+ All Categories
Home > News & Politics > Huntington Levee Community Meeting

Huntington Levee Community Meeting

Date post: 15-Jul-2015
Category:
Upload: fairfax-county
View: 405 times
Download: 0 times
Share this document with a friend
34
January 29, 2015 Building Design Branch Huntington Levee Community Meeting
Transcript
Page 1: Huntington Levee Community Meeting

January 29, 2015

Building Design Branch

Huntington Levee Community Meeting

Page 2: Huntington Levee Community Meeting

Building Design Branch

Agenda

I. Project Background & Completed Tasks

II. Interior Drainage Analysis

III. Pump Station Design

IV. Construction Access

V. Schedule and Next Steps

VI. Community Outreach

VII. Questions

2

Page 3: Huntington Levee Community Meeting

Building Design Branch

• June 2006 -160 homes were flooded from a storm event

• 2009 – US Army Corps of Engineers (USACE) completed a study to evaluate flood damage reduction measures in the Huntington Community

3

Project Background

Page 4: Huntington Levee Community Meeting

Building Design Branch

• November 6, 2012 – Fairfax County voters approved stormwater bond referendum to fund design and construction of flood damage reduction measures proposed by the USACE

• June 2013 – Fairfax County awarded the levee design contract to ARCADIS

• November 2013 – ARCADIS submitted the Phase I design package to Fairfax County

• Survey, Geotechnical Investigation, Wetland Delineation, and Conceptual Design

• January 2014 – Fairfax County and Huntington Community reach consensus on conceptual design features

4

Project Background

Page 5: Huntington Levee Community Meeting

Building Design Branch

• July 2014 – ARCADIS completed Hydraulic and Hydrologic Modelling for Cameron Run

• September 2014 – ARCADIS submitted Schematic (30%) Design package to Fairfax County

• October 2014 - Fairfax County conducted Value Engineering Workshop

• December 2014 – ARCADIS began Design Development (60%) phase

• December 2014 – Geotechnical Report submitted for Permitting

• January 2015 – ARCADIS completed the Interior Drainage Analysis

5

Project Background

Page 6: Huntington Levee Community Meeting

Building Design Branch

Project Background

• Earthen Levee/I-Wall Combination

• Collection Drains

• Pump Station Location – East end of levee

• Stormwater Diversion – Concrete box culverts

Key Design Features

6

Page 7: Huntington Levee Community Meeting

Building Design Branch

Interior Drainage Analysis

Interior Levee Exterior

Note: Exterior (Cameron Run) Modeling Completed July 2014

Page 8: Huntington Levee Community Meeting

Building Design Branch

Interior Drainage Analysis

Purpose

• Understand how water flows on land behind levee

• Understand how adding the levee will change the water flow

• Set design water elevation

• Size pumps and interior water storage area

• Provides the data necessary for the FEMA Accreditation package and revision to the Floodplain Maps.

• Support the Floodplain Study for submission to the County Land Development Services

Page 9: Huntington Levee Community Meeting

Building Design Branch 9

Existing 100-year Water Surface Elevation

Interior Drainage Analysis

Page 10: Huntington Levee Community Meeting

Building Design Branch

Interior Drainage Analysis

Page 11: Huntington Levee Community Meeting

Building Design Branch

Interior Drainage Analysis

HEC-HMS Modeling Approach

Page 12: Huntington Levee Community Meeting

Building Design Branch

Interior Drainage Analysis

HEC-HMS Results – Hypothetical EventsClosed Drainage Structures

Peak Pond Elevation based on HEC-HMS modelling

Storm Intensity Rainfall Depth (in.) Peak Pond Elevation (ft.)

2- year 3.17 5.5

5- year 4.07 6.1

10- year 4.87 6.6

25- year 6.09 7.1

50- year 7.18 7.5

100- year 8.41 8.0

500- year 12.00 9.1

Page 13: Huntington Levee Community Meeting

Building Design Branch

Interior Drainage Analysis

Project Cross-Section Key Elevations

Page 14: Huntington Levee Community Meeting

Building Design Branch 14

100-year stormwater ponding at elevation 8.0’

Interior Drainage Analysis

Page 15: Huntington Levee Community Meeting

Building Design Branch

Interior Drainage Analysis

Historical Flood Events - Cameron Run – Jones Point Rainfall

Historical Event Rainfall at Jones Point Station

(Inches)

Peak Water Surface Elevation

(Feet)

July 28, 2000 1.12 4.1

September 23, 2003* 1.80 4.6

June 25, 2006 3.51 5.1

September 6, 2008 3.40 4.4

September 8, 2011** 2.64 4.5

June 10, 2013 2.30 4.6

June 28, 2013 1.59 4.4

July 12, 2013 2.46 4.8

May 16, 2014 2.68 4.5

Peak Water Surface Elevation based on HEC-HMS modelling

* Tropical Storm Isabel

** Tropical Storm Lee

Page 16: Huntington Levee Community Meeting

Building Design Branch

Interior Drainage Analysis

Historical Flood Events - Cameron Run – Jones Point Rainfall

Peak Water Surface Elevation based on HEC-HMS modelling

Page 17: Huntington Levee Community Meeting

Building Design Branch 17

25-year stormwater ponding

Interior Drainage Analysis

Page 18: Huntington Levee Community Meeting

Building Design Branch 18

10-year stormwater ponding

Interior Drainage Analysis

Page 19: Huntington Levee Community Meeting

Building Design Branch

Interior Drainage Analysis

Interior Ponding Area

• Provides location for stormwater until it can be pumped out

• Controlled flooding area

• Coordinating with Fairfax County Park Authority on design and possible amenities

• Likely not athletic fields

Page 20: Huntington Levee Community Meeting

Building Design Branch 20

Levee impact and storage requirements

Interior Drainage Analysis

Page 21: Huntington Levee Community Meeting

Building Design Branch 21

Pump Station

Page 22: Huntington Levee Community Meeting

Building Design Branch 22

Pump Station

Pump Station Equipment

• 3 Active Stormwater Pumps

• 1 Backup Stormwater Pump

• 2 Dewatering Pumps

• Generator for Emergency Power

Page 23: Huntington Levee Community Meeting

Building Design Branch 23

Preliminary Interior Rendering

Pump Station

Page 24: Huntington Levee Community Meeting

Building Design Branch 24

Scaled Model of PumpingConfiguration

Pump Station

Page 25: Huntington Levee Community Meeting

Building Design Branch 25

Preliminary Exterior Rendering

Pump Station

Page 26: Huntington Levee Community Meeting

Building Design Branch 26

Preliminary Exterior Rendering

Pump Station

Page 27: Huntington Levee Community Meeting

Building Design Branch 27

Construction and Maintenance Access

Page 28: Huntington Levee Community Meeting

Building Design Branch

• Phase II (January 2014-Winter 2017)

• Schematic Design (30%)

• Design Development (60%)

• Permitting

• Land Acquisition

• Construction Documents (100%)

• Bidding

• Phase III (Winter 2017-Spring 2019)

• Construction

28

Schedule

Schedule

Page 29: Huntington Levee Community Meeting

Building Design Branch

• Next Steps

• Site Permit Submission – February 2015

• Pump Station Work Session – February 2015

• Design Development Submission (60%) – April 2015

29

Schedule

Schedule

Page 30: Huntington Levee Community Meeting

Building Design Branch

Schedule

30

Page 31: Huntington Levee Community Meeting

Building Design Branch

Community Outreach

31

Page 32: Huntington Levee Community Meeting

Building Design Branch

Community Outreach

• Community Meeting notes will be placed on the web site 2 weeks after the meeting

• Quarterly emails sent out to the project listserv with progress made in the past three months and what to expect in the next three months

• Schedule – added a feature to the web site to help the Community track the progress of the active components of the project.

Communication

32

Page 33: Huntington Levee Community Meeting

Building Design Branch

Community Outreach

• Bi-annually

• Important Milestones

• Next Community meeting – July 2015

• Updates on Permitting

• Interior Ponding Development

• Pump Station

Community Meetings

33

Page 34: Huntington Levee Community Meeting

Building Design Branch

Questions

Contact Information – Huntington Levee Project Phone #: 703-324-5800

Email address: [email protected]

Contact Information – Stormwater Questions Phone #: 703-324-5821

Email address: [email protected]

Huntington Levee Website: www.fairfaxcounty.gov/dpwes/huntingtonlevee

To request this document in an alternate format call 703-324-5800, TTY 711.

34


Recommended