) at the roof. Seedrawing for details. No 4.00 -
12 Steel truss (TRUSS 11) at the roof. Seedrawing for details. No 1.00 -
13 Steel frame fixed ladder inside the toilet as theaccess way to the roof. The work and the cost
includes construction of fixed later to the walland the opening pane, its hardware and other
accessories to complete the installation as per
drawing and schedule. This also includes
painting according to the schedules and
specifications for steel surfaces painting.LS 1.00 -
Subtotal Structure -
4. Enclosure
4.1 Waterproofing 4.1 Waterproofing system schedule
1 Bitumen water-proofing coat. This is a 3-5mmthick hot bitumen painting coats on dried PCC
surface. The item applies on 40mm PCC at
the floor beneath the 20 Mpa, 100mm thick
PCC layer. This cost includes supplying and
applying the coats with all needed accessories
and work to do the job as per manufacturer's
data and to the full satisfaction of UNOPS
engineer. SQ.M 360.00 -
NOTE: Cost for steel related items in this section
includes supplying materials and installation to the
complete condition for all members, gussets,
fasteners, connections, welding and other
accessories and works needed to complete the
job. The cost also includes painting according to
the schedules and specifications for steel memberpainting, which is at least on coat of anti-rust
followed by 2 other coats of oil-based painting for
all surfaces and sides of the steel members.
16/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
17/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Description of Work/Items Unit Quantity Unit Cost Total CostPos.
2 Single layer bitumen membrane at the floorand walls of toilets/kitchen. This includes
preparation of base layers shown on the
drawings. Refer to schedule/drawing for
details. SQ.M 55.00 -
4.2 Roofing 4.2 Roofing materials, and 4.2 Gutterand Down pipe Schedules
1 Standing seam metal roofing (using GI sheetgauge 24). This includes all accessories
required for installation of roof on the prepared
timber plank (see item 3.9.1 for the cost of
timber plank on roof). The cost also includes
all flashings, capping etc needed on the metal
roof. SQ.M 495.00 - 2 Metallic gutter around the roof (using GI sheet
gauge 20). The cost includes all accessories
required for complete installation of gutter
such as supplying, fixing and others as per
drawing and schedules.Lin M 98.00 -
3 Down pipes, PVC pipe class-B. This includesall accessories required for complete
installation such as supplying, fixing and
others as per drawing and schedules.Lin M 38.00 -
4.3 Windows and Window Hardware 4.3 Window, 4.3 Window Hardware, 4.5Annealed Glasses, and 4.6 Glassblock
work schedules
1 Wooden frame windows. The work includesmaking, transportation, installation, hardware,
glazing, glass-block work around window,
insect screen, 3 coats of oil-based painting,
and other accessories required for complete
installation as per drawings and schedule.SQ.M 50.00 -
4.4 Doors and Door Hardware 4.4 Joinery doors 4.4 PVC doors, 4.4Steel doors and 4.5 Annealed Glasses
schedules
1 Wooden frame doors. The work includesmaking, transportation, installation, hardware,
glazing, and other accessories required forcomplete installation as per drawings and
schedule. SQ.M 60.00 -
2 PVC frame doors. The work includes making,transportation, installation, hardware, glazing,
and other accessories required for complete
installation as per drawings and schedule.SQ.M 6.00 -
3 Steel frame doors. The work includes making,transportation, installation, hardware, glazing,
1 coat of anti-rust followed by 2 other coats of
oil-based painting, and other accessories
required for complete installation as per
drawings and schedule.SQ.M 2.00 -
4.5 Glazing 4.5 Mirrors schedules
1 Mirrors (40x60cm) at toilets. This includescomplete installation. No 5.00 -
4.7 Insulation and Vapour Barriers 4.7 Insulation Schedules
1 Glasswool thermal insulation on RCC roof,beneath roof structure. See drawings and
schedules for details. SQ.M 495.00 -
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
17/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
18/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Description of Work/Items Unit Quantity Unit Cost Total CostPos.
4.8 Exterior Insulation and Finish System 4.8 EFIS Schedules
1 External wall insulation system,STOTHERM CLASSIC, (expanded
polystyrene foam and organically bound
render) "or equivalent ". See drawing and
schedule for location and detail. The cost
includes one preparation layer of cement
render and all other process required for a
complete job as per product's manufacturer
data and UNOPS engineer satisfaction. SQ.M 250.00 -
Subtotal enclosure -
5. Interior
5.4 Suspended Ceiling 5.4 Suspended Ceiling Schedule
1 Lasani wooden board, 16mmm, fixed ceilingfor all soffits around the building. The cost
includes all framing, fixing, oil based painting
and needed work for a complete job to the full
satisfaction of Engineer.SQ M 117.00 -
2 Gypsum board, 16mmm, reflected ceiling forthe side entrances of the building. The cost
includes all framing, fixing, and needed work
for complete job. SQ M 4.00 -
5.5 Joinery 5.5 Joinery fixtures schedule
1 Wooden frame, MDF finish, wall mountedcabinet at the kitchen. See drawings for
details. The cost includes making, installation,
framing, hardware, finish, 3 coats oil-based
painting and all to the complete job.LS 1.00 -
2 Wooden frame, MDF finish, floor mountedcupboard at the kitchen. See drawings for
details. The cost includes making, installation,
framing, finish, hardware, stone table top,
splash back, 3 coats oil-based painting and all
to the complete job. LS 1.00 -
5.6 Metalwork 5.6 Metal Fixtures Schedule
1 Metallic plaster beads for outer corners at thecorridors only, including edge of walls. This
includes any needed work for complete
installation. See schedules and drawings for
details. Lin M 54.00 -
2 Toilet roll holders. This also includesinstallation. No 3.00 -
3 Grab rail for handicap toilet. One completeset. This includes supplying and complete
installation. LS 1.00 -
4 Soap dishes. This also includes installation.No 4.00 -
5.8 Fire Extinguishers and Blankets 5.8 Fire Extinguishers Schedule
1 Extinguishers, wall mounted, powder-type(9kg). No 4.00 -
Subtotal Interior -
6. Finish
6.1 Plastering 6.1 Plastering Schedule
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
18/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
19/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Description of Work/Items Unit Quantity Unit Cost Total CostPos.
Internal surfaces
1 Cement render medium CRM followed bycement render fine CRF on all internal
surfaces of walls/ ceilings/ beams/ columns/
reveals. See schedule for detail. SQ.M 880.00 -
External surfaces
2 Gypsum board, decorative finish, at both mainentrances foreheads. The cost includes
supplying, making, installation and all to the
complete condition as per Engineer's approval.
SQ.M 40.00 -
6.2 Cementitious Toppings 6.2 Cementitious Toppings Schedule
1 In situ colored chips, colored mortar terrazzo,including marble trims for joints, for all floors
as shown on the drawing. See schedule for
details. The cost also includes stainless steel
nosing at the outer edges of the stair steps at
the entrances. SQ.M 390.00 -
6.3 Tiling 6.3 Wall tiling and 6.3 Floor tilingschedules
1 Ceramic wall tiles for toilets, kitchen, aroundthe drinking water fountain and any place
shown. The cost includes bed preparation,
bedding and grout. SQ.M 70.00 -
2 Ceramic floor tiles for toilets including bedpreparation, bedding and grout. SQ.M 35.00 -
3 Marble skirting for all rooms and halls wheredid not receive ceramic tiles. The cost
includes bedding and grout. Lin M 360.00 -
6.6 Painting 6.6 Interior/Exterior painting schedule
Internal surfaces
1 Flat water based: Interior, on all surfaces thatreceive cement plaster. The cost includes wall
putty (gypsum filling) layer before painting and
all needed preparation of the surfaces for
painting. See schedule for detail on this paintsystem SQ.M 880.00 -
Subtotal Finishes -
8. Water Services
8.1 Water Services 8.1 Water services samples, 8.1 Watersystem piping, 8.1 Sanitary fixtures, 8.1
Water heater schedules and 8.1 W ater
Services Testing schedules
NOTE: The cost for all pipes exposed to
weather includes glass wool thermal insulation
cover. The cost given for all GI and PVC pipes
with diameter less than 60mm includes all
required fittings, accessories and work forcomplete system installation.
Water supply piping
1 GI water supply pipe D=32mm, includingfittings and installation. Lin M 30.00 -
NOTE: Prior to work, samples must be approved byUNOPS Engineer.
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
NOTE: Prior to work, samples must be approved by
UNOPS Engineer.
19/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
20/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Description of Work/Items Unit Quantity Unit Cost Total CostPos.
2 GI water supply pipe D=25mm, includingfittings and installation. Lin M 22.00 -
3 GI water supply pipe D=20mm, includingfittings and installation. Lin M 59.00 -
4 GI water supply pipe D=15mm, includingfittings and installation. Lin M 78.00 -
5 Water supply bronze Valve D=32mm,including fittings and installation. No 2.00 -
6 Water supply bronze Valve D=20mm,including fittings and installation. No 2.00 -
7 Damp proof Insulation rubber tape for all GIPiping. Lin M 200.00 -
8 Water supply inspection manhole less than
1200mm deep. This includes excavation andany needed work to make the manhole as per
drawings and schedule. No 4.00 -
Sanitation Piping
9 PVC pipe D=100mm, including supply andinstallation. This also includes supply and
installation of PVC pipe from GI sheet
downpipes to the open channel collector at the
side walks. Lin M 50.00 -
10 PVC pipe D=50mm, including fittings andinstallation. Lin M 45.00 -
11 Ventilation PVC pipes D=100mm (from toiletsto roof). This also includes supplying and
installation of PVC screen at the pipe inlets
inside the toilets. See drawing and schedule
for details.Lin M 23.00 -
12 Ventilation PVC pipes D=50mm (from toiletsto roof). This also includes supplying and
installation of PVC screen at the pipe inlets
inside the toilets. See drawing and schedule
for details. Lin M 8.00 -
13 PVC Elbow D=100x100,45 , including supplyand installation. No 10.00 -
14 PVC Tee D=100x100, 45 , including supplyand installation. No 15.00 -
15 Sanitation Grease Trap less than 1200mmdeep. This includes excavation and any
needed work to make the manhole according
to the drawings and schedules. No 1.00 -
Sanitary and other fixtures
16 Western toilet, including supply, installationand accessories. No 5.00 -
17 Water fountain , including supply, installationand accessories. No 2.00 -
18 Ceramic sink at toilets and labs, includingmixer and all accessories, supplying and
installation. No 6.00 -
19 Floor trap D=50mm, including supply andinstallation. No 7.00 -
20 Stainless steel sink, including supply andinstallation. No 1.00 -
21 Ventilation cap D=100mm, including supplyand installation. No 3.00 -
22 Ventilation cap D=50mm, including supplyand installation. No 1.00 -
23 Service Sink, including supply and installation.No 1.00 -
24 Electrical water boiler with capacity of 50Liter, including supply and installation. No 2.00 -
25 Electrical water boiler with capacity of 30Liter, including supply and installation. No 2.00 -
20/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
21/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Description of Work/Items Unit Quantity Unit Cost Total CostPos.
26 Sewer Manholes More than 1200mm deep.This includes excavation and any needed work
to make the manhole according to the
drawings and schedules. No 3.00 -
Subtotal Water Services -
9. Electrical Services
9.1 Electrical Services 9.1 Electrical systems, 9.1 Electricalsupply mains, 9.1 Electrical switchboard
design, 9.1 Main 380VAC Distribution
System, 9.1 Panel Construction, 9.1
Power accessories, 9.1 Lighting controland fittings, 9.1 Fire Detection
Equipment Schedule Schedules and the
Attachments
Note: for all items below the cost includes
complete/installations with all needed
accessories and works.
Switchboard and sub boards
1 Sub distribution panel, 750x500x250 mm,powder coated, weatherproof, outdoor
mounted metal. With Digital Measurement
equipments. No. 1.00 -
2 Main circuit breaker, MCCB, 3x160Amps,Type-C. No. 1.00 -
3 Circuit breaker, MCB, 1x32Amps, Type-CNo. 12.00 -
4 Circuit breaker, MCB, 1x20Amps, Type-CNo. 30.00 -
Distribution wiring
5 3 (1X6mm2) wires pulled in 24mm PVCConduit, assorted colors as per phase
requirement RST/UVW, white color for neutral
and green color for grounding. Lin M 400.00 -
6 3 (1X4mm2) wires pulled in 24mm PVCConduit, assorted colors as per phase
requirement RST/UVW, white color for neutral
and green color for grounding. Lin M 900.00 -
Fittings/Fixtures
7 Single pole/double pole or two way lightswitch. No 38.00 -
8 32W circular surface ceiling mount, IP54fluorescent light fixture. No 26.00 -
9 60W circular Pendant ceiling mount, IP54fluorescent light fixture with all accessories. No 16.00 -
10 60W Circular Surface ceiling mount, IP54fluorescent light fixture with all accessories. No 2.00 -
11 2x36W pendant ceiling mounted fluorescentlight fixture, IP-44.with all accessories.
No 16.00 -
12 1x36W pendant ceiling mounted fluorescentlight fixture, IP-56. with all accessories.
No 3.00 -
13 16 Amp Duplex power receptacle.No 54.00 -
14 16 Amp single water proof power receptacle.No 16.00 -
15 25 Amp single water proof power receptaclefor electrical water heater and kitchen.
No 12.00 -
AC/Split Units and Exhaust fans
16 12000 BTU AC/ Split unit 220 V, 50 HZSamsung made in Italy with all accessories.
No 8.00 -
21/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
22/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Description of Work/Items Unit Quantity Unit Cost Total CostPos.
17 Roof mounted exhaust fans .No 5.00 -
18 25 Amp single electrical non-fusedisconnecting switch for AC/ Split unit. No 8.00 -
Emergency evacuation lighting
19 2x10 watt IP-65 wall mounted EmergencyLight Fixture. No 5.00 -
20 1X10W surface mounted IP-40 Exit light.No 4.00 -
Fire alarm system (including all associated
cabling, wiring, mounting, etc)
21 Addressable fire alarm panel, with all
accessories, to the complete and functioning job. LS 1.00 -
22 Fire alarm push button, double action type, ULListed No 4.00 -
23 Fire alarmNo 4.00 -
24 Photoelectric type smoke detectors, UL ListedNo 16.00 -
Electrical Grounding and Lightning
Protection.
25 Lightening protection as mentioned inlightening protection drawing with air terminal,
electrodes, tape, connectors, clamp and
grounding cable Set 1.00 -
26 Grounding system as mentioned in groundingdrawing with electrodes, tape, connectors,
clamp and grounding cable Set 1.00 -
Labeling
27 Proper and correct all circuits numbering,cable circuit drawings, cable and switchboard
labeling to the full satisfaction of UNOPS
engineer. LS 1.00 -
Subtotal Electrical Services -
22/24
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
23/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Component: Police Office Building
Original Issue: February 25, 2010
Work Type
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total for Water Supply Services
Total for Electrical Services
Total for Structure
Total for Enclosure
Total for Interior
Total for Finish
Total for Police Office Building 0.00
Total for General
Total for Site
UNOPS
SUMMARY OF COMPONENT
Vertical Structures Unit
8/20/2019 https___www.unops.org_ApplyBO_File.aspx_BOQ Office Buildings.pdf
24/24
Currency: US Dollars
Project No: 810
Project Title: Ai Khanem Border Crossing Point Facilities
Location: Takhar, Afghanistan
Tender No: 04
Tender Title: Customs and Police Office Buildings
Original Issue: February 25, 2010
CONTRACT COMPONENTS
Signature
Total for Customs Office Building
Total for Police Office Building
UNOPS
SUMMARY BILL OF QUANTITIES
Vertical Structures Unit
Signature
Address and
Mobile Number
Name Name
Position Position
Agreed on behalf of Contractor UNOPS
BOQ Value for whole tender in words:
Zero